TIME OPTIMIZATION OF PRECAST PLANNING USING BIM SOFTWARE
S. Madhu Anand1, Ujjwal Kumar2, Arunima Rajish3
1Head- Construction Methods Planning Centre, Residential Buildings and Factories, L&T Construction, Chennai
2,3B.Tech Graduate, Department of Civil Engineering, Pondicherry Engineering College, Puducherry
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Time is the essence of any project. Adoption of
precast construction is the key to meetthetimeline foranyfast
track construction projects whereasplanningisavitalpartfor
the successful completion of precast projects. Being precast,
advance planning is necessary. Conventional method is the
most common practice for the planningofanyprecastprojects
whereas BIM software is not yet well-practiced. Hence,
software Tekla (a BIM software) has been adopted for the
planning of a precast construction project of a G+3 structure.
Precast planning involves precast element layout, casting
yard, moulds, production, stacking, transportation, erection,
and finishing of precast elements. This paper emphasizes the
application of BIM software for time optimization of the
planning of precast elements, since it benefits precast
construction planning especiallyinproductionplanning, saves
time in the planning process, prevents human errors,
automation of production and tracking of projects. The model
provides a platform where the information is storedanditcan
be utilized in various phases during the precast construction
process, directly by using functionalitiesinTeklastructures, or
by linking the building information to other software
solutions. Even though the softwarehasmoreadvantagesover
the conventional method, still the awareness of technology
needs more encouragement to meet the global benchmark.
Key Words: Precast Planning, Tekla, Organizer, Palletizer,
Crane Checks, Task Manager.
1. INTRODUCTION
Precast construction is one of the most promising solutions
to the fast-growing infrastructure in any country. Precast
construction has more advantages over cast-in-place
construction including better quality production, speedy
construction, less wastage,lessmanpowerrequirement,safe
construction site, etc. In precast construction, structural
components are standardized based on structural and
production requirements, produced in plants / yards at a
location nearer to the construction site, cured, transported
to the site and erected. Planning is the crucial stage for
successful completion of any precast construction.Effective,
detailed and advance planning is necessary for any precast
construction project
Building Information Modelling benefits the user by
providing a platform which enables to create and manage all
aspects of a building with the help of numerous virtual
models. With BIM, buildings can be created virtually before
they are constructed at the site and have many features
including model-based cost estimation, better builds, better
collaboration, and communication, etc.
1.1 Project Brief
A sample live project, Construction of additional buildings
for boys and girls hostels has been considered. It consists of
1+3 precast buildings of G+3 storey each.
No. of Buildings : 4 no.s
Total Built up Area : 4414.64 sqm per hostel
Plan Size : 69.79 m x 16.94 m
Height : + 17.3 m above GL
No. of Storeys : 4
Type of construction : Precast
2. METHODOLOGY
The challenge is to adopt a BIM software solution which
enables the planning of precast project in an effective
manner. Hence in this paper, Tekla structures has been
analyzed for precast planning and the time optimization in
precast planning using software is studied. All the activities
in a precast construction project, i.e. from quantity
estimation to project monitoring and tracking, can be done
using this BIM software. It helps to collaborate on site
activities with the schedule to track the project as well as to
compensate for the delays.
2.1 Precast Elements Layout
Precast element layout is the basic input for any precast
construction planning. Typical floor layout and thedetailsof
total precast elements for the project are listed below.
Fig -1: Typical Floor Plan
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1777
Table -1: Details of precast elements
Element
Total element per
hostel
Total elements need to be
produced
Wall 538 2152
Beam 96 384
Column 47 188
Slab 392 1568
Stairs 24 96
POD 8 32
Total 1105 4420
2.2 Modelling using BIM
The structural drawing can be imported to software, using
Reference model, from which the structure can be
developed. Reference model can be of various file formats
including IFC, DWG, XML, DXF, SKP, PDF, etc. From the
model, quantity estimation, pallet arrangements, lifting
hooks, cranes, stacking, scheduling and tracking has been
done using various tools namely organizer, palletizer, lifting
anchors, crane checker, stacker and task manager
respectively. The model developed is shown below.
Fig -2: 3D View of model
2.3 Quantity Estimation
Model based quantity estimate can be obtained from
software using organizer or reports. Organizer can be used
for managing all model information, for queries regarding
object properties and for object classification. Reports of
various aspects can be created using predefined or user
defined templates.
