PMP EXAM
SAMPLE Q & A
Two team members are arguing over how to organize the work packages in the work breakdown
structure (WBS). One says the work packages should be arranged in the order the work is planned to
be carried out, while the other insists the order of the work packages in the WBS does not matter.
The two ask the project manager for advice.
What is the project manager's best response?
A. Work is decomposed and sequenced in the Define Activities process.
B. Any approach is good as long as the team members avoid the conflict.
C. The chronological order of tasks is defined in the Sequence Activities process.
D. The approach should be defined by the project management office (PMO).
HINT: In what process are project activities sequenced?
Question
The correct answer is C.
To answer this question correctly, one should be able to distinguish a deliverable and work
package from the schedule and activities. The planned work is contained within the lowest level of
the components of the work breakdown structure (WBS). These components are called work
packages.
A work package can be used to group the activities where work is scheduled and estimated,
monitored, and controlled. In the context of the WBS, work refers to work products or deliverables
that are the result of activity and not to the activity itself.
The work packages are further decomposed into schedule activities that are then sequenced to
obtain the greatest efficiency given all the project's constraints. The Create WBS process provides a
framework of 'what' has to be delivered but does not involve sequencing.
Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.

More Related Content

PDF
Free PMP Exam Sample Question
PDF
Free PMP Sample Q & A
PDF
Free PMP Sample Q & A
PPTX
PROJECT MANAGEMENT Work Breakdown Structure
PPTX
WBS-final-1.Project Management and Ethics.pptx
PPT
Chapter 2 Work Break down Structure1.ppt
PPT
Chapter 2 Work Break down Structure (1).ppt
PDF
AnAr project management overview
Free PMP Exam Sample Question
Free PMP Sample Q & A
Free PMP Sample Q & A
PROJECT MANAGEMENT Work Breakdown Structure
WBS-final-1.Project Management and Ethics.pptx
Chapter 2 Work Break down Structure1.ppt
Chapter 2 Work Break down Structure (1).ppt
AnAr project management overview

Similar to Free PMP Exam Sample Question of the Week (20)

PPTX
Work breakdown structure
PPTX
5. Work Breakdown Structure-- slides for help 1.pptx
PPTX
SEN-22413 - UNIT - V.pptx
DOCX
188 Chapter 6Chapter 6I keep six honest serving-men (they taug
PPTX
Work Breakdown Structure Aritrya Kumar.pptx
PPTX
Work breakdown structure ppt
PPTX
Project Management -WBS,Gantt Chart Presentation
PDF
A Work Breakdown Structure ( Wbs )
PPTX
Sequencing
PDF
How do you apply earned value management successfully
PPTX
Work breakdown structure in project management ppt by kiran j
PPTX
Work breakdown structure (WBS) PRESENTATION.pptx
PPTX
Engineering Economics|Work Breakdown Structure
PDF
The Importance of Work Packages in Project Scope.pdf
PDF
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
PDF
Workbreakdownstructureppt 130410021152-phpapp02
PPT
wbs.ppt
PPT
Work Breakdown Structure in Construction Cost Engineering.ppt
PPT
PM Session 4
PDF
Pmbok6
Work breakdown structure
5. Work Breakdown Structure-- slides for help 1.pptx
SEN-22413 - UNIT - V.pptx
188 Chapter 6Chapter 6I keep six honest serving-men (they taug
Work Breakdown Structure Aritrya Kumar.pptx
Work breakdown structure ppt
Project Management -WBS,Gantt Chart Presentation
A Work Breakdown Structure ( Wbs )
Sequencing
How do you apply earned value management successfully
Work breakdown structure in project management ppt by kiran j
Work breakdown structure (WBS) PRESENTATION.pptx
Engineering Economics|Work Breakdown Structure
The Importance of Work Packages in Project Scope.pdf
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
Workbreakdownstructureppt 130410021152-phpapp02
wbs.ppt
Work Breakdown Structure in Construction Cost Engineering.ppt
PM Session 4
Pmbok6
Ad

More from OSP International LLC (20)

PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Ad

Recently uploaded (20)

PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Pre independence Education in Inndia.pdf
PPTX
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PPTX
master seminar digital applications in india
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
PPH.pptx obstetrics and gynecology in nursing
PDF
01-Introduction-to-Information-Management.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PPTX
Cell Types and Its function , kingdom of life
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Cell Structure & Organelles in detailed.
PDF
TR - Agricultural Crops Production NC III.pdf
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Supply Chain Operations Speaking Notes -ICLT Program
Pre independence Education in Inndia.pdf
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Renaissance Architecture: A Journey from Faith to Humanism
master seminar digital applications in india
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPH.pptx obstetrics and gynecology in nursing
01-Introduction-to-Information-Management.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
Cell Types and Its function , kingdom of life
Anesthesia in Laparoscopic Surgery in India
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
Microbial diseases, their pathogenesis and prophylaxis
Cell Structure & Organelles in detailed.
TR - Agricultural Crops Production NC III.pdf

Free PMP Exam Sample Question of the Week

  • 2. Two team members are arguing over how to organize the work packages in the work breakdown structure (WBS). One says the work packages should be arranged in the order the work is planned to be carried out, while the other insists the order of the work packages in the WBS does not matter. The two ask the project manager for advice. What is the project manager's best response? A. Work is decomposed and sequenced in the Define Activities process. B. Any approach is good as long as the team members avoid the conflict. C. The chronological order of tasks is defined in the Sequence Activities process. D. The approach should be defined by the project management office (PMO). HINT: In what process are project activities sequenced? Question
  • 3. The correct answer is C. To answer this question correctly, one should be able to distinguish a deliverable and work package from the schedule and activities. The planned work is contained within the lowest level of the components of the work breakdown structure (WBS). These components are called work packages. A work package can be used to group the activities where work is scheduled and estimated, monitored, and controlled. In the context of the WBS, work refers to work products or deliverables that are the result of activity and not to the activity itself. The work packages are further decomposed into schedule activities that are then sequenced to obtain the greatest efficiency given all the project's constraints. The Create WBS process provides a framework of 'what' has to be delivered but does not involve sequencing. Answer
  • 4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.