IT Project Management
In this course, we only introduce project management, but the
main
concepts are covered. In order to be a good project manager,
you
should specialize in this area. Project management certificates
are
offered by universities such as UMUC, and there is at least one
recognized certification authority—the Project Management
Institute
(PMI). PMI evaluates both your experience as well as your
knowledge
before a certification is awarded. So, you can see that project
management cannot really be learned from a book or a class, but
from
those combined with experience in the "real world."
A couple of definitions with which you should be familiar are:
• project: a temporary endeavor undertaken to create a unique
product, service, or result
• project management: the application of knowledge, skills,
tools, and techniques to project activities to meet project
requirements
What is the role of a project manager? Is it different for an IT
project
manager? A project manager must control the four key variables
associated with any project: time (schedule), resources (human
and
financial), scope of work, and quality.
The project manager leads the development of a project plan
that
takes all of these into consideration. Frequently, trade-offs are
required. For instance, the budget may be limited, which
restricts the
scope of the work and perhaps how many people can work on
the
project. Or, the project is needed within a certain time frame,
which
may drive up the costs, since more people would have to be
hired to
complete the project on time.
When any one of the four variables changes, there is an impact
on at
least one (and often more than one) other variable. A strong
project
manager pays attention to the project plan and the progress of
the
project against the plan, and manages the variables
appropriately to
ensure successful completion of the project. Successful
completion is
accomplished if the project is delivered on time, stays within
the
allocated budget, performs the required functions, and does so
correctly. This role is the same for any project manager,
including an
IT project manager.
1
The four variables are interdependent. You cannot change one
without affecting the others. For example,
cost of the project or decreasing the scope of the project to meet
the new deadline.
project's time frame or increasing the project's cost—or both—
to meet the increased scope changes.
necessitate a reevaluation of the scope and/or the quality. The
scope may need to be reduced to avoid decreasing the quality,
or if the scope must remain unchanged, quality will suffer.
time and money to incorporate more perfection and test all
possible outcomes for correctness.
Project management is the science of making intelligent trade-
offs
among time, cost, scope, and quality. This is the job of the
project
manager. As things change, the project manager must adjust the
four
variables to keep them in balance.
The first step is the selection of strategic projects. Now, the
project
manager does not select the projects alone; usually, that is done
by
senior management after the presentation of a "business case"
that
outlines the project plan, stating the objectives (how the project
supports the corporate strategy), cost, schedule, functionality,
and risk
associated with the proposed project. Once senior management
allocates resources, the project manager ensures the project plan
is
executed according to plan. A smart project manager makes sure
that
a plan has "SMART" criteria—aspects to ensure that the project
has
created understandable and measurable objectives:
• Specific
• Measurable
• Agreed upon
• Realistic
• Time framed
These objectives are documented in the project plan, used
throughout
the project's life to help keep the project on track to a
successful
2
completion. The project manager monitors progress against the
plan
and manages any changes and mitigates risks as they become
known.
Project risk management involves identifying potential events
or
conditions that could have a negative effect on the project,
estimating
the impact if the risk occurs, determining a mitigation strategy
to
reduce the likelihood of the risk occurring, and identifying what
will be
done if the event or condition actually arises.
Since almost no project goes exactly according to the plan, the
project
manager needs a tool to detect and manage the changes. The
process
of change management is this tool. The project manager
documents
all approved changes, revises the project plan accordingly, and
then
continues managing and monitoring the project.
Keep in mind that the job of the project manager is to stay on
top of
all the variables and manage the cost, schedule (time), scope
and
quality. He or she must seek additional resources (money or
people)
or a schedule change (time) when the scope increases, and must
be
able to articulate the effect on quality if additional resources or
a
schedule change are not authorized. The project manager is
responsible to senior leaders to monitor the variables, keep
leadership
informed, and propose solutions for changes as they occur.
We begin our study of IT project management by reading
Section III
of the
Solution
Management module. Leadership and change
management are also important aspects of project management,
and
will be discussed in more depth next week, in the Leadership
and
Change Management module. The next sections include
readings on
project management and the project life cycle. We then take a
look at
why projects fail and risk management.
3
Week 4 Discussion 1
Top of Form
4
· 5
Please respond to the following: "Brand Stretch Spectrum and
Market Product Grid"
Assess the importance of evaluating newly developed health
care products in order to determine whether the products should
carry existing brand names or whether they should be assigned
new brand names. Suggest realistic branding strategies needed
for marketers to evaluate newly developed health care products
or services. Provide support for your rationale.
Use the Internet to research the product offerings of a local
health care organization. (Note:These offerings are often found
on the health care organizations homepage.) Based on your
knowledge of your local region, consider the potential markets
for these products. With the grid, you should, at a minimum,
analyze the resulting market-product combination. Determine
whether or not the product offerings that you selected are
consistent with the perceived selections of the given health care
entity. Explain your rationale.
