Scheduling a Project
                   At Different Levels
                Gui Ponce de Leon PhD, PE, PMP, LEED AP
                         Philip Spittler PMP
                    PMA Consultants, LLC
                            May 2,
                            M 2 2011
02 May 11   2
Schedule Level Resources




02 May 11   3
Scheduling a Project at the Right
                           Level at the Right Time
                           Level,

            An important consideration in planning and scheduling
            During management planning
               When executive and senior managers are involved
               Project-level schedules prevail
            Schedules become detailed as the planning horizon
            switches from the whole of the project to stages or
            phases
               With assumptions tested and information firmed-up
               Management can engage in detailed planning
            Various participants have different levels of interest
            Some consensus but yet to reach standard status
                                  y

02 May 11      4
Protocols Considered

            Jelen’s schedule levels
            The CII schedule levels
            Guide to the Forensic Scheduling Body of Knowledge
            Part I (FSBOK Guide)
            AACE International Recommended Practice No. 37R-06
            Schedule Levels of Detail─As Applied in Engineering,
            Procurement and Construction (RP 37)
                                            (      )
            The Chartered Institute of Building Guide to Good
            Practice in the Management of Time in Complex Projects
            (CIOB Guide)
            Mosaic’s Schedule Levels─Major Projects
            DOE Schedule Planning and Development Guide 1.8


02 May 11     5
Jelen s
                Jelen’s
                Levels




02 May 11   6
Varying Interpretations of Level 2
                      Schedules in Construction
                      S h d l i C          t ti




02 May 11   7
Recent Developments
            RP 37 describes a 5-level method based on schedule
            level requirements, levels of interest and the intended
            use of each schedule level
               This RP 37 method is based on Stephenson’s levels
            The CIOB Guide advocates five schedule reporting
            levels
            le els
               Levels 1 - 3 accomplished through summarizations
               Activity duration ranges vary within a schedule based on
               planning h i
                l    i horizon
            Neither the PMBOK Guide nor The Practice Standard
            for Scheduling deals with schedule levels
            Weaver/Mosaic offers a hierarchy of Level 1–5
            schedules, from summary- to detailed- level schedules
               Activity duration ranges may vary either based on schedule
                      y             g      y    y
               level or planning horizon within a schedule

02 May 11      8
The CSI Approach to
                           Construction WBS Hierarchy
            The Construction Specifications Institute publishes the
            MasterFormat, a master list th t classifies project work
            M t F         t      t li t that l    ifi      j t     k
            by deliverables and components and by construction
            practices
               General Requirements Division 01
               Facility Construction Divisions 02-19
               Facility Services Divisions 20-29
               Site and Infrastructure Divisions 30-39
               Process Equipment Divisions 40-49
            The MasterFormat is one scheme
            that can be used to organize the project
            WBS, detail cost accounts and
            activity codes

02 May 11      9
Guide to the Forensic Scheduling
                                 Body of Knowledge
            A schedule hierarchy for coherent summary and detailed
                                                               detailed-
            level schedules intended for mega contracts and major
            contracts, but scalable to other contracts; it advocates:
               Network-based
               Network based level 1 4 schedules
                                     1–4
               Maintaining the Level 1 schedule and Level 2 schedule─both in
               time-scaled network format─current for the duration of the project
               Limiting rolling wave planning techniques to Level 4 schedules
            Suitable to top-down and roll-up integration
               Top-down─base a lower-level schedule on the next higher level
               Roll-up─carry re-baselining and updating to higher levels
            By way of example, the hierarchy is aligned with the
            MasterFormat approach to construction WBS hierarchies


02 May 11     10
FSBOK Guide Level 1
                                   Executive Schedule
                                   E    ti S h d l
   General Intent and Format
            Establishes Contractual Milestones (if Included with
            the Request for Bids) or Demonstrates
            Conformance to Contractual and Other Milestones
            (if Included with the Bid and/or the Contract)
            Time-Scaled Network Diagram─Commonly One
                                       g               y
            Sheet
            Kept Current with Level 2
            Compares t RP 37 L
            C           to        Level 1 Wi k i et al. L
                                       l 1, Wickwire t l Level 1
                                                             l
            and Mosaic Level 1


