PROJECT ON CONSTRUCTION MANAGEMENT
GROUP MEMBERS
1. EHSANULLAH (001)
2. QAZI NABEEL (144)
3. ANAS AHMED ABIDI(080)
4. ZUHAIR NADEEM(072)
5. MUHAMMAD JAWAD HASSAN(117)
6. MUHAMMAD ARIF SIDDIQUE KHAN(043)
7. AGHA BABAR ALI(078)
PROJECT INTERNAL
(ENGR. SYED FARAZ JAFRI)
PROJECT EXTERNAL
(ENGR.UMAR FAROOQ)
PROJECT INTERNAL & EXTERNAL
PROJECT DETAILS
CLIENT AL-GHAZI TRACTORS
DESIGN CONSULTANT NES-PAK.
MAIN CONTRACTOR TAHIR ENTERPRISES
ARCHITECT NES-PAK
LOCATION DEFENCE PHASE-1 PLOT 102-B
TOTAL COVERED AREA 4240 SQ FT
SRART DATE 31 DECEMBER 2013
EXPECTED FINISH DATE 31 MAY 2015
DURATION 15 MONTHS
PURPOSE OFFICE BUILDING
PARKING AREA 1 BASEMENT (FOR 22 CARS)
NUMBER OF STORIES 2 BASEMENT+ 4 FLOORS
PROJECT OBJECTIVES
 To evaluate working drawings and prepare BOQ
 Preparation of bar bending schedule
 Perform rate analysis
 To evaluate productivity and duration of various activities
 To study the effectiveness of site safety and quality in a
success of construction project
 To identify causes of delay and disputes on construction
project.
 Planning and scheduling of all construction activities on
primavera p6e.
PROJECT SCOPE
 To provide overall co-ordination and project team management.
 To perform project budgeting, scheduling, cost accounting and
reporting.
 To ensure the quality standard keeping in view the cost.
 Managing time within the whole project.
 Efficient use of computer softwares.
 Construction planning and resource allocation and optimization.
 To get familiar with responsibilities and tasks of a civil engineer.
 To observe the site safety.
final year presentation revised
final year presentation revised
final year presentation revised
final year presentation revised
final year presentation revised
final year presentation revised
final year presentation revised
Principles of Management
 Division of work
 Discipline
 Unity of command
 Unity in Direction
 Centralization of power to do work
 Change individual interest into organizational interest
 Authority and responsibility should always be together
 Equality, stability and motivation
5M’s of Management
In the management literature, five M’s of management called
as:
 Money
 Material
 Man power
 Machinery
 Methodology
METHODOLOGY
PROJECT MILESTONES
We have successfully achieved the following milestones
 Evaluated working drawings.
 Prepared bar bending schedule and BOQ.
 Performed rate analysis.
 Evaluated productivity and duration of various activities.
 Studied the effectiveness of site safety and quality in a success of
construction project.
 Identify causes of delay and disputes on construction project.
 Planned and scheduled all construction activities on primavera p6e.
Selection Of Project (WHY?)
We have selected the project due to the following reasons.
 First of all the reason we selected the project in construction
management was due to our interest and better understanding
provided by teachers about the management in the field of civil
engineering.
 The topic which we have selected for final year project show our
interest about cost evaluation of construction project and how to
control project cost through better resource allocation & optimization
and also to get awareness about job site safety and quality issues
related to construction project.
Site Visit And Data Collection
Frequently visited site for
 Collection of data such as working drawings.
 Observing Different construction activities on site.
 Discussing problems with external.
 Getting awareness about sequence of work required to plan and
schedule the project.
 To observe and understand safety and quality parameters.
Preparation and Submission of
Synopsis
Synopsis was submitted to our internal in the month of February 2015
which included
 Project title
 Project details
 Project technical information
 3c’s of project
 Objectives and scope of project
 Time frame
Rate Analysis and Workout
Productivity
 All Rates and productivity (except productivity of machinery) are taken
from NES-PAK Contract section 12th floor PNIC Building opp. Shahra-
e-Faisal, with cooperation of GM of Contract section Engr. Nasir Jamal.
