How to Manage Work Order Dependencies in Odoo 17 Manufacturing
Enterprise
Introduction
Enterprise
This slide will show How to Manage Work Order Dependencies in Odoo 17
Manufacturing.
When we manufacture certain products, some procedures may need to be
completed before others may begin. To ensure that operations take place in the
correct order, work order dependencies in the manufacturing module allow
operations on a Bill of Materials (BoM) to be blocked by other operations that
should be performed first.
Enterprise
● Let’s check the functionality of work order dependency.
● Go to Manufacturing > Settings > Work Orders.
● Enable the Work Order Dependencies.
Enterprise
Enterprise
● Add the dependencies on the BOM.
● Go to the Manufacturing > Products > Bill of Material.
Enterprise
● Enable the feature ‘Operation Dependencies’ under the Miscellaneous tab.
Enterprise
● Under the Operation tab, we can view the various operations that will
take place in various work centres.
Enterprise
● Add the blocked by operations for the operations.
● Here the operation for cutting the panel is completed first, followed by the operation
for Assemble cable management box.
Enterprise
● Let’s create a manufacturing order.
● Go to Manufacturing > Operations > Manufacturing Orders.
Enterprise
● Create a manufacturing order for the product cable management box, select
the BoM we configured, and confirm the order.
Enterprise
● Here the operations are being blocked by the work centres.
● The cutting panel operation is in the Ready stage; however, the cable box
assembly operation is just blocked.
Enterprise
● Work orders that are not blocked by other work orders are shown as in the
Ready state.
● In the status section, work orders that one or more work orders have blocked
are indicated with the Waiting for another work order tag.
● Once the blocked work order is completed, the tag is updated as Ready.
Enterprise
● We need to plan the work orders for the work centre by clicking the Plan
button.
Enterprise
● Then start the work by clicking on the Start button on the operations, and
once it is completed, click on the Done button.
Enterprise
● Now that the blocked work order has been completed, the operation of the
Assemble cable management box is in the Ready stage.
● Then start the work, and once it is completed, Done the operation.
Enterprise
● Next go to Manufacturing > Panning > Planning by Workcenter.
● Here we can see all operations performed on the work centres.
Enterprise
● This is how we can manage the work order dependencies in the
Manufacturing module in Odoo 17.
For More Info.
Check our company website for related blogs
and Odoo book.
Check our YouTube channel for
functional and technical videos in Odoo.
Enterprise
www.cybrosys.com

More Related Content

PPTX
How to Configure Split & Merge Manufacturing Orders in Odoo 17 Manufacturing
PPTX
How to Manage Scraping of Product in Odoo 17 Manufacturing
PPTX
How to Unbuild Order in Odoo 17 Manufacturing
PPTX
How to Configure Manufacturing in One Step Odoo 17 Manufacturing App
PPTX
Bills of Material (BoM) in Odoo 17 - Odoo 17 Slides
PDF
Odoo manufacturing v12
PPTX
Subcontracting in Odoo14 Manufacturing | Cybrosys
PPTX
How to configure work centers in odoo14 manufacturing
How to Configure Split & Merge Manufacturing Orders in Odoo 17 Manufacturing
How to Manage Scraping of Product in Odoo 17 Manufacturing
How to Unbuild Order in Odoo 17 Manufacturing
How to Configure Manufacturing in One Step Odoo 17 Manufacturing App
Bills of Material (BoM) in Odoo 17 - Odoo 17 Slides
Odoo manufacturing v12
Subcontracting in Odoo14 Manufacturing | Cybrosys
How to configure work centers in odoo14 manufacturing

Similar to How to Manage Work Order Dependencies in Odoo 17 Manufacturing (20)

