Clearvale Tutorials Tutorial 2 Teamwork Work Plan Tracking
Tutorial episodes Work plan setup. Work plan tracking. Work plan performance evaluation and bonus assignment.
What do I need to do?  I have already created a work  plan using Teamwork to plan and monitor the activities involved in organizing Clearsoft’s User Conference. The organization is in progress and I, as the project manager, need to monitor the progress of the activities and identify any bottlenecks and issues. In the work plan set up I decided to check progress every Friday.
What do I need to do ? I will check the progress of the following task in the Top Goal:  Gather and prepare presentation materials Prepare roadmap materials Assigned to and accepted by Jason Heggs. This assignment commences at the beginning of February and there are checkpoints every Friday until the planned Due date (end of March). I will also check the progress of the following tasks in the Subgoal:  Define community page layout Add Forums, DocuVault and Newest Items widgets Assigned to and accepted by Gabriella Jarratt. These assignments commence at the beginning of 4 th  January and there are checkpoints every Friday until the planned Due date (end of January).
Clearvale’s Teamwork tool has been used to set up the project for the organization of the Clearsoft User Conference and to coordinate the team involved in the organization. Weekly checkpoints have been defined to monitor progress. Assignments (called Goals and Tasks) have been defined and assigned to members of the team. Goals are generally made up of a series of Tasks which can be monitored in terms of progress. Each goal has a Completion rate (in terms of %)  At each checkpoint date you can see how much progress has been made (the Actual progress) with respect to what the planned progress should be (the Target progress). Based on the progress of the tasks the Completion rate of the Goal(s) above will be updated accordingly. How can Clearvale help ?
How to: View task details In the list of  Goals  and  Tasks , Jason and Gabriella have accepted the tasks assigned to them. By double-clicking on each Task line, each member will see the details of each task (see following slide).
How to: View task details Use the tabs to see more details about the task.
How to: View task details To view tasks and goals assigned to a different member go to the  My Objectives  tab and select the member from the  Switch View  area In this case we can see the assignments given to Jason Heggs.
How to: Manage task progress Now sign into the Clearsoft network as Jason Heggs and access Teamwork via The home page OR The appropriate community. Once in Teamwork go to  My Objectives  and view the Task details as mentioned before.
How to: Manage task progress The dates for this activity are from 2 nd   February to 31 st   March. Go to the  % Complete  tab. In the bottom part of the screen Jason will move the arrow to indicate the % of the task he would like to have reached when that checkpoint date arrives (the  Plan % Complete ).
How to: Manage task progress In this example he plans to have completed 20% of the task by the third checkpoint for this task.
How to: Manage task progress To show the actual progress of completion for each task, Jason will move the arrow in the  % Complete  bar. In this case the task is in the future so the bar cannot be moved.
How to: Manage task progress Gabriella has also been managing her progress chart for the tasks assigned to her One of her tasks starts 4 th  January and ends 31 st  January. The task is simple and quick to accomplish so she plans to complete it within the first two weeks of assignment.
How to: Manage task progress However due to unforeseen circumstances Gabriella manages to complete 10% of this task assigned by the end of the first week and at the first checkpoint date. This displays in the chart in the  % Complete  tab.
How to: Check for overall progress As project manager you wish to check progress on a checkpoint date (15 th  January). Open your Teamwork Plan and you will be taken to the  My Objectives  page. You will see a summary of all the  Goals  and  Tasks . The ones you are interested in include:
How to: Check for overall progress From the list of  Goals  and  Tasks , you can see the % completion. The task are completed as follows by this checkpoint date: 2.2.1. : 10% 2.2.2. : 10% 2.2.3. : 20% The overall subgoal,  Define community page layout ,  is 13% complete by this checkpoint date.
How to: Check for overall progress The calculation of the  %Complete  for  Define community page layout  is carried out as follows: Totals of weight * % completion / total weight (5*10) + (5*10) + (5*20) = 200 200 / 15 = 13
How to: Check for overall progress The overall Top Goal,  Create and setup user conference   community  is calculated as being 3% complete by this checkpoint date.
How to: Check for overall progress To see more detail about progress click on the bar on the far right-hand side. In this way it is possible to see which assignments are active for this period and their progress in terms of planned and actual completion.  Actual is shown in blue and planned in orange.
How to: Check for overall progress You see from here that the completion of the tasks is behind schedule . By the 15 th  the tasks should be completed but they are far behind completion date.  With this information you can intervene to resolve the problem .
How to: Complete a task To specify that a task is completed, start by editing the details of the task. Highlight the task line and double-click or right-click it and select  Task Detail . Only the task assignee can specify the task is complete.
How to: Complete a task There are two ways to set a task as completed: By setting the completion date in the top part of the details screen This however does not set the status of the task as being completed.  By setting the  Complete  button in the bottom part of the screen In this way you set the task status as completed.
How to: Complete a task By setting the completion date the actual ratios are not affected
How to: Complete a task By selecting the  Complete  button the  % Complete  is set to 100%  The  Completion   Date  is set to the current date.  The task is considered closed.
Next Work plan setup. Work plan tracking. Work plan performance evaluation and bonus assignment.

