OPEN ENDED PROBLEM
HIERARCHICAL GRID CONNECTION OF
INDIA
MAYURSINH RATHOD - 150043109026
ELECTRICAL DEPARTMENT
150043109026
HIERARCHICAL GRID CONNECTION:
FUNCTIONS OF EACH LDC (Load Dispatch Centre):
NLDC:
 Supervision over the Regional Load Despatch Centres.
 Scheduling and Dispatch of electricity over the inter-regional links in accordance with
grid.
 Coordination with Regional Load Despatch Centres for achieving maximum economy and
efficiency in the operation of National Grid.
 Monitoring of operations and grid security of the National Grid.
 Supervision and control over the inter-regional links as may be required for ensuring
Stability of the power system.
 Coordination with Regional Load Despatch Centres for the energy accounting of inter-
regional exchange of power.
 Coordination for restoration of Synchronous Operation of national grid with Regional
Load Despatch Centres.
 Providing Operational feedback for national grid planning to the Authority and Central
Transmission Utility.
 Collection of such fee and charges from the generating companies or licensees involved in
the power system.
RLDC:
 System parameters and security.
 To ensure the integrated operation of the power system grid in the respective region.
 System studies, planning and contingency analysis.
 Daily scheduling and operational planning.
 Computation of energy despatch.
 Augmentation of telemetry, computing and communication facilities.
ELECTRICAL DEPARTMENT
150043109026
SLDC:
 Be responsible for optimum scheduling and despatch of electricity within a State, in
accordance with the contracts entered into with the licensees or the generating companies
operating in that State;
 Monitor grid operations
 Keep accounts of the quantity of electricity transmitted through the State grid
 Exercise supervision and control over the intra-state transmission system
 Be responsible for carrying out real time operations for grid control and despatch of
electricity within the State through secure and economic operation of the State grid in
accordance with the Grid Standards and the State Grid Code.
ALDC:
 Monitoring of system parameters and security.
 To ensure the integrated operation of the power system of HPSEBL with Northern Load
Dispatch Centre.
 System Studies and Planning.
 Analysis of tripping/disturbances and facilitating immediate remedial measures.
 Daily scheduling and operational planning.
 Facilitating bilateral exchanges.
 Computation of energy dispatch and drawl values.
 Augmentation of Computing and Communication facilities.
Locations of LDCs of India:
 All LDCs are operated by Power System Operation Corporation Limited (POSOCO).
 NLDC is located at New Delhi, which having back-up centre at Kolkata.
 Western Region LDC is located at Andheri (East), Mumbai.
 Eastern Region LDC is located at Kolkata.
 South Region LDC is located at Bangalore.
 Northern Region is located at New Delhi.
 Gujarat State LDC is located at Vadodara.
Real time Data of Northern Region LDC as below…
Sr. No. Name of Line Ckt Tower Length in km Conductor O & M
1 Badarpur S/C 136 Zebra RRVPNL
2 Bharatpur S/C 48 Zebra RRVPNL
3 Bhakra D/C 55 Zebra PSTCL
4 Ganguwal S/C 44 Zebra PSTCL
5 Hiranagar S/C 45 Zebra J & K

More Related Content

PPTX
Load dispatch center
DOCX
Report its
PPTX
Intelligent management of electrical systems in industries
PPTX
Srldc 28 May2013_congestionEnergy & Power Meet
PPTX
NPTI 15th batch Indian electricity grid code (IEGC)
PDF
Congestion management using facts devices in deregulated power system
PPT
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
PPTX
Connectivity
Load dispatch center
Report its
Intelligent management of electrical systems in industries
Srldc 28 May2013_congestionEnergy & Power Meet
NPTI 15th batch Indian electricity grid code (IEGC)
Congestion management using facts devices in deregulated power system
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Connectivity

What's hot (20)