02 May 11     11
FSBOK Guide Level 1
                                  Executive Schedule
                                  E    ti S h d l
   Scheduling Objective
            Portrays Controlling, Summary-Level Activity(ies)
            Between Milestones at CSI Division Grouping Level
            Key Procurement Scope and Overall Commissioning
            Sequence Included
            Empirical Mega Construction Activity Duration: 20%
            to 40% of Contract, Generally 6 to 18 Months
            Empirical Major Construction Activity Duration: 10%
                p       j                       y
            to 30% of Contract, Generally 3 to 12 Months



02 May 11     12
FSBOK Guide Level 2
                                 M
                                 Management S h d l
                                          t Schedule
   General Intent and Format
            Project Manager Input and Sign-Off
            Developed with the Bid or Before Mobilization
            Time-scaled Network Diagram
            Establishes the Critical Path, Near-Critical Paths and Key
            Target Dates for the Initial (Rev. 0) Progress Schedule
            Conforms to the Construction Plan, Including
            Constructability, Targeted Means and Methods, Craft
            Levels and Shared-Resource Dependencies
            Mostly Finish-to-Start Logic Ties
            Roll-Up of Level 3 Re-Baselining and Updating
            Compares to RP 37 Level 2 and Mosaic Level 2

02 May 11     13
FSBOK Guide Level 2
                                   M
                                   Management S h d l
                                             t Schedule
   Scheduling Objective
      Driving Path for Structures & Major P
      D i i P th f St t             M j Process S t
                                                  Systems at CSI
                                                             t
      Division Level (e.g., Earthwork, Foundations, Framing, etc.)
      May Subdivide Into Area Grouping or Tier Grouping
      Constructability and Normal Adverse Weather-Validated
      Long-Lead Equipment & Material Procurements and Critical
      Commissioning Sequences
      Empirical Construction Activity Duration:
            Mega contracts: 10% to 20% of Contract, Generally 3 to 9 Months
            Major Contracts: 5% to15% of Contract, Generally 2 to 6 Months
      Lower end is for activities for which hard logic applies
      Upper limit is for activities scoping bulk commodities

02 May 11    14
FSBOK Guide Level 3
                                    P
                                    Progress S h d l
                                             Schedule
   General Intent and Format
            Site/Construction Manager Input and Sign-Off
            Time-scaled Network Diagram or Bar Chart with Logic
            Drives the Updating Process
            Integrates Vendor Design, Fab/Delivery, Construction,
            System Completion and Commissioning
            May be Craft Loaded (Typically, Critical Crafts) and Rely
            on Critical Shared-Resource Dependencies (e.g.,
            Shared Crane)  )
            Activity Cost Loading, if Contractually Required
            Compares to RP 37 Level 3, Wickwire et al. Level 2 and
            Mosaic Level 3

02 May 11    15
FSBOK Guide Level 3
                                   P
                                   Progress S h d l
                                            Schedule
   Scheduling Objective
            Grouping of CSI Divisions in Areas or Elevations for
            Structures and Major Process Systems
            Level 2 Earthwork, Foundation, Framing etc Subdivided
                    Earthwork Foundation Framing, etc.
            into Component Chunks
            Normal Adverse Weather-Validated
            Detailed Delivery Sequences and Integrated, Detailed
            Commissioning Sequence
            Formula Mega Construction Activity Duration: 2% to 5%
                         g                    y
            of Contract, Generally 3 to 12 Weeks
            Formula Major Construction Activity Duration: 1% to 3%
            of Contract, 2 to 6 Weeks
               Contract

02 May 11     16
FSBOK Guide Level 4
                                     W ki S h d l
                                     Working Schedules
   General Intent and Format
            Supervision Input and Sign-Off
            Developed Before Starting a Phase or Area
            Often Developed as Separate Schedules
                          p        p
            Time-scaled Network Diagrams or Bar Charts with Logic
            Coordinated with Field Supervision (Contractor) and
            Subcontractor Input
            Trade Coordination
            May be Craft Loaded and Detail Crew Movements and other
            Means & Methods
            May be Done on a Rolling Wave Basis (e.g., Every 3 Months)
            Compares to RP 37 Level 4, Wickwire et al. Level 3 and
            Mosaic L
            M    i Level 4
                        l

02 May 11     17
FSBOK Guide Level 4
                               W ki S h d l
                               Working Schedules
   Scheduling Objective
       Groups CSI Sections Within Elevation or Area for
       Structure or Process System
       Level 3 Earthwork, Foundation, Framing Enclosure MEP
                 Earthwork Foundation Framing, Enclosure,
       & Process Installations Subdivided into Fragnets;
       Activities Biased Towards a Subcontractor or Trade
       Normal Ad
       N       l Adverse W th V lid t d
                         Weather-Validated
       Working-Level Detail in Procurement and Commissioning
       Formula Mega Construction Activity Duration: 1% to 3%
                     g                   y
       of Contract, Generally 2 to 6 Weeks
       Formula Major Construction Activity Duration: 1% to 2%
       of Contract, Generally 2 to 4 Weeks
          Contract

