SlideShare a Scribd company logo
Building a Project Dashboard with Formulas
                in MS Project

                 Relu Rosenberg
             PMP, Six Sigma Black Belt
Introduction

 This presentation will show how to build a Project Dashboard using Excel like formulas and
  functions in MS Project
 The study case will walk through the steps for creating a field called “Task Progress” to
  calculate the Progress status of a task and use graphical indicators for creating a dashboard
  view for active tasks (task level) or project summary view (Summary tasks level)
 Steps
           Define the logic
           Build the formula
           Add graphical indicators for quick identification of tasks status, issues
           Build filter based on calculated values to select tasks of interest (focus tasks)
           Make customizations available to all your Project plans
           Make customizations available to someone else , publish a template plan
 Benefits
           Automated calculation and identification of active tasks
           Automated identification of tasks requiring attention
           One step preparation of high level project status report for management
 As always, a good, detailed plan will drive the quality of the resulting report !




10/6/2010                                Relu Rosenberg, PMP, Six Sigma Black Belt                2
Introduction - 2
 The end result will take you from a project plan with no easy way to identify a status (left) to a
  toolbox to produce one click status reports, issues , focus tasks list (right side).
  If this interests you, follow the rest of this presentation !




10/6/2010                          Relu Rosenberg, PMP, Six Sigma Black Belt                           3
Logic #1 - Calculate Task Progress based on Start/End dates




10/6/2010             Relu Rosenberg, PMP, Six Sigma Black Belt   4
Logic #1 – Notes


        •Logic #1 is very simple to implement as it is based only on
        “% Complete” and Start, End dates of the task.
        It automates calculation and identification of 8 task status values !
        •If %Complete is >0 it will know task work started and it will mark as “In
        progress”
        •Doesn’t require accurate estimate of %Complete.
        •It is suitable for tasks of short duration, w/o interim milestones

        •This calculation cannot establish if a task in progress is late or ahead of
        the schedule. This is where logic #2 and #3 will help




10/6/2010                       Relu Rosenberg, PMP, Six Sigma Black Belt              5
Logic #2 – Use task “Status” field
                                                                           Task Status        Field
                             Condition
                                                                             Display          Value
 %Complete = 100                                                   Complete               0
 Timephased Cumulative %Complete >0 on midnight of day before      On Schedule            1
 Timephased Cumulative %Complete =0 on midnight before             Late                   2
 Task Start Date > Today                                           Future Task            3




    Go To View->More Views ->”Task Usage”
    To add fields
    Format -> “Detail Styles” and add “Cumulative Percent Complete” to show pane
    To change displayed fields
    Format->”Details” and Check/Uncheck fields
    Note:
    In order to use Task Status and be able to display “Cumulative %Complete“ you
    must assign a resource (real or generic) to each task !




10/6/2010                                     Relu Rosenberg, PMP, Six Sigma Black Belt               6
Logic #2 – Notes


        •Logic #2 leverages the “Status” task field from Microsoft Project. This
        will help to determine not just if a task is in Progress but also if it is on
        Schedule or Late.
        •It is the correct way to calculate because the time phased
        “% Complete” accounts for the actual work performed over elapsed
        time.
        •A resource can have days off , days not worked full time, etc and
        comparing ((Date()-*Start+)/*Duration+) with “% Complete” is
        misleading.
        •Requires more accurate estimate of %Complete of a task
        •It’s suitable for tasks of longer duration where %Complete can be
        measured




10/6/2010                       Relu Rosenberg, PMP, Six Sigma Black Belt               7
Logic 2 - Task Progress using “Status” field (task field)




10/6/2010                Relu Rosenberg, PMP, Six Sigma Black Belt   8
Logic 3 - Using EVM SPI

   Resources
           Define all resources
           Assign rates to each resource (Std. Rate,
            Ovt. Rate)
           Assign resource to each task
   Define Earned Value Calculation options
    (Tools ->Options -> Calculation)
           Default task Earned Value method:
            % Complete
           Edits to total task % complete will be
            spread to the status date (to see SPI>1)
   Baseline project
           Re-baseline every time you add tasks and
            resources or change tasks, resources