PPTX
Complete step by step guide to odoo 13 manufacturing
PPTX
How to Manage Engineering to Order in Odoo 17
PPTX
Work order messages in odoo mrp
DOCX
Complete step by step guide to odoo manufacturing
PPTX
Odoo functional tips
PPTX
How to Configure Access Rights of Manufacturing Orders in Odoo 17 Manufacturing
PPTX
How to Configure Manufacturing in Two Step Odoo 17 Manufacturing App
PPTX
How to manage various step manufacturing in odoo v13
PDF
Detailed Guide to Safely Customize Workflows in Odoo ERP
PPTX
How to Manage Allocation Report for Manufacturing Orders in Odoo 18
PDF
Field Service Management in Odoo 13
PPTX
The Shop Floor Overview in the Odoo 17 ERP
PPT
Workcenter in Odoo Manufacturing
PPT
Manufacturing In Odoo
PDF
tenthplanet.in-Odoo Manufacturing Management.pdf
PPTX
How to Configure Manufacturing in 3 Steps in Odoo 17 Manufacturing App
PDF
Webinar #26 - Mastering OpenBOM for Solidworks Part III
PPTX
How to Manage By Products in Odoo 17 Manufacturing
PDF
How to manage semi finished products
PPTX
Odoo fundamental tips
Complete step by step guide to odoo 13 manufacturing
How to Manage Engineering to Order in Odoo 17
Work order messages in odoo mrp
Complete step by step guide to odoo manufacturing
Odoo functional tips
How to Configure Access Rights of Manufacturing Orders in Odoo 17 Manufacturing
How to Configure Manufacturing in Two Step Odoo 17 Manufacturing App
How to manage various step manufacturing in odoo v13
Detailed Guide to Safely Customize Workflows in Odoo ERP
How to Manage Allocation Report for Manufacturing Orders in Odoo 18
Field Service Management in Odoo 13
The Shop Floor Overview in the Odoo 17 ERP
Workcenter in Odoo Manufacturing
Manufacturing In Odoo
tenthplanet.in-Odoo Manufacturing Management.pdf
How to Configure Manufacturing in 3 Steps in Odoo 17 Manufacturing App
Webinar #26 - Mastering OpenBOM for Solidworks Part III
How to Manage By Products in Odoo 17 Manufacturing
How to manage semi finished products
Odoo fundamental tips
Ad

More from Celine George (20)

PPTX
Managing Customer Rewards_ Gift Cards, Loyalty Programs, and E-Wallets in Odo...
PPTX
How to Manage Coupons in Odoo 18 Sales - Odoo slides
PPTX
What is Next Order Coupons in Odoo 18 Sales
PPTX
How to Manage Buy X Get Y Free in Odoo 18 Sales
PPTX
How to Implement OWL Notification Service in Odoo 18
PPTX
Tracking Profit Margins in Sales Orders with Odoo 18
PPTX
How to Configure Outgoing Shipment in 3 Steps Using Odoo 18
PPTX
How to Configure Outgoing Shipment in 1 Step Using Odoo 18.pptx
PPTX
How to Configure Outgoing Shipment in 2 Steps Using Odoo 18
PPTX
How to Add New Applicants in Odoo 18 Recruitment
PPTX
How to Analyze the Recruitment Process in Odoo 18 Recruitment
PPTX
How to Manage Referral Reporting in Odoo 18 Referrals
PPTX
How to Set, Track, & Review Employee Goals in Odoo 18 Appraisals
PPTX
Revamp in MTO Odoo 18 Inventory - Odoo Slides
PPTX
How to Manage Starshipit in Odoo 18 - Odoo Slides
PPTX
How to Manage Bill Control Policy in Odoo 18
PPTX
How to Manage Loyalty Points in Odoo 18 Sales
PPTX
Odoo 18 Sales_ Managing Quotation Validity
PPTX
How to Manage Global Discount in Odoo 18 POS
PPTX
How to Manage Leads in Odoo 18 CRM - Odoo Slides
Managing Customer Rewards_ Gift Cards, Loyalty Programs, and E-Wallets in Odo...
How to Manage Coupons in Odoo 18 Sales - Odoo slides
What is Next Order Coupons in Odoo 18 Sales
How to Manage Buy X Get Y Free in Odoo 18 Sales
How to Implement OWL Notification Service in Odoo 18
Tracking Profit Margins in Sales Orders with Odoo 18
How to Configure Outgoing Shipment in 3 Steps Using Odoo 18
How to Configure Outgoing Shipment in 1 Step Using Odoo 18.pptx
How to Configure Outgoing Shipment in 2 Steps Using Odoo 18
How to Add New Applicants in Odoo 18 Recruitment
How to Analyze the Recruitment Process in Odoo 18 Recruitment
How to Manage Referral Reporting in Odoo 18 Referrals
How to Set, Track, & Review Employee Goals in Odoo 18 Appraisals
Revamp in MTO Odoo 18 Inventory - Odoo Slides
How to Manage Starshipit in Odoo 18 - Odoo Slides
How to Manage Bill Control Policy in Odoo 18
How to Manage Loyalty Points in Odoo 18 Sales
Odoo 18 Sales_ Managing Quotation Validity
How to Manage Global Discount in Odoo 18 POS
How to Manage Leads in Odoo 18 CRM - Odoo Slides
Ad