PPT
Powerlinecommunicatin ppt
PPTX
TRANSMISSION PLANNING CRITERIA
PPTX
GSM based Prepaid Electricity Meter
PPTX
CONTROLLING FREQUENCY DEVIATIONS IN INTERCONNECTED POWER SYSTEM USING SMART ...
PPTX
Congestion issues and its related management
PDF
Differential game approach for the analysis of two area load frequency control
PPT
ATC for congestion management in deregulated power system
PDF
Managing Power System
PDF
Detection and Instantaneous Prevention of Power Theft
PDF
IRJET- Load Frequency Control of an Interconnected Power System using Grey Wo...
PDF
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
PDF
Analysis optimization and monitoring system
PPTX
Power Grid and development in India
PDF
Load frequency control in co ordination with frequency controllable hvdc link...
DOC
A solution to remote detection of illegal electricity.
PPTX
PREPAID ENERGY METER USING SMART CARD
PDF
Sjef Cobben - Power quality and electromagnetic compatibility.
PDF
Electric09
PPTX
Load flow analysis of 132 kv substation using etap
PDF
Gsm based energy meter with cost indicator
Powerlinecommunicatin ppt
TRANSMISSION PLANNING CRITERIA
GSM based Prepaid Electricity Meter
CONTROLLING FREQUENCY DEVIATIONS IN INTERCONNECTED POWER SYSTEM USING SMART ...
Congestion issues and its related management
Differential game approach for the analysis of two area load frequency control
ATC for congestion management in deregulated power system
Managing Power System
Detection and Instantaneous Prevention of Power Theft
IRJET- Load Frequency Control of an Interconnected Power System using Grey Wo...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Analysis optimization and monitoring system
Power Grid and development in India
Load frequency control in co ordination with frequency controllable hvdc link...
A solution to remote detection of illegal electricity.
PREPAID ENERGY METER USING SMART CARD
Sjef Cobben - Power quality and electromagnetic compatibility.
Electric09
Load flow analysis of 132 kv substation using etap
Gsm based energy meter with cost indicator
Ad

Similar to Hierarchical grid connection of Idia (20)

PPTX
PPTX
Introduction to Power system operation & control
PPTX
UNIT-1-PPT-Introduction about Power System Operation and Control
PDF
TRAINING REPORT
PPTX
Power system operation corporation ltd (posoco)
PPTX
UNIT-1-PPT.pptx
PPTX
SMART GRID.pptx
PPT
Indian electricity grid code presentation
PPT
Automation in Power Sector-Dr.Priyabrata Patnaik,OERC.ppt
PDF
9i9 determination-of-bus-voltages-libre
PPT
IEGC_PPT_SLDC.ppt
PPTX
Application of scada for system automation on smart grid rev2
PDF
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
PPT
Power sector mis
PDF
Manual_on_Transmission_Planning_Criteria_2023.pdf
PPTX
Power grid operation in India
PPTX
Restructuring of power grid
PPT
Grid code
DOCX
Ephraim Issac Das (CV)
PPTX
Sysc 5302 101079892
Introduction to Power system operation & control
UNIT-1-PPT-Introduction about Power System Operation and Control
TRAINING REPORT
Power system operation corporation ltd (posoco)
UNIT-1-PPT.pptx
SMART GRID.pptx
Indian electricity grid code presentation
Automation in Power Sector-Dr.Priyabrata Patnaik,OERC.ppt
9i9 determination-of-bus-voltages-libre
IEGC_PPT_SLDC.ppt
Application of scada for system automation on smart grid rev2
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
Power sector mis
Manual_on_Transmission_Planning_Criteria_2023.pdf
Power grid operation in India
Restructuring of power grid
Grid code
Ephraim Issac Das (CV)
Sysc 5302 101079892
Ad

More from MAYURSINH RATHOOD (6)

PPTX
Type of Transducers
PPTX
Boost converter
PPTX
Case Study on Ramachandrapura
PPTX
Cockroft Walten Generator
PPTX
Gas welding
PPTX
Current Transformer
Type of Transducers
Boost converter
Case Study on Ramachandrapura
Cockroft Walten Generator
Gas welding
Current Transformer

Recently uploaded (20)

