CENG 424-Engineering Hydrology
Scientists discover things. Engineers make them true.
EBRAHIM A. OMAR
Department of Civil Engineering
College of Engineering and Computing-USM Page 1
ASSIGNMENT in FLOOD ROUTING
Reporter: Robelie Mae Gilapon
1. Differentiate Stream flow Routing from Reservoir Routing.
Answer:
Reservoir Routing is a process of determining the reservoir stage (referring to the
height/elevation of water surface above a fixed datum), storage volume of the outflow
hydrograph provided that the inflow hydrograph of the reservoir is known. The solution of
this routing involves the use of capacity curves such as ‘storage vs. pool elevation’ and
‘outflow rate vs. pool elevation’.
Meanwhile, stream flow routing involves the storage in the reach in which it
comprises two parts-prism storage and wedge storage since the water surface is not uniform
during floods. This actually depends on both the inflow and outflow where prism storage
depends on the outflow alone and wedge storage depends on the difference of inflow and
outflow. Its routing calculations is aided by the use of Muskingum Method.
2. The inflow hydrograph readings for a stream reach are given below for which
the Muskingum coefficients K= 30 hrs and x= 0.20 apply. Route the flood
through the reach and determine the reduction in peak and the time of peak of
outflow. Outflow at the beginning of the flood may be taken as the same as
inflow.
Answer:
Given:
K=30 hours
X=0.20
Routing period is taken from the inflow hydrograph readings to be t=12 hours.
This problem is manipulated through the use of Muskingum Method in which the
fundamental formula is 𝑶 𝟐 = 𝑪 𝟎 𝑰 𝟐 + 𝑪 𝟏 𝑰 𝟏 + 𝑪 𝟐 𝑰 𝟏.
CENG 424-Engineering Hydrology
Scientists discover things. Engineers make them true.
EBRAHIM A. OMAR
Department of Civil Engineering
College of Engineering and Computing-USM Page 2
Basically, we compute first the C0 , C1 , and C2 using their respective formulae.
𝐶0 =
𝐾𝑥−0.5𝑡
𝐾−𝐾𝑥+0.5𝑡
𝐶1 =
𝐾𝑥+0.5𝑡
𝐾−𝐾𝑥+0.5𝑡
𝐶2 =
𝐾−𝐾𝑥−0.5𝑡
𝐾−𝐾𝑥+0.5𝑡
Substituting the available data,
𝐶0 =
30(0.2)−0.5(12)
30−30(0.2)+0.5(12)
= 0
𝐶1 =
30(0.2)+0.5(12)
30−30(0.2)+0.5(12)
= 0.40
𝐶2 =
30−30(0.2)−0.5(12)
30−30(0.2)+0.5(12)
= 0.60
To check: C0 + C1 + C2 =1
0+0.40+0.60=1
In the Table below, I1 is known from the inflow hydrograph and O1 is taken as I1 at the beginning of
the flood.
Tabular Computation:
Time(hr) Inflow(I), cumec 0.40I1,cumec 0.60O1, cumec Outflow(O), cumec
0 15 -- -- 15.00
12 16 6.0 9.00 15.00
24 31 6.4 9.00 15.40
36 96 12.4 9.24 21.64
48 121 38.4 12.98 51.38
60 102 48.4 30.83 79.23
72 85 40.8 47.54 88.34
84 70 34.0 53.00 87.00
96 57 28.0 52.20 80.20
108 47 22.8 48.12 70.92
120 39 18.8 42.55 61.35
132 32 15.6 36.81 52.41
144 28 12.8 31.45 44.25
156 24 11.2 26.55 37.75
168 22 9.6 22.65 32.25
180 20 8.8 19.35 28.15
192 19 8.0 16.89 24.89
204 18 7.6 14.93 22.53
216 17 7.2 13.52 20.72
228 16 6.8 12.43 19.23
240 15 6.4 11.54 17.94
Answers are reflected in the graph below.
CENG 424-Engineering Hydrology
Scientists discover things. Engineers make them true.
EBRAHIM A. OMAR
Department of Civil Engineering
College of Engineering and Computing-USM Page 3

