6
Most read
7
Most read
9
Most read
INTERNSHIP ON
ERECTION, COMMISSIONING AND PRE-
COMISSIONING OF 500MVA TRANSFORMER
PRESENTED BY
AKINAPELLI RAHUL
161230007
Internship at
400/220KV POWER GRID
WARANGAL-SS
Submitted at
NATIONAL INSTIUTE OF TECHNOLOY DELHI
PGCIL
PGCIL –POWERGRID CORPORATION OF INDIA LIMITED
Incorporated on 23 October 1989 under the Companies Act, 1956 with an authorized share capital of Rs. 5,000
Crore.
POWERGRID transmits about 50% of the total power generated in India on its transmission network.
Its transmission network consists of roughly 148,838 circuit kilometres and 236 EHVAC and HVDC substations,
which provide total transformation capacity of 332,163 MVA. POWERGRID's interregional capacity is 75,050 MW.
POWER TRANSMISSION
THROUGH GRID SYSTEM
SINGLE LINE DIAGRAM
OF POWER GRID
DUTIES OF 400/220KV PGCIL WARANGAL-SS
Connects three power
plants with 400KV lines
Khammam
Bhupalpally
Ramagundam
Supplies power to two
cities with 220KV lines
Nagaram
Durshed
Uses ICT’s to step down
voltage from 400KV to
220KV.
One 500MVA
ICT
Two 315MVA
ICT
500MVA INTER CONNECTING TRANSFORMER
AND ITS PARTS
Provided with 3 windings
•Primary winding of 400KV and star type
•Secondary winding of 220KV and star type
•Tertiary winding of 33KV and delta type
Parts of 500MVA ICT
•Main Tank
•Laminated Core
•Windings
•Transformer Oil
•Conservator Tank
•Breather
•Radiator
•Buchholz Relay
•Pressure relief valve
•Tap Changer
ERECTION AND UNLOADING TRANSFORMER
Unloading of transformer
Erection process
• External and internal inspection
• Final tightness test with vacuum and pressure.
• Oil filling
• Hot oil circulation using oil filter machine
PRE-COMMISSIONING CHECKS
• 1st step is to prepare testing program schedule.
• Next step is pre-commissioning checks
Examples :-
a. Should be from visible defects,
b. All the valves are tightened properly,
c. Oil is filled up to desired level in bushings, main tank, conservator tank and also in
OLTC etc,.
d. All the cables are tightened and etc,.
PRE-COMMISSIONING TESTS
SFRA test:
Sweep Frequency Response Analysis is
to evaluate the mechanical integrity of core,
windings and clamping structures by
measuring their electrical transfer functions
over a wide frequency range.
Performed at 10V AC from 20Hz-20MHz
supply
Eg :-
Voltage and Turns ratio measurement:
1. Voltage ratio test uses digital multi
meter performed at 415V.
2. Transformer turns ratio test uses
automatic transformer turns ratio(TTR)
meter performed at 110V.
• Performed to locate defect
in magnetic core structure,
shifting of windings, failure
in turn to turn insulation or
problem in tap changer.
• Performed at 440V AC on
HV side and LV side is open
• Carried on min, normal and
max tap positions.
Magnetizing
current test:
• Performed to check balance in the
magnetic circuit.
• 1-phase 230V supplied between phase
and neutral and measure the voltage
induced in other two phases of the
same winding.
• Equipment used is digital multimeter.
• When voltage is applied at R-phase, Y-
phase should be 50-90% and B- phase
should be in 20-40%
• When voltage is applied at Y-phase,
other two phases induced voltage
should be in 30-70%.
Magnetic
balance
test:
• Performed to detect winding
movement which occurs due to
heavy fault current or mechanical
damage during transportation.
• A 3 phase 440V supply is given to
HV winding and LV is shorted .
• Measure primary voltage and
current in primary and secondary
• Performed on min, normal and
maximum tap positions.
• Acceptance values should be
within 3 % of impedance specified.
Short
circuit
impedance
test
• BDV test
acceptance value > 70KV
• PPM test
Moisture content < 5ppm
Tan delta at 90 degree
<0.01 Moisture content <
5ppm
Oil
characteristics
test
OTHER REMAINING TESTS
Capacitance and tan delta measurement
Verification of vector group and polarity test
Measurement of winding resistance
Winding insulation resistance measurement
Core insulation test
Testing on bushing CT’s
Measurement of earthing resistance
FINAL COMMISSIONING CHECKS
All the test results are verified and compared with factory results before commissioning.
No leakage oil in any part of unit. Ensure oil level in the Bushings
Ensure that tertiary winding terminals are insulated, when they are not used.
Ensure earthing of Neutral, main tank body, radiator frame structure, fans and motor.
And all the final verifications, continuity between switchyard and transformer meters, connections, sensors, fans attached and etc,.
ENERGISATION OF UNIT
1st charge the transformer under no load for 24 – 48 hours.
Gradually load the transformer observing the noise, vibration, temperature rise, oil leakage etc.
Check OLTC operation.
Carry out Thermo vision scanning of HV/LV terminals and tank body.
Carry out DGA test of oil as per schedule given in flow chart of this manual.
THANK YOU!!!