10/6/2010                                 Relu Rosenberg, PMP, Six Sigma Black Belt   9
Logic 3 – Notes


        • Logic #3 is the most sophisticated and accurate. It will allow to
        determine if a task in progress is Behind Schedule, On Schedule, Ahead
        of Schedule.
        • It uses Earned Value Methodology and specifically it uses Schedule
        Performance Index.
        • For older versions of Microsoft Project which don’t have the SPI
        calculated you can add SPI as a customized field, Number , with
        following formula:
               IIf([BCWS]>0,[BCWP]/[BCWS],0)
        Since BCWS is 0 For future tasks in MS Project 2000, the formula checks
        and returns SPI=0 to prevent Error due to division by 0.
        • It requires accurate measurement of %Complete to provide accurate
        indicator of progress status (Ahead, On Schedule, Behind)




10/6/2010                     Relu Rosenberg, PMP, Six Sigma Black Belt           10
Logic 3 - Task Progress using EVM SPI




10/6/2010             Relu Rosenberg, PMP, Six Sigma Black Belt   11
Creating a custom field

   The are several types of fields you can customize, depending on desired data type
           Text, Date , Number are the most used
           Start, Finish, Cost, Duration, Flag are additional types
   Right click on project headings to “Insert Column” , will choose Text type field, Text2 for “Task Progress”
    field




10/6/2010                                  Relu Rosenberg, PMP, Six Sigma Black Belt                              12
Customize field applet

   Right click on field header and select Customize field
   Use Rename to rename the field from Text2 to “Task Progress” for use in formulas
   Check the boxes for Formula and Graphical Indicators buttons for customization




10/6/2010                             Relu Rosenberg, PMP, Six Sigma Black Belt        13
Writing Formulas – simple examples

   We will use these statements and functions
           IIf(expression-to-test, Do-this-if-true,Do-this-if-False)
           Date() - returns current system date
           Project fields - designated as [field-name]
   Examples
           Flag all active tasks (Start < Date < Finish)
                  IIf((Date() > [Start]) And (Date() < [Finish]),"Active Task","")

           Flag all overdue tasks – (Finish < Date) and (%Complete <100)
                  IIf(([Finish] < Date()) And ([% Complete] < 100),"Overdue","")

           Flag active and overdue tasks – combine the above
                  IIf((Date()>[Start]) And (Date()<[Finish]),
                       "Active Task",
                       IIf(([Finish]<Date()) And ([% Complete]<100),"Overdue","")
                   )




10/6/2010                                     Relu Rosenberg, PMP, Six Sigma Black Belt   14
Writing the Formulas for “Task Progress” logic

   Below formulas implement the logic diagrams (decision trees) depicted in slides
   It is recommended to check each decision path in the formula using the Logic diagram
   Easiest way to test the values is by adjusting the % Complete


      Logic 1 - % Complete and Start/Finish Dates

      IIf(*% Complete+=100,"Complete",IIf(*Estimated+=Yes,"TBD",IIf(Date()>*Finish+,”Not Finished",
      IIf(Date()>*Start+,IIf(*% Complete+=0,“Not Started",IIf((*Finish+-Date())<7,"Ending Next",
      "In progress")),IIf([Start]-Date()<7,"Starting Next","Future")))))


      Logic 2 - % Complete, Task Status and Start/Finish Dates
      IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not
      Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending
      Next",IIf([Status]=1,"On Schedule","Late"))),IIf([Start]-Date()<7,"Starting Next","Future")))))



      Logic 3 - Use SPI and Start/Finish Dates
      IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not
      Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending
      Next",IIf([SPI]<1,"Late",IIf([SPI]>1,"Ahead","On Schedule")))),IIf([Start]-Date()<7,"Starting
      Next","Future")))))




