LEAD & LAG
DEFINITIONS, EXAMPLES AND
DIAGRAMS
Designed and Developed by https://www.pmbypm.com 1
AGENDA
• Definitions, Examples & Diagrammatic Representations
• Lead with 4 Types of Scheduling Relationships
• Lag with 4 Types of Scheduling Relationships
Designed and Developed by https://www.pmbypm.com 2
LEAD
• The amount of time whereby a successor activity can be
advanced with respect to a predecessor activity.
• Example
• In an Engineering Project, collection of requirement can LEAD creation of
design.
• In a Construction Project, interior finishing of a room will follow
plastering of walls.
Designed and Developed by https://www.pmbypm.com 3
REPRESENTATION OF LEAD
Designed and Developed by https://www.pmbypm.com 4
B(S) = A(F) – 1d
Example
Duration of A = 3 Days, Duration of B = 2 Days, Duration of Lead = n Days (nD)
The scheduled Start(S) of B is 1 day before (-1d) the scheduled Finish(F) of B
Mathematical
Network Diagram
A B-nD
FS-nD
A B
Bar Chart
LAG
• The amount of time whereby a successor activity is required to
be delayed with respect to a predecessor activity.
• Example
• A – Lay ceiling for Floor I, B – Construct Columns for Floor II.
• A – Ship goods to a customer, B – Check if shipment has been delivered.
Designed and Developed by https://www.pmbypm.com 5
REPRESENTATION OF LAG
Designed and Developed by https://www.pmbypm.com 6
B(S) = A(F) + 1d
Example
Duration of A = 3 Days, Duration of B = 2 Days, Duration of Lag = n Days (nD)
The scheduled Start(S) of B is 1 day after (+1d) the scheduled Finish(F) of A
Mathematical
Network Diagram
A B
+nD
FS+nD
A B
Bar Chart
AGENDA
• Definitions, Examples & Diagrammatic Representations
• Lead with 4 Types of Scheduling Relationships
• Lag with 4 Types of Scheduling Relationships
Designed and Developed by https://www.pmbypm.com 7
LEAD AND FINISH TO START
Designed and Developed by https://www.pmbypm.com 8
Duration of A = 3 Days
Duration of B = 2 Days
B has a Finish to Start Relationship with A
The scheduled Start of B is 1 day before the
scheduled Finish of A
A B
A B
FS-1d
-1d
-1d
Network Diagram Bar Chart
Example
LEAD AND FINISH TO FINISH
Designed and Developed by https://www.pmbypm.com 9
Duration of A = 3 Days
Duration of B = 2 Days
B has a Finish to Finish Relationship with A
The scheduled Finish of B is 1 day before the
scheduled Finish of A
A B
A B
FF-1d
-1d
-1d
Network Diagram Bar Chart
Example
-1d
LEAD AND START TO START
Designed and Developed by https://www.pmbypm.com 10
Duration of A = 3 Days
Duration of B = 2 Days
B has a Start to Start Relationship with A
The scheduled Start of B is 1 day before the
scheduled Start of A
A B
A B
SS-1d
-1d
Network Diagram Bar Chart
Example
-1d
LEAD AND START TO FINISH
Designed and Developed by https://www.pmbypm.com 11
Duration of A = 3 Days
Duration of B = 2 Days
B has a Start to Finish Relationship with A
The scheduled Finish of B is 1 day before the
scheduled Start of A
A B
A BSF-1d
-1d
Network Diagram Bar Chart
Example
-1d
AGENDA
• Definitions, Examples & Diagrammatic Representations
• Lead with 4 Types of Scheduling Relationships
• Lag with 4 Types of Scheduling Relationships
Designed and Developed by https://www.pmbypm.com 12
LAG AND FINISH TO START
Designed and Developed by https://www.pmbypm.com 13
Duration of A = 3 Days
Duration of B = 2 Days
B has a Finish to Start Relationship with A
The scheduled Start of B is 1 day after the scheduled
Finish of A
A B
A B
FS+1d
+1d
Network Diagram Bar Chart
Example
+1d
LAG AND FINISH TO FINISH
Designed and Developed by https://www.pmbypm.com 14
Duration of A = 3 Days
Duration of B = 2 Days
B has a Finish to Finish Relationship with A
The scheduled Finish of B is 1 day after the scheduled
Finish of A
A B
A B
FF+1d
+1d
Network Diagram Bar Chart
Example
+1d
LAG AND START TO START
Designed and Developed by https://www.pmbypm.com 15
Duration of A = 3 Days
Duration of B = 2 Days
B has a Start to Start Relationship with A
The scheduled Start of B is 1 day after the scheduled
Start of A
A B
A B
SS+1d
+1d
Network Diagram Bar Chart
Example
+1d
LAG AND START TO FINISH
Designed and Developed by https://www.pmbypm.com 16
Duration of A = 3 Days
Duration of B = 2 Days
B has a Start to Finish Relationship with A
The scheduled Finish of B is 1 day after the scheduled
Start of A
A B
A B
SF+1d
+1d
Network Diagram Bar Chart
Example
+1d
YOUR OPINION IS IMPORTANT TO US
FOR ANY QUESTIONS OR SUGGESTIONS CONTACT US @
HTTPS://WWW.PMBYPM.COM/CONTACT-PRAVEEN-
MALIK/
Designed and Developed by https://www.pmbypm.com 17