02 May 11   18
FSBOK Guide Level 5
                         L k Ah d S h d l
                         Look-Ahead Schedule
   General Intent and Format
     Subdivide Progress and Upcoming Level 3 or
     Level 4 Activities into Tasks for the Next 2 to 3
     Weeks
     Developed by Crew Foreman Typically in Bar
     Charts or Similar Format
     Tasks are Crew Loaded
     Reviewed in Site Progress Meetings
                            g             g
     Compares to RP 37 Level 5 and Mosaic Level 5


02 May 11   19
FSBOK Guide Level 5
                               L k Ah d S h d l
                               Look-Ahead Schedule
   Scheduling Objective
            Work Assigned to Crews
            Broken Down by Specific Components, Based
                             y p            p
            on Verification That Work Can Proceed and
            That Materials, Design Documentation and
            Other Installation Information are Packaged and
            Made Available to Crew Foremen
            Task Duration: From a Few Days to Three
                                            y
            Weeks



02 May 11     20
FSBOK Guide Advocates Network-
                   Based Level 1 4 S h d l
                   B    dL    l 1-4 Schedules
   Absent Contrary Contractual Language:
                 y                g g
            Level 2 schedules and Level 3 schedules are
            appropriate forecasting tools to evaluate:
              Timely performance
              Delay and disruption, and
              Time extension requests
            Whether
              When
              Wh such ih issues arise, or
                                  i
              Where the evaluation is undertaken post-completion


02 May 11    21
FSBOK Guide View of Level
                                    2S h d l
                                      Schedules
                                             g
   A Relevant and Reliable Forecasting Tool if:
    In a time-scaled network format
    It portrays the contractor’s plan at contract award
    at an appropriate granularity
      t            i t        l it
    It remains current and in conformance to the
    contract
    It establishes the critical/near-critical paths based:
            On contract dates
            On the construction plan, e.g., means and methods, etc.
            On normal adverse weather
            On key deliveries
02 May 11    22
FSBOK Guide View of Level
                              3S h d l
                                Schedules
   As Source Document for Forensic Modeling         g
    Depending on the analysis method used, a Level 3
    schedule may be overly detailed, particularly where
    not relevant to the facts of the case
       t l      t t th f t f th
    Forensic analysis using a Level 3 schedule may
    divert attention to non issues and detract from the
                        non-issues
    issues in dispute without gaining analysis accuracy
     Where this compromises analysis accuracy, an
                      p              y           y,
    acceptable protocol is to generate a reliable
    summarization of the Level 3 schedule


02 May 11   23
FSBOK Guide View of Level 4
                           and L
                             d Level 1 S h d l
                                   l Schedules
     The subdivisions of Level 3 schedule activities
     existing in a Level 4 schedule are often suitable
     bases for time impact analysis at the fragnet level
     A Level 1 schedule i a time-scaled network f
       L     l    h d l in i           l d       k format
     that is coherent with the Level 2 schedule is a valid
     source for a forensic demonstrative provided:
                            demonstrative,
            It portrays controlling summary activities between
            milestones at the CSI Division Grouping Level or
            equivalent indenture in another WBS scheme
            It includes critical procurement activities, commissioning
            activities and, possibly, schedule reserve


02 May 11    24
Example of a Level 1 Schedule




02 May 11   25
Schedule Granularity vs.
                                       Schedule Density

            When the
            Wh th project i scheduled i multi-level schedules
                     j t is h d l d in    lti l   l h d l
              For instance, where separate rolling wave Level 4 schedules are
              generated, it is practical to design Level 2 and Level 3 schedules
              with uniform activity duration ranges
            Where duration range is uniform for the duration of level
            2-3 schedules, appropriate to the level in the hierarchy
              The
              Th term activity or schedule granularity i used rather than
                          i i       h d l       l i is      d h h
              schedule density
            CIOB Guide schedule density implies varying duration
            ranges within a schedule
                      ithi    h d l
            FSBOK Guide schedule granularity prescribes a uniform
            duration range for each schedule
                           g