Reply to classmate 150 words
Discussion 2
Please respond to the following: "Lateral Marketing Strategy"
· Assess the value of target marketing as an effective health
care marketing strategy. Appraise the degree to which vertical
and traditional segmentation help marketing managers use target
marketing strategies. Support your rationale with at least two
(2) specific examples of target marketing within a health care
organization with which you are familiar.
· Evaluate the impact of lateral segmentation in encouraging
marketing managers to look broadly at markets in order to
identify previously overlooked opportunities. Provide at least
one (1) specific example of quality initiatives within a health
care organization.
Reply to classmate 150 words
Case Study 1: Revitalizing a Brand
Due Week 4 and worth 200 points
Read the case study titled “Revitalizing a Brand”, located in the
online course shell. Use the Internet or Strayer databases to
research the branding and communication strategies of one (1)
health services organization that is similar to the health services
organizations mentioned in the case study.
Write a four to six (4-6) page paper in which you:
1. Describe the current marketing communication, identity, and
brand position of Plaza Home Health Services.
2. Conduct a Strengths Weaknesses Opportunities Threats
(SWOT) analysis associated with the current marketing
communication, identity, and brand position of Plaza Home
Health Services.
3. Assess the importance of benchmarking in Plaza Home
Health Services’ development and implementation of an
effective brand strategy (marketing communication, identity,
and brand position).
4. Compare branding and communication strategies of a similar
health services organization with that of Plaza Home Health
Services. Determine whether or not Plaza Home Health Services
should apply additional best practices into its current branding
and communication strategies. Provide a rationale and support
for your response.
5. Use at least five (5) quality academic resources. Note:
Wikipedia and other Websites do not qualify as academic
resources.
Your assignment must follow these formatting requirements:
· Be typed, double spaced, using Times New Roman font (size
12), with one-inch margins on all sides; citations and references
must follow APA or school-specific format. Check with your
professor for any additional instructions.
· Include a cover page containing the title of the assignment, the
student’s name, the professor’s name, the course title, and the
date. The cover page and the reference page are not included in
the required assignment page length.
What is Project Management? by Merrie Barron and Andrew R.
Barron is available under a Creative
Commons Attribution 3.0 license. © 2009, Merrie Barron and
Andrew R. Barron.
http://cnx.org/contents/[email protected]/What-is-Project-
Management
http://creativecommons.org/licenses/by/3.0/
http://creativecommons.org/licenses/by/3.0/
OpenStax-CNX module: m31508 1
What is Project Management?
∗
Merrie Barron, PMP, CSM
Andrew R. Barron
This work is produced by OpenStax-CNX and licensed under the
Creative Commons Attribution License 3.0†
You've determined that you have a project. What now? The
notes you scribbled down on the back of
the napkin at lunch are a start, but not exactly good project
management practice. Too often, organizations
follow Nike's advice when it comes to managing projects when
they �just do it.� An assignment is made
and the project team members jump directly into the
development of the product or service requested. In
the end the delivered product doesn't meet the expectations of
the customer. Unfortunately, many projects
follow this poorly constructed path and that is a primary
contributor to why a large percentage of projects
don't meet their original objectives de�ned by performance,
schedule, and budget.
In the United States, more than $250 billion dollars is spent
each year on IT application development
in approximately 175,000 projects. The Standish Group (a
Boston-based leader in project and value perfor-
mance research) just released the summary version of their 2009
CHAOS Report that tracks project failure
rates across a broad range of companies and industries (Figure
1).
Figure 1: Summary of 2009 Standish Group CHAOS report.
Jim Johnson, chairman of the Standish Group has stated that
�this year's results show a marked decrease
in project success rates, with 32% of all projects succeeding
which are delivered on time, on budget, with
∗ Version 1.4: Oct 14, 2009 11:21 am -0500
†http://creativecommons.org/licenses/by/3.0/
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/[email protected]”
OpenStax-CNX module: m31508 2
required features and functions, 44% were challenged which are
late, over budget, and/or with less than
the required features and functions and 24% failed which are
cancelled prior to completion or delivered and
never used.�
When are companies going to stop wasting billions of dollars on
failed projects? The vast majority of this
waste is completely avoidable; simply get the right business
needs (requirements) understood early in the
process and ensure that project management techniques are
applied and followed and the project activities
are monitored.
Applying good project management discipline is the way to help
reduce the risks. But keep in mind,
having good project management skills does not mean you have
no problems, it does not mean that risks go
away, or that there won't be any surprises. The value of good
project management is that you have standard
processes in place to deal with all contingencies.
Project Management is the application of knowledge, skills,
tools, and techniques applied to project
activities in order to meet the project requirements. Project
management is a process that includes planning,
putting the project plan into action, and measuring progress and
performance.
Managing a project includes identifying your project's
requirements; writing down what everyone needs
from the project. What are the objectives for your project?