More Related Content

PPTX
Evolution of project management
PPTX
ppt for primevera
PPT
Project Management Tools and Techniques
PPT
Project Execution
PDF
construction project planing
PDF
Work Breakdown Structure
PDF
Primavera - Tutorial
PPTX
Project Cost Management
Evolution of project management
ppt for primevera
Project Management Tools and Techniques
Project Execution
construction project planing
Work Breakdown Structure
Primavera - Tutorial
Project Cost Management

What's hot (20)

PDF
Construction Project management
PPTX
Primavera presentation
PDF
Project management in construction
PPTX
PROJECT SCHEDULE
PPT
Project Planning Scheduling
PDF
Project Controlling and Project Monitoring
PPTX
Construction management
PPTX
6.5 Resource Leveling and Resource Smoothing
PDF
50 Planning Fundamentals V5.0 - procedures only
PPS
An Introduction To Project Management
PDF
Introduction to Project Management
PDF
PMP Lecture 1: Introduction to Project Management
PDF
PERT AND CPM PROJECT MANAGEMENT
PPTX
Project planning and scheduling techniques
PDF
Lecture 2. project management – Description (1)
PDF
PM using P6
PPTX
PERT-CPM : PROJECT MANAGEMENT TOOLS
PPT
project planning-estimation
PDF
PMP Lecture 3: Project Management Processes
PDF
Schedule Updates
Construction Project management
Primavera presentation
Project management in construction
PROJECT SCHEDULE
Project Planning Scheduling
Project Controlling and Project Monitoring
Construction management
6.5 Resource Leveling and Resource Smoothing
50 Planning Fundamentals V5.0 - procedures only
An Introduction To Project Management
Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
PERT AND CPM PROJECT MANAGEMENT
Project planning and scheduling techniques
Lecture 2. project management – Description (1)
PM using P6
PERT-CPM : PROJECT MANAGEMENT TOOLS
project planning-estimation
PMP Lecture 3: Project Management Processes
Schedule Updates
Ad

Similar to How To Use Scheduling Lead And Lag With 4 Types Of Relationships (20)

PDF
Session B1 - Planning, Scheduling Monitoring and Control
PPTX
UNIT-IIbdffdggfdgfdgfdgfdgdgfdghdhdhdh.pptx
PPTX
NETWORK SHEDULLING, BUSINESS ENTERPRENURESHIP.pptx
PPTX
Additional ppt Time Management Slides.pptx
PDF
Lol2 jdkxb jdj. Dj bri. Djd. Djidososdiddoodo
PPTX
actitvity_scheduling ppt for activity planning
PPT
6.3 sequence activities
PPTX
Short Comings of Bar Chart and Remidial Measures
PDF
NETWORK SCHEDULING TECHNIQUES Of software
PPT
Project Scheduling in the project management
PPTX
Lecture 3 - Project Planning - Contd.pptx
PPTX
Unit three Advanced State Modelling
PPTX
Network diagrams
PPTX
Unit2 network optimization
PPTX
Chap 4- CPM & PERT.pptx
PDF
CHAPTER-4 NETWORK MODEL Techniques that enable complex projects to be schedul...
PPT
Basics CPM&PERT.ppt
PDF
Uml examples
PPT
08. Project Time Management Upload
PDF
Network construction
Session B1 - Planning, Scheduling Monitoring and Control
UNIT-IIbdffdggfdgfdgfdgfdgdgfdghdhdhdh.pptx
NETWORK SHEDULLING, BUSINESS ENTERPRENURESHIP.pptx
Additional ppt Time Management Slides.pptx
Lol2 jdkxb jdj. Dj bri. Djd. Djidososdiddoodo
actitvity_scheduling ppt for activity planning
6.3 sequence activities
Short Comings of Bar Chart and Remidial Measures
NETWORK SCHEDULING TECHNIQUES Of software
Project Scheduling in the project management
Lecture 3 - Project Planning - Contd.pptx
Unit three Advanced State Modelling
Network diagrams
Unit2 network optimization
Chap 4- CPM & PERT.pptx
CHAPTER-4 NETWORK MODEL Techniques that enable complex projects to be schedul...
Basics CPM&PERT.ppt
Uml examples
08. Project Time Management Upload
Network construction
Ad