 Some Rates and productivity were provided by our Site supervisor of
AL Ghazi Office Building Associate Engr. MR Fahad
 Productivity of machinery was found from internet by pdf manuals of
manufacturers of respective machineries.
Preparation Of Bar bending schedule and BOQ
 We prepared BBS and BOQ by following working drawings
(Ground Floor, 1st Floor, 2nd Floor, 3rd Floor and Basement 1)
S.# WBS NAME Shuttering
(sq. ft)
Volume
(Cu. Ft)
Reinforcement
(kg)
Plastering
(sq. ft)
1 Beams 3125 1157 3783 2702
2 Columns 877.1 325.68 1641.6 877.1
3 Walls 8177
4 Slab 4172.1 3184.3 5700 9074.8
Basement 2
Activity Concreting Reinforcement
(Kg)
Plastering Blocks
Sand
(cft.)
Cement
(bags)
Crush
(Cft.)
Sand
(cft)
Cement
(bags)
Beams 496
cft
199
bags
992cft 3783 kgs 135 cft 27 bags
Columns 207.5 83 415 2280 64.3 cft 13
Slabs 1365 546 2730 5700 461 92
Walls 625.4 125 9875
Substructure
work
S.# WBS Name Shuttering Volume Reinforcement
1 Pile 88970(Excavation)
5242.21 (pouring)
22500 kg
2 Back Filling 10000 cft
3 Pile Cap 5164 13700 18650 kg
4 Column up to
Plinth
785 cft 4270 kg
Study and observation of site safety
and quality
 The biggest concern which we observed at the site that for engineers
and supervisors personal protection equipment's (PPE ) were given and
other safety precautions were followed but for the laborers the
equipment's (PPE) was not properly provided due various delays
occurred because of accidents.
 Through sites visits we observed that proper quality control procedures
were implemented to get the required quality construction and in
quality assurance teams were assigned to check that all the design
specifications and codes were followed according to standards.
Planning and scheduling of al-ghazi
project on primavera P6
 Planning and scheduling on P6 was started at 4 December 2014 and
was successfully completed on 7 Jan 2015
 Budgeted total cost of project which we estimated by P6 is Rs 38907213
final year presentation revised
final year presentation revised
PROJECT S CURVE
Activity usage profile
What we Learnt?/Conclusion
 This construction management project gave us a better understanding about the site sense
and skills required to execute the task properly within limited cost & given time at the site.
 We have computed the bill of quantities and learnt about cost estimation of various
activities of the project. We worked out and understood the bar bending schedule of the project.
 We also performed the rate analysis to get familiar with cost evaluation of construction projects.
 We studied the effectiveness of jobsite safety program in a project success and observed that if safety
standards and precautions are strictly carried out on site then the chances of site accidents
can be avoided up to great extent as well time delays in the project as a result of accidents can also be
controlled.
 We also observed that quality assurance & control on site leads to reliable and economical
construction in many aspects.
 We evaluated productivity and duration of various activities and resources of our project.
 Planning and scheduling of all construction activities was performed on primavera p6e and learnt to
effectively utilize available resources for a various activities of project and control their cost using
primavera P6e
 After working on the management software Primavera P6e, We learnt the satisfactory level of software
towards handling and working and were able to understand the user friendliness of the software.
References
 [1] Rizwan U. Farooqui, Farrukh Arif and S.F.A. Rafeeqi (August
2008) (Safety Performance in Construction Industry of Pakistan,
First International Conference on Construction in Developing
Countries (ICCIDC–I). Advancing and Integrating Construction
Education, Research & Practice” August 4-5, 2008, Karachi,
Pakistan).
 [2] Pratibha Joshi,Promila Sharma ,T.C. Thakur and Amit Khatter
,IJAERS/Vol. I/ Issue III/April-June, 2012/30-34 (Safety in
Construction Line: Important Issue For Risk Identification and
Prevention), International Journal of Advanced Engineering
Research and Studies E-ISSN2249–8974. AdressDepartment of
Resource Management, G.B.Pant Univ. of Agri. & Tech.,
Pantnagar- 263145, Uttrakhand, India.