Software provides individual element estimate and it can be
sorted to get the required quantities. Summary of estimate
obtained from table are given below.
Table -2: Quantity estimate
Elements
Total no. of
elements
(no.s)
Volume of
concrete
(cu. m)
Weight
(ton)
Wall 538 1028.74 2571.78
Beam 96 57.1 142.74
Column 47 15.96 39.91
Slab 392 345.9 864.79
Stairs 24 51.56 128.91
Pod 8 18.55 46.36
Total 1105 1517.81 3794.49
Time optimization for quantity estimation using software is
approximately 85%.
2.4 Palletizer
Factory based production has all standard moulds and only
approximately 30% non-standard moulds need to be
produced for any project specification. Palletizertool isused
for planning the optimal pallet layout for precast elements.
Once the elements are imported to palletizer, it allocates
elements on the production pallets based on geometry,
visualizes them and defines the casting sequence. Limit
values and occupancy ratio (for optimizing) will be
automatically calculated and notified. Manual placing, low
spacing and UDA spacing are various optionsavailable.Even
though options for providing spacing between moulds for
activities like shuttering and de shuttering is not available,it
will provide approximate arrangement of moulds and it can
be exported to pdf. Time optimization is around 60% - 70%.
Fig -4: Pallet arrangement for typical walls
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1778
Fig -5: Pallet arrangement for typical slabs
2.5 Lifting Anchor
Lifting anchors is a tool used for assigning hooks for lifting
and handling of precast elements. The location of hooks is
assigned based on the element weight and properties and
hooks for all elements can be assigned together
automatically. Grade, type, diameter, embedded length and
other details of anchors needs to be provided as input and
based on it the lifting hooks will be assignedtoeachelement.
Time optimization approximately 50% on comparison with
conventional method.
Fig -6: Lifting Hooks in wall
2.6 Crane Manager
Crane check helps to assign the suitable crane for erection
based on the model. It is available only in crane manager
role. With the help of crane check, we can check number of
elements that can be erected with the selected crane placed
at specified locations for the assigned crane, lifting area and
rigging details (such as hook weight, capacity, jib length,
limit ratio, etc.). It performs checks for each configuration
and thus optimum configuration can be selected which
allows lifting of majority of elements. Crane model can be
assigned using the components MCTM, MCCM and Tower
Crane. The drawings of the appropriate configurationcan be
created along with lifting plan, lifting view and other lifting
details. Time optimization nearly 45%-50%.
Fig -7: Crane lifting view
2.7 Stacker
Stacker is a tool which is used to plan the arrangements of
elements in the trucks/ trailer. Based on the delivery dates
of elements, stack plan can be obtained, and it can also be
exported to pdf. For stacking planning, import the elements
to stacker and giveinformationlikemaximumcapacity,stack
model and custom model. Elements need to be arranged
manually in the stacker (even in real time model of trucks)
and it will notify when maximum load capacity is exceeded.
Details about how many elements can be transported in a
trip, number of trips required to transport elements needed
for erection and other necessary information regarding
transportation can be obtained. Time optimization upto
50%.
Fig -7: Stack plan for beams
2.8 Task Manager
Task manager enables the users to create and store
schedules and it links the elements to the corresponding
tasks. The tasks can be either created in Task managerorthe
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1779
tasks can be imported from other project management tools
such as Primavera P6 or MS Project. It incorporates time-
sensitive data into 3D models and controls the schedule at
various stages throughout the project. Time optimization
nearly 80%.
Fig -8: Schedule using Task Manager
2.9 Project Status
Progress status tool helps to visualize the progress of the
project according to theproduction/erectiondates.Byfixing
the review date, we can track the progress of work on each
day as well as delays in work can also be monitored easily.
The review dates can be adjusted to check the progress at
any span of project duration. Progress monitoring using
project status with the help of object representation is
shown below. Time optimization nearly 80% and helps for
speedy construction.
Fig -9: Progress Monitoring
2.10 Drawings
The software enablesto extractstheshopandformdrawings
from the model automatically and the production data can
also be exported to other formats like BVBS, unitechnik or
Elematic as well as data can be directly transferred to rebar
manufacturing machinery and to differentprecastandrebar
production management software. Cast unit drawingsgivea
better understanding of the production of elements.
Model and the related information can be exported to
different formats including IFC, pdf, drawings, etc. Time
optimization approximately 90%.
