Project 2010: Creating Customized Field with Images &
Formula
You can use customized field feature in Microsoft Project 2010 to create a dashboard and to
quickly identify problem areas in the project. In this exercise, we will create the following four
customized fields:
    • Status_as_text: This will be a field with a drop down menu to select text: Red, Yellow,
       Green
    • Status_as_Image: This will provide the user a drop down menu to select an image to
       display the status as an image.
    • Status_as_Eval_text: This will be an automated field that evaluates %complete and
       displays the result as text.
    • Status_as_Eval_Image: This will be an automated field to evaluate %complete and
       display the result as an image.

By the end of the exercise, you will have a project plan with status, text (red, green or yellow)
and images:
NR Computer Learning Center
        2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475

Custom Field to display status as a Text
Follow the steps below to create a customized field with a drop down menu that allows user to
select one of the text: Red, Yellow, Green.

Step 1: Select Project Tab> Properties Group > Custom Fields.




Step 2: In Cutom Fields window, select Text1 fields and click on the Rename button. Type
Status_as_text and click the OK button.




Step 3: Click on the Lookup button. While in Edit Lookup Table Window, in the value field type:
Red, Yellow, Green. Click on the Close button to close the Edit Lookup Table for
Status_as_text window.
Step 4: Click on OK button to save the changes.
Step 5: Left Click the Add New Column in the Table View, and select Status_as_text from the
drop down menu.




Select the colors in the drop down to manually assign the color as status to each of the tasks.
NR Computer Learning Center
         2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475

Custom Field to display status as an Image
Follow the steps below to create a customized field with a drop down menu that allows user to select one
of the images from the drop down menu:

Step 1: Select Project Tab> Properties Group > Custom Fields.
Step 2: Select Text2 and rename to Status_as_Image.
Click on Lookup button to add the options: Red, Yellow & Green.
Click on the Graphical Indicators… to add the images for text red, yellow and green.




Enter the following information in the Graphical Indictor window:
Test for      Values(s)    Image
Equals        Red
Equals      Yellow
Equals      Green

Click OK to Save the Graphical Indicators. Click OK again to save the custom fields.




Once you select the color from the dropdown menu, the field is replaced with matching image.
NR Computer Learning Center
         2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475

Custom Field to automatically display % complete status as text
Follow the steps below to create a customized field with a drop down menu that allow automatically
populates the data in the column based on a business rule:

Step 1: Select Project Tab> Properties Group > Custom Fields.
Step 2: Select Text2 and rename to Status_as_Eval_Text.
Step 3: Click on the Formula button.




Type in the below formula in the Formula box that populated the data based on the rule specified below:

        IIf ([% Complete]<30,"Red",IIf([% Complete]<70,"Yellow","Green"))




Click the OK button. Add the column Status_as_Eval_Text. The Microsoft Project will automatically fill
up the column based on the rule specified above.
NR Computer Learning Center
         2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475

Custom Field to automatically display % complete status as Image
Step 1: Select Project Tab> Properties Group > Custom Fields.
Step 2: Select Text2 and rename to Status_as_Eval_Image.
Step 3: Click on the Formula button.

Type in the following formula in the Formula box:
        IIf ([% Complete]<30,"Red",IIf([% Complete]<70,"Yellow","Green"))




Click the OK button.
Click on the Graphical Indicators button.




Click the OK button to close the Graphical Indicator Window and click the OK button to close the
Custom Field Window. Add the column Status_as_Eval_Image to the project Table. The Microsoft
Project will automatically fill up the column with images based on the rule specified above.
NR Computer Learning Center
         2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475



If you want to learn more about Microsoft Project 2010, NR Computer Learning Center provide following
options:

    •   Articles (http://www.nrclc.com/blog/project/)
    •   Classroom Training (www.nrclc.com/Project2010 )
    •   E-learning Course ( http://www.nrclc.com/VideoTraining/Project Management.html )
    •   Online Classes (www.nrclc.com/Project2010)
    •   Corporate Training ( http://www.nrclc.com/CorporateTraining )

To join our email list to receive information on promotion, webinars, event and monthly newsletter, visit
www.nrclc.com.




