Part 1: 
Team velocity is 30 points* 
Sprint length is two weeks** 
How many Sprints will it take to complete Product Backlog? 
Part 2: 
What is the duration to complete? 
Part 3: 
What is the cost if a two week Sprint has a total resource rate of $30,000? 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
Forecasting Total Cost and Duration of Product Backlog 
* If team velocity is not know you can extrapolate it by conducting a pseudo Sprint Planning session 
**Team predetermines Sprint length –for the sake of this example I have select to use a two week Sprint 
Copyright © 2014 Russell Pannone. All rights reserved.
Part 1: 
Team velocity is 30 points 
Sprint length is two weeks 
How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) 
Part 2: 
What is the timeline to complete? 
Part 3: 
What is the cost if a two week Sprint has a total resource rate of $30,000? 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
Forecasting Total Cost and Duration of Product Backlog 
1 
2 
3 
4 
5 
Copyright © 2014 Russell Pannone. All rights reserved.
Part 1: 
Team velocity is 30 points 
Sprint length is two weeks 
How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) 
Part 2: 
What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) 
Part 3: 
What is the cost if a two week Sprint has a total resource rate of $30,000? 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
Forecasting Total Cost and Duration of Product Backlog 
Copyright © 2014 Russell Pannone. All rights reserved.
Part 1: 
Team velocity is 30 points 
Sprint length is two weeks 
How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) 
Part 2: 
What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) 
Part 3: 
What is the total cost if a two week Sprint has a total resource rate of $30,000? Answer: $300,000 ( 10 Sprints x $30,000 = $300,000.00) 
Product Backlog 
Story 
Size 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
12 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
3 
As a … I want to…So that….. 
2 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
8 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
5 
As a … I want to…So that….. 
20 
As a … I want to…So that….. 
20 
ForcastingTotal Cost and Duration of Product Backlog 
Copyright © 2014 Russell Pannone. All rights reserved.
Forecasting Total Cost and Duration of Product Backlog 
Copyright © 2014 Russell Pannone. All rights reserved. 
Forecast based on calculations from previous slides = 
•Duration to complete = 10 weeks 
•Cost to complete = $300,000.00 
Because of the relevance of the cone-of-uncertainty I would change forecast to: 
Duration to complete = 14 weeks 
Cost to complete = $360,000.00

More Related Content

PDF
Agile and Lean Business Proposition
PDF
Agile and lean product development the fundamentals
PDF
3isystem fase3
PPSX
Bloque Pacie
DOC
6. introducción
PDF
Proyecto completo
PDF
Diseño de una estrategia para la diseminación de la información...
PDF
Antecedentes LOE 2009 Venezuelsa
Agile and Lean Business Proposition
Agile and lean product development the fundamentals
3isystem fase3
Bloque Pacie
6. introducción
Proyecto completo
Diseño de una estrategia para la diseminación de la información...
Antecedentes LOE 2009 Venezuelsa

Viewers also liked (16)

PDF
Diseño de una estrategia para la búsqueda de informacion.
PDF
Haz que la realidad cobre vida
PDF
Normalizing agile and lean product development and aim
PPT
Modelo Educativo Transformador de Vidas
PPTX
Agile product development for the business
PDF
What is an agile coach
PDF
Lean Agile and Respect for People
PDF
Megatendencias Sociales: Ambientes Laborales Amigables para Personas con Nece...
PDF
Risk guideline
PDF
How To Know Your Stories Are At The Right Level Of Detail
PDF
AcceptCriteria_TestCases_TestScripts
PDF
Project Management And Being Agile
PPT
Curso En LíNea Trabajo Colaborativo
PDF
Movilización de prácticas educativas abiertas (PEA) en ambientes de aprendiz...
PDF
Agile-Lean requirements position statement
PDF
Agile Business Driven Development
Diseño de una estrategia para la búsqueda de informacion.
Haz que la realidad cobre vida
Normalizing agile and lean product development and aim
Modelo Educativo Transformador de Vidas
Agile product development for the business
What is an agile coach
Lean Agile and Respect for People
Megatendencias Sociales: Ambientes Laborales Amigables para Personas con Nece...
Risk guideline
How To Know Your Stories Are At The Right Level Of Detail
AcceptCriteria_TestCases_TestScripts
Project Management And Being Agile
Curso En LíNea Trabajo Colaborativo
Movilización de prácticas educativas abiertas (PEA) en ambientes de aprendiz...
Agile-Lean requirements position statement
Agile Business Driven Development
Ad