 [3] Zubair Ahmed Memon, Kanya Lal Khatri, and Allah Bux
Memon, Mehran University Research Journal of Engineering &
Technology, Volume 32, No. 2, April, 2013 [ISSN 02547821],(
Identifying the Critical Factors Affecting Safety Program
Performance for Construction Projects within Pakistan
Construction Industry)
 [4] Jafri, S.F., "Construction Safety and Promotion, Conceptual
Approach Based on the Labor Law of Pakistan", Journal of
Mechanical and Civil Engineering, Volume 1, No. 2, pp. 24-27, July-
August, 2012.
 [5] Syed Faraz Jafri1, Zubair Iqbal Rao2, Khawaja Sheeraz(Policy
Formulation of Construction Safety associated with Labor
Requirements - Substantial Approach for the Metropolitan City,
Karachi, Pakistan), IOSR Journal of Mechanical and Civil
Engineering (IOSRJMCE) ISSN : 2278-1684 Volume 1, Issue 1
(May-June 2012), PP 01-06 www.iosrjournals.org
 [6] ILOSafety and health in construction: An ILO code of practice
Geneva, International Labour Office, 1992/Code of practice/,
/Occupational safety/, /Occupational health/, /Construction
industry/.08.10.1 ISBN 92-2-107104-9
 http://tenrox.com/glossary/organization-breakdown-structure-obs/
 http://www.brighthubpm.com/templates-forms/2645-what-is-a-work-
breakdown-structure/#
 http://www.workbreakdownstructure.com/
 https://www.projectsmart.co.uk/project-management-methodology-
explained.php
 http://www.designingbuildings.co.uk/wiki/Risk_in_building_design_
and_construction.
 http://www.tandfonline.com/doi/pdf/10.1080/16111699.2006.9636126.
 http://www.scribd.com/mobile/doc/14565333/Risk-Assessment-and-
Management-inConstruction-Projects-Full-Thesis#scribd.
final year presentation revised

More Related Content

DOCX
Azhar civil engr(cv)
DOCX
updated CV
PDF
Arsalan CV final (December 2016)
PDF
CV 25-12-15 M.K.Narayana _ Seaport Technology & Engineering
DOCX
New CV Faisal Rauf
DOC
cv.dchand copy
DOCX
DHAKSHINA MURTHY RESUME normal
Azhar civil engr(cv)
updated CV
Arsalan CV final (December 2016)
CV 25-12-15 M.K.Narayana _ Seaport Technology & Engineering
New CV Faisal Rauf
cv.dchand copy
DHAKSHINA MURTHY RESUME normal

What's hot (20)

DOCX
RICKY - CV- 01-Apr-2015
PDF
CarlCharlie_FinalResume
PDF
CV 2016
DOC
Krishna Updated Resume
PDF
CV 15-08-16 M.K.Narayana _ Seaport Technology & Engineering -
DOC
CV SAIF UR REHMAN
DOCX
CV AMINUL 19-05-2015
DOC
Resume othman sulaiman
DOCX
Resume latest
DOC
B_Naik-CV1
DOCX
Civil Engineer
DOCX
Abi Ninan Joseph cv 10-01-2016
DOC
M.A.Iqbal C.V
DOC
Rohitkaps
DOC
RESUME_sushil__latest_
DOC
CV latestone
PDF
Nikhil T - coating inspector
PDF
Mohamad Seth Farabi - Resume
DOC
K. Srinivas Rao- CV - QS
DOCX
CV - NAZEER AHMED -Oversees
RICKY - CV- 01-Apr-2015
CarlCharlie_FinalResume
CV 2016
Krishna Updated Resume
CV 15-08-16 M.K.Narayana _ Seaport Technology & Engineering -
CV SAIF UR REHMAN
CV AMINUL 19-05-2015
Resume othman sulaiman
Resume latest
B_Naik-CV1
Civil Engineer
Abi Ninan Joseph cv 10-01-2016
M.A.Iqbal C.V
Rohitkaps
RESUME_sushil__latest_
CV latestone
Nikhil T - coating inspector
Mohamad Seth Farabi - Resume
K. Srinivas Rao- CV - QS
CV - NAZEER AHMED -Oversees
Ad

Viewers also liked (15)

PDF
How to choose a final year project ?
PDF
Final Project Presentation - COMPREHENSIVE ANALYSIS OF CORROSION ON THE INTER...