When everyone understands the goal, it's much
easier to keep them all on the right path. Make sure you set
goals that everyone agrees on to avoid team
con�icts later on. Understanding and addressing the needs of
everyone a�ected by the project means the
end result of your project is far more likely to satisfy your
stakeholders, and last but not least, as project
manager you will also be balancing the many competing project
constraints.
On any project, you will have a number of competing project
constraints that are competing for your
attention. They are cost, scope, quality, risk, resources and
time.
• Cost is budget approved for the project including all necessary
expenses needed to deliver the project.
Within organizations, project managers have to balance between
not running out of money and not
under spending because many projects receive funds or grants
that have contract clauses with an �use
it or lose it� approach to project funds. Poorly executed budget
plans can result in a last minute rush
to spend the allocated funds. For virtually all projects, cost is
ultimately a limiting constraint; few
projects can go over budget without eventually requiring a
corrective action.
• Scope is what the project is trying to achieve, it entails all the
work involved in delivering the projects
outcomes and the processes used to produce them. It is the
reason and the purpose of the project.
• Quality is the standards and criteria to which the project's
products must be delivered for them to
perform e�ectively. First, the product must perform to provide
the functionality expected, and to solve
the problem, and deliver the bene�t and value expected of it. It
must also meet other performance
requirements, or service levels, such as availability, reliability
and maintainability, and have acceptable
�nish and polish. Quality on a project is controlled through
quality assurance (QA) that is the process
of evaluating overall project's performance on a regular basis to
provide con�dence that the project
will satisfy the relevant quality standards.
• Risk is de�ned by potential external events that will have a
negative impact on your project if they
occur. Risk refers to the combination of the probability the
event will occur and the impact on the
project if the event occurs. If the combination of the probability
of the occurrence and the impact to
the project is too high, you should identify the potential event
as a risk and put a proactive plan in
place to manage the risk.
• Resources are required to carry out the project tasks. They can
be people, equipment, facilities,
funding, or anything else capable of de�nition (usually other
than labor) required for the completion
of a project activity.
• Time is de�ned as the time to complete the project. Time is
often the most frequent project oversight
in developing projects. This is re�ected in missed deadlines and
incomplete deliverables. Proper control
of the schedule requires the careful identi�cation of tasks to be
performed, an accurate estimation of
their durations, the sequence in which they are going to be
done, and how people and other resources
are allocated.
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/[email protected]”
OpenStax-CNX module: m31508 3
You may have heard of the term �Triple Constraint� which
traditionally only consisted of Time, Cost &
Scope. These are the primary competing project constraints that
you have to be aware of most. The triple
constraint is illustrated in the form of a triangle to visualize the
project work and to see the relationship
between the scope/quality, schedule/time, and cost/resource
(Figure 2).
Figure 2: A schematic of the triple constraint triangle.
In this triangle, each side represents one of the constraints (or
related constraints) wherein any changes
to any one side cause a change in the other sides. The best
projects have a perfectly balanced triangle.
Maintaining this balance is di�cult because projects are prone
to change. For example, if scope increases,
cost and time may increase disproportionately. Alternatively, if
the amount of money you have for your
project decreases, you may be able to do as much, but your time
may increase.
Your project may have additional constraints that you are
facing, and as the project manager you have to
balance the needs of these constraints against the needs of the
stakeholders and against your project goals.
For instance, if your sponsor wants to add functionality to the
original scope you will very likely need more
money to �nish the project or if they cut the budget you have to
reduce the quality of your scope and if
you don't get the appropriate resources to work on your project
tasks you will have to extend your schedule
because the resources you have take much longer to �nish the
work.
You get the idea; they are all dependent on each other. Think of
all of these constraints as the classic
carnival game of Whac-a-mole (Figure 3). Each time you try to
push one mole back in the hole, another one
pops out. The best advice is to rely on your project team to keep
these moles in place!
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/[email protected]”
OpenStax-CNX module: m31508 4
Figure 3: Go to
www.dorneypark.com/public/online_fun/mole.cfm to play
Whac-a-mole.
Here is an example of a project that cut quality because the
project costs were �xed. The P-36 oil
platform (Figure 4) was the largest �oating production platform
in the world capable of processing 180,000
barrels of oil per day and 7.2 million cubic meters of gas per
day. Located in the Roncador Field, Campos
Basin, Brazil the P-36 was operated by Petrobras.
Figure 4: The Petrobras P-36 oil platform.
In March 2001, the P-36 was producing around 84,000 barrels
of oil and 1.3 million cubic meters of gas
per day when it became destabilized by two explosions and
subsequently sank in 3900 feet of water with
1650 short tons of crude oil remaining on board, killing 11
people.
The sinking is attributed to a complete failure in quality
assurance and pressure for increased production
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/[email protected]”
OpenStax-CNX module: m31508 5
led to corners being cut on safety procedures. It is listed as one
of the most expensive accidents with a price
tag of $515,000,000.
