The document discusses scheduling a project at different levels. It describes the FSBOK Guide's 5-level schedule hierarchy from Level 1 executive schedules down to Level 5 look-ahead schedules. Key points include maintaining Level 1 and 2 schedules as time-scaled networks, limiting rolling wave planning to Level 4, and keeping uniform activity duration ranges within each schedule level. Network-based schedules are advocated for reliability in forecasting and evaluating delays. Massive schedules with high density can degrade usefulness, so alternative approaches like multi-level scheduling are suggested.