More Related Content

PDF
design of weirs
PDF
PDF
RESERVOIR SEDIMENTATION
PDF
Unit 12 River training work.pdf
PDF
Water Resources Engineering - Question Bank (Subjective)
PDF
Open channel design
PDF
Chapter 3 channel design
PDF
Chapter 6 design of irrigation channel1
design of weirs
RESERVOIR SEDIMENTATION
Unit 12 River training work.pdf
Water Resources Engineering - Question Bank (Subjective)
Open channel design
Chapter 3 channel design
Chapter 6 design of irrigation channel1

What's hot (20)

PPT
Flood estimation
PPTX
Losses IN Canals
PDF
Gravity dam stability analysis
PPTX
Design of gravity dams
PPTX
Reservoir Planning
PPTX
economic channel section
PDF
Chapter 7 spillway and energy dissipators
PPTX
Canal Regulation & Cross Drainage Works
PPTX
Spillway and its types
PPTX
Hyetograph and hydrograph analysis
PDF
050218 chapter 7 spillways and energy dissipators
PPT
Hydrology (Estimation of peak flood discharge)
PPTX
Canal headworks
PPT
Kennedy's and laccy's theory
PDF
Design of Hydraulic Structures
PPTX
Stream Gauging
PDF
Presentation 78 flood routing.pdf
PPTX
Ppt on terminology of ground water
PPTX
Reservoir capacity
PPTX
Open Channel Flow
Flood estimation
Losses IN Canals
Gravity dam stability analysis
Design of gravity dams
Reservoir Planning
economic channel section
Chapter 7 spillway and energy dissipators
Canal Regulation & Cross Drainage Works
Spillway and its types
Hyetograph and hydrograph analysis
050218 chapter 7 spillways and energy dissipators
Hydrology (Estimation of peak flood discharge)
Canal headworks
Kennedy's and laccy's theory
Design of Hydraulic Structures
Stream Gauging
Presentation 78 flood routing.pdf
Ppt on terminology of ground water
Reservoir capacity
Open Channel Flow
Ad

Viewers also liked (12)

PDF
economy Chapter2_by louy Al hami
PDF
economy Chapter7_by louy Al hami
PDF
Surface runoff
PDF
economy Chapter6 2011_by louy Al hami
PDF
hydro chapter_11_hydrology_by louy al hami
PDF
hydro chapter_7_groundwater_by louy Al hami
PDF
hydro chapter_4_b_pipe_network_by louy Al hami
PPT
PPTX
Flood routing
PDF
hydro chapter_4_a_by louy al hami
PDF
hydro chapter_5_a_by louy Al hami
PDF
hydro chapter_3 by louy Al hami
economy Chapter2_by louy Al hami
economy Chapter7_by louy Al hami
Surface runoff
economy Chapter6 2011_by louy Al hami
hydro chapter_11_hydrology_by louy al hami
hydro chapter_7_groundwater_by louy Al hami
hydro chapter_4_b_pipe_network_by louy Al hami
Flood routing
hydro chapter_4_a_by louy al hami
hydro chapter_5_a_by louy Al hami
hydro chapter_3 by louy Al hami
Ad

Similar to Flood Routing using Muskingum Method (20)

PDF
Hydraulic Routing.pdf ndeuofeufoehufheuhf
 
PPT
Flood Routing.ppt:flood routing and control
PDF
13_sp20_routing-revised routing-revised.pdf
PPTX
Presentation aboout flood routing
PPTX
Chapter-7 Flood routing notes pdf (1).pptx
PPTX
2150602 hwre 150113106007-008 (HYDROLOGY & WATER RESOURCE ENGINEERING)
PPTX
L 10 e selecting the appropriate routing technique
PPTX
4_HYDROLOGY.pptx fdfjyf6r6 uyguydtdhtytdys
 
