Heathrow Terminal 5 Project Success or Failure?- a tale of two halves 8th May 2009 Dr David Hancock PhD MBA BEng CEng FRSA FIMMM RRP Chartered FCIPD David Hancock Consulting
Agenda Fundamentals of risk management? Why was Terminal 5 different ? T5 Handbook & Contract Risk and Opportunity Conclusions Operations - So what happened? Lessons from T5 and other projects
“ The uncertainty of outcome, whether positive or negative threat, of actions and events. It is the combination of likelihood and impact, including perceived importance.” (HM Treasury, The Orange Book, 2004) A statistical certainty? What is meant by a Risk?
Evaluating A Risk Likelihood The chance that the risk may actually be realised, (occur), sometimes called probability Impact The effect that the risk being realised would have on the Objectives, sometimes called consequence
Scoring and Traffic Light Notation L I K 5 E L I 4 H O O 3 D 2 1 1 2 3 4 5 SEVERITY LDA Legal Impact 1  Improvement notice 2  Prohibition notice. 3  Prosecution with fine. 4  Directors charged with Corporate killing, fraud etc.. 5  Directors charged with Corporate killing, fraud etc.. LDA Reputation Impact 1  No press coverage 2  Minor, local reputation damage. 3  Major, local reputation damage. 4  National adverse media coverage. 5  International adverse media coverage Financial 1  £ thousands 2  £ tens of 3  £ hundreds of 4  £  Millions 5  £ tens of millions thousands thousands Descriptor 1  Improbable 2  Unlikely 3  Less likely than not 4  Likely 5  Probable Likelihood Descriptor 1  Minor 2  Moderate 3  Significant 4  Substantial 5  Catastrophic Impact LDA Output Targets 1  Exactly meets targets 2  Significantly meets targets 3  Meets 50% of targets 4  partially meets targets 5  Does not meet  targets Health & Safety 1  Negligible injuries 2  Minor injuries 3  Major injuries 4  Single fatality 5  Multiple fatalities Schedule 1  Day 2  Week 3  Month 4  Year 5  Years
The Risk Process Set Objectives Monitor the risks Report movement of the risk Identify Threats and Opportunities to Objectives Assess the risks associated with each threat and  opportunity ( Inherent ) and  map exposure (PxC) Consider actions to manage risk terminate, tolerate, treat, transfer Reassess the risk  ( Residual ) and remap  (PxC) in light of actions  in place
Response to risk… the 4 Ts Terminate – Do things differently and thus remove the risk Tolerate  – Nothing can be done at a reasonable cost to mitigate the risk or the likelihood and impact are at a reasonable level Treat – Take action to control the risk either by reducing the likelihood of the risk developing or limiting the impact it will have on the project Transfer   – Some of the financial risk may be transferable via insurance or contractual arrangements or accepted by third parties
Risk and Opportunity
Risk Assessment Quantitative An attempt to apply meaningful and objective probabilities and subsequently consider and then quantify the potential of such risks in terms of time, cost and quality  (Laxtons guide to risk analysis and management) Qualitative Involves the registration of the identified risks, by ‘experts’ in a formal manner using subjective probabilities. Selection of stakeholders is critical to its success. Need to take into consideration Group Dynamics. Also used to identify Opportunities
What is Risk? (Part 2) Exists in the future There are many possible futures available The model is not reality “ Recognising the possibility of different outcomes and trying to make sure that activities are directed towards making an acceptable set of outcomes more likely” - CIPFA Treasury discussion paper
Understanding what is meant by project success is crucial
General Project Delivery Trends Increased complexity of solutions Projects solved and delivered through diverse teams Increased relationships/partnerships Increased societal interaction Increased interaction with ‘non experts’  (General Public) Increased political involvement Higher customer expectation Increased expectations of performance Increased informed risk taking What are the particular challenges?
Project Failures American Companies and Government agencies spent $81 billion on cancelled IT projects 31% of projects deemed complete failures 53% were late, over budget and did not meet expectations Only 9% delivered on time or within budget Only 16% considered successful Average time overrun 222% of original estimate 52.7% of projects will cost over 189% of their original estimates Projects completed by the largest American companies have only approximately 42% of the originally-proposed features and functions UK Government procured construction projects suffer on average 11% time overrun.
Why was T5 Different? Where we want to  be
Terminal 5 Project - Background The Public Inquiry into the proposal to build a fifth terminal at Heathrow Airport started in May 1995 and finally finished after having sat for 525 days, in March 1999, making it the longest public inquiry in British planning history and at a cost of £80m in legal fees.  The report was submitted to the UK Government 20 th  December 2000. Planning costs at risk were £320m. The decision to go ahead was given on 20 th  November 2001 by Stephen Byers transport secretary and the terminal is expected to be completed by 04:00 on 30 March 2008.