PDF
Pre independence Education in Inndia.pdf
PDF
VCE English Exam - Section C Student Revision Booklet
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PDF
01-Introduction-to-Information-Management.pdf
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PPTX
Lesson notes of climatology university.
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
Complications of Minimal Access Surgery at WLH
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
Insiders guide to clinical Medicine.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
Pre independence Education in Inndia.pdf
VCE English Exam - Section C Student Revision Booklet
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
01-Introduction-to-Information-Management.pdf
102 student loan defaulters named and shamed – Is someone you know on the list?
Renaissance Architecture: A Journey from Faith to Humanism
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Lesson notes of climatology university.
FourierSeries-QuestionsWithAnswers(Part-A).pdf
O7-L3 Supply Chain Operations - ICLT Program
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
2.FourierTransform-ShortQuestionswithAnswers.pdf
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Complications of Minimal Access Surgery at WLH
human mycosis Human fungal infections are called human mycosis..pptx
Insiders guide to clinical Medicine.pdf
Final Presentation General Medicine 03-08-2024.pptx

Hierarchical grid connection of Idia

  • 1. OPEN ENDED PROBLEM HIERARCHICAL GRID CONNECTION OF INDIA MAYURSINH RATHOD - 150043109026
  • 2. ELECTRICAL DEPARTMENT 150043109026 HIERARCHICAL GRID CONNECTION: FUNCTIONS OF EACH LDC (Load Dispatch Centre): NLDC:  Supervision over the Regional Load Despatch Centres.  Scheduling and Dispatch of electricity over the inter-regional links in accordance with grid.  Coordination with Regional Load Despatch Centres for achieving maximum economy and efficiency in the operation of National Grid.  Monitoring of operations and grid security of the National Grid.  Supervision and control over the inter-regional links as may be required for ensuring Stability of the power system.  Coordination with Regional Load Despatch Centres for the energy accounting of inter- regional exchange of power.  Coordination for restoration of Synchronous Operation of national grid with Regional Load Despatch Centres.  Providing Operational feedback for national grid planning to the Authority and Central Transmission Utility.  Collection of such fee and charges from the generating companies or licensees involved in the power system. RLDC:  System parameters and security.  To ensure the integrated operation of the power system grid in the respective region.  System studies, planning and contingency analysis.  Daily scheduling and operational planning.  Computation of energy despatch.  Augmentation of telemetry, computing and communication facilities.
  • 3. ELECTRICAL DEPARTMENT 150043109026 SLDC:  Be responsible for optimum scheduling and despatch of electricity within a State, in accordance with the contracts entered into with the licensees or the generating companies operating in that State;  Monitor grid operations  Keep accounts of the quantity of electricity transmitted through the State grid  Exercise supervision and control over the intra-state transmission system  Be responsible for carrying out real time operations for grid control and despatch of electricity within the State through secure and economic operation of the State grid in accordance with the Grid Standards and the State Grid Code. ALDC:  Monitoring of system parameters and security.  To ensure the integrated operation of the power system of HPSEBL with Northern Load Dispatch Centre.  System Studies and Planning.  Analysis of tripping/disturbances and facilitating immediate remedial measures.  Daily scheduling and operational planning.  Facilitating bilateral exchanges.  Computation of energy dispatch and drawl values.  Augmentation of Computing and Communication facilities. Locations of LDCs of India:  All LDCs are operated by Power System Operation Corporation Limited (POSOCO).  NLDC is located at New Delhi, which having back-up centre at Kolkata.  Western Region LDC is located at Andheri (East), Mumbai.  Eastern Region LDC is located at Kolkata.  South Region LDC is located at Bangalore.  Northern Region is located at New Delhi.  Gujarat State LDC is located at Vadodara. Real time Data of Northern Region LDC as below… Sr. No. Name of Line Ckt Tower Length in km Conductor O & M 1 Badarpur S/C 136 Zebra RRVPNL 2 Bharatpur S/C 48 Zebra RRVPNL 3 Bhakra D/C 55 Zebra PSTCL 4 Ganguwal S/C 44 Zebra PSTCL 5 Hiranagar S/C 45 Zebra J & K