Similar to Forecasting total cost and duration of Product Backlog (20)

PPTX
Agile Budgeting and Forecasting
PPTX
Benzne Webinar : Product Discovery - Where Agile & Design Thinking meet!
PDF
Scrum and-xp-from-the-trenches 02 sprint planning
PDF
Minimum viable product_to_deliver_business_value_v0.4
PPTX
Keeping Product Backlog Healthy
PDF
Agile = No Planning = Bull$h!t
PDF
Agile Project Management and Scrum Introduction
PDF
Agile Estimation
PPTX
Scrum & Sprint Planning.pptx
PPTX
Introduction to backlog grooming in Agile
PPTX
Customized Scrum
PDF
Comp-1807-week5-abcbahsbchsa12345@ba.pdf
PDF
Minimum viable product to delivery business value
PDF
Synerzip Agile Cheat Sheet
PDF
Scrum and-xp-from-the-trenches 01 intro & backlog
PDF
Introduction to Agile Project Management and Scrum
PDF
Introduction to Agile Project Management and Scrum
PPTX
Notes to Myself: Product Backlog
PPT
Agile Estimation - By V. Lee Henson
PPTX
SCRUM Estimation
Agile Budgeting and Forecasting
Benzne Webinar : Product Discovery - Where Agile & Design Thinking meet!
Scrum and-xp-from-the-trenches 02 sprint planning
Minimum viable product_to_deliver_business_value_v0.4
Keeping Product Backlog Healthy
Agile = No Planning = Bull$h!t
Agile Project Management and Scrum Introduction
Agile Estimation
Scrum & Sprint Planning.pptx
Introduction to backlog grooming in Agile
Customized Scrum
Comp-1807-week5-abcbahsbchsa12345@ba.pdf
Minimum viable product to delivery business value
Synerzip Agile Cheat Sheet
Scrum and-xp-from-the-trenches 01 intro & backlog
Introduction to Agile Project Management and Scrum
Introduction to Agile Project Management and Scrum
Notes to Myself: Product Backlog
Agile Estimation - By V. Lee Henson
SCRUM Estimation
Ad

More from Russell Pannone (11)

PDF
Agile Lean Kanban in the Real World - A Case Study
PDF
Agile Lean Kanban in the real world
PDF
The Role of Quality Assurance in the World of Agile Development and Scrum
PDF
Agile & Lean & Kanban in the Real World - A Case Study
PDF
Agile needs resurgence of visual modeling
PDF
5 Levels of Agile Planning Explained Simply
PDF
Product backlog stories_acceptancecriteria_size_priority
PDF
Agile Lean Scrum ITIL V2
PDF
Creating A Product Backlog
PDF
Conducting An Agile Retrospective
PDF
The World of Agile/Lean Product Development and Delivery with Scrum Made Easy
Agile Lean Kanban in the Real World - A Case Study
Agile Lean Kanban in the real world
The Role of Quality Assurance in the World of Agile Development and Scrum
Agile & Lean & Kanban in the Real World - A Case Study
Agile needs resurgence of visual modeling
5 Levels of Agile Planning Explained Simply
Product backlog stories_acceptancecriteria_size_priority
Agile Lean Scrum ITIL V2
Creating A Product Backlog
Conducting An Agile Retrospective
The World of Agile/Lean Product Development and Delivery with Scrum Made Easy

Recently uploaded (20)

PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Modernizing your data center with Dell and AMD
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
cuic standard and advanced reporting.pdf
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
Approach and Philosophy of On baking technology
PDF
Network Security Unit 5.pdf for BCA BBA.
PPT
Teaching material agriculture food technology
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
A Presentation on Artificial Intelligence
PDF
CIFDAQ's Market Insight: SEC Turns Pro Crypto
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
20250228 LYD VKU AI Blended-Learning.pptx
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Modernizing your data center with Dell and AMD
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
cuic standard and advanced reporting.pdf
Diabetes mellitus diagnosis method based random forest with bat algorithm
Dropbox Q2 2025 Financial Results & Investor Presentation
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Mobile App Security Testing_ A Comprehensive Guide.pdf
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
Approach and Philosophy of On baking technology
Network Security Unit 5.pdf for BCA BBA.
Teaching material agriculture food technology
Building Integrated photovoltaic BIPV_UPV.pdf
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
Encapsulation_ Review paper, used for researhc scholars
A Presentation on Artificial Intelligence
CIFDAQ's Market Insight: SEC Turns Pro Crypto

Forecasting total cost and duration of Product Backlog

  • 1. Part 1: Team velocity is 30 points* Sprint length is two weeks** How many Sprints will it take to complete Product Backlog? Part 2: What is the duration to complete? Part 3: What is the cost if a two week Sprint has a total resource rate of $30,000? Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 Forecasting Total Cost and Duration of Product Backlog * If team velocity is not know you can extrapolate it by conducting a pseudo Sprint Planning session **Team predetermines Sprint length –for the sake of this example I have select to use a two week Sprint Copyright © 2014 Russell Pannone. All rights reserved.
  • 2. Part 1: Team velocity is 30 points Sprint length is two weeks How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) Part 2: What is the timeline to complete? Part 3: What is the cost if a two week Sprint has a total resource rate of $30,000? Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 Forecasting Total Cost and Duration of Product Backlog 1 2 3 4 5 Copyright © 2014 Russell Pannone. All rights reserved.
  • 3. Part 1: Team velocity is 30 points Sprint length is two weeks How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) Part 2: What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) Part 3: What is the cost if a two week Sprint has a total resource rate of $30,000? Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 Forecasting Total Cost and Duration of Product Backlog Copyright © 2014 Russell Pannone. All rights reserved.
  • 4. Part 1: Team velocity is 30 points Sprint length is two weeks How many Sprints will it take to complete Product Backlog? Answer: 5 (based on Velocity of 30 points) Part 2: What is the duration to complete? Answer: 10 weeks (5 (Sprints) x 2 (weeks each Sprint) = 10) Part 3: What is the total cost if a two week Sprint has a total resource rate of $30,000? Answer: $300,000 ( 10 Sprints x $30,000 = $300,000.00) Product Backlog Story Size As a … I want to…So that….. 3 As a … I want to…So that….. 8 As a … I want to…So that….. 2 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 2 As a … I want to…So that….. 2 As a … I want to…So that….. 12 As a … I want to…So that….. 3 As a … I want to…So that….. 3 As a … I want to…So that….. 2 As a … I want to…So that….. 8 As a … I want to…So that….. 8 As a … I want to…So that….. 5 As a … I want to…So that….. 8 As a … I want to…So that….. 20 As a … I want to…So that….. 20 As a … I want to…So that….. 5 As a … I want to…So that….. 20 As a … I want to…So that….. 20 ForcastingTotal Cost and Duration of Product Backlog Copyright © 2014 Russell Pannone. All rights reserved.
  • 5. Forecasting Total Cost and Duration of Product Backlog Copyright © 2014 Russell Pannone. All rights reserved. Forecast based on calculations from previous slides = •Duration to complete = 10 weeks •Cost to complete = $300,000.00 Because of the relevance of the cone-of-uncertainty I would change forecast to: Duration to complete = 14 weeks Cost to complete = $360,000.00