3. CONCLUSIONS
The conventional method of planning is based on the
experience of planner whereas software for planning is
based on the model. BIM software benefits precast
construction planning especially in production planning,
saves time in the planning process,preventinghuman errors
in information transfer between detailing and production
and tracking of projects. Some of the key aspects in Tekla
over conventional method are:
 The planning process is dependent on the model as
well as it saves time in planning.
 Progress monitoring and tracking are easy as they
can be tracked with the help of the model by the
collaboration of site engineers and planner.
 Model can be used for storing information and can
be utilized when needed, using various tools
available or by exporting to other formats.
 Trimble Connect is a cloud-based platform which
enables all the stakeholders to track the progress
and for discussions.
 Model-based quantity estimation, optimized pallet
calculation, and stacker, crane assignment basedon
the model, drawings for automated production and
progress monitoring and tracking are some of the
features of the software.
 Optimization of time and resources is a key benefit
of Tekla. Up to 85% of time optimization for
planning can be obtained using Tekla for precast
projects.
 In UK 25% of construction is in precast, 40-50% in
North European countries, whereas in India, only
2% of construction is in precast. Hence, the
awareness of technology needs more
encouragement to meet the global benchmark.
 Build once, build right, build to last.
ACKNOWLEDGEMENT
We express our deep sense of gratitude and indebtedness to
Larsen & Toubro Constructions (L&T), HQ, Chennai for
giving us the opportunity to carry out the study in their
organization. A note of special thanks to Mr. T. Arun Kumar
and Mr. R. Nallasivam for continuous support and
encouragement. We would like to express our special
gratitude and thanks to all other persons who knowingly or
unknowingly helped us throughout the project work.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1780
REFERENCES
[1] Dong Wang, Guiwen Liu, Kaijian Li, Tongjing Wang,
Asheen Shrestha, Igor Martek and Xiaobo Tao (2018),
“Layout OptimizationModel fortheProduction Planning
of Precast Concrete Building Components,Sustainability
2018, 10,1807; doi:10.3390/su10061807
[2] Kuo-Chuan Shih and Shu-Shun Liu (2010), “An
Optimization Model for Precast Project Planning using
Group Concepts”, Journal of the Operations Research
Society of Japan, volume 53, No. 3, pp.189-206
[3] S. Madhu Anand (2016), “Architectural Precast Façade
Construction for High Rise Buildings- Construction
Method Approach”, International Journal of Researchin
Engineering and Technology, volume 05, special issue
20
[4] Shreyanka S. MuraiandAshwinM.Joshi(2018),“Precast
Construction Methodology in Construction Industry”
[5] TEKLA structures for precast, User Assistance-
https://teklastructures.support.tekla.com
[6] An Overview of Construction of Buildings in Precast
Concrete masterbuilder-
https://www.masterbuilder.co.in/an-overview-
ofconstruction-of-buildings-in-precast-concrete/ D.
Kornack and P. Rakic, “Cell Proliferation without
Neurogenesis in Adult Primate Neocortex,” Science, vol.
294, Dec. 2001, pp. 2127-2130,
doi:10.1126/science.1065467.
BIOGRAPHIES
S. Madhu Anand, Post Graduate in structures with field
experience of more than 20 years in L&T Constructions as
Head of Construction methods planning for Residential
Buildings & Factories. Provided methods for landmark
buildings in India. Good knowledge in latest construction
technology, precast methods and high rise building
construction, trouble shooting at construction site and
expertise in selection of right Site logistics, Suitable
formwork, Plant and Machineries, erection scheme for
structural steel and shoring system for deep excavation.
Ujjwal Kumar completed B.Tech in Civil Engineering from
Pondicherry EngineeringCollegein2019.UndergoneProject
Internship in L&T Construction on precast construction
planning using conventional methodandsoftwareapproach.
Arunima Rajish completed B.TechinCivil Engineeringfrom
Pondicherry EngineeringCollegein2019.UndergoneProject
Internship in L&T Construction on precast construction
planning using conventional methodandsoftwareapproach.