More Related Content

PPTX
MICROSOFT PROJECT TUTORIAL
PPT
Tutorial 2 Teamwork Work Plan Tracking
PPT
Tutorial 2 Teamwork Work Plan Tracking
PDF
Review # 6
PDF
Review # 6 v2
DOC
Stages of Production - Contents Page
DOCX
Production Plan
PDF
Omni plan 2-manual
MICROSOFT PROJECT TUTORIAL
Tutorial 2 Teamwork Work Plan Tracking
Tutorial 2 Teamwork Work Plan Tracking
Review # 6
Review # 6 v2
Stages of Production - Contents Page
Production Plan
Omni plan 2-manual

Viewers also liked (7)

DOC
παρουσίαση κειμενοκεντρικά από βιβλίο β'
PPT
BlackBerry Week - Oi
PDF
Upaya penyelamatan
PPT
παρουσίαση1
PPTX
ENG 101 Choosing a Topic
PDF
Οδηγός Moodle για προσθήκη υλικού
PPT
παρουσίαση πλήρης
παρουσίαση κειμενοκεντρικά από βιβλίο β'
BlackBerry Week - Oi
Upaya penyelamatan
παρουσίαση1
ENG 101 Choosing a Topic
Οδηγός Moodle για προσθήκη υλικού
παρουσίαση πλήρης
Ad

Similar to Jan 2010 Tutorial 2 Teamwork Work Plan Tracking (20)

PPT
Jan 2010 Tutorial 1 Teamwork Work Plan Setup
PPT
Tutorial 1 Teamwork Work Plan Setup
PPT
Tutorial 1 Teamwork Work Plan Setup V2.0
DOCX
Project NameCommunication PlanOverviewEffective and .docx
PDF
Oracle PPM. What's new in P6release 8.2?
PDF
Oracle Primavera Team member 8.3
PDF
Building Formulas And Dashboard In Ms Project
DOCX
Project Scope and Business Objective WorksheetA. General Informa.docx
PDF
Say hola to new orange scrum enterprise updates
PPTX
06 Tracking Progress on Tasks
PPT
Apptivo milestone app ss
PDF
sMs project tutorial_iit
PDF
Ms project tutorial
PPT
Tutorial 3 Teamwork Work Plan Performance Evaluation And Bonus Assignment...
PDF
Managing your Training Project through Teamwork Projects
PPSX
Quick Look - Employee Management, Task and Timesheet
PDF
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
PPT
Apptivo Project Apps Milestone
PDF
Enterprise Task Management Solution - Q Track
PPT
Jan 2010 Tutorial 3 Teamwork Work Plan Performance Evaluation And Bonus...
Jan 2010 Tutorial 1 Teamwork Work Plan Setup
Tutorial 1 Teamwork Work Plan Setup
Tutorial 1 Teamwork Work Plan Setup V2.0
Project NameCommunication PlanOverviewEffective and .docx
Oracle PPM. What's new in P6release 8.2?
Oracle Primavera Team member 8.3
Building Formulas And Dashboard In Ms Project
Project Scope and Business Objective WorksheetA. General Informa.docx
Say hola to new orange scrum enterprise updates
06 Tracking Progress on Tasks
Apptivo milestone app ss
sMs project tutorial_iit
Ms project tutorial
Tutorial 3 Teamwork Work Plan Performance Evaluation And Bonus Assignment...
Managing your Training Project through Teamwork Projects
Quick Look - Employee Management, Task and Timesheet
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
Apptivo Project Apps Milestone
Enterprise Task Management Solution - Q Track
Jan 2010 Tutorial 3 Teamwork Work Plan Performance Evaluation And Bonus...
Ad