PPTX
Steps for making presentation of final year project
PPTX
Final review ppt project EFFECTIVENESS OF USING RECYCLED COARSE AGGREGATES IN...
PPTX
Project management using primavera project planner
PPTX
Presentation on Comparative study Of concrete using Recycled coarse aggregates
PPTX
Recycled concrete aggregate
PPTX
Green concrete
PPTX
Civil department presentation
PPT
Recycled Aggregate Concrete
PPTX
Use of Waste Materials As a replacement of Coarse Aggregate in Concrete Mix
PPTX
reuse and recycle of construction material
PPTX
Final Year Project Presentation
PPT
Final Year Project
PDF
Pdf primavera tutorial
How to choose a final year project ?
Final Project Presentation - COMPREHENSIVE ANALYSIS OF CORROSION ON THE INTER...
Steps for making presentation of final year project
Final review ppt project EFFECTIVENESS OF USING RECYCLED COARSE AGGREGATES IN...
Project management using primavera project planner
Presentation on Comparative study Of concrete using Recycled coarse aggregates
Recycled concrete aggregate
Green concrete
Civil department presentation
Recycled Aggregate Concrete
Use of Waste Materials As a replacement of Coarse Aggregate in Concrete Mix
reuse and recycle of construction material
Final Year Project Presentation
Final Year Project
Pdf primavera tutorial
Ad

Similar to final year presentation revised (20)

PPTX
Industrial Training On Construction At Simplex Infrastructures Ltd
PDF
Fawad Pervez Raja (PM)
PDF
Construction Planning of an Offshore Petroleum Platform
PDF
Success factors enhancing business performance of engineering procurement c...
PDF
Success factors enhancing business performance of engineering procurement
DOCX
Engr salman cv
PDF
Cv @Ali maruoof
PDF
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
PDF
CV - Sunil Sharma
RTF
Rakesh CV (4)
PDF
Analysis and Design of Commercial Building using ETABS
PDF
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
PDF
RESUME PIPING SUPERVISOR
DOCX
Civil Engineer
PDF
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
PDF
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
PDF
Eng. Whameed-CV
DOCX
John Okusolubo Resume 2015
PDF
A Framework to optimize Construction Site Layout Planning
PDF
Element of Cost overrun and Delay in Construction: A Review
Industrial Training On Construction At Simplex Infrastructures Ltd
Fawad Pervez Raja (PM)
Construction Planning of an Offshore Petroleum Platform
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of engineering procurement
Engr salman cv
Cv @Ali maruoof
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
CV - Sunil Sharma
Rakesh CV (4)
Analysis and Design of Commercial Building using ETABS
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
RESUME PIPING SUPERVISOR
Civil Engineer
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
Eng. Whameed-CV
John Okusolubo Resume 2015
A Framework to optimize Construction Site Layout Planning
Element of Cost overrun and Delay in Construction: A Review

final year presentation revised

  • 3. PROJECT ON CONSTRUCTION MANAGEMENT GROUP MEMBERS 1. EHSANULLAH (001) 2. QAZI NABEEL (144) 3. ANAS AHMED ABIDI(080) 4. ZUHAIR NADEEM(072) 5. MUHAMMAD JAWAD HASSAN(117) 6. MUHAMMAD ARIF SIDDIQUE KHAN(043) 7. AGHA BABAR ALI(078) PROJECT INTERNAL (ENGR. SYED FARAZ JAFRI) PROJECT EXTERNAL (ENGR.UMAR FAROOQ) PROJECT INTERNAL & EXTERNAL
  • 4. PROJECT DETAILS CLIENT AL-GHAZI TRACTORS DESIGN CONSULTANT NES-PAK. MAIN CONTRACTOR TAHIR ENTERPRISES ARCHITECT NES-PAK LOCATION DEFENCE PHASE-1 PLOT 102-B TOTAL COVERED AREA 4240 SQ FT SRART DATE 31 DECEMBER 2013 EXPECTED FINISH DATE 31 MAY 2015 DURATION 15 MONTHS PURPOSE OFFICE BUILDING PARKING AREA 1 BASEMENT (FOR 22 CARS) NUMBER OF STORIES 2 BASEMENT+ 4 FLOORS
  • 5. PROJECT OBJECTIVES  To evaluate working drawings and prepare BOQ  Preparation of bar bending schedule  Perform rate analysis  To evaluate productivity and duration of various activities  To study the effectiveness of site safety and quality in a success of construction project  To identify causes of delay and disputes on construction project.  Planning and scheduling of all construction activities on primavera p6e.