More Related Content

PDF
evolution of cad/cam
PPTX
CAD/CAM Lecture #2
PDF
geometric modelling and PLC
PDF
CADCAM CAE Notes
PPTX
CAD/CAM Lecture #5
PPTX
CAD/CAM Lecture #4
PPTX
Lecture 3 Computer - Aided Manufacturing (CAM)
PDF
IRJET- Systematic Construction Equipment Handling in Construction Industr...
evolution of cad/cam
CAD/CAM Lecture #2
geometric modelling and PLC
CADCAM CAE Notes
CAD/CAM Lecture #5
CAD/CAM Lecture #4
Lecture 3 Computer - Aided Manufacturing (CAM)
IRJET- Systematic Construction Equipment Handling in Construction Industr...

What's hot (20)

PDF
IRJET- Final Modeling and Prototype & Analysis of Hydraulic Scissor Lift
PDF
Design of computer aided process plan for a casing cover plate
PDF
IRJET-Automation in Construction –The Need of Mega Construction and Fast Trac...
PPTX
Software presentation
PDF
BIM, Lean & Advanced Work Packaging - How do they fit together?
PDF
Caso de Sucesso da Magna Steyr
PDF
Ppc 2mark answer
PPTX
Cad cam
PPTX
Intro to CAD/CAM/CIM
PPTX
BIM Based Project Controls
PDF
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
PPTX
Cad and cam
PPSX
Introduction of computer aided manufacturing.pptx
PDF
IRJET- Equipment Planning and Management in Road Construction Project
PDF
Unit i computer aided design
PDF
CNC & 3D Printing Lab Manual
PDF
IRJET- Equipment Planning and Management in Road Construction Project
PDF
INFORMATION TECHNOLOGY MODEL FOR PRODUCT LIFECYCLE ENGINEERING
PDF
Information technology model for product lifecycle engineering
PDF
CAD/CAM/CIM ( Lecture 2 model construction and product design)
IRJET- Final Modeling and Prototype & Analysis of Hydraulic Scissor Lift
Design of computer aided process plan for a casing cover plate
IRJET-Automation in Construction –The Need of Mega Construction and Fast Trac...
Software presentation
BIM, Lean & Advanced Work Packaging - How do they fit together?
Caso de Sucesso da Magna Steyr
Ppc 2mark answer
Cad cam
Intro to CAD/CAM/CIM
BIM Based Project Controls
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
Cad and cam
Introduction of computer aided manufacturing.pptx
IRJET- Equipment Planning and Management in Road Construction Project
Unit i computer aided design
CNC & 3D Printing Lab Manual
IRJET- Equipment Planning and Management in Road Construction Project
INFORMATION TECHNOLOGY MODEL FOR PRODUCT LIFECYCLE ENGINEERING
Information technology model for product lifecycle engineering
CAD/CAM/CIM ( Lecture 2 model construction and product design)
Ad

Similar to IRJET- Time Optimization of Precast Planning using BIM Software (20)

PDF
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
PDF
Integrating Project Management Information System and BIM for Inspecting and ...
PDF
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
PDF
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
PDF
STUDY OF BUILDING INFORMATION MODELING PROCESS
PDF
Application of Building Information Modelling Software’s for Planning and Sch...
PDF
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
PDF
IRJET- Redevelopment of Structure with the Help of Building Information M...
PDF
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
PDF
RURAL ROAD DESIGN ENHANCEMENT USING CIVIL 3D
PDF
STUDY ON BUILDING INFORMATION MODELING AND IMPLEMENTATION OF CLASH DETECTION ...
PPTX
Building Information Modelling ppt.pptx
PDF
Software Presentation Slides
PDF
Software
PDF
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
PDF
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
PDF
A Statistical Analysis Of Building Information Modeling In Project Management
PDF
A Statistical Analysis of Building Information Modeling in Project Management
PDF
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
PDF
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
Integrating Project Management Information System and BIM for Inspecting and ...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
STUDY OF BUILDING INFORMATION MODELING PROCESS
Application of Building Information Modelling Software’s for Planning and Sch...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Redevelopment of Structure with the Help of Building Information M...
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
RURAL ROAD DESIGN ENHANCEMENT USING CIVIL 3D
STUDY ON BUILDING INFORMATION MODELING AND IMPLEMENTATION OF CLASH DETECTION ...
Building Information Modelling ppt.pptx
Software Presentation Slides
Software
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
A Statistical Analysis Of Building Information Modeling In Project Management
A Statistical Analysis of Building Information Modeling in Project Management
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...