Recently uploaded (20)

PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
PDF
NewMind AI Weekly Chronicles - August'25-Week II
PDF
August Patch Tuesday
PDF
NewMind AI Weekly Chronicles – August ’25 Week III
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
Getting started with AI Agents and Multi-Agent Systems
PPTX
TLE Review Electricity (Electricity).pptx
PDF
A comparative study of natural language inference in Swahili using monolingua...
PPT
What is a Computer? Input Devices /output devices
PDF
Hybrid model detection and classification of lung cancer
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PDF
Enhancing emotion recognition model for a student engagement use case through...
PPTX
Modernising the Digital Integration Hub
PDF
Developing a website for English-speaking practice to English as a foreign la...
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PPTX
cloud_computing_Infrastucture_as_cloud_p
PDF
project resource management chapter-09.pdf
PDF
A novel scalable deep ensemble learning framework for big data classification...
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
NewMind AI Weekly Chronicles - August'25-Week II
August Patch Tuesday
NewMind AI Weekly Chronicles – August ’25 Week III
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
Getting started with AI Agents and Multi-Agent Systems
TLE Review Electricity (Electricity).pptx
A comparative study of natural language inference in Swahili using monolingua...
What is a Computer? Input Devices /output devices
Hybrid model detection and classification of lung cancer
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Enhancing emotion recognition model for a student engagement use case through...
Modernising the Digital Integration Hub
Developing a website for English-speaking practice to English as a foreign la...
Assigned Numbers - 2025 - Bluetooth® Document
cloud_computing_Infrastucture_as_cloud_p
project resource management chapter-09.pdf
A novel scalable deep ensemble learning framework for big data classification...