10/6/2010                                  Relu Rosenberg, PMP, Six Sigma Black Belt                    15
Formula written in structured format
            IIf([ % Complete]=100,
                 “Complete"
                 IIf([Estimated]=Yes,
                       "TBD",
                       IIf(Date()>[Finish],
                                "Not Finished",
                                IIf(Date()>[Start],
                                         IIf([%Complete]=0,
                                                    "Not Started",
                                                    IIf(([Finish]-Date())<7,
                                                              "Ending Next",
                                                              IIf([Status]=1,
                                                                       “On Schedule”,
                                                                       “Late”
                                                             )
                                                    )
                                         ),
                                         IIf([Start]-Date()<7,
                                                   "Starting Next",
                                                   "Future Task"
                                         )
                                )
                       )
                )
            )


10/6/2010                                    Relu Rosenberg, PMP, Six Sigma Black Belt   16
Using Formula Applet

   Press Formula button to open the applet
   Use Field button to inserts field names in formula and Function button to select functions
   To learn more about functions search for “Project functions” in Help




10/6/2010                           Relu Rosenberg, PMP, Six Sigma Black Belt                    17
Add Graphical Indicators

   Check Graphical Indicators … Radio button to enable
   Press Graphical Indicator… Button to define the values
   Select “Nonsummary rows” to display indicator for tasks only
   Assign icon for each status value – right click and select from pull-down menu




10/6/2010                            Relu Rosenberg, PMP, Six Sigma Black Belt       18
Set Calculations Mode

   Confirm/Set Calculations mode to Automatic
           Tools->Options->Calculation Tab
           Check/Set Calculation Mode: Automatic




10/6/2010                            Relu Rosenberg, PMP, Six Sigma Black Belt   19
Project Plan without Graphical Indicators
                     Very difficult to understand tasks status




10/6/2010                 Relu Rosenberg, PMP, Six Sigma Black Belt   20
Project Plan with Calculated Status & Graphical Indicators




10/6/2010            Relu Rosenberg, PMP, Six Sigma Black Belt   21
Project Plan with Graphical Indicators – 2
            Optional – Display also Status Values (can also be seen when pointing over the Indicator )




10/6/2010                                 Relu Rosenberg, PMP, Six Sigma Black Belt                      22
Project tasks review using filters

   Select tasks of interest
           In progress, Ending Next, Starting Next
   Select issues
           Not started, Late, Not Finished, TBD (Dates not Confirmed)
   Create Filter
           Got to Project->Filtered For->More Filters
           Select New
           Check radio button for Task filter
           In New Filter Applet
              o Define the Name
              o Check Show In Menu to see it in Filters list
              o Define the rules for tasks selection




10/6/2010                                  Relu Rosenberg, PMP, Six Sigma Black Belt   23
New Filter Applet




10/6/2010   Relu Rosenberg, PMP, Six Sigma Black Belt   24
Project tasks review – Filter: Focus tasks (less clutter)
                                     Optional – Data can be seen also when pointer is over the indicator




10/6/2010               Relu Rosenberg, PMP, Six Sigma Black Belt                                          25
Project tasks review – Filter: Issues
              Not Started, Not Finished, Late, Duration estimated (TBD)




10/6/2010                  Relu Rosenberg, PMP, Six Sigma Black Belt      26
Project Dashboard – phase level report for management

      Apply Dashboard filter to produce this phase level view ((Outline level <=2) And (Summary=Yes))




10/6/2010                           Relu Rosenberg, PMP, Six Sigma Black Belt                           27
Project Dashboard – Phase & Major Activities review
              Add filter with ((Outline level <=3) And (Summary=Yes))




10/6/2010                    Relu Rosenberg, PMP, Six Sigma Black Belt   28
Share customizations


   Make customizations available to all your projects
           Any MS Project object customized in a project plan will be saved within the project file only.
           In order to make these objects available to the other projects they need to be saved in the global template.
           Identify all customizations
              o Tools->Organizer and go through each tab (object category).
              o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project
                file.
              o Select object from Fields, Filters, Views, etc, on right side, press Copy and it will be copied to Global Template.