The following quote is from a Petrobras executive, citing the
bene�ts of cutting quality assurance and
inspection costs on the project, while the accompanying pictures
are the result of this proud achievement in
project management by Petrobras.
Figure 5: "Petrobras has established new global benchmarks for
the generation of exceptional share-
holder wealth through an aggressive and innovative program of
cost cutting on its P36 production facility."
Figure 6: "Conventional constraints have been successfully
challenged and replaced with new paradigms
appropriate to the globalized corporate market place."
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/f0a795f0-0309-
43f1-b93c-eb77[email protected]”
OpenStax-CNX module: m31508 6
Figure 7: "Through an integrated network of facilitated
workshops, the project successfully rejected the
established constricting and negative in�uences of prescriptive
engineering, onerous quality requirements,
and outdated concepts of inspection and client control."
Figure 8: "Elimination of these unnecessary straitjackets has
empowered the project's suppliers and
contractors to propose highly economical solutions, with the
win-win bonus of enhanced pro�tability
margins for themselves."
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/[email protected]”
OpenStax-CNX module: m31508 7
Figure 9: "The P36 platform shows the shape of things to come
in the unregulated global market
economy of the 21st century."
The dynamic trade-o�s between the project constraint values
has been humorously but accurately de-
scribed in Figure 10.
Figure 10: A sign seen at an automotive repair shop.
1 Bibliography
• CHAOS 2009 Summary and EPPM Study, The Standish Group,
Boston, MA (2009).
http://cnx.org/content/m31508/1.4/
"Download for free at http://cnx.org/contents/[email protected]”

More Related Content

PPTX
Project Management Overview
PPT
Ch01
PPT
Software Project Management Basics
PPTX
Project Management for Medical Informatics.
PPT
Ben Mkt 347 Week 4
PPTX
Fundamentals of Project Management
PPTX
1 b. introduction to project management
DOCX
Read about the Quality Management Process on page 25 of the text. .docx
Project Management Overview
Ch01
Software Project Management Basics
Project Management for Medical Informatics.
Ben Mkt 347 Week 4
Fundamentals of Project Management
1 b. introduction to project management
Read about the Quality Management Process on page 25 of the text. .docx

Similar to IT Project Management In this course, we only introduce p.docx (20)

PPTX
13115 intro to project management presentation
PPTX
L1project management (2).pptxmlnmklmlmkmkmklmk
PPT
PDF
Project Manager Primer
PDF
INTERVIEW WITH ANTONIO NIETO RODRIGUEZ
PPTX
Introduction to Project Management - PMP Workgroup
PPTX
Lecture No. 1227 Project Management.pptx
PDF
Project report submitted in IIM Calcutta
DOCX
MGT 6302, Project Management Strategy and Tactics 1 .docx
PDF
Project Management Tools & Techniques by Susan W. Carey
PPT
01 itpm6
PDF
Introduction to PMI and PMP
PDF
Topic 1 - Introduction of Project Management.pdf
PPTX
Introduction to ict project management
PPT
1. introduction
DOCX
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
PPT
Cs244 w10ch1
PPTX
9781337101356_PPT_ch01-Introduction to Project Management.pptx
PPT
Chapter 1 An Overview Of Project Management
PPTX
1 a. introduction to project management
13115 intro to project management presentation
L1project management (2).pptxmlnmklmlmkmkmklmk
Project Manager Primer
INTERVIEW WITH ANTONIO NIETO RODRIGUEZ
Introduction to Project Management - PMP Workgroup
Lecture No. 1227 Project Management.pptx
Project report submitted in IIM Calcutta
MGT 6302, Project Management Strategy and Tactics 1 .docx
Project Management Tools & Techniques by Susan W. Carey
01 itpm6
Introduction to PMI and PMP
Topic 1 - Introduction of Project Management.pdf
Introduction to ict project management
1. introduction
Pearson HND BTEC Level 5 HNDManaging a Successful Business Pr.docx
Cs244 w10ch1
9781337101356_PPT_ch01-Introduction to Project Management.pptx
Chapter 1 An Overview Of Project Management
1 a. introduction to project management

More from christiandean12115 (20)

DOCX
100 Original WorkZero PlagiarismGraduate Level Writing Required.docx
DOCX
10.11771066480704270150THE FAMILY JOURNAL COUNSELING AND THE.docx
DOCX
10.11771066480703252339 ARTICLETHE FAMILY JOURNAL COUNSELING.docx
DOCX
10.11770022427803260263ARTICLEJOURNAL OF RESEARCH IN CRIME AN.docx
DOCX
10.11770022487105285962Journal of Teacher Education, Vol. 57,.docx
DOCX
10.11770011000002250638ARTICLETHE COUNSELING PSYCHOLOGIST M.docx
DOCX
10.1 What are three broad mechanisms that malware can use to propa.docx
DOCX
10.0 ptsPresentation of information was exceptional and included.docx
DOCX
10-K1f12312012-10k.htm10-KUNITED STATESSECURIT.docx
DOCX
10-K 1 f12312012-10k.htm 10-K UNITED STATESSECURITIES AN.docx
DOCX
10 What does a golfer, tennis player or cricketer (or any othe.docx
DOCX
10 September 2018· Watch video· Take notes withfor students.docx
DOCX
10 Research-Based Tips for Enhancing Literacy Instruct.docx
DOCX
10 Strategic Points for the Prospectus, Proposal, and Direct Pract.docx
DOCX
10 Most Common Err.docx
DOCX
10 Introduction Ask any IT manager about the chall.docx
DOCX
10 Customer Acquisition and Relationship ManagementDmitry .docx
DOCX
10 ELEMENTS OF LITERATURE (FROM A TO Z)   1  ​PLOT​ (seri.docx
DOCX
10 ers. Although one can learn definitions favor- able to .docx
DOCX
10 academic sources about the topic (Why is America so violent).docx
100 Original WorkZero PlagiarismGraduate Level Writing Required.docx
10.11771066480704270150THE FAMILY JOURNAL COUNSELING AND THE.docx
10.11771066480703252339 ARTICLETHE FAMILY JOURNAL COUNSELING.docx
10.11770022427803260263ARTICLEJOURNAL OF RESEARCH IN CRIME AN.docx
10.11770022487105285962Journal of Teacher Education, Vol. 57,.docx