Jan 2010 Tutorial 2 Teamwork Work Plan Tracking

  • 1. Clearvale Tutorials Tutorial 2 Teamwork Work Plan Tracking
  • 2. Tutorial episodes Work plan setup. Work plan tracking. Work plan performance evaluation and bonus assignment.
  • 3. What do I need to do? I have already created a work plan using Teamwork to plan and monitor the activities involved in organizing Clearsoft’s User Conference. The organization is in progress and I, as the project manager, need to monitor the progress of the activities and identify any bottlenecks and issues. In the work plan set up I decided to check progress every Friday.
  • 4. What do I need to do ? I will check the progress of the following task in the Top Goal: Gather and prepare presentation materials Prepare roadmap materials Assigned to and accepted by Jason Heggs. This assignment commences at the beginning of February and there are checkpoints every Friday until the planned Due date (end of March). I will also check the progress of the following tasks in the Subgoal: Define community page layout Add Forums, DocuVault and Newest Items widgets Assigned to and accepted by Gabriella Jarratt. These assignments commence at the beginning of 4 th January and there are checkpoints every Friday until the planned Due date (end of January).
  • 5. Clearvale’s Teamwork tool has been used to set up the project for the organization of the Clearsoft User Conference and to coordinate the team involved in the organization. Weekly checkpoints have been defined to monitor progress. Assignments (called Goals and Tasks) have been defined and assigned to members of the team. Goals are generally made up of a series of Tasks which can be monitored in terms of progress. Each goal has a Completion rate (in terms of %) At each checkpoint date you can see how much progress has been made (the Actual progress) with respect to what the planned progress should be (the Target progress). Based on the progress of the tasks the Completion rate of the Goal(s) above will be updated accordingly. How can Clearvale help ?
  • 6. How to: View task details In the list of Goals and Tasks , Jason and Gabriella have accepted the tasks assigned to them. By double-clicking on each Task line, each member will see the details of each task (see following slide).
  • 7. How to: View task details Use the tabs to see more details about the task.
  • 8. How to: View task details To view tasks and goals assigned to a different member go to the My Objectives tab and select the member from the Switch View area In this case we can see the assignments given to Jason Heggs.
  • 9. How to: Manage task progress Now sign into the Clearsoft network as Jason Heggs and access Teamwork via The home page OR The appropriate community. Once in Teamwork go to My Objectives and view the Task details as mentioned before.
  • 10. How to: Manage task progress The dates for this activity are from 2 nd February to 31 st March. Go to the % Complete tab. In the bottom part of the screen Jason will move the arrow to indicate the % of the task he would like to have reached when that checkpoint date arrives (the Plan % Complete ).
  • 11. How to: Manage task progress In this example he plans to have completed 20% of the task by the third checkpoint for this task.
  • 12. How to: Manage task progress To show the actual progress of completion for each task, Jason will move the arrow in the % Complete bar. In this case the task is in the future so the bar cannot be moved.
  • 13. How to: Manage task progress Gabriella has also been managing her progress chart for the tasks assigned to her One of her tasks starts 4 th January and ends 31 st January. The task is simple and quick to accomplish so she plans to complete it within the first two weeks of assignment.
  • 14. How to: Manage task progress However due to unforeseen circumstances Gabriella manages to complete 10% of this task assigned by the end of the first week and at the first checkpoint date. This displays in the chart in the % Complete tab.
  • 15. How to: Check for overall progress As project manager you wish to check progress on a checkpoint date (15 th January). Open your Teamwork Plan and you will be taken to the My Objectives page. You will see a summary of all the Goals and Tasks . The ones you are interested in include:
  • 16. How to: Check for overall progress From the list of Goals and Tasks , you can see the % completion. The task are completed as follows by this checkpoint date: 2.2.1. : 10% 2.2.2. : 10% 2.2.3. : 20% The overall subgoal, Define community page layout , is 13% complete by this checkpoint date.
  • 17. How to: Check for overall progress The calculation of the %Complete for Define community page layout is carried out as follows: Totals of weight * % completion / total weight (5*10) + (5*10) + (5*20) = 200 200 / 15 = 13
  • 18. How to: Check for overall progress The overall Top Goal, Create and setup user conference community is calculated as being 3% complete by this checkpoint date.
  • 19. How to: Check for overall progress To see more detail about progress click on the bar on the far right-hand side. In this way it is possible to see which assignments are active for this period and their progress in terms of planned and actual completion. Actual is shown in blue and planned in orange.
  • 20. How to: Check for overall progress You see from here that the completion of the tasks is behind schedule . By the 15 th the tasks should be completed but they are far behind completion date. With this information you can intervene to resolve the problem .
  • 21. How to: Complete a task To specify that a task is completed, start by editing the details of the task. Highlight the task line and double-click or right-click it and select Task Detail . Only the task assignee can specify the task is complete.
  • 22. How to: Complete a task There are two ways to set a task as completed: By setting the completion date in the top part of the details screen This however does not set the status of the task as being completed. By setting the Complete button in the bottom part of the screen In this way you set the task status as completed.
  • 23. How to: Complete a task By setting the completion date the actual ratios are not affected
  • 24. How to: Complete a task By selecting the Complete button the % Complete is set to 100% The Completion Date is set to the current date. The task is considered closed.
  • 25. Next Work plan setup. Work plan tracking. Work plan performance evaluation and bonus assignment.