More from Praveen Malik, PMP (11)

PPTX
Learn The Right Way To Apply TCPI Formulas In Project Management
PPTX
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
PPTX
Calculating ETC In 4 Different Scenarios
PPTX
101 - A Beginner's Guide To Earned Value Management
PPTX
A Comprehensive Beginners Guide To Cost Planning
PPTX
How To Do Planning Using 4 Types of Project Dependencies?
PPTX
5 Steps Of Project Scheduling Process For Absolute Beginners
PPTX
Successful Project Managers Use These 5 Ways to Represent Project Schedule
PPTX
4 Project Estimation Techniques That Can Make You Super Successful
PDF
Ignore Project Scope & WBS At Your Own Peril
PPTX
How Project Network Diagram's Can Help You Become A Better Project Manager
Learn The Right Way To Apply TCPI Formulas In Project Management
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating ETC In 4 Different Scenarios
101 - A Beginner's Guide To Earned Value Management
A Comprehensive Beginners Guide To Cost Planning
How To Do Planning Using 4 Types of Project Dependencies?
5 Steps Of Project Scheduling Process For Absolute Beginners
Successful Project Managers Use These 5 Ways to Represent Project Schedule
4 Project Estimation Techniques That Can Make You Super Successful
Ignore Project Scope & WBS At Your Own Peril
How Project Network Diagram's Can Help You Become A Better Project Manager

Recently uploaded (20)

PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PPTX
Institutional Correction lecture only . . .
PDF
01-Introduction-to-Information-Management.pdf
PPTX
GDM (1) (1).pptx small presentation for students
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
Classroom Observation Tools for Teachers
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
Complications of Minimal Access Surgery at WLH
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
Basic Mud Logging Guide for educational purpose
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
STATICS OF THE RIGID BODIES Hibbelers.pdf
Institutional Correction lecture only . . .
01-Introduction-to-Information-Management.pdf
GDM (1) (1).pptx small presentation for students
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
Classroom Observation Tools for Teachers
Pharmacology of Heart Failure /Pharmacotherapy of CHF
O7-L3 Supply Chain Operations - ICLT Program
Complications of Minimal Access Surgery at WLH
Microbial disease of the cardiovascular and lymphatic systems
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Basic Mud Logging Guide for educational purpose
Microbial diseases, their pathogenesis and prophylaxis
Computing-Curriculum for Schools in Ghana
Renaissance Architecture: A Journey from Faith to Humanism
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
102 student loan defaulters named and shamed – Is someone you know on the list?