PPTX
Hydrology CEP Presentation.pptx we perform different type of calculation for ...
PDF
1 ijsrms 02516 (1)
PPTX
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
PPTX
groundwater flood routing presentationhazard.pptx
PDF
Unit 5 Diapo 2PAO2024 Part2hidroaaaa.pdf
PPTX
L 10 d muskingum cunge routing method
PDF
Water Resources Engineering - Question Bank (objective)
PDF
15005_Hydrology
PDF
12-runoffprocesses.pdf
PPTX
GROUP10_CHAPTER9.6-9.7.pptx
Hydraulic Routing.pdf ndeuofeufoehufheuhf
 
Flood Routing.ppt:flood routing and control
13_sp20_routing-revised routing-revised.pdf
Presentation aboout flood routing
Chapter-7 Flood routing notes pdf (1).pptx
2150602 hwre 150113106007-008 (HYDROLOGY & WATER RESOURCE ENGINEERING)
L 10 e selecting the appropriate routing technique
4_HYDROLOGY.pptx fdfjyf6r6 uyguydtdhtytdys
 
Hydrology CEP Presentation.pptx we perform different type of calculation for ...
1 ijsrms 02516 (1)
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
groundwater flood routing presentationhazard.pptx
Unit 5 Diapo 2PAO2024 Part2hidroaaaa.pdf
L 10 d muskingum cunge routing method
Water Resources Engineering - Question Bank (objective)
15005_Hydrology
12-runoffprocesses.pdf
GROUP10_CHAPTER9.6-9.7.pptx

Recently uploaded (20)

PPTX
neck nodes and dissection types and lymph nodes levels
PPTX
Protein & Amino Acid Structures Levels of protein structure (primary, seconda...
PDF
Phytochemical Investigation of Miliusa longipes.pdf
PPTX
Introduction to Cardiovascular system_structure and functions-1
PPTX
TOTAL hIP ARTHROPLASTY Presentation.pptx
PPT
protein biochemistry.ppt for university classes
PDF
An interstellar mission to test astrophysical black holes
PPTX
cpcsea ppt.pptxssssssssssssssjjdjdndndddd
PPTX
7. General Toxicologyfor clinical phrmacy.pptx
PDF
CAPERS-LRD-z9:AGas-enshroudedLittleRedDotHostingaBroad-lineActive GalacticNuc...
PPTX
famous lake in india and its disturibution and importance
PPTX
INTRODUCTION TO EVS | Concept of sustainability
PDF
Biophysics 2.pdffffffffffffffffffffffffff
PDF
bbec55_b34400a7914c42429908233dbd381773.pdf
PPTX
Cell Membrane: Structure, Composition & Functions
PPTX
ECG_Course_Presentation د.محمد صقران ppt
PDF
AlphaEarth Foundations and the Satellite Embedding dataset
PDF
SEHH2274 Organic Chemistry Notes 1 Structure and Bonding.pdf
PDF
Placing the Near-Earth Object Impact Probability in Context
PPTX
ognitive-behavioral therapy, mindfulness-based approaches, coping skills trai...
neck nodes and dissection types and lymph nodes levels
Protein & Amino Acid Structures Levels of protein structure (primary, seconda...
Phytochemical Investigation of Miliusa longipes.pdf
Introduction to Cardiovascular system_structure and functions-1
TOTAL hIP ARTHROPLASTY Presentation.pptx
protein biochemistry.ppt for university classes
An interstellar mission to test astrophysical black holes
cpcsea ppt.pptxssssssssssssssjjdjdndndddd
7. General Toxicologyfor clinical phrmacy.pptx
CAPERS-LRD-z9:AGas-enshroudedLittleRedDotHostingaBroad-lineActive GalacticNuc...
famous lake in india and its disturibution and importance
INTRODUCTION TO EVS | Concept of sustainability
Biophysics 2.pdffffffffffffffffffffffffff
bbec55_b34400a7914c42429908233dbd381773.pdf
Cell Membrane: Structure, Composition & Functions
ECG_Course_Presentation د.محمد صقران ppt
AlphaEarth Foundations and the Satellite Embedding dataset
SEHH2274 Organic Chemistry Notes 1 Structure and Bonding.pdf
Placing the Near-Earth Object Impact Probability in Context
ognitive-behavioral therapy, mindfulness-based approaches, coping skills trai...