Terminal 5 Project – What? A main passenger terminal and two satellites to handle 30 million passengers a year. The £4.2 billion complex would also include; service tunnels and roads, car parks, facilities for the next generation of 'super-jumbo' aircraft and a hotel. A complete transport interchange with its own high-speed rail and Underground links, bus and coach station and a spur road to the M25. Designed by Sir Richard Rogers, the terminal will feature a light, airy interior with spectacular views of the airfield. It will be spacious, elegant and user-friendly as well as functional. Offering the highest customer service standards for essential airport procedures and a range of facilities to enhance comfort and enjoyment, including shops and catering. Will provide an efficient and enjoyable airport experience for customers. All British Airways flights will be concentrated in Terminal 5.
Terminal 5 Project - Orientation Terminal 4 Terminal 1 Terminal 2 Terminal 3 Terminal 5
Terminal 5 Project - Orientation
Terminal 5 Project - Orientation
The Vision To deliver the Terminal 5 project within our Cost Plan and Programme.  This will be done with sensitivity to the impact on the local community and with exemplary safety and environmental standards.  The project will deliver the quality of facility and service described by the Project Brief with a satisfactory return on investment for BAA.  BAA will implement the principles of the "Memorandum of Understanding" agreed with British Airways and work openly and constructively in the execution of a successful project.  There will be fair reward for the achievements of our partners in delivering the project - and no surprises for our shareholders.  By the time we’ve finished we will have created a new standard for project delivery in the UK   “ THE WORLD’S MOST REFRESHING INTERCHANGE”
The Project Organisations Rod  Eddington Chief Executive John  Rishton Chief Financial Officer Mike  Street Director Customer Service and Operations Robert  Boyle Director of Commercial Planning Paul  Coby  Chief Information Officer Lloyd Cromwell Griffiths Director of Flight Operations Martin  George Commercial Director Alan  Mcdonald  Engineering Director Robert  Webb QC General Counsel Neil Robertson Director For People
Environment – October 1994 Canteen & Welfare Units Cambourne House
Heathrow Express Collapse Record fine after tunnel collapse One of the worst civil engineering disasters for 25 years. Builder Balfour Beatty has been fined a record £1.2m for the collapse of a tunnel at Heathrow Airport, which put lives at risk and caused the cancellation of hundreds of flights.  The tunnel collapsed in the early hours of October 21, 1994. Fortunately no-one was in the tunnel at the time.  However, the court was told that the collapse could have crushed to death people using the nearby Piccadilly tube line and the judge hearing the case, Justice Peter Cresswell, said it was "luck more than judgment" that this did not happen.  Huge crater   The collapse could have ended in real disaster. The engineering disaster caused a huge crater to appear between the airport's two main runways and caused damage to car parks and buildings. It took months to clear up the damage. The collapse occurred during the construction of a tunnel for the Heathrow Express Rail Link.  Balfour Beatty pleaded guilty to failing to ensure the safety of both its employees and members of the public. Austrian engineering firm Geoconsult, which was responsible for monitoring the progress of the Heathrow Express Link, was also fined £500,000. The judge ordered both companies to pay a further £100,00 each in costs.  Terrible disaster  Justice Cresswell said: "This was one of the worst civil engineering disasters in the United Kingdom in the last quarter of a century. The tunnels were being built below part of the world's busiest international airport and there was considerable potential for harm."  Both firms were found guilty of falling "seriously short" of the appropriate standards and reasonable steps, resulting in serious breaches of the Health and Safety Regulations.  Martin Thurgood, of the Health and Safety Executive, told the BBC: "This level of fine sends a clear message to the industry, whether (to) the client's designers, contractors or sub-contractors, that they do need to take full account of workers safety and public safety in the way in which they go about their business."  Balfour Beatty, based in Edinburgh, is one of the UK's largest building groups, and is part of the engineering group BICC. It said it deeply regretted the accident. The tunnel's collapse delayed the opening of the Heathrow Express by six months and caused long hold ups on part of the Jubilee line extension, where engineers were using similar building techniques.
Understanding what is meant by project success is crucial
BAA Risk Principles BAA HOLDS ALL OF THE RISK ALL OF THE TIME USE OF INTEGRATED TEAMS TO HELP BAA MANAGE RISK RISK IS LINKED TO REWARD T5 HANDBOOK SETS OUT BASIC PRINCIPLES
Risk and Opportunity
Risk Assessment Quantitative An  attempt  to apply  meaningful  and objective probabilities and subsequently consider and then quantify the potential of such risks in terms of time, cost and quality (Laxtons guide to risk analysis and management) Qualitative Involves the registration of the identified risks, by ‘experts’ in a formal manner using  subjective  probabilities. Selection of stakeholders is critical to its success. Need to take into consideration Group Dynamics. Also used to identify Opportunities
T5 Agreement
Behavioural Contract
Problem Areas Tame Problems Systems Complexity Messes (Ackoff 1970)  Behavioural Complexity Wicked Problems (Rittel & Weber 1973) Wicked Messes (Roth & Senge 1996)
Problem Solving Problem Solution Gather Data Analyse Data Formulate Solution Implement Solution “ TAME” Problems can be solved by linear or “waterfall” process Time since beginning
Systems Complexity Clusters of interrelated or interdependent  problems Messes (Ackoff 1970)
“ MESSES ”   meet the following criteria: Organisational Complexity  - clusters of interrelated or interdependent problems, or systems of problems. Messes  are puzzles; rather than solving them we  resolve   their complexities. Cannot be solved in relative isolation from one another .