  • 6. PROJECT SCOPE  To provide overall co-ordination and project team management.  To perform project budgeting, scheduling, cost accounting and reporting.  To ensure the quality standard keeping in view the cost.  Managing time within the whole project.  Efficient use of computer softwares.  Construction planning and resource allocation and optimization.  To get familiar with responsibilities and tasks of a civil engineer.  To observe the site safety.
  • 14. Principles of Management  Division of work  Discipline  Unity of command  Unity in Direction  Centralization of power to do work  Change individual interest into organizational interest  Authority and responsibility should always be together  Equality, stability and motivation
  • 15. 5M’s of Management In the management literature, five M’s of management called as:  Money  Material  Man power  Machinery  Methodology
  • 17. PROJECT MILESTONES We have successfully achieved the following milestones  Evaluated working drawings.  Prepared bar bending schedule and BOQ.  Performed rate analysis.  Evaluated productivity and duration of various activities.  Studied the effectiveness of site safety and quality in a success of construction project.  Identify causes of delay and disputes on construction project.  Planned and scheduled all construction activities on primavera p6e.
  • 18. Selection Of Project (WHY?) We have selected the project due to the following reasons.  First of all the reason we selected the project in construction management was due to our interest and better understanding provided by teachers about the management in the field of civil engineering.  The topic which we have selected for final year project show our interest about cost evaluation of construction project and how to control project cost through better resource allocation & optimization and also to get awareness about job site safety and quality issues related to construction project.
  • 19. Site Visit And Data Collection Frequently visited site for  Collection of data such as working drawings.  Observing Different construction activities on site.  Discussing problems with external.  Getting awareness about sequence of work required to plan and schedule the project.  To observe and understand safety and quality parameters.
  • 20. Preparation and Submission of Synopsis Synopsis was submitted to our internal in the month of February 2015 which included  Project title  Project details  Project technical information  3c’s of project  Objectives and scope of project  Time frame
  • 21. Rate Analysis and Workout Productivity  All Rates and productivity (except productivity of machinery) are taken from NES-PAK Contract section 12th floor PNIC Building opp. Shahra- e-Faisal, with cooperation of GM of Contract section Engr. Nasir Jamal.  Some Rates and productivity were provided by our Site supervisor of AL Ghazi Office Building Associate Engr. MR Fahad  Productivity of machinery was found from internet by pdf manuals of manufacturers of respective machineries.
  • 22. Preparation Of Bar bending schedule and BOQ  We prepared BBS and BOQ by following working drawings (Ground Floor, 1st Floor, 2nd Floor, 3rd Floor and Basement 1) S.# WBS NAME Shuttering (sq. ft) Volume (Cu. Ft) Reinforcement (kg) Plastering (sq. ft) 1 Beams 3125 1157 3783 2702 2 Columns 877.1 325.68 1641.6 877.1 3 Walls 8177 4 Slab 4172.1 3184.3 5700 9074.8 Basement 2 Activity Concreting Reinforcement (Kg) Plastering Blocks Sand (cft.) Cement (bags) Crush (Cft.) Sand (cft) Cement (bags) Beams 496 cft 199 bags 992cft 3783 kgs 135 cft 27 bags Columns 207.5 83 415 2280 64.3 cft 13 Slabs 1365 546 2730 5700 461 92 Walls 625.4 125 9875
  • 23. Substructure work S.# WBS Name Shuttering Volume Reinforcement 1 Pile 88970(Excavation) 5242.21 (pouring) 22500 kg 2 Back Filling 10000 cft 3 Pile Cap 5164 13700 18650 kg 4 Column up to Plinth 785 cft 4270 kg
  • 24. Study and observation of site safety and quality  The biggest concern which we observed at the site that for engineers and supervisors personal protection equipment's (PPE ) were given and other safety precautions were followed but for the laborers the equipment's (PPE) was not properly provided due various delays occurred because of accidents.  Through sites visits we observed that proper quality control procedures were implemented to get the required quality construction and in quality assurance teams were assigned to check that all the design specifications and codes were followed according to standards.