Flood Routing using Muskingum Method

  • 1. CENG 424-Engineering Hydrology Scientists discover things. Engineers make them true. EBRAHIM A. OMAR Department of Civil Engineering College of Engineering and Computing-USM Page 1 ASSIGNMENT in FLOOD ROUTING Reporter: Robelie Mae Gilapon 1. Differentiate Stream flow Routing from Reservoir Routing. Answer: Reservoir Routing is a process of determining the reservoir stage (referring to the height/elevation of water surface above a fixed datum), storage volume of the outflow hydrograph provided that the inflow hydrograph of the reservoir is known. The solution of this routing involves the use of capacity curves such as ‘storage vs. pool elevation’ and ‘outflow rate vs. pool elevation’. Meanwhile, stream flow routing involves the storage in the reach in which it comprises two parts-prism storage and wedge storage since the water surface is not uniform during floods. This actually depends on both the inflow and outflow where prism storage depends on the outflow alone and wedge storage depends on the difference of inflow and outflow. Its routing calculations is aided by the use of Muskingum Method. 2. The inflow hydrograph readings for a stream reach are given below for which the Muskingum coefficients K= 30 hrs and x= 0.20 apply. Route the flood through the reach and determine the reduction in peak and the time of peak of outflow. Outflow at the beginning of the flood may be taken as the same as inflow. Answer: Given: K=30 hours X=0.20 Routing period is taken from the inflow hydrograph readings to be t=12 hours. This problem is manipulated through the use of Muskingum Method in which the fundamental formula is 𝑶 𝟐 = 𝑪 𝟎 𝑰 𝟐 + 𝑪 𝟏 𝑰 𝟏 + 𝑪 𝟐 𝑰 𝟏.
  • 2. CENG 424-Engineering Hydrology Scientists discover things. Engineers make them true. EBRAHIM A. OMAR Department of Civil Engineering College of Engineering and Computing-USM Page 2 Basically, we compute first the C0 , C1 , and C2 using their respective formulae. 𝐶0 = 𝐾𝑥−0.5𝑡 𝐾−𝐾𝑥+0.5𝑡 𝐶1 = 𝐾𝑥+0.5𝑡 𝐾−𝐾𝑥+0.5𝑡 𝐶2 = 𝐾−𝐾𝑥−0.5𝑡 𝐾−𝐾𝑥+0.5𝑡 Substituting the available data, 𝐶0 = 30(0.2)−0.5(12) 30−30(0.2)+0.5(12) = 0 𝐶1 = 30(0.2)+0.5(12) 30−30(0.2)+0.5(12) = 0.40 𝐶2 = 30−30(0.2)−0.5(12) 30−30(0.2)+0.5(12) = 0.60 To check: C0 + C1 + C2 =1 0+0.40+0.60=1 In the Table below, I1 is known from the inflow hydrograph and O1 is taken as I1 at the beginning of the flood. Tabular Computation: Time(hr) Inflow(I), cumec 0.40I1,cumec 0.60O1, cumec Outflow(O), cumec 0 15 -- -- 15.00 12 16 6.0 9.00 15.00 24 31 6.4 9.00 15.40 36 96 12.4 9.24 21.64 48 121 38.4 12.98 51.38 60 102 48.4 30.83 79.23 72 85 40.8 47.54 88.34 84 70 34.0 53.00 87.00 96 57 28.0 52.20 80.20 108 47 22.8 48.12 70.92 120 39 18.8 42.55 61.35 132 32 15.6 36.81 52.41 144 28 12.8 31.45 44.25 156 24 11.2 26.55 37.75 168 22 9.6 22.65 32.25 180 20 8.8 19.35 28.15 192 19 8.0 16.89 24.89 204 18 7.6 14.93 22.53 216 17 7.2 13.52 20.72 228 16 6.8 12.43 19.23 240 15 6.4 11.54 17.94 Answers are reflected in the graph below.
  • 3. CENG 424-Engineering Hydrology Scientists discover things. Engineers make them true. EBRAHIM A. OMAR Department of Civil Engineering College of Engineering and Computing-USM Page 3