More Related Content

PPTX
coursera Safety In The Utility Industry (Health & Safety)
PDF
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
PDF
Busbar Presentation2.pdf
PPT
Tema 8 a calculo de lineas electricas
PPTX
Topic2_Force Method of Analysis Truss.pptx
PDF
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
PPTX
Resistencia Electrica
PDF
tower spotting
coursera Safety In The Utility Industry (Health & Safety)
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Busbar Presentation2.pdf
Tema 8 a calculo de lineas electricas
Topic2_Force Method of Analysis Truss.pptx
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
Resistencia Electrica
tower spotting

What's hot (20)

PPTX
Transmission line Project
PPTX
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
PPT
Presentation2(cond)
PDF
ROLES OF ENERGY MANAGERS IN SUSTAINABLE ENERGY MANAGEMENT IMPLEMENTATION
PPTX
Capacitive voltage transformer (1)
PDF
Tes p-122.10-r0 (1)
PPTX
STC-TrD-03-c-Safety rules for OHE.pptx
PDF
Gsm developer guide gsm at commands - rev a
PDF
50096171 ntc1650
PPTX
2017 intro to commercial products comms
PDF
Principles of Cable Sizing
PPT
Transformer oil-specifications new
PPT
Busbar Design
PPT
Traction distribution
PDF
Curso para electricistas idóneos clase 3 - módulo 2 - ing. e.u
PDF
Autocosumo y la Generación Distribuida
PPT
Chapter 33
PDF
Tes p-122.01-r0 (2)
PDF
Chapter01.pdf
Transmission line Project
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
Presentation2(cond)
ROLES OF ENERGY MANAGERS IN SUSTAINABLE ENERGY MANAGEMENT IMPLEMENTATION
Capacitive voltage transformer (1)
Tes p-122.10-r0 (1)
STC-TrD-03-c-Safety rules for OHE.pptx
Gsm developer guide gsm at commands - rev a
50096171 ntc1650
2017 intro to commercial products comms
Principles of Cable Sizing
Transformer oil-specifications new
Busbar Design
Traction distribution
Curso para electricistas idóneos clase 3 - módulo 2 - ing. e.u
Autocosumo y la Generación Distribuida
Chapter 33
Tes p-122.01-r0 (2)
Chapter01.pdf
Ad

Similar to INSTALLATION OF 500MVA TRANSFORMER AT PGCIL (20)

PDF
REPORT -VALLUR THERMAL POWER PLANT
DOC
cv of pjnehru
PDF
16950
DOCX
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
PPTX
Appraisal ppt ankur
PPT
TESTING,MAINTENANCE&PROTECTION.ppt
PPT
TESTING,MAINTENANCE&PROTECTION.ppt
PPT
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
PPT
Vocational training
PPTX
EIT_Presentation
PPT
Testing,maintenance&protection
PPTX
Testing, Maintenace and Protection of Transformer.pptx
PPTX
tcee-161003100321.pptx
PPTX
Testing of transformer
PPTX
Introduction of transfromer
PPTX
MPEB, MPPKVVCL Indore 15 days Training Seminar
PPTX
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
PPT
Transformer
PPTX
Gss ppt by kanhaiya
DOC
C18808 elc tech
REPORT -VALLUR THERMAL POWER PLANT
cv of pjnehru
16950
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
Appraisal ppt ankur
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
Vocational training
EIT_Presentation
Testing,maintenance&protection
Testing, Maintenace and Protection of Transformer.pptx
tcee-161003100321.pptx
Testing of transformer
Introduction of transfromer
MPEB, MPPKVVCL Indore 15 days Training Seminar
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
Transformer
Gss ppt by kanhaiya
C18808 elc tech
Ad

Recently uploaded (20)

PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
DOCX
Cambridge-Practice-Tests-for-IELTS-12.docx
PDF
Empowerment Technology for Senior High School Guide
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
advance database management system book.pdf
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
International_Financial_Reporting_Standa.pdf
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PPTX
20th Century Theater, Methods, History.pptx
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
IGGE1 Understanding the Self1234567891011
PPTX
Computer Architecture Input Output Memory.pptx
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
Weekly quiz Compilation Jan -July 25.pdf
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
Cambridge-Practice-Tests-for-IELTS-12.docx
Empowerment Technology for Senior High School Guide
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
Unit 4 Computer Architecture Multicore Processor.pptx
advance database management system book.pdf
History, Philosophy and sociology of education (1).pptx
Paper A Mock Exam 9_ Attempt review.pdf.
International_Financial_Reporting_Standa.pdf
A powerpoint presentation on the Revised K-10 Science Shaping Paper
20th Century Theater, Methods, History.pptx
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
Chinmaya Tiranga quiz Grand Finale.pdf
IGGE1 Understanding the Self1234567891011
Computer Architecture Input Output Memory.pptx
Share_Module_2_Power_conflict_and_negotiation.pptx
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
Environmental Education MCQ BD2EE - Share Source.pdf