10/6/2010                                  Relu Rosenberg, PMP, Six Sigma Black Belt                                            29
Share customizations - 2


   Share customizations with others
           Create a blank project files
           Copy all customizations from Global to the Project file
              o Tools->Organizer and go through each tab (object category).
              o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project
                file.
              o Select a an object field, filter, etc, on Left side, Global Template, and press Copy to copy to project file




10/6/2010                                  Relu Rosenberg, PMP, Six Sigma Black Belt                                            30
Questions ?
            Email: relur@comcast.net




10/6/2010       Relu Rosenberg, PMP, Six Sigma Black Belt   31

More Related Content

PPTX
00 Introduction of project scheduling
PPSX
How to Create S Curve by MS Project 2013
PDF
Exercice ms project 2020
PPTX
PPTX
Planification
PPTX
Forensic schedule analysis acesss
PDF
Wbs Building Use This
PDF
Schedule Updates
00 Introduction of project scheduling
How to Create S Curve by MS Project 2013
Exercice ms project 2020
Planification
Forensic schedule analysis acesss
Wbs Building Use This
Schedule Updates

What's hot (20)

PDF
Thibaut Petit - Memento / Guide du Lean Construction
PDF
Synerzip Agile Cheat Sheet
PPT
MS Project et le management de projet
PPT
Ms project
PPTX
Formation Professional Scrum Master I
PDF
Kanban step bystep
PDF
Les algorithmes d'arithmetique
PDF
Tests & recette - Les fondamentaux
PPT
Ms project 1 principes de gestion de projets
PDF
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
PDF
Schedule levels-as-presented 02-may11
PDF
Gestion de projet
PDF
Scrum cheatsheet
PPT
Microsoft project (msp)
PDF
Methode Agile
PDF
Microsoft Projects; a step by-step guide for beginner's
PDF
Introduction à la méthodologie Prince2
PPT
Pc 2011 Epmo Plan
PPT
20mn scrum
Thibaut Petit - Memento / Guide du Lean Construction
Synerzip Agile Cheat Sheet
MS Project et le management de projet
Ms project
Formation Professional Scrum Master I
Kanban step bystep
Les algorithmes d'arithmetique
Tests & recette - Les fondamentaux
Ms project 1 principes de gestion de projets
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Schedule levels-as-presented 02-may11
Gestion de projet
Scrum cheatsheet
Microsoft project (msp)
Methode Agile
Microsoft Projects; a step by-step guide for beginner's
Introduction à la méthodologie Prince2
Pc 2011 Epmo Plan
20mn scrum
Ad

Viewers also liked (20)

PDF
Microsoft project 2010 creating customized field with image & formula
PPTX
Project Performance Dashboard
PPTX
Executive Status Report Template
PDF
Practical Use of Microsoft Project for Project Managers
PPTX
Project planning and project work plan
PPT
Graphical Indicators in MS Project
PDF
Ms project lectures
PPSX
Project management
PPTX
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
PPT
Fundamentals of Project Management
PDF
Project Management Concepts (from PMBOK 5th Ed)
PPTX
Enterprise Project Management using Microsoft Project
PDF
Formulae of financial management
PDF
Inbound Marketing - Marketo
PPT
1346 A Single Chip Microcomputer
PPTX
PPT
Search Engine Optimization in Web Technology
PPSX
Integrated Lifecycle Marketing Workshop: Putting the Marketing Democracy to W...
PPTX
Mobile Marketing 101
PPTX
Social Aspect in human life
Microsoft project 2010 creating customized field with image & formula
Project Performance Dashboard
Executive Status Report Template
Practical Use of Microsoft Project for Project Managers
Project planning and project work plan
Graphical Indicators in MS Project
Ms project lectures
Project management
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Fundamentals of Project Management
Project Management Concepts (from PMBOK 5th Ed)
Enterprise Project Management using Microsoft Project
Formulae of financial management
Inbound Marketing - Marketo
1346 A Single Chip Microcomputer
Search Engine Optimization in Web Technology
Integrated Lifecycle Marketing Workshop: Putting the Marketing Democracy to W...
Mobile Marketing 101
Social Aspect in human life
Ad