10.11770011000002250638ARTICLETHE COUNSELING PSYCHOLOGIST M.docx
10.1 What are three broad mechanisms that malware can use to propa.docx
10.0 ptsPresentation of information was exceptional and included.docx
10-K1f12312012-10k.htm10-KUNITED STATESSECURIT.docx
10-K 1 f12312012-10k.htm 10-K UNITED STATESSECURITIES AN.docx
10 What does a golfer, tennis player or cricketer (or any othe.docx
10 September 2018· Watch video· Take notes withfor students.docx
10 Research-Based Tips for Enhancing Literacy Instruct.docx
10 Strategic Points for the Prospectus, Proposal, and Direct Pract.docx
10 Most Common Err.docx
10 Introduction Ask any IT manager about the chall.docx
10 Customer Acquisition and Relationship ManagementDmitry .docx
10 ELEMENTS OF LITERATURE (FROM A TO Z)   1  ​PLOT​ (seri.docx
10 ers. Although one can learn definitions favor- able to .docx
10 academic sources about the topic (Why is America so violent).docx

Recently uploaded (20)

PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
01-Introduction-to-Information-Management.pdf
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PPTX
Cell Structure & Organelles in detailed.
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
GDM (1) (1).pptx small presentation for students
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PDF
Trump Administration's workforce development strategy
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
FourierSeries-QuestionsWithAnswers(Part-A).pdf
human mycosis Human fungal infections are called human mycosis..pptx
Weekly quiz Compilation Jan -July 25.pdf
01-Introduction-to-Information-Management.pdf
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Cell Structure & Organelles in detailed.
Module 4: Burden of Disease Tutorial Slides S2 2025
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
Supply Chain Operations Speaking Notes -ICLT Program
2.FourierTransform-ShortQuestionswithAnswers.pdf
O7-L3 Supply Chain Operations - ICLT Program
Chinmaya Tiranga quiz Grand Finale.pdf
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Anesthesia in Laparoscopic Surgery in India
GDM (1) (1).pptx small presentation for students
Abdominal Access Techniques with Prof. Dr. R K Mishra
Trump Administration's workforce development strategy
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Microbial disease of the cardiovascular and lymphatic systems

IT Project Management In this course, we only introduce p.docx

  • 1. IT Project Management In this course, we only introduce project management, but the main concepts are covered. In order to be a good project manager, you should specialize in this area. Project management certificates are offered by universities such as UMUC, and there is at least one recognized certification authority—the Project Management Institute (PMI). PMI evaluates both your experience as well as your knowledge before a certification is awarded. So, you can see that project management cannot really be learned from a book or a class, but from those combined with experience in the "real world." A couple of definitions with which you should be familiar are: • project: a temporary endeavor undertaken to create a unique product, service, or result • project management: the application of knowledge, skills, tools, and techniques to project activities to meet project requirements What is the role of a project manager? Is it different for an IT project manager? A project manager must control the four key variables associated with any project: time (schedule), resources (human
  • 2. and financial), scope of work, and quality. The project manager leads the development of a project plan that takes all of these into consideration. Frequently, trade-offs are required. For instance, the budget may be limited, which restricts the scope of the work and perhaps how many people can work on the project. Or, the project is needed within a certain time frame, which may drive up the costs, since more people would have to be hired to complete the project on time. When any one of the four variables changes, there is an impact on at least one (and often more than one) other variable. A strong project manager pays attention to the project plan and the progress of the project against the plan, and manages the variables appropriately to ensure successful completion of the project. Successful completion is accomplished if the project is delivered on time, stays within the allocated budget, performs the required functions, and does so correctly. This role is the same for any project manager, including an IT project manager. 1
  • 3. The four variables are interdependent. You cannot change one without affecting the others. For example, cost of the project or decreasing the scope of the project to meet the new deadline. project's time frame or increasing the project's cost—or both— to meet the increased scope changes. necessitate a reevaluation of the scope and/or the quality. The scope may need to be reduced to avoid decreasing the quality, or if the scope must remain unchanged, quality will suffer. time and money to incorporate more perfection and test all possible outcomes for correctness. Project management is the science of making intelligent trade- offs among time, cost, scope, and quality. This is the job of the project manager. As things change, the project manager must adjust the four variables to keep them in balance. The first step is the selection of strategic projects. Now, the project