                                      NR Computer Learning Center
                                     2100 W. Orangewood, Suite 110
                                            Orange, CA 92868
                                             www.nrclc.com
                                             (714) 505-3475
                                           Twitter: @NRCLC
                                  Facebook: www.facebook.com/NRCLC
                                       Blog: www.nrclc.com/blog

More Related Content

PPTX
MS Project
PPSX
How to create S-Curve by MS Project 2013
PDF
MS Project Integration: Tips, Tricks and What's New for You
PDF
204460 create s curve reports
PPSX
How to Create S Curve by MS Project 2013
PPT
Ms project management
PDF
MS Project
PDF
Ms Project Workshop
MS Project
How to create S-Curve by MS Project 2013
MS Project Integration: Tips, Tricks and What's New for You
204460 create s curve reports
How to Create S Curve by MS Project 2013
Ms project management
MS Project
Ms Project Workshop

What's hot (20)

PDF
sMs project tutorial_iit
PPT
Graphical Indicators in MS Project
PDF
Project management by MS Project 2010
PDF
Building Formulas And Dashboard In Ms Project
PPTX
2010 ms project 2010 (2)
PDF
Master MSProject 2010
PDF
Ms project lectures
PDF
Ms project 2000 tutorial
PPTX
MICROSOFT PROJECT TUTORIAL
PDF
Introduction to Primavera Reflections
PPT
Microsoft project 2010
PPSX
Project network scheduling and S-curve
PPTX
Microsoft Project 2013
DOCX
Uses of Project Status field
PDF
Project 2007 full handout
PDF
Pdf primavera tutorial
PDF
Microsoft Project - MSP | 2013-2016
PDF
Oracle Primavera P6 PRO R8 Tips & tricks
PPTX
05 Formatting and Sharing Your Plan
PDF
Microsoft Projects; a step by-step guide for beginner's
sMs project tutorial_iit
Graphical Indicators in MS Project
Project management by MS Project 2010
Building Formulas And Dashboard In Ms Project
2010 ms project 2010 (2)
Master MSProject 2010
Ms project lectures
Ms project 2000 tutorial
MICROSOFT PROJECT TUTORIAL
Introduction to Primavera Reflections
Microsoft project 2010
Project network scheduling and S-curve
Microsoft Project 2013
Uses of Project Status field
Project 2007 full handout
Pdf primavera tutorial
Microsoft Project - MSP | 2013-2016
Oracle Primavera P6 PRO R8 Tips & tricks
05 Formatting and Sharing Your Plan
Microsoft Projects; a step by-step guide for beginner's
Ad

Viewers also liked (20)

PPTX
Project Performance Dashboard
PDF
Utilizing Dashboards to improve efficiency
PPT
Developing a Dashboard to Aid in Effective Project Management
PPT
Telelogic Dashboard Presentation
PDF
Program Management Dashboards
PDF
2017 | E-Brochure | Communication Skills For Project Leaders & Managers | Pro...
PDF
2017 | E-Brochure | Project Management for Non Project Manager - PMNPM (2 Day...
PPT
Dashboard For Enterprise Architects
PPTX
Management Dashboard Sample
 
PDF
Planning Your Dashboard Project
PDF
SAP BOBJ Enterprise Dashboard - Sales Plan, Pipeline and Forecast
PDF
IMT Lecture: Innovation S Curve+ Disruptive. M M Biztel 01 Jul09.97 03
PDF
Demand Metric - Playbooks
PPT
ERP System Development Plan
PPT
S Curve
PDF
S curve innovation #BBTwisnu
PPTX
64 UX Design Interview Questions at Google, Facebook, Amazon, Microsoft, Sale...
PDF
Effective Dashboard Design: Why Your Baby is Ugly
PDF
Manual microsoft project professional 2013
PPTX
What are your career goals
Project Performance Dashboard
Utilizing Dashboards to improve efficiency
Developing a Dashboard to Aid in Effective Project Management
Telelogic Dashboard Presentation
Program Management Dashboards
2017 | E-Brochure | Communication Skills For Project Leaders & Managers | Pro...
2017 | E-Brochure | Project Management for Non Project Manager - PMNPM (2 Day...
Dashboard For Enterprise Architects
Management Dashboard Sample
 
Planning Your Dashboard Project
SAP BOBJ Enterprise Dashboard - Sales Plan, Pipeline and Forecast
IMT Lecture: Innovation S Curve+ Disruptive. M M Biztel 01 Jul09.97 03
Demand Metric - Playbooks
ERP System Development Plan
S Curve
S curve innovation #BBTwisnu
64 UX Design Interview Questions at Google, Facebook, Amazon, Microsoft, Sale...
Effective Dashboard Design: Why Your Baby is Ugly
Manual microsoft project professional 2013
What are your career goals
Ad

Similar to Microsoft project 2010 creating customized field with image & formula (20)