Recently uploaded (20)

PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PPT
Total quality management ppt for engineering students
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PPT
Occupational Health and Safety Management System
PDF
PPT on Performance Review to get promotions
PPTX
Artificial Intelligence
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PPTX
Current and future trends in Computer Vision.pptx
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
UNIT 4 Total Quality Management .pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
communication and presentation skills 01
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PPT
introduction to datamining and warehousing
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
Total quality management ppt for engineering students
R24 SURVEYING LAB MANUAL for civil enggi
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
Occupational Health and Safety Management System
PPT on Performance Review to get promotions
Artificial Intelligence
Exploratory_Data_Analysis_Fundamentals.pdf
Current and future trends in Computer Vision.pptx
III.4.1.2_The_Space_Environment.p pdffdf
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
UNIT 4 Total Quality Management .pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
communication and presentation skills 01
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Automation-in-Manufacturing-Chapter-Introduction.pdf
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
introduction to datamining and warehousing
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...

IRJET- Time Optimization of Precast Planning using BIM Software

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1776 TIME OPTIMIZATION OF PRECAST PLANNING USING BIM SOFTWARE S. Madhu Anand1, Ujjwal Kumar2, Arunima Rajish3 1Head- Construction Methods Planning Centre, Residential Buildings and Factories, L&T Construction, Chennai 2,3B.Tech Graduate, Department of Civil Engineering, Pondicherry Engineering College, Puducherry ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Time is the essence of any project. Adoption of precast construction is the key to meetthetimeline foranyfast track construction projects whereasplanningisavitalpartfor the successful completion of precast projects. Being precast, advance planning is necessary. Conventional method is the most common practice for the planningofanyprecastprojects whereas BIM software is not yet well-practiced. Hence, software Tekla (a BIM software) has been adopted for the planning of a precast construction project of a G+3 structure. Precast planning involves precast element layout, casting yard, moulds, production, stacking, transportation, erection, and finishing of precast elements. This paper emphasizes the application of BIM software for time optimization of the planning of precast elements, since it benefits precast construction planning especiallyinproductionplanning, saves time in the planning process, prevents human errors, automation of production and tracking of projects. The model provides a platform where the information is storedanditcan be utilized in various phases during the precast construction process, directly by using functionalitiesinTeklastructures, or by linking the building information to other software solutions. Even though the softwarehasmoreadvantagesover the conventional method, still the awareness of technology needs more encouragement to meet the global benchmark. Key Words: Precast Planning, Tekla, Organizer, Palletizer, Crane Checks, Task Manager. 1. INTRODUCTION Precast construction is one of the most promising solutions to the fast-growing infrastructure in any country. Precast construction has more advantages over cast-in-place construction including better quality production, speedy construction, less wastage,lessmanpowerrequirement,safe construction site, etc. In precast construction, structural components are standardized based on structural and production requirements, produced in plants / yards at a location nearer to the construction site, cured, transported to the site and erected. Planning is the crucial stage for successful completion of any precast construction.Effective, detailed and advance planning is necessary for any precast construction project Building Information Modelling benefits the user by providing a platform which enables to create and manage all aspects of a building with the help of numerous virtual models. With BIM, buildings can be created virtually before they are constructed at the site and have many features including model-based cost estimation, better builds, better collaboration, and communication, etc. 1.1 Project Brief A sample live project, Construction of additional buildings for boys and girls hostels has been considered. It consists of 1+3 precast buildings of G+3 storey each. No. of Buildings : 4 no.s Total Built up Area : 4414.64 sqm per hostel Plan Size : 69.79 m x 16.94 m Height : + 17.3 m above GL No. of Storeys : 4 Type of construction : Precast 2. METHODOLOGY The challenge is to adopt a BIM software solution which enables the planning of precast project in an effective manner. Hence in this paper, Tekla structures has been analyzed for precast planning and the time optimization in precast planning using software is studied. All the activities in a precast construction project, i.e. from quantity estimation to project monitoring and tracking, can be done using this BIM software. It helps to collaborate on site activities with the schedule to track the project as well as to compensate for the delays. 2.1 Precast Elements Layout Precast element layout is the basic input for any precast construction planning. Typical floor layout and thedetailsof total precast elements for the project are listed below. Fig -1: Typical Floor Plan