Recently uploaded (20)

PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
advance database management system book.pdf
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PPTX
20th Century Theater, Methods, History.pptx
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Computing-Curriculum for Schools in Ghana
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
PDF
HVAC Specification 2024 according to central public works department
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PPTX
Introduction to Building Materials
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
LDMMIA Reiki Yoga Finals Review Spring Summer
History, Philosophy and sociology of education (1).pptx
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Paper A Mock Exam 9_ Attempt review.pdf.
advance database management system book.pdf
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
20th Century Theater, Methods, History.pptx
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Computing-Curriculum for Schools in Ghana
FORM 1 BIOLOGY MIND MAPS and their schemes
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
Practical Manual AGRO-233 Principles and Practices of Natural Farming
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
HVAC Specification 2024 according to central public works department
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
Introduction to Building Materials
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx

How to Manage Work Order Dependencies in Odoo 17 Manufacturing

  • 1. How to Manage Work Order Dependencies in Odoo 17 Manufacturing Enterprise
  • 2. Introduction Enterprise This slide will show How to Manage Work Order Dependencies in Odoo 17 Manufacturing. When we manufacture certain products, some procedures may need to be completed before others may begin. To ensure that operations take place in the correct order, work order dependencies in the manufacturing module allow operations on a Bill of Materials (BoM) to be blocked by other operations that should be performed first.
  • 3. Enterprise ● Let’s check the functionality of work order dependency. ● Go to Manufacturing > Settings > Work Orders. ● Enable the Work Order Dependencies.
  • 5. Enterprise ● Add the dependencies on the BOM. ● Go to the Manufacturing > Products > Bill of Material.
  • 6. Enterprise ● Enable the feature ‘Operation Dependencies’ under the Miscellaneous tab.
  • 7. Enterprise ● Under the Operation tab, we can view the various operations that will take place in various work centres.
  • 8. Enterprise ● Add the blocked by operations for the operations. ● Here the operation for cutting the panel is completed first, followed by the operation for Assemble cable management box.
  • 9. Enterprise ● Let’s create a manufacturing order. ● Go to Manufacturing > Operations > Manufacturing Orders.
  • 10. Enterprise ● Create a manufacturing order for the product cable management box, select the BoM we configured, and confirm the order.
  • 11. Enterprise ● Here the operations are being blocked by the work centres. ● The cutting panel operation is in the Ready stage; however, the cable box assembly operation is just blocked.
  • 12. Enterprise ● Work orders that are not blocked by other work orders are shown as in the Ready state. ● In the status section, work orders that one or more work orders have blocked are indicated with the Waiting for another work order tag. ● Once the blocked work order is completed, the tag is updated as Ready.
  • 13. Enterprise ● We need to plan the work orders for the work centre by clicking the Plan button.
  • 14. Enterprise ● Then start the work by clicking on the Start button on the operations, and once it is completed, click on the Done button.
  • 15. Enterprise ● Now that the blocked work order has been completed, the operation of the Assemble cable management box is in the Ready stage. ● Then start the work, and once it is completed, Done the operation.
  • 16. Enterprise ● Next go to Manufacturing > Panning > Planning by Workcenter. ● Here we can see all operations performed on the work centres.
  • 17. Enterprise ● This is how we can manage the work order dependencies in the Manufacturing module in Odoo 17.
  • 18. For More Info. Check our company website for related blogs and Odoo book. Check our YouTube channel for functional and technical videos in Odoo. Enterprise www.cybrosys.com