  • 4. manager does not select the projects alone; usually, that is done by senior management after the presentation of a "business case" that outlines the project plan, stating the objectives (how the project supports the corporate strategy), cost, schedule, functionality, and risk associated with the proposed project. Once senior management allocates resources, the project manager ensures the project plan is executed according to plan. A smart project manager makes sure that a plan has "SMART" criteria—aspects to ensure that the project has created understandable and measurable objectives: • Specific • Measurable • Agreed upon • Realistic • Time framed These objectives are documented in the project plan, used throughout the project's life to help keep the project on track to a successful 2 completion. The project manager monitors progress against the plan and manages any changes and mitigates risks as they become known.
  • 5. Project risk management involves identifying potential events or conditions that could have a negative effect on the project, estimating the impact if the risk occurs, determining a mitigation strategy to reduce the likelihood of the risk occurring, and identifying what will be done if the event or condition actually arises. Since almost no project goes exactly according to the plan, the project manager needs a tool to detect and manage the changes. The process of change management is this tool. The project manager documents all approved changes, revises the project plan accordingly, and then continues managing and monitoring the project. Keep in mind that the job of the project manager is to stay on top of all the variables and manage the cost, schedule (time), scope and quality. He or she must seek additional resources (money or people) or a schedule change (time) when the scope increases, and must be able to articulate the effect on quality if additional resources or a schedule change are not authorized. The project manager is responsible to senior leaders to monitor the variables, keep leadership informed, and propose solutions for changes as they occur. We begin our study of IT project management by reading
  • 6. Section III of the Solution Management module. Leadership and change management are also important aspects of project management, and will be discussed in more depth next week, in the Leadership and Change Management module. The next sections include readings on project management and the project life cycle. We then take a look at why projects fail and risk management. 3 Week 4 Discussion 1 Top of Form 4 · 5
  • 7. Please respond to the following: "Brand Stretch Spectrum and Market Product Grid" Assess the importance of evaluating newly developed health care products in order to determine whether the products should carry existing brand names or whether they should be assigned new brand names. Suggest realistic branding strategies needed for marketers to evaluate newly developed health care products or services. Provide support for your rationale. Use the Internet to research the product offerings of a local health care organization. (Note:These offerings are often found on the health care organizations homepage.) Based on your knowledge of your local region, consider the potential markets for these products. With the grid, you should, at a minimum, analyze the resulting market-product combination. Determine whether or not the product offerings that you selected are consistent with the perceived selections of the given health care entity. Explain your rationale. Reply to classmate 150 words Discussion 2 Please respond to the following: "Lateral Marketing Strategy" · Assess the value of target marketing as an effective health care marketing strategy. Appraise the degree to which vertical and traditional segmentation help marketing managers use target
  • 8. marketing strategies. Support your rationale with at least two (2) specific examples of target marketing within a health care organization with which you are familiar. · Evaluate the impact of lateral segmentation in encouraging marketing managers to look broadly at markets in order to identify previously overlooked opportunities. Provide at least one (1) specific example of quality initiatives within a health care organization. Reply to classmate 150 words Case Study 1: Revitalizing a Brand Due Week 4 and worth 200 points Read the case study titled “Revitalizing a Brand”, located in the online course shell. Use the Internet or Strayer databases to research the branding and communication strategies of one (1) health services organization that is similar to the health services organizations mentioned in the case study. Write a four to six (4-6) page paper in which you: 1. Describe the current marketing communication, identity, and brand position of Plaza Home Health Services. 2. Conduct a Strengths Weaknesses Opportunities Threats (SWOT) analysis associated with the current marketing communication, identity, and brand position of Plaza Home
  • 9. Health Services. 3. Assess the importance of benchmarking in Plaza Home Health Services’ development and implementation of an effective brand strategy (marketing communication, identity, and brand position). 4. Compare branding and communication strategies of a similar health services organization with that of Plaza Home Health Services. Determine whether or not Plaza Home Health Services should apply additional best practices into its current branding and communication strategies. Provide a rationale and support for your response. 5. Use at least five (5) quality academic resources. Note: Wikipedia and other Websites do not qualify as academic resources. Your assignment must follow these formatting requirements: · Be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides; citations and references must follow APA or school-specific format. Check with your professor for any additional instructions. · Include a cover page containing the title of the assignment, the student’s name, the professor’s name, the course title, and the date. The cover page and the reference page are not included in the required assignment page length.