Behavioural Complexity Conflicting social ethics and beliefs ‘ Wickedness’ (Rittel & Webber 1973)
“ WICKED PROBLEMS ”   are characterised by: An  evolving set of interlocking issues and constraints  - no definitive statement of the problem (no understanding of the problem until the solution has been developed). Many   stakeholders  - the problem solving process is fundamentally social (getting the right answer is not as important as having stakeholders accept the solution). The constraints  (resources, politics)  change with time  - stakeholders come and go, change their minds or change the rules. Since there is no definitive Problem there is no definitive Solution .
Wickedness Time since beginning “ WICKED”  Problems  cannot  be solved by linear or “waterfall” process Problem Solution
Wicked Problem Solving Because of the number of stakeholders, changing constraints and dynamics of the problem, there is no ideal solution-it is “as good as it gets” or “good enough” The Problem solving process ends when resource (time, money energy etc.) runs out! Therefore we need a different approach when handling risk with respect to problems which are not Tame Resolving  “ WICKED MESSES ”   is “ SATISFICING ”  (H. Simon 1956)
Risk Management
“ The most important difference between Terminal 5 and other large building projects has been the approach to project management, and especially to risk”. Tony Douglas T5 Managing Director  The Economist  18th August 2005
Operations – So what happened? The first flight of the day was captained by BA’s first female pilot, Lynn Barton, and touched down a full eight minutes ahead of schedule. Six months of trials failed to detect the glitches - Walsh said the problems had not emerged in the trial process. T5 is designed to process 70,000 passengers per day but in its "soft launch" phase it should handle 40,000 - a reduced number that the baggage system was unable to cope with initially. The problems, BA blamed on staff not being familiar with new systems BAA claimed that the baggage system was working properly but had become clogged with bags because BA had too few staff to unload them from conveyor belts.  BA said that BAA had provided too few security staff to process its baggage handlers as they arrived for work. A BAA spokeswoman admitted: A software problem has arisen in the baggage system at Terminal 5. This is entirely BAA's responsibility.
Operations – So what happened? BA had been preparing for the switch to Terminal 5 for three years and claimed that it had trained thousands of staff on the new systems. But many were delayed after being unable to park their cars or to find their way to their work stations. Pilots slam BA management over Terminal 5 chaos. British Airways pilots urged investors to take action over the airline's leadership yesterday after warning that poor management had turned the airline into a "laughing stock". In a scathing letter to shareholders and government ministers, the British Air Line Pilots' Association (Balpa) blamed BA executives including the chief executive, Willie Walsh, for the bungled debut of Heathrow airport's Terminal 5 The baggage handlers identified a few system glitches during the trials but as usual with BA management their concerns were ignored, (we get paid to manage - you get paid to do as we say)."  My heart goes out to all the staff, they have tried to do their best with very little or no training under extreme pressure.  Willie Walsh, the chief executive, said he needs the extra time to avoid the "staff familiarisation issues"
Operations – So what happened? Apparently there was a lot of ’show and tell’ rather than hands on involvement. Simulations were unrealistically light in the amounts of baggage used. Not enough people - handlers and passengers - were involved. Simple work aids have been misplaced or mis-managed, and pre-opening testing was too light weight to reveal this. Having enough parking so that your baggage handlers don’t spend vital time driving around looking for a space is a good idea. So, too, is having enough direction and information signs so that staff know where they are and what they’re doingThe baggage handlers identified a few system glitches during the trials but as usual with BA management their concerns were ignored, (we get paid to manage - you get paid to do as we say)."  the problem was not insufficient training, but the wrong type of training: show and tell lectures without sufficient realism, live testing of systems, full simulations of everything from driving to work to dealing with stroppy customers. Done right, as part of a coherent management plan, the right sort of training would have made some difference
Why might this be?
British Airways Financial Highlights
BAA Terminal 5 Project Costs Multiplex losses £183 million Multiplex sues Cleveland steel for £38 million counter case for £22.6 million Multiplex sues FA for £150 million (Settled at £36 million)  Multiplex sued by shareholders for £40 million Multiplex sues designer Mott MacDonald for £253 million ** Costs at project end * Costs at contract signing Costs Original (millions) Costs Final (millions) Costs Claims (millions) Opening Costs (millions) Terminal 5 £4,200 £4,200 0 £10 ? Wembley £326.5 *£445 £900 **£757 £36 (£291) 0
Terminal 5 – The future?
“ When all you have is a hammer, everything looks like a nail ” .  Japanese Proverb “ Successful problem solving requires finding the right solution to the right problem. We fail more often because we solve the wrong problem than because we get the wrong solution to the right problem”.  Russell Ackoff, 1974
Any Questions ? [email_address]