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1777 Table -1: Details of precast elements Element Total element per hostel Total elements need to be produced Wall 538 2152 Beam 96 384 Column 47 188 Slab 392 1568 Stairs 24 96 POD 8 32 Total 1105 4420 2.2 Modelling using BIM The structural drawing can be imported to software, using Reference model, from which the structure can be developed. Reference model can be of various file formats including IFC, DWG, XML, DXF, SKP, PDF, etc. From the model, quantity estimation, pallet arrangements, lifting hooks, cranes, stacking, scheduling and tracking has been done using various tools namely organizer, palletizer, lifting anchors, crane checker, stacker and task manager respectively. The model developed is shown below. Fig -2: 3D View of model 2.3 Quantity Estimation Model based quantity estimate can be obtained from software using organizer or reports. Organizer can be used for managing all model information, for queries regarding object properties and for object classification. Reports of various aspects can be created using predefined or user defined templates. Software provides individual element estimate and it can be sorted to get the required quantities. Summary of estimate obtained from table are given below. Table -2: Quantity estimate Elements Total no. of elements (no.s) Volume of concrete (cu. m) Weight (ton) Wall 538 1028.74 2571.78 Beam 96 57.1 142.74 Column 47 15.96 39.91 Slab 392 345.9 864.79 Stairs 24 51.56 128.91 Pod 8 18.55 46.36 Total 1105 1517.81 3794.49 Time optimization for quantity estimation using software is approximately 85%. 2.4 Palletizer Factory based production has all standard moulds and only approximately 30% non-standard moulds need to be produced for any project specification. Palletizertool isused for planning the optimal pallet layout for precast elements. Once the elements are imported to palletizer, it allocates elements on the production pallets based on geometry, visualizes them and defines the casting sequence. Limit values and occupancy ratio (for optimizing) will be automatically calculated and notified. Manual placing, low spacing and UDA spacing are various optionsavailable.Even though options for providing spacing between moulds for activities like shuttering and de shuttering is not available,it will provide approximate arrangement of moulds and it can be exported to pdf. Time optimization is around 60% - 70%. Fig -4: Pallet arrangement for typical walls
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1778 Fig -5: Pallet arrangement for typical slabs 2.5 Lifting Anchor Lifting anchors is a tool used for assigning hooks for lifting and handling of precast elements. The location of hooks is assigned based on the element weight and properties and hooks for all elements can be assigned together automatically. Grade, type, diameter, embedded length and other details of anchors needs to be provided as input and based on it the lifting hooks will be assignedtoeachelement. Time optimization approximately 50% on comparison with conventional method. Fig -6: Lifting Hooks in wall 2.6 Crane Manager Crane check helps to assign the suitable crane for erection based on the model. It is available only in crane manager role. With the help of crane check, we can check number of elements that can be erected with the selected crane placed at specified locations for the assigned crane, lifting area and rigging details (such as hook weight, capacity, jib length, limit ratio, etc.). It performs checks for each configuration and thus optimum configuration can be selected which allows lifting of majority of elements. Crane model can be assigned using the components MCTM, MCCM and Tower Crane. The drawings of the appropriate configurationcan be created along with lifting plan, lifting view and other lifting details. Time optimization nearly 45%-50%. Fig -7: Crane lifting view 2.7 Stacker Stacker is a tool which is used to plan the arrangements of elements in the trucks/ trailer. Based on the delivery dates of elements, stack plan can be obtained, and it can also be exported to pdf. For stacking planning, import the elements to stacker and giveinformationlikemaximumcapacity,stack model and custom model. Elements need to be arranged manually in the stacker (even in real time model of trucks) and it will notify when maximum load capacity is exceeded. Details about how many elements can be transported in a trip, number of trips required to transport elements needed for erection and other necessary information regarding transportation can be obtained. Time optimization upto 50%. Fig -7: Stack plan for beams 2.8 Task Manager Task manager enables the users to create and store schedules and it links the elements to the corresponding tasks. The tasks can be either created in Task managerorthe