PPT
Formula Support in OrgPublisher 9.1 Premier
PDF
DYNDEC Company Overview
PPTX
Earning your bullhorn black belt with russ wallis
PDF
Booz Allen Hamilton - KM presentation to UNDP
PDF
Version comparisondesktop
PDF
Alfresco Plays Well With Others
PDF
Project Controls Expo, 13th Nov 2013 - "Integrated Project Planning/Schedulin...
PDF
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
PDF
Customizing helpdesk and user portal
PDF
Tech Tips (NLADA Substantive Law Conference 2010)
PDF
27 development
PDF
MBASmart - DYNDEC Assessment Partner
PPTX
Administering Windows Server 2012
PDF
Microsoft Office 2010 by Mr. EJ Lopez
PDF
Project Activities Resource Portfolio Dashboards
PPT
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
PPTX
Work smarter using sharepoint 2010 misa version2
PDF
Ms project tutorial
PDF
Exchange 2013
PPTX
Office And Share Point 2010 - Sneak Peak Event, Baltimore, MD
Formula Support in OrgPublisher 9.1 Premier
DYNDEC Company Overview
Earning your bullhorn black belt with russ wallis
Booz Allen Hamilton - KM presentation to UNDP
Version comparisondesktop
Alfresco Plays Well With Others
Project Controls Expo, 13th Nov 2013 - "Integrated Project Planning/Schedulin...
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
Customizing helpdesk and user portal
Tech Tips (NLADA Substantive Law Conference 2010)
27 development
MBASmart - DYNDEC Assessment Partner
Administering Windows Server 2012
Microsoft Office 2010 by Mr. EJ Lopez
Project Activities Resource Portfolio Dashboards
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
Work smarter using sharepoint 2010 misa version2
Ms project tutorial
Exchange 2013
Office And Share Point 2010 - Sneak Peak Event, Baltimore, MD

More from NR Computer Learning Center (20)

PPTX
Power BI Desktop Overview
PPTX
Building Dashboard with Excel
PPTX
Introduction to Data Analytics
PPTX
Python - Data Structures
PPTX
Introduction to SQL
PDF
Office 2019 tips & tricks
PDF
App Development with Apple Swift Certification at Certiport Centers
PDF
Project management fundamentals
PDF
National College Testing Association (NCTA)
PDF
National College Testing Association (NCTA)
PDF
Building a Dashboard in an hour with Power Pivot and Power BI
PPTX
Introduction to the basic mathematical concept with Python Turtle.
PDF
Stem presentation - Pathways to Technology Oriented Careers
PDF
MTA 98 364 - database fundamentals
PDF
MTA 361 software development fundamentals
PDF
Introduction to java
PDF
Introduction to c++
PDF
Executive dashboard for small business
PDF
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
PDF
Arduino for teens
Power BI Desktop Overview
Building Dashboard with Excel
Introduction to Data Analytics
Python - Data Structures
Introduction to SQL
Office 2019 tips & tricks
App Development with Apple Swift Certification at Certiport Centers
Project management fundamentals
National College Testing Association (NCTA)
National College Testing Association (NCTA)
Building a Dashboard in an hour with Power Pivot and Power BI
Introduction to the basic mathematical concept with Python Turtle.
Stem presentation - Pathways to Technology Oriented Careers
MTA 98 364 - database fundamentals
MTA 361 software development fundamentals
Introduction to java
Introduction to c++
Executive dashboard for small business
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Arduino for teens

Recently uploaded (20)

PDF
My 'novel' Account of Human Possibility pdf.pdf
PPTX
cấu trúc sử dụng mẫu Cause - Effects.pptx
PPTX
Identity Development in Adolescence.pptx
PPTX
Learn how to use Portable Grinders Safely
PPT
cypt-cht-healthy-relationships-part1-presentation-v1.1en.ppt
PPTX
Personal Development - By Knowing Oneself?
PPTX
Presentation on interview preparation.pt
PPTX
Pradeep Kumar Roll no.30 Paper I.pptx....
PPTX
Learn numerology content and join tarot reading
PPTX
Self -Management and Self Awareness.pptx
PDF
The Zeigarnik Effect by Meenakshi Khakat.pdf
PPTX
Learn how to prevent Workplace Incidents?
PPT
proper hygiene for teenagers for secondary students .ppt
PPTX
Travel mania in india needs to change the world
PPTX
show1- motivational ispiring positive thinking
PDF
The Spotlight Effect No One Is Thinking About You as Much as You Think - by M...
PPTX
How to Deal with Imposter Syndrome for Personality Development?
PDF
Red Light Wali Muskurahat – A Heart-touching Hindi Story
PDF
Attachment Theory What Childhood Says About Your Relationships.pdf
PPTX
Understanding the Self power point presentation
My 'novel' Account of Human Possibility pdf.pdf
cấu trúc sử dụng mẫu Cause - Effects.pptx
Identity Development in Adolescence.pptx
Learn how to use Portable Grinders Safely
cypt-cht-healthy-relationships-part1-presentation-v1.1en.ppt
Personal Development - By Knowing Oneself?
Presentation on interview preparation.pt
Pradeep Kumar Roll no.30 Paper I.pptx....
Learn numerology content and join tarot reading
Self -Management and Self Awareness.pptx
The Zeigarnik Effect by Meenakshi Khakat.pdf
Learn how to prevent Workplace Incidents?
proper hygiene for teenagers for secondary students .ppt
Travel mania in india needs to change the world
show1- motivational ispiring positive thinking
The Spotlight Effect No One Is Thinking About You as Much as You Think - by M...
How to Deal with Imposter Syndrome for Personality Development?
Red Light Wali Muskurahat – A Heart-touching Hindi Story
Attachment Theory What Childhood Says About Your Relationships.pdf
Understanding the Self power point presentation