INSTALLATION OF 500MVA TRANSFORMER AT PGCIL

  • 1. INTERNSHIP ON ERECTION, COMMISSIONING AND PRE- COMISSIONING OF 500MVA TRANSFORMER PRESENTED BY AKINAPELLI RAHUL 161230007 Internship at 400/220KV POWER GRID WARANGAL-SS Submitted at NATIONAL INSTIUTE OF TECHNOLOY DELHI
  • 2. PGCIL PGCIL –POWERGRID CORPORATION OF INDIA LIMITED Incorporated on 23 October 1989 under the Companies Act, 1956 with an authorized share capital of Rs. 5,000 Crore. POWERGRID transmits about 50% of the total power generated in India on its transmission network. Its transmission network consists of roughly 148,838 circuit kilometres and 236 EHVAC and HVDC substations, which provide total transformation capacity of 332,163 MVA. POWERGRID's interregional capacity is 75,050 MW.
  • 5. DUTIES OF 400/220KV PGCIL WARANGAL-SS Connects three power plants with 400KV lines Khammam Bhupalpally Ramagundam Supplies power to two cities with 220KV lines Nagaram Durshed Uses ICT’s to step down voltage from 400KV to 220KV. One 500MVA ICT Two 315MVA ICT
  • 6. 500MVA INTER CONNECTING TRANSFORMER AND ITS PARTS Provided with 3 windings •Primary winding of 400KV and star type •Secondary winding of 220KV and star type •Tertiary winding of 33KV and delta type Parts of 500MVA ICT •Main Tank •Laminated Core •Windings •Transformer Oil •Conservator Tank •Breather •Radiator •Buchholz Relay •Pressure relief valve •Tap Changer
  • 7. ERECTION AND UNLOADING TRANSFORMER Unloading of transformer Erection process • External and internal inspection • Final tightness test with vacuum and pressure. • Oil filling • Hot oil circulation using oil filter machine
  • 8. PRE-COMMISSIONING CHECKS • 1st step is to prepare testing program schedule. • Next step is pre-commissioning checks Examples :- a. Should be from visible defects, b. All the valves are tightened properly, c. Oil is filled up to desired level in bushings, main tank, conservator tank and also in OLTC etc,. d. All the cables are tightened and etc,.
  • 9. PRE-COMMISSIONING TESTS SFRA test: Sweep Frequency Response Analysis is to evaluate the mechanical integrity of core, windings and clamping structures by measuring their electrical transfer functions over a wide frequency range. Performed at 10V AC from 20Hz-20MHz supply Eg :- Voltage and Turns ratio measurement: 1. Voltage ratio test uses digital multi meter performed at 415V. 2. Transformer turns ratio test uses automatic transformer turns ratio(TTR) meter performed at 110V.
  • 10. • Performed to locate defect in magnetic core structure, shifting of windings, failure in turn to turn insulation or problem in tap changer. • Performed at 440V AC on HV side and LV side is open • Carried on min, normal and max tap positions. Magnetizing current test: • Performed to check balance in the magnetic circuit. • 1-phase 230V supplied between phase and neutral and measure the voltage induced in other two phases of the same winding. • Equipment used is digital multimeter. • When voltage is applied at R-phase, Y- phase should be 50-90% and B- phase should be in 20-40% • When voltage is applied at Y-phase, other two phases induced voltage should be in 30-70%. Magnetic balance test:
  • 11. • Performed to detect winding movement which occurs due to heavy fault current or mechanical damage during transportation. • A 3 phase 440V supply is given to HV winding and LV is shorted . • Measure primary voltage and current in primary and secondary • Performed on min, normal and maximum tap positions. • Acceptance values should be within 3 % of impedance specified. Short circuit impedance test • BDV test acceptance value > 70KV • PPM test Moisture content < 5ppm Tan delta at 90 degree <0.01 Moisture content < 5ppm Oil characteristics test
  • 12. OTHER REMAINING TESTS Capacitance and tan delta measurement Verification of vector group and polarity test Measurement of winding resistance Winding insulation resistance measurement Core insulation test Testing on bushing CT’s Measurement of earthing resistance
  • 13. FINAL COMMISSIONING CHECKS All the test results are verified and compared with factory results before commissioning. No leakage oil in any part of unit. Ensure oil level in the Bushings Ensure that tertiary winding terminals are insulated, when they are not used. Ensure earthing of Neutral, main tank body, radiator frame structure, fans and motor. And all the final verifications, continuity between switchyard and transformer meters, connections, sensors, fans attached and etc,.
  • 14. ENERGISATION OF UNIT 1st charge the transformer under no load for 24 – 48 hours. Gradually load the transformer observing the noise, vibration, temperature rise, oil leakage etc. Check OLTC operation. Carry out Thermo vision scanning of HV/LV terminals and tank body. Carry out DGA test of oil as per schedule given in flow chart of this manual.