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1779 tasks can be imported from other project management tools such as Primavera P6 or MS Project. It incorporates time- sensitive data into 3D models and controls the schedule at various stages throughout the project. Time optimization nearly 80%. Fig -8: Schedule using Task Manager 2.9 Project Status Progress status tool helps to visualize the progress of the project according to theproduction/erectiondates.Byfixing the review date, we can track the progress of work on each day as well as delays in work can also be monitored easily. The review dates can be adjusted to check the progress at any span of project duration. Progress monitoring using project status with the help of object representation is shown below. Time optimization nearly 80% and helps for speedy construction. Fig -9: Progress Monitoring 2.10 Drawings The software enablesto extractstheshopandformdrawings from the model automatically and the production data can also be exported to other formats like BVBS, unitechnik or Elematic as well as data can be directly transferred to rebar manufacturing machinery and to differentprecastandrebar production management software. Cast unit drawingsgivea better understanding of the production of elements. Model and the related information can be exported to different formats including IFC, pdf, drawings, etc. Time optimization approximately 90%. 3. CONCLUSIONS The conventional method of planning is based on the experience of planner whereas software for planning is based on the model. BIM software benefits precast construction planning especially in production planning, saves time in the planning process,preventinghuman errors in information transfer between detailing and production and tracking of projects. Some of the key aspects in Tekla over conventional method are:  The planning process is dependent on the model as well as it saves time in planning.  Progress monitoring and tracking are easy as they can be tracked with the help of the model by the collaboration of site engineers and planner.  Model can be used for storing information and can be utilized when needed, using various tools available or by exporting to other formats.  Trimble Connect is a cloud-based platform which enables all the stakeholders to track the progress and for discussions.  Model-based quantity estimation, optimized pallet calculation, and stacker, crane assignment basedon the model, drawings for automated production and progress monitoring and tracking are some of the features of the software.  Optimization of time and resources is a key benefit of Tekla. Up to 85% of time optimization for planning can be obtained using Tekla for precast projects.  In UK 25% of construction is in precast, 40-50% in North European countries, whereas in India, only 2% of construction is in precast. Hence, the awareness of technology needs more encouragement to meet the global benchmark.  Build once, build right, build to last. ACKNOWLEDGEMENT We express our deep sense of gratitude and indebtedness to Larsen & Toubro Constructions (L&T), HQ, Chennai for giving us the opportunity to carry out the study in their organization. A note of special thanks to Mr. T. Arun Kumar and Mr. R. Nallasivam for continuous support and encouragement. We would like to express our special gratitude and thanks to all other persons who knowingly or unknowingly helped us throughout the project work.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 11 | Nov 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1780 REFERENCES [1] Dong Wang, Guiwen Liu, Kaijian Li, Tongjing Wang, Asheen Shrestha, Igor Martek and Xiaobo Tao (2018), “Layout OptimizationModel fortheProduction Planning of Precast Concrete Building Components,Sustainability 2018, 10,1807; doi:10.3390/su10061807 [2] Kuo-Chuan Shih and Shu-Shun Liu (2010), “An Optimization Model for Precast Project Planning using Group Concepts”, Journal of the Operations Research Society of Japan, volume 53, No. 3, pp.189-206 [3] S. Madhu Anand (2016), “Architectural Precast Façade Construction for High Rise Buildings- Construction Method Approach”, International Journal of Researchin Engineering and Technology, volume 05, special issue 20 [4] Shreyanka S. MuraiandAshwinM.Joshi(2018),“Precast Construction Methodology in Construction Industry” [5] TEKLA structures for precast, User Assistance- https://teklastructures.support.tekla.com [6] An Overview of Construction of Buildings in Precast Concrete masterbuilder- https://www.masterbuilder.co.in/an-overview- ofconstruction-of-buildings-in-precast-concrete/ D. Kornack and P. Rakic, “Cell Proliferation without Neurogenesis in Adult Primate Neocortex,” Science, vol. 294, Dec. 2001, pp. 2127-2130, doi:10.1126/science.1065467. BIOGRAPHIES S. Madhu Anand, Post Graduate in structures with field experience of more than 20 years in L&T Constructions as Head of Construction methods planning for Residential Buildings & Factories. Provided methods for landmark buildings in India. Good knowledge in latest construction technology, precast methods and high rise building construction, trouble shooting at construction site and expertise in selection of right Site logistics, Suitable formwork, Plant and Machineries, erection scheme for structural steel and shoring system for deep excavation. Ujjwal Kumar completed B.Tech in Civil Engineering from Pondicherry EngineeringCollegein2019.UndergoneProject Internship in L&T Construction on precast construction planning using conventional methodandsoftwareapproach. Arunima Rajish completed B.TechinCivil Engineeringfrom Pondicherry EngineeringCollegein2019.UndergoneProject Internship in L&T Construction on precast construction planning using conventional methodandsoftwareapproach.