Microsoft project 2010 creating customized field with image & formula

  • 2. NR Computer Learning Center 2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475 Project 2010: Creating Customized Field with Images & Formula You can use customized field feature in Microsoft Project 2010 to create a dashboard and to quickly identify problem areas in the project. In this exercise, we will create the following four customized fields: • Status_as_text: This will be a field with a drop down menu to select text: Red, Yellow, Green • Status_as_Image: This will provide the user a drop down menu to select an image to display the status as an image. • Status_as_Eval_text: This will be an automated field that evaluates %complete and displays the result as text. • Status_as_Eval_Image: This will be an automated field to evaluate %complete and display the result as an image. By the end of the exercise, you will have a project plan with status, text (red, green or yellow) and images:
  • 3. NR Computer Learning Center 2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475 Custom Field to display status as a Text Follow the steps below to create a customized field with a drop down menu that allows user to select one of the text: Red, Yellow, Green. Step 1: Select Project Tab> Properties Group > Custom Fields. Step 2: In Cutom Fields window, select Text1 fields and click on the Rename button. Type Status_as_text and click the OK button. Step 3: Click on the Lookup button. While in Edit Lookup Table Window, in the value field type: Red, Yellow, Green. Click on the Close button to close the Edit Lookup Table for Status_as_text window. Step 4: Click on OK button to save the changes. Step 5: Left Click the Add New Column in the Table View, and select Status_as_text from the drop down menu. Select the colors in the drop down to manually assign the color as status to each of the tasks.
  • 4. NR Computer Learning Center 2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475 Custom Field to display status as an Image Follow the steps below to create a customized field with a drop down menu that allows user to select one of the images from the drop down menu: Step 1: Select Project Tab> Properties Group > Custom Fields. Step 2: Select Text2 and rename to Status_as_Image. Click on Lookup button to add the options: Red, Yellow & Green. Click on the Graphical Indicators… to add the images for text red, yellow and green. Enter the following information in the Graphical Indictor window: Test for Values(s) Image Equals Red Equals Yellow Equals Green Click OK to Save the Graphical Indicators. Click OK again to save the custom fields. Once you select the color from the dropdown menu, the field is replaced with matching image.
  • 5. NR Computer Learning Center 2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475 Custom Field to automatically display % complete status as text Follow the steps below to create a customized field with a drop down menu that allow automatically populates the data in the column based on a business rule: Step 1: Select Project Tab> Properties Group > Custom Fields. Step 2: Select Text2 and rename to Status_as_Eval_Text. Step 3: Click on the Formula button. Type in the below formula in the Formula box that populated the data based on the rule specified below: IIf ([% Complete]<30,"Red",IIf([% Complete]<70,"Yellow","Green")) Click the OK button. Add the column Status_as_Eval_Text. The Microsoft Project will automatically fill up the column based on the rule specified above.
  • 6. NR Computer Learning Center 2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475 Custom Field to automatically display % complete status as Image Step 1: Select Project Tab> Properties Group > Custom Fields. Step 2: Select Text2 and rename to Status_as_Eval_Image. Step 3: Click on the Formula button. Type in the following formula in the Formula box: IIf ([% Complete]<30,"Red",IIf([% Complete]<70,"Yellow","Green")) Click the OK button. Click on the Graphical Indicators button. Click the OK button to close the Graphical Indicator Window and click the OK button to close the Custom Field Window. Add the column Status_as_Eval_Image to the project Table. The Microsoft Project will automatically fill up the column with images based on the rule specified above.
  • 7. NR Computer Learning Center 2100 W. Oangewood . Suite 110 . Orange. CA 92868 . www.nrclc.com . (714) 505-3475 If you want to learn more about Microsoft Project 2010, NR Computer Learning Center provide following options: • Articles (http://www.nrclc.com/blog/project/) • Classroom Training (www.nrclc.com/Project2010 ) • E-learning Course ( http://www.nrclc.com/VideoTraining/Project Management.html ) • Online Classes (www.nrclc.com/Project2010) • Corporate Training ( http://www.nrclc.com/CorporateTraining ) To join our email list to receive information on promotion, webinars, event and monthly newsletter, visit www.nrclc.com. NR Computer Learning Center 2100 W. Orangewood, Suite 110 Orange, CA 92868 www.nrclc.com (714) 505-3475 Twitter: @NRCLC Facebook: www.facebook.com/NRCLC Blog: www.nrclc.com/blog