  • 10. What is Project Management? by Merrie Barron and Andrew R. Barron is available under a Creative Commons Attribution 3.0 license. © 2009, Merrie Barron and Andrew R. Barron. http://cnx.org/contents/[email protected]/What-is-Project- Management http://creativecommons.org/licenses/by/3.0/ http://creativecommons.org/licenses/by/3.0/ OpenStax-CNX module: m31508 1 What is Project Management? ∗ Merrie Barron, PMP, CSM Andrew R. Barron This work is produced by OpenStax-CNX and licensed under the
  • 11. Creative Commons Attribution License 3.0† You've determined that you have a project. What now? The notes you scribbled down on the back of the napkin at lunch are a start, but not exactly good project management practice. Too often, organizations follow Nike's advice when it comes to managing projects when they �just do it.� An assignment is made and the project team members jump directly into the development of the product or service requested. In the end the delivered product doesn't meet the expectations of the customer. Unfortunately, many projects follow this poorly constructed path and that is a primary contributor to why a large percentage of projects don't meet their original objectives de�ned by performance, schedule, and budget. In the United States, more than $250 billion dollars is spent each year on IT application development in approximately 175,000 projects. The Standish Group (a Boston-based leader in project and value perfor- mance research) just released the summary version of their 2009 CHAOS Report that tracks project failure rates across a broad range of companies and industries (Figure 1).
  • 12. Figure 1: Summary of 2009 Standish Group CHAOS report. Jim Johnson, chairman of the Standish Group has stated that �this year's results show a marked decrease in project success rates, with 32% of all projects succeeding which are delivered on time, on budget, with ∗ Version 1.4: Oct 14, 2009 11:21 am -0500 †http://creativecommons.org/licenses/by/3.0/ http://cnx.org/content/m31508/1.4/ "Download for free at http://cnx.org/contents/[email protected]” OpenStax-CNX module: m31508 2 required features and functions, 44% were challenged which are late, over budget, and/or with less than the required features and functions and 24% failed which are cancelled prior to completion or delivered and never used.�
  • 13. When are companies going to stop wasting billions of dollars on failed projects? The vast majority of this waste is completely avoidable; simply get the right business needs (requirements) understood early in the process and ensure that project management techniques are applied and followed and the project activities are monitored. Applying good project management discipline is the way to help reduce the risks. But keep in mind, having good project management skills does not mean you have no problems, it does not mean that risks go away, or that there won't be any surprises. The value of good project management is that you have standard processes in place to deal with all contingencies. Project Management is the application of knowledge, skills, tools, and techniques applied to project activities in order to meet the project requirements. Project management is a process that includes planning, putting the project plan into action, and measuring progress and performance. Managing a project includes identifying your project's requirements; writing down what everyone needs
  • 14. from the project. What are the objectives for your project? When everyone understands the goal, it's much easier to keep them all on the right path. Make sure you set goals that everyone agrees on to avoid team con�icts later on. Understanding and addressing the needs of everyone a�ected by the project means the end result of your project is far more likely to satisfy your stakeholders, and last but not least, as project manager you will also be balancing the many competing project constraints. On any project, you will have a number of competing project constraints that are competing for your attention. They are cost, scope, quality, risk, resources and time. • Cost is budget approved for the project including all necessary expenses needed to deliver the project. Within organizations, project managers have to balance between not running out of money and not under spending because many projects receive funds or grants that have contract clauses with an �use it or lose it� approach to project funds. Poorly executed budget plans can result in a last minute rush to spend the allocated funds. For virtually all projects, cost is
  • 15. ultimately a limiting constraint; few projects can go over budget without eventually requiring a corrective action. • Scope is what the project is trying to achieve, it entails all the work involved in delivering the projects outcomes and the processes used to produce them. It is the reason and the purpose of the project. • Quality is the standards and criteria to which the project's products must be delivered for them to perform e�ectively. First, the product must perform to provide the functionality expected, and to solve the problem, and deliver the bene�t and value expected of it. It must also meet other performance requirements, or service levels, such as availability, reliability and maintainability, and have acceptable �nish and polish. Quality on a project is controlled through quality assurance (QA) that is the process of evaluating overall project's performance on a regular basis to provide con�dence that the project will satisfy the relevant quality standards. • Risk is de�ned by potential external events that will have a negative impact on your project if they