Similar to Building Formulas And Dashboard In Ms Project (20)

DOCX
Project NameCommunication PlanOverviewEffective and .docx
PPTX
06 Tracking Progress on Tasks
PDF
Primavera P6 basics-tips-and-tricks
PDF
Ms Project Workshop
PPTX
Microsoft Project Foundations Course.pptx
PDF
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
PPS
MS Project Svcs Productivity
PDF
Ms.project brochure
PPT
Jan 2010 Tutorial 2 Teamwork Work Plan Tracking
PDF
Ms project tutorial
PDF
sMs project tutorial_iit
PPTX
MICROSOFT PROJECT
PPT
Tutorial 2 Teamwork Work Plan Tracking
PPT
Tutorial 2 Teamwork Work Plan Tracking
PDF
Disrupting Lean Six Sigma; How to make Lean Six Sigma relevant to Start-Ups?
PDF
Introduction to schedule management
PDF
Oracle Primavera P6 PRO R8 Tips & tricks
PDF
Six sigmayellowbelt part1
PPT
Microsoft project 2010
PDF
MS Project Guide.pdf
Project NameCommunication PlanOverviewEffective and .docx
06 Tracking Progress on Tasks
Primavera P6 basics-tips-and-tricks
Ms Project Workshop
Microsoft Project Foundations Course.pptx
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
MS Project Svcs Productivity
Ms.project brochure
Jan 2010 Tutorial 2 Teamwork Work Plan Tracking
Ms project tutorial
sMs project tutorial_iit
MICROSOFT PROJECT
Tutorial 2 Teamwork Work Plan Tracking
Tutorial 2 Teamwork Work Plan Tracking
Disrupting Lean Six Sigma; How to make Lean Six Sigma relevant to Start-Ups?
Introduction to schedule management
Oracle Primavera P6 PRO R8 Tips & tricks
Six sigmayellowbelt part1
Microsoft project 2010
MS Project Guide.pdf