How To Use Scheduling Lead And Lag With 4 Types Of Relationships

  • 1. LEAD & LAG DEFINITIONS, EXAMPLES AND DIAGRAMS Designed and Developed by https://www.pmbypm.com 1
  • 2. AGENDA • Definitions, Examples & Diagrammatic Representations • Lead with 4 Types of Scheduling Relationships • Lag with 4 Types of Scheduling Relationships Designed and Developed by https://www.pmbypm.com 2
  • 3. LEAD • The amount of time whereby a successor activity can be advanced with respect to a predecessor activity. • Example • In an Engineering Project, collection of requirement can LEAD creation of design. • In a Construction Project, interior finishing of a room will follow plastering of walls. Designed and Developed by https://www.pmbypm.com 3
  • 4. REPRESENTATION OF LEAD Designed and Developed by https://www.pmbypm.com 4 B(S) = A(F) – 1d Example Duration of A = 3 Days, Duration of B = 2 Days, Duration of Lead = n Days (nD) The scheduled Start(S) of B is 1 day before (-1d) the scheduled Finish(F) of B Mathematical Network Diagram A B-nD FS-nD A B Bar Chart
  • 5. LAG • The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity. • Example • A – Lay ceiling for Floor I, B – Construct Columns for Floor II. • A – Ship goods to a customer, B – Check if shipment has been delivered. Designed and Developed by https://www.pmbypm.com 5
  • 6. REPRESENTATION OF LAG Designed and Developed by https://www.pmbypm.com 6 B(S) = A(F) + 1d Example Duration of A = 3 Days, Duration of B = 2 Days, Duration of Lag = n Days (nD) The scheduled Start(S) of B is 1 day after (+1d) the scheduled Finish(F) of A Mathematical Network Diagram A B +nD FS+nD A B Bar Chart
  • 7. AGENDA • Definitions, Examples & Diagrammatic Representations • Lead with 4 Types of Scheduling Relationships • Lag with 4 Types of Scheduling Relationships Designed and Developed by https://www.pmbypm.com 7
  • 8. LEAD AND FINISH TO START Designed and Developed by https://www.pmbypm.com 8 Duration of A = 3 Days Duration of B = 2 Days B has a Finish to Start Relationship with A The scheduled Start of B is 1 day before the scheduled Finish of A A B A B FS-1d -1d -1d Network Diagram Bar Chart Example
  • 9. LEAD AND FINISH TO FINISH Designed and Developed by https://www.pmbypm.com 9 Duration of A = 3 Days Duration of B = 2 Days B has a Finish to Finish Relationship with A The scheduled Finish of B is 1 day before the scheduled Finish of A A B A B FF-1d -1d -1d Network Diagram Bar Chart Example -1d
  • 10. LEAD AND START TO START Designed and Developed by https://www.pmbypm.com 10 Duration of A = 3 Days Duration of B = 2 Days B has a Start to Start Relationship with A The scheduled Start of B is 1 day before the scheduled Start of A A B A B SS-1d -1d Network Diagram Bar Chart Example -1d
  • 11. LEAD AND START TO FINISH Designed and Developed by https://www.pmbypm.com 11 Duration of A = 3 Days Duration of B = 2 Days B has a Start to Finish Relationship with A The scheduled Finish of B is 1 day before the scheduled Start of A A B A BSF-1d -1d Network Diagram Bar Chart Example -1d
  • 12. AGENDA • Definitions, Examples & Diagrammatic Representations • Lead with 4 Types of Scheduling Relationships • Lag with 4 Types of Scheduling Relationships Designed and Developed by https://www.pmbypm.com 12
  • 13. LAG AND FINISH TO START Designed and Developed by https://www.pmbypm.com 13 Duration of A = 3 Days Duration of B = 2 Days B has a Finish to Start Relationship with A The scheduled Start of B is 1 day after the scheduled Finish of A A B A B FS+1d +1d Network Diagram Bar Chart Example +1d
  • 14. LAG AND FINISH TO FINISH Designed and Developed by https://www.pmbypm.com 14 Duration of A = 3 Days Duration of B = 2 Days B has a Finish to Finish Relationship with A The scheduled Finish of B is 1 day after the scheduled Finish of A A B A B FF+1d +1d Network Diagram Bar Chart Example +1d
  • 15. LAG AND START TO START Designed and Developed by https://www.pmbypm.com 15 Duration of A = 3 Days Duration of B = 2 Days B has a Start to Start Relationship with A The scheduled Start of B is 1 day after the scheduled Start of A A B A B SS+1d +1d Network Diagram Bar Chart Example +1d
  • 16. LAG AND START TO FINISH Designed and Developed by https://www.pmbypm.com 16 Duration of A = 3 Days Duration of B = 2 Days B has a Start to Finish Relationship with A The scheduled Finish of B is 1 day after the scheduled Start of A A B A B SF+1d +1d Network Diagram Bar Chart Example +1d
  • 17. YOUR OPINION IS IMPORTANT TO US FOR ANY QUESTIONS OR SUGGESTIONS CONTACT US @ HTTPS://WWW.PMBYPM.COM/CONTACT-PRAVEEN- MALIK/ Designed and Developed by https://www.pmbypm.com 17