02 May 11     26
Recapping the
                                  FSBOK Guide Hierarchy
   Main Points
      Network-based schedules at all levels but for look-ahead
            Better ensures relevant and reliable forecasting tools
      ALLevel 2 schedule k t current f th project d ti
             l     h d l kept        t for the  j t duration
      promotes continuing executive and senior management
      involvement when re-baselining schedule performance
      Derive a lower-level schedule from the next higher-level
      Limit use of rolling wave planning techniques to Level 4
      Hold schedule granularity uniform as opposed to varying
      schedule density with planning horizon
      Interplay between WBS and Schedule level


02 May 11    27
The Downside of Schedules that Become
           Massive as D
           M     i     Density I
                            it Increases

      When the schedule multiplies in the number of activities as
      schedule density increases from update to update, its
      usefulness as a relevant reliable forecasting tool degrades
                      relevant,
            Schedule integrity is affected by data machinations the scheduler
            may have engaged in to attain realistic dates and critical paths
            Ever-growing multi-thousand activity schedules trend toward a
            highly-disordered schedule document




02 May 11    28
FSBOK and CIOB Guidance on
                      Activity Duration R
                      A i i D       i Ranges




02 May 11   29
FSBOK Guide Schedule Hierarchy
                              in Summary




02 May 11   30
The Sayonara Conclusion


            The time has come to bid farewell to bar chart
            techniques for Level 1 and Level 2 schedules,
            as well as Level 4 schedules
            This will not only promote more coherent
            p
            planning, but will allow all contemporaneous
                    g,                         p
            schedules to play a role in forensic scheduling




02 May 11     31
The TMI Conclusion

            An alternative to working with Level 3 schedules
            that become massive as schedule density
            increases is to approach the scheduling of a project
            in a multi-level schedule sequence that involves
              Deriving a lower-level schedule from the next higher-level
              schedule
              Limiting reliance on rolling wave planning techniques to
              the network-based Level 4 schedules
            For any schedule in the hierarchy, maintaining
            granularity unniform, from beginning to end, better
            ensures a highly-ordered network of realistic dates
            and reasonable floats, ergo a relevant and reliable
            forecasting document

02 May 11     32
The Less is More…
                   You Had Me at Level 2 Conclusion
            The activity granularity designed into a Level 2
            schedule is likely to yield a relevant and reliable
            source document for forensic schedule analysis
            Because of the activity granularity typically
            followed, a Level 3 schedule may detail paths not
            relevant to the facts of the case; analyzing non-
                                                           non
            issues may detract from and confuse the issues in
            dispute without gaining analysis accuracy
            The d t il i
            Th detail in a Level 3 schedule used i f
                            L    l     h d l       d in forensic
                                                              i
            schedule analysis should be made proportionate to
            the facts at issue by means of reliable
            summarizations
02 May 11     33
The New Standard Conclusion

            Favor approaching the scheduling of a project
            in separate but coherent summary- and
            detailed-level schedules, each schedule with
            uniform granularity
            Note ─the principles discussed are adaptable to
            schedule level approaches that are based on
                             pp
            one schedule designed at different levels of
            detail by varying schedule density based on
            planning horizon



02 May 11     34
Thank You
                 For Attending!


02 May 11   35

More Related Content

PDF
Primavera p6 18.8 planning and scheduling guide r3
PPTX
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
PPTX
PRIMAVERA P6 manual.pptx
PDF
Primavera p6 advanced project planning
PPTX
Construction Delay Analysis, Simplified
PDF
Loading cost in primavera schedule using resources and expenses r01
PPTX
44259126 ms-project-presentation
PDF
Primavera P6 manual
Primavera p6 18.8 planning and scheduling guide r3
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
PRIMAVERA P6 manual.pptx
Primavera p6 advanced project planning
Construction Delay Analysis, Simplified
Loading cost in primavera schedule using resources and expenses r01
44259126 ms-project-presentation
Primavera P6 manual

What's hot (20)

PDF
Pdf primavera tutorial
PDF
Project Schedule Management
PDF
Methods of delay analysis
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PPT
Fast Tracking a Project and Project Crashing.ppt
PPTX
Work breakdown structures
PPTX
Introduction To Primavera (P6)
PDF
BIM Execution plan
PDF
Project Scheduling & Controls
PPTX
Planning_and_scheduling.pptx
PDF
Promo_Epc project rule of credit and progress measurement
PDF
Project Time Management - PMBOK 5th Edition
PPTX
Primavara
PDF
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
PPTX
Project Management using MS Project 2010
PDF
Wbs Building Use This
DOCX
MS Project