  • 25. Planning and scheduling of al-ghazi project on primavera P6  Planning and scheduling on P6 was started at 4 December 2014 and was successfully completed on 7 Jan 2015  Budgeted total cost of project which we estimated by P6 is Rs 38907213
  • 30. What we Learnt?/Conclusion  This construction management project gave us a better understanding about the site sense and skills required to execute the task properly within limited cost & given time at the site.  We have computed the bill of quantities and learnt about cost estimation of various activities of the project. We worked out and understood the bar bending schedule of the project.  We also performed the rate analysis to get familiar with cost evaluation of construction projects.  We studied the effectiveness of jobsite safety program in a project success and observed that if safety standards and precautions are strictly carried out on site then the chances of site accidents can be avoided up to great extent as well time delays in the project as a result of accidents can also be controlled.  We also observed that quality assurance & control on site leads to reliable and economical construction in many aspects.  We evaluated productivity and duration of various activities and resources of our project.  Planning and scheduling of all construction activities was performed on primavera p6e and learnt to effectively utilize available resources for a various activities of project and control their cost using primavera P6e  After working on the management software Primavera P6e, We learnt the satisfactory level of software towards handling and working and were able to understand the user friendliness of the software.
  • 31. References  [1] Rizwan U. Farooqui, Farrukh Arif and S.F.A. Rafeeqi (August 2008) (Safety Performance in Construction Industry of Pakistan, First International Conference on Construction in Developing Countries (ICCIDC–I). Advancing and Integrating Construction Education, Research & Practice” August 4-5, 2008, Karachi, Pakistan).  [2] Pratibha Joshi,Promila Sharma ,T.C. Thakur and Amit Khatter ,IJAERS/Vol. I/ Issue III/April-June, 2012/30-34 (Safety in Construction Line: Important Issue For Risk Identification and Prevention), International Journal of Advanced Engineering Research and Studies E-ISSN2249–8974. AdressDepartment of Resource Management, G.B.Pant Univ. of Agri. & Tech., Pantnagar- 263145, Uttrakhand, India.  [3] Zubair Ahmed Memon, Kanya Lal Khatri, and Allah Bux Memon, Mehran University Research Journal of Engineering & Technology, Volume 32, No. 2, April, 2013 [ISSN 02547821],( Identifying the Critical Factors Affecting Safety Program Performance for Construction Projects within Pakistan Construction Industry)  [4] Jafri, S.F., "Construction Safety and Promotion, Conceptual Approach Based on the Labor Law of Pakistan", Journal of Mechanical and Civil Engineering, Volume 1, No. 2, pp. 24-27, July- August, 2012.  [5] Syed Faraz Jafri1, Zubair Iqbal Rao2, Khawaja Sheeraz(Policy Formulation of Construction Safety associated with Labor Requirements - Substantial Approach for the Metropolitan City, Karachi, Pakistan), IOSR Journal of Mechanical and Civil Engineering (IOSRJMCE) ISSN : 2278-1684 Volume 1, Issue 1 (May-June 2012), PP 01-06 www.iosrjournals.org  [6] ILOSafety and health in construction: An ILO code of practice Geneva, International Labour Office, 1992/Code of practice/, /Occupational safety/, /Occupational health/, /Construction industry/.08.10.1 ISBN 92-2-107104-9  http://tenrox.com/glossary/organization-breakdown-structure-obs/  http://www.brighthubpm.com/templates-forms/2645-what-is-a-work- breakdown-structure/#  http://www.workbreakdownstructure.com/  https://www.projectsmart.co.uk/project-management-methodology- explained.php  http://www.designingbuildings.co.uk/wiki/Risk_in_building_design_ and_construction.  http://www.tandfonline.com/doi/pdf/10.1080/16111699.2006.9636126.  http://www.scribd.com/mobile/doc/14565333/Risk-Assessment-and- Management-inConstruction-Projects-Full-Thesis#scribd.