Building Formulas And Dashboard In Ms Project

  • 1. Building a Project Dashboard with Formulas in MS Project Relu Rosenberg PMP, Six Sigma Black Belt
  • 2. Introduction  This presentation will show how to build a Project Dashboard using Excel like formulas and functions in MS Project  The study case will walk through the steps for creating a field called “Task Progress” to calculate the Progress status of a task and use graphical indicators for creating a dashboard view for active tasks (task level) or project summary view (Summary tasks level)  Steps  Define the logic  Build the formula  Add graphical indicators for quick identification of tasks status, issues  Build filter based on calculated values to select tasks of interest (focus tasks)  Make customizations available to all your Project plans  Make customizations available to someone else , publish a template plan  Benefits  Automated calculation and identification of active tasks  Automated identification of tasks requiring attention  One step preparation of high level project status report for management  As always, a good, detailed plan will drive the quality of the resulting report ! 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 2
  • 3. Introduction - 2  The end result will take you from a project plan with no easy way to identify a status (left) to a toolbox to produce one click status reports, issues , focus tasks list (right side). If this interests you, follow the rest of this presentation ! 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 3
  • 4. Logic #1 - Calculate Task Progress based on Start/End dates 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 4
  • 5. Logic #1 – Notes •Logic #1 is very simple to implement as it is based only on “% Complete” and Start, End dates of the task. It automates calculation and identification of 8 task status values ! •If %Complete is >0 it will know task work started and it will mark as “In progress” •Doesn’t require accurate estimate of %Complete. •It is suitable for tasks of short duration, w/o interim milestones •This calculation cannot establish if a task in progress is late or ahead of the schedule. This is where logic #2 and #3 will help 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 5
  • 6. Logic #2 – Use task “Status” field Task Status Field Condition Display Value %Complete = 100 Complete 0 Timephased Cumulative %Complete >0 on midnight of day before On Schedule 1 Timephased Cumulative %Complete =0 on midnight before Late 2 Task Start Date > Today Future Task 3 Go To View->More Views ->”Task Usage” To add fields Format -> “Detail Styles” and add “Cumulative Percent Complete” to show pane To change displayed fields Format->”Details” and Check/Uncheck fields Note: In order to use Task Status and be able to display “Cumulative %Complete“ you must assign a resource (real or generic) to each task ! 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 6
  • 7. Logic #2 – Notes •Logic #2 leverages the “Status” task field from Microsoft Project. This will help to determine not just if a task is in Progress but also if it is on Schedule or Late. •It is the correct way to calculate because the time phased “% Complete” accounts for the actual work performed over elapsed time. •A resource can have days off , days not worked full time, etc and comparing ((Date()-*Start+)/*Duration+) with “% Complete” is misleading. •Requires more accurate estimate of %Complete of a task •It’s suitable for tasks of longer duration where %Complete can be measured 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 7
  • 8. Logic 2 - Task Progress using “Status” field (task field) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 8
  • 9. Logic 3 - Using EVM SPI  Resources  Define all resources  Assign rates to each resource (Std. Rate, Ovt. Rate)  Assign resource to each task  Define Earned Value Calculation options (Tools ->Options -> Calculation)  Default task Earned Value method: % Complete  Edits to total task % complete will be spread to the status date (to see SPI>1)  Baseline project  Re-baseline every time you add tasks and resources or change tasks, resources 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 9
  • 10. Logic 3 – Notes • Logic #3 is the most sophisticated and accurate. It will allow to determine if a task in progress is Behind Schedule, On Schedule, Ahead of Schedule. • It uses Earned Value Methodology and specifically it uses Schedule Performance Index. • For older versions of Microsoft Project which don’t have the SPI calculated you can add SPI as a customized field, Number , with following formula: IIf([BCWS]>0,[BCWP]/[BCWS],0) Since BCWS is 0 For future tasks in MS Project 2000, the formula checks and returns SPI=0 to prevent Error due to division by 0. • It requires accurate measurement of %Complete to provide accurate indicator of progress status (Ahead, On Schedule, Behind) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 10
  • 11. Logic 3 - Task Progress using EVM SPI 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 11
  • 12. Creating a custom field  The are several types of fields you can customize, depending on desired data type  Text, Date , Number are the most used  Start, Finish, Cost, Duration, Flag are additional types  Right click on project headings to “Insert Column” , will choose Text type field, Text2 for “Task Progress” field 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 12
  • 13. Customize field applet  Right click on field header and select Customize field  Use Rename to rename the field from Text2 to “Task Progress” for use in formulas  Check the boxes for Formula and Graphical Indicators buttons for customization 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 13