  • 16. occur. Risk refers to the combination of the probability the event will occur and the impact on the project if the event occurs. If the combination of the probability of the occurrence and the impact to the project is too high, you should identify the potential event as a risk and put a proactive plan in place to manage the risk. • Resources are required to carry out the project tasks. They can be people, equipment, facilities, funding, or anything else capable of de�nition (usually other than labor) required for the completion of a project activity. • Time is de�ned as the time to complete the project. Time is often the most frequent project oversight in developing projects. This is re�ected in missed deadlines and incomplete deliverables. Proper control of the schedule requires the careful identi�cation of tasks to be performed, an accurate estimation of their durations, the sequence in which they are going to be done, and how people and other resources are allocated. http://cnx.org/content/m31508/1.4/
  • 17. "Download for free at http://cnx.org/contents/[email protected]” OpenStax-CNX module: m31508 3 You may have heard of the term �Triple Constraint� which traditionally only consisted of Time, Cost & Scope. These are the primary competing project constraints that you have to be aware of most. The triple constraint is illustrated in the form of a triangle to visualize the project work and to see the relationship between the scope/quality, schedule/time, and cost/resource (Figure 2). Figure 2: A schematic of the triple constraint triangle. In this triangle, each side represents one of the constraints (or related constraints) wherein any changes to any one side cause a change in the other sides. The best projects have a perfectly balanced triangle. Maintaining this balance is di�cult because projects are prone to change. For example, if scope increases, cost and time may increase disproportionately. Alternatively, if
  • 18. the amount of money you have for your project decreases, you may be able to do as much, but your time may increase. Your project may have additional constraints that you are facing, and as the project manager you have to balance the needs of these constraints against the needs of the stakeholders and against your project goals. For instance, if your sponsor wants to add functionality to the original scope you will very likely need more money to �nish the project or if they cut the budget you have to reduce the quality of your scope and if you don't get the appropriate resources to work on your project tasks you will have to extend your schedule because the resources you have take much longer to �nish the work. You get the idea; they are all dependent on each other. Think of all of these constraints as the classic carnival game of Whac-a-mole (Figure 3). Each time you try to push one mole back in the hole, another one pops out. The best advice is to rely on your project team to keep these moles in place! http://cnx.org/content/m31508/1.4/
  • 19. "Download for free at http://cnx.org/contents/[email protected]” OpenStax-CNX module: m31508 4 Figure 3: Go to www.dorneypark.com/public/online_fun/mole.cfm to play Whac-a-mole. Here is an example of a project that cut quality because the project costs were �xed. The P-36 oil platform (Figure 4) was the largest �oating production platform in the world capable of processing 180,000 barrels of oil per day and 7.2 million cubic meters of gas per day. Located in the Roncador Field, Campos Basin, Brazil the P-36 was operated by Petrobras. Figure 4: The Petrobras P-36 oil platform. In March 2001, the P-36 was producing around 84,000 barrels of oil and 1.3 million cubic meters of gas per day when it became destabilized by two explosions and subsequently sank in 3900 feet of water with
  • 20. 1650 short tons of crude oil remaining on board, killing 11 people. The sinking is attributed to a complete failure in quality assurance and pressure for increased production http://cnx.org/content/m31508/1.4/ "Download for free at http://cnx.org/contents/[email protected]” OpenStax-CNX module: m31508 5 led to corners being cut on safety procedures. It is listed as one of the most expensive accidents with a price tag of $515,000,000. The following quote is from a Petrobras executive, citing the bene�ts of cutting quality assurance and inspection costs on the project, while the accompanying pictures are the result of this proud achievement in project management by Petrobras. Figure 5: "Petrobras has established new global benchmarks for
  • 21. the generation of exceptional share- holder wealth through an aggressive and innovative program of cost cutting on its P36 production facility." Figure 6: "Conventional constraints have been successfully challenged and replaced with new paradigms appropriate to the globalized corporate market place." http://cnx.org/content/m31508/1.4/ "Download for free at http://cnx.org/contents/f0a795f0-0309- 43f1-b93c-eb77[email protected]” OpenStax-CNX module: m31508 6 Figure 7: "Through an integrated network of facilitated workshops, the project successfully rejected the established constricting and negative in�uences of prescriptive engineering, onerous quality requirements, and outdated concepts of inspection and client control." Figure 8: "Elimination of these unnecessary straitjackets has empowered the project's suppliers and
  • 22. contractors to propose highly economical solutions, with the win-win bonus of enhanced pro�tability margins for themselves." http://cnx.org/content/m31508/1.4/ "Download for free at http://cnx.org/contents/[email protected]” OpenStax-CNX module: m31508 7 Figure 9: "The P36 platform shows the shape of things to come in the unregulated global market economy of the 21st century." The dynamic trade-o�s between the project constraint values has been humorously but accurately de- scribed in Figure 10. Figure 10: A sign seen at an automotive repair shop. 1 Bibliography • CHAOS 2009 Summary and EPPM Study, The Standish Group,
  • 23. Boston, MA (2009). http://cnx.org/content/m31508/1.4/ "Download for free at http://cnx.org/contents/[email protected]”