More Related Content

PPTX
TENDERS.pptx
PPTX
Construction project delivery methods
PPTX
Tender & bidding in construction projects
PPTX
Gcc vs scc
PPTX
Types of contracts
PPTX
Professional practice 2
PPTX
Construction Contracts: Basics of Contracts and Contract Administration
PPTX
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
TENDERS.pptx
Construction project delivery methods
Tender & bidding in construction projects
Gcc vs scc
Types of contracts
Professional practice 2
Construction Contracts: Basics of Contracts and Contract Administration
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...

What's hot (20)

PPT
Heathrow Terminal 5
PDF
Risk and assurance on crossrail - rob halstead
DOCX
Burj Khalifa
PPTX
Edinburgh Trams to Newhaven Project.pptx
DOCX
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PDF
EY Germany FinTech Landscape
 
PDF
Fueling the Energy Future
PPTX
Construction Delay Analysis, Simplified
PPT
Project planning and Scheduling
PPT
“Construction Risk Management”
PPTX
Construction industry
PPTX
fidic , jct and nec contracts
PPTX
Sustainable transport planning
PPTX
Unleashing Competitiveness on the Cloud Continuum | Accenture
PDF
Project management in construction
PPT
Project management tools and techniques
PPTX
Land use transportation relation
PDF
Moving London Forward - Crossrail
PDF
Construction Management PowerPoint Presentation Slides
PDF
Crossrail Presentation: Moving London Forward
Heathrow Terminal 5
Risk and assurance on crossrail - rob halstead
Burj Khalifa
Edinburgh Trams to Newhaven Project.pptx
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
EY Germany FinTech Landscape
 
Fueling the Energy Future
Construction Delay Analysis, Simplified
Project planning and Scheduling
“Construction Risk Management”
Construction industry
fidic , jct and nec contracts
Sustainable transport planning
Unleashing Competitiveness on the Cloud Continuum | Accenture
Project management in construction
Project management tools and techniques
Land use transportation relation
Moving London Forward - Crossrail
Construction Management PowerPoint Presentation Slides
Crossrail Presentation: Moving London Forward
Ad

Viewers also liked (20)

DOCX
London heathrow airport
PPTX
Heathrow airport Presentation by Ayisha Irshad
PPTX
Stakeholder (heathrow airport)
PDF
Managing Government Projects
PDF
Project Controls Expo, Oct 2012 - Planning – How to Succeed Hints and Tips fr...
PDF
Heathrow booklet for release_final
PPTX
Kandla port
PPT
Testing Sociotechnical Systems: Heathrow Terminal 5
PPTX
Heathrow Airport - Refurbishment of Terminal 1
PPSX
Kandala port view
PPT
The Effect of the Recession on Partnering in the Construction Sector
PPSX
Terminal 3_Indira Gandhi International Airport
PPTX
Risk management
PDF
Case study British Airways
PPTX
Indira Gandhi International Airport
PPTX
Nairobi Airport fire - Crises Management 2.0 Case Study and Analysis #Jkia #J...
PPT
Strategic planning for managers
PPTX
Analysis of 11 greatest supply chain disasters
PDF
IoTの規格標準化動向とデバイスWebAPI
PPT
Chapter 7 managing risk
London heathrow airport
Heathrow airport Presentation by Ayisha Irshad
Stakeholder (heathrow airport)
Managing Government Projects
Project Controls Expo, Oct 2012 - Planning – How to Succeed Hints and Tips fr...
Heathrow booklet for release_final
Kandla port
Testing Sociotechnical Systems: Heathrow Terminal 5
Heathrow Airport - Refurbishment of Terminal 1
Kandala port view
The Effect of the Recession on Partnering in the Construction Sector
Terminal 3_Indira Gandhi International Airport
Risk management
Case study British Airways
Indira Gandhi International Airport
Nairobi Airport fire - Crises Management 2.0 Case Study and Analysis #Jkia #J...
Strategic planning for managers
Analysis of 11 greatest supply chain disasters
IoTの規格標準化動向とデバイスWebAPI
Chapter 7 managing risk
Ad

Similar to Heathrow Terminal 5 - Success or Failure? (20)

PPTX
Heathrow Expansion Plan.pptx
DOCX
Mario megaprojekt 2 11.4.2021
DOCX
Floating Alternative In The Thames Estuary
PPTX
Lessons learnt from projects
PPTX
Reflections on lessons learnt from projects
PDF
Heathrow airport expansion consultation
PDF
Governance at heathrow - final for sharing (gov100615)
PDF
Hackpen Brochure
PPT
Masters Programme On RM
PPTX
Maya Jani - Expanding Heathrow: Building for the future
PPT
Career summary
DOC
Airport Expertise 26 Mar 09[1]
PDF
B502e2a3 1030-4a98-b6ab-e3648efbaac6
PPTX
The construction programme - assurance and controls
PDF
UFNewsletter02
PDF
World Class Programme and Project Management - Are We There Yet?
DOC
1CV plus Experience Report
PPT
Public Sector Enterprise Risk Management
PPTX
British Airways
PDF
DML CV 17
Heathrow Expansion Plan.pptx
Mario megaprojekt 2 11.4.2021
Floating Alternative In The Thames Estuary
Lessons learnt from projects
Reflections on lessons learnt from projects
Heathrow airport expansion consultation
Governance at heathrow - final for sharing (gov100615)
Hackpen Brochure
Masters Programme On RM
Maya Jani - Expanding Heathrow: Building for the future
Career summary
Airport Expertise 26 Mar 09[1]
B502e2a3 1030-4a98-b6ab-e3648efbaac6
The construction programme - assurance and controls
UFNewsletter02
World Class Programme and Project Management - Are We There Yet?
1CV plus Experience Report
Public Sector Enterprise Risk Management
British Airways
DML CV 17

More from Dr David Hancock (8)

PPT
Positioning project, programme and portfolio risk
PDF
Risk Leadership
PDF
The application of the ‘New Sciences’ to Risk and Project Management
PPT
Banja Luka
PPT
Playing For Gold! (And Black)
PPT
Cipfa Workshops Scotland
PPT
Fundamentals Of Risk Management
PDF
Where next for the Enterprise Risk Manager
Positioning project, programme and portfolio risk
Risk Leadership
The application of the ‘New Sciences’ to Risk and Project Management
Banja Luka
Playing For Gold! (And Black)
Cipfa Workshops Scotland
Fundamentals Of Risk Management
Where next for the Enterprise Risk Manager

Recently uploaded (20)

PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
Unit 1 Cost Accounting - Cost sheet
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
A Brief Introduction About Julia Allison
PDF
Nidhal Samdaie CV - International Business Consultant
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PPT
Chapter four Project-Preparation material
DOCX
Business Management - unit 1 and 2
PPTX
5 Stages of group development guide.pptx
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Roadmap Map-digital Banking feature MB,IB,AB
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Probability Distribution, binomial distribution, poisson distribution
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
New Microsoft PowerPoint Presentation - Copy.pptx
WRN_Investor_Presentation_August 2025.pdf
Unit 1 Cost Accounting - Cost sheet
HR Introduction Slide (1).pptx on hr intro
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
Belch_12e_PPT_Ch18_Accessible_university.pptx
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
A Brief Introduction About Julia Allison
Nidhal Samdaie CV - International Business Consultant
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Chapter four Project-Preparation material
Business Management - unit 1 and 2
5 Stages of group development guide.pptx
Power and position in leadershipDOC-20250808-WA0011..pdf

Heathrow Terminal 5 - Success or Failure?

  • 1. Heathrow Terminal 5 Project Success or Failure?- a tale of two halves 8th May 2009 Dr David Hancock PhD MBA BEng CEng FRSA FIMMM RRP Chartered FCIPD David Hancock Consulting
  • 2. Agenda Fundamentals of risk management? Why was Terminal 5 different ? T5 Handbook & Contract Risk and Opportunity Conclusions Operations - So what happened? Lessons from T5 and other projects
  • 3. “ The uncertainty of outcome, whether positive or negative threat, of actions and events. It is the combination of likelihood and impact, including perceived importance.” (HM Treasury, The Orange Book, 2004) A statistical certainty? What is meant by a Risk?
  • 4. Evaluating A Risk Likelihood The chance that the risk may actually be realised, (occur), sometimes called probability Impact The effect that the risk being realised would have on the Objectives, sometimes called consequence
  • 5. Scoring and Traffic Light Notation L I K 5 E L I 4 H O O 3 D 2 1 1 2 3 4 5 SEVERITY LDA Legal Impact 1 Improvement notice 2 Prohibition notice. 3 Prosecution with fine. 4 Directors charged with Corporate killing, fraud etc.. 5 Directors charged with Corporate killing, fraud etc.. LDA Reputation Impact 1 No press coverage 2 Minor, local reputation damage. 3 Major, local reputation damage. 4 National adverse media coverage. 5 International adverse media coverage Financial 1 £ thousands 2 £ tens of 3 £ hundreds of 4 £ Millions 5 £ tens of millions thousands thousands Descriptor 1 Improbable 2 Unlikely 3 Less likely than not 4 Likely 5 Probable Likelihood Descriptor 1 Minor 2 Moderate 3 Significant 4 Substantial 5 Catastrophic Impact LDA Output Targets 1 Exactly meets targets 2 Significantly meets targets 3 Meets 50% of targets 4 partially meets targets 5 Does not meet targets Health & Safety 1 Negligible injuries 2 Minor injuries 3 Major injuries 4 Single fatality 5 Multiple fatalities Schedule 1 Day 2 Week 3 Month 4 Year 5 Years
  • 6. The Risk Process Set Objectives Monitor the risks Report movement of the risk Identify Threats and Opportunities to Objectives Assess the risks associated with each threat and opportunity ( Inherent ) and map exposure (PxC) Consider actions to manage risk terminate, tolerate, treat, transfer Reassess the risk ( Residual ) and remap (PxC) in light of actions in place
  • 7. Response to risk… the 4 Ts Terminate – Do things differently and thus remove the risk Tolerate – Nothing can be done at a reasonable cost to mitigate the risk or the likelihood and impact are at a reasonable level Treat – Take action to control the risk either by reducing the likelihood of the risk developing or limiting the impact it will have on the project Transfer – Some of the financial risk may be transferable via insurance or contractual arrangements or accepted by third parties
  • 9. Risk Assessment Quantitative An attempt to apply meaningful and objective probabilities and subsequently consider and then quantify the potential of such risks in terms of time, cost and quality (Laxtons guide to risk analysis and management) Qualitative Involves the registration of the identified risks, by ‘experts’ in a formal manner using subjective probabilities. Selection of stakeholders is critical to its success. Need to take into consideration Group Dynamics. Also used to identify Opportunities
  • 10. What is Risk? (Part 2) Exists in the future There are many possible futures available The model is not reality “ Recognising the possibility of different outcomes and trying to make sure that activities are directed towards making an acceptable set of outcomes more likely” - CIPFA Treasury discussion paper
  • 11. Understanding what is meant by project success is crucial
  • 12. General Project Delivery Trends Increased complexity of solutions Projects solved and delivered through diverse teams Increased relationships/partnerships Increased societal interaction Increased interaction with ‘non experts’ (General Public) Increased political involvement Higher customer expectation Increased expectations of performance Increased informed risk taking What are the particular challenges?
  • 13. Project Failures American Companies and Government agencies spent $81 billion on cancelled IT projects 31% of projects deemed complete failures 53% were late, over budget and did not meet expectations Only 9% delivered on time or within budget Only 16% considered successful Average time overrun 222% of original estimate 52.7% of projects will cost over 189% of their original estimates Projects completed by the largest American companies have only approximately 42% of the originally-proposed features and functions UK Government procured construction projects suffer on average 11% time overrun.
  • 14. Why was T5 Different? Where we want to be
  • 15. Terminal 5 Project - Background The Public Inquiry into the proposal to build a fifth terminal at Heathrow Airport started in May 1995 and finally finished after having sat for 525 days, in March 1999, making it the longest public inquiry in British planning history and at a cost of £80m in legal fees. The report was submitted to the UK Government 20 th December 2000. Planning costs at risk were £320m. The decision to go ahead was given on 20 th November 2001 by Stephen Byers transport secretary and the terminal is expected to be completed by 04:00 on 30 March 2008.
  • 16. Terminal 5 Project – What? A main passenger terminal and two satellites to handle 30 million passengers a year. The £4.2 billion complex would also include; service tunnels and roads, car parks, facilities for the next generation of 'super-jumbo' aircraft and a hotel. A complete transport interchange with its own high-speed rail and Underground links, bus and coach station and a spur road to the M25. Designed by Sir Richard Rogers, the terminal will feature a light, airy interior with spectacular views of the airfield. It will be spacious, elegant and user-friendly as well as functional. Offering the highest customer service standards for essential airport procedures and a range of facilities to enhance comfort and enjoyment, including shops and catering. Will provide an efficient and enjoyable airport experience for customers. All British Airways flights will be concentrated in Terminal 5.
  • 17. Terminal 5 Project - Orientation Terminal 4 Terminal 1 Terminal 2 Terminal 3 Terminal 5
  • 18. Terminal 5 Project - Orientation
  • 19. Terminal 5 Project - Orientation
  • 20. The Vision To deliver the Terminal 5 project within our Cost Plan and Programme. This will be done with sensitivity to the impact on the local community and with exemplary safety and environmental standards. The project will deliver the quality of facility and service described by the Project Brief with a satisfactory return on investment for BAA. BAA will implement the principles of the "Memorandum of Understanding" agreed with British Airways and work openly and constructively in the execution of a successful project. There will be fair reward for the achievements of our partners in delivering the project - and no surprises for our shareholders. By the time we’ve finished we will have created a new standard for project delivery in the UK “ THE WORLD’S MOST REFRESHING INTERCHANGE”
  • 21. The Project Organisations Rod Eddington Chief Executive John Rishton Chief Financial Officer Mike Street Director Customer Service and Operations Robert Boyle Director of Commercial Planning Paul Coby Chief Information Officer Lloyd Cromwell Griffiths Director of Flight Operations Martin George Commercial Director Alan Mcdonald Engineering Director Robert Webb QC General Counsel Neil Robertson Director For People
  • 22. Environment – October 1994 Canteen & Welfare Units Cambourne House
  • 23. Heathrow Express Collapse Record fine after tunnel collapse One of the worst civil engineering disasters for 25 years. Builder Balfour Beatty has been fined a record £1.2m for the collapse of a tunnel at Heathrow Airport, which put lives at risk and caused the cancellation of hundreds of flights. The tunnel collapsed in the early hours of October 21, 1994. Fortunately no-one was in the tunnel at the time. However, the court was told that the collapse could have crushed to death people using the nearby Piccadilly tube line and the judge hearing the case, Justice Peter Cresswell, said it was "luck more than judgment" that this did not happen. Huge crater The collapse could have ended in real disaster. The engineering disaster caused a huge crater to appear between the airport's two main runways and caused damage to car parks and buildings. It took months to clear up the damage. The collapse occurred during the construction of a tunnel for the Heathrow Express Rail Link. Balfour Beatty pleaded guilty to failing to ensure the safety of both its employees and members of the public. Austrian engineering firm Geoconsult, which was responsible for monitoring the progress of the Heathrow Express Link, was also fined £500,000. The judge ordered both companies to pay a further £100,00 each in costs. Terrible disaster Justice Cresswell said: "This was one of the worst civil engineering disasters in the United Kingdom in the last quarter of a century. The tunnels were being built below part of the world's busiest international airport and there was considerable potential for harm." Both firms were found guilty of falling "seriously short" of the appropriate standards and reasonable steps, resulting in serious breaches of the Health and Safety Regulations. Martin Thurgood, of the Health and Safety Executive, told the BBC: "This level of fine sends a clear message to the industry, whether (to) the client's designers, contractors or sub-contractors, that they do need to take full account of workers safety and public safety in the way in which they go about their business." Balfour Beatty, based in Edinburgh, is one of the UK's largest building groups, and is part of the engineering group BICC. It said it deeply regretted the accident. The tunnel's collapse delayed the opening of the Heathrow Express by six months and caused long hold ups on part of the Jubilee line extension, where engineers were using similar building techniques.
  • 24. Understanding what is meant by project success is crucial
  • 25. BAA Risk Principles BAA HOLDS ALL OF THE RISK ALL OF THE TIME USE OF INTEGRATED TEAMS TO HELP BAA MANAGE RISK RISK IS LINKED TO REWARD T5 HANDBOOK SETS OUT BASIC PRINCIPLES
  • 27. Risk Assessment Quantitative An attempt to apply meaningful and objective probabilities and subsequently consider and then quantify the potential of such risks in terms of time, cost and quality (Laxtons guide to risk analysis and management) Qualitative Involves the registration of the identified risks, by ‘experts’ in a formal manner using subjective probabilities. Selection of stakeholders is critical to its success. Need to take into consideration Group Dynamics. Also used to identify Opportunities
  • 30. Problem Areas Tame Problems Systems Complexity Messes (Ackoff 1970) Behavioural Complexity Wicked Problems (Rittel & Weber 1973) Wicked Messes (Roth & Senge 1996)
  • 31. Problem Solving Problem Solution Gather Data Analyse Data Formulate Solution Implement Solution “ TAME” Problems can be solved by linear or “waterfall” process Time since beginning
  • 32. Systems Complexity Clusters of interrelated or interdependent problems Messes (Ackoff 1970)
  • 33. “ MESSES ” meet the following criteria: Organisational Complexity - clusters of interrelated or interdependent problems, or systems of problems. Messes are puzzles; rather than solving them we resolve their complexities. Cannot be solved in relative isolation from one another .
  • 34. Behavioural Complexity Conflicting social ethics and beliefs ‘ Wickedness’ (Rittel & Webber 1973)
  • 35. “ WICKED PROBLEMS ” are characterised by: An evolving set of interlocking issues and constraints - no definitive statement of the problem (no understanding of the problem until the solution has been developed). Many stakeholders - the problem solving process is fundamentally social (getting the right answer is not as important as having stakeholders accept the solution). The constraints (resources, politics) change with time - stakeholders come and go, change their minds or change the rules. Since there is no definitive Problem there is no definitive Solution .
  • 36. Wickedness Time since beginning “ WICKED” Problems cannot be solved by linear or “waterfall” process Problem Solution
  • 37. Wicked Problem Solving Because of the number of stakeholders, changing constraints and dynamics of the problem, there is no ideal solution-it is “as good as it gets” or “good enough” The Problem solving process ends when resource (time, money energy etc.) runs out! Therefore we need a different approach when handling risk with respect to problems which are not Tame Resolving “ WICKED MESSES ” is “ SATISFICING ” (H. Simon 1956)
  • 39. “ The most important difference between Terminal 5 and other large building projects has been the approach to project management, and especially to risk”. Tony Douglas T5 Managing Director The Economist 18th August 2005
  • 40. Operations – So what happened? The first flight of the day was captained by BA’s first female pilot, Lynn Barton, and touched down a full eight minutes ahead of schedule. Six months of trials failed to detect the glitches - Walsh said the problems had not emerged in the trial process. T5 is designed to process 70,000 passengers per day but in its "soft launch" phase it should handle 40,000 - a reduced number that the baggage system was unable to cope with initially. The problems, BA blamed on staff not being familiar with new systems BAA claimed that the baggage system was working properly but had become clogged with bags because BA had too few staff to unload them from conveyor belts. BA said that BAA had provided too few security staff to process its baggage handlers as they arrived for work. A BAA spokeswoman admitted: A software problem has arisen in the baggage system at Terminal 5. This is entirely BAA's responsibility.
  • 41. Operations – So what happened? BA had been preparing for the switch to Terminal 5 for three years and claimed that it had trained thousands of staff on the new systems. But many were delayed after being unable to park their cars or to find their way to their work stations. Pilots slam BA management over Terminal 5 chaos. British Airways pilots urged investors to take action over the airline's leadership yesterday after warning that poor management had turned the airline into a "laughing stock". In a scathing letter to shareholders and government ministers, the British Air Line Pilots' Association (Balpa) blamed BA executives including the chief executive, Willie Walsh, for the bungled debut of Heathrow airport's Terminal 5 The baggage handlers identified a few system glitches during the trials but as usual with BA management their concerns were ignored, (we get paid to manage - you get paid to do as we say)." My heart goes out to all the staff, they have tried to do their best with very little or no training under extreme pressure. Willie Walsh, the chief executive, said he needs the extra time to avoid the "staff familiarisation issues"
  • 42. Operations – So what happened? Apparently there was a lot of ’show and tell’ rather than hands on involvement. Simulations were unrealistically light in the amounts of baggage used. Not enough people - handlers and passengers - were involved. Simple work aids have been misplaced or mis-managed, and pre-opening testing was too light weight to reveal this. Having enough parking so that your baggage handlers don’t spend vital time driving around looking for a space is a good idea. So, too, is having enough direction and information signs so that staff know where they are and what they’re doingThe baggage handlers identified a few system glitches during the trials but as usual with BA management their concerns were ignored, (we get paid to manage - you get paid to do as we say)." the problem was not insufficient training, but the wrong type of training: show and tell lectures without sufficient realism, live testing of systems, full simulations of everything from driving to work to dealing with stroppy customers. Done right, as part of a coherent management plan, the right sort of training would have made some difference
  • 45. BAA Terminal 5 Project Costs Multiplex losses £183 million Multiplex sues Cleveland steel for £38 million counter case for £22.6 million Multiplex sues FA for £150 million (Settled at £36 million) Multiplex sued by shareholders for £40 million Multiplex sues designer Mott MacDonald for £253 million ** Costs at project end * Costs at contract signing Costs Original (millions) Costs Final (millions) Costs Claims (millions) Opening Costs (millions) Terminal 5 £4,200 £4,200 0 £10 ? Wembley £326.5 *£445 £900 **£757 £36 (£291) 0
  • 46. Terminal 5 – The future?
  • 47. “ When all you have is a hammer, everything looks like a nail ” . Japanese Proverb “ Successful problem solving requires finding the right solution to the right problem. We fail more often because we solve the wrong problem than because we get the wrong solution to the right problem”. Russell Ackoff, 1974
  • 48. Any Questions ? [email_address]

Editor's Notes

  • #44: Willy Walsh joins BA May 2005 Ferrovial acquires BAA June 2006