  • 14. Writing Formulas – simple examples  We will use these statements and functions  IIf(expression-to-test, Do-this-if-true,Do-this-if-False)  Date() - returns current system date  Project fields - designated as [field-name]  Examples  Flag all active tasks (Start < Date < Finish) IIf((Date() > [Start]) And (Date() < [Finish]),"Active Task","")  Flag all overdue tasks – (Finish < Date) and (%Complete <100) IIf(([Finish] < Date()) And ([% Complete] < 100),"Overdue","")  Flag active and overdue tasks – combine the above IIf((Date()>[Start]) And (Date()<[Finish]), "Active Task", IIf(([Finish]<Date()) And ([% Complete]<100),"Overdue","") ) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 14
  • 15. Writing the Formulas for “Task Progress” logic  Below formulas implement the logic diagrams (decision trees) depicted in slides  It is recommended to check each decision path in the formula using the Logic diagram  Easiest way to test the values is by adjusting the % Complete Logic 1 - % Complete and Start/Finish Dates IIf(*% Complete+=100,"Complete",IIf(*Estimated+=Yes,"TBD",IIf(Date()>*Finish+,”Not Finished", IIf(Date()>*Start+,IIf(*% Complete+=0,“Not Started",IIf((*Finish+-Date())<7,"Ending Next", "In progress")),IIf([Start]-Date()<7,"Starting Next","Future"))))) Logic 2 - % Complete, Task Status and Start/Finish Dates IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending Next",IIf([Status]=1,"On Schedule","Late"))),IIf([Start]-Date()<7,"Starting Next","Future"))))) Logic 3 - Use SPI and Start/Finish Dates IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending Next",IIf([SPI]<1,"Late",IIf([SPI]>1,"Ahead","On Schedule")))),IIf([Start]-Date()<7,"Starting Next","Future"))))) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 15
  • 16. Formula written in structured format IIf([ % Complete]=100, “Complete" IIf([Estimated]=Yes, "TBD", IIf(Date()>[Finish], "Not Finished", IIf(Date()>[Start], IIf([%Complete]=0, "Not Started", IIf(([Finish]-Date())<7, "Ending Next", IIf([Status]=1, “On Schedule”, “Late” ) ) ), IIf([Start]-Date()<7, "Starting Next", "Future Task" ) ) ) ) ) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 16
  • 17. Using Formula Applet  Press Formula button to open the applet  Use Field button to inserts field names in formula and Function button to select functions  To learn more about functions search for “Project functions” in Help 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 17
  • 18. Add Graphical Indicators  Check Graphical Indicators … Radio button to enable  Press Graphical Indicator… Button to define the values  Select “Nonsummary rows” to display indicator for tasks only  Assign icon for each status value – right click and select from pull-down menu 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 18
  • 19. Set Calculations Mode  Confirm/Set Calculations mode to Automatic  Tools->Options->Calculation Tab  Check/Set Calculation Mode: Automatic 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 19
  • 20. Project Plan without Graphical Indicators Very difficult to understand tasks status 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 20
  • 21. Project Plan with Calculated Status & Graphical Indicators 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 21
  • 22. Project Plan with Graphical Indicators – 2 Optional – Display also Status Values (can also be seen when pointing over the Indicator ) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 22
  • 23. Project tasks review using filters  Select tasks of interest  In progress, Ending Next, Starting Next  Select issues  Not started, Late, Not Finished, TBD (Dates not Confirmed)  Create Filter  Got to Project->Filtered For->More Filters  Select New  Check radio button for Task filter  In New Filter Applet o Define the Name o Check Show In Menu to see it in Filters list o Define the rules for tasks selection 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 23
  • 24. New Filter Applet 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 24
  • 25. Project tasks review – Filter: Focus tasks (less clutter) Optional – Data can be seen also when pointer is over the indicator 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 25
  • 26. Project tasks review – Filter: Issues Not Started, Not Finished, Late, Duration estimated (TBD) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 26
  • 27. Project Dashboard – phase level report for management Apply Dashboard filter to produce this phase level view ((Outline level <=2) And (Summary=Yes)) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 27
  • 28. Project Dashboard – Phase & Major Activities review Add filter with ((Outline level <=3) And (Summary=Yes)) 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 28
  • 29. Share customizations  Make customizations available to all your projects  Any MS Project object customized in a project plan will be saved within the project file only.  In order to make these objects available to the other projects they need to be saved in the global template.  Identify all customizations o Tools->Organizer and go through each tab (object category). o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project file. o Select object from Fields, Filters, Views, etc, on right side, press Copy and it will be copied to Global Template. 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 29
  • 30. Share customizations - 2  Share customizations with others  Create a blank project files  Copy all customizations from Global to the Project file o Tools->Organizer and go through each tab (object category). o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project file. o Select a an object field, filter, etc, on Left side, Global Template, and press Copy to copy to project file 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 30
  • 31. Questions ? Email: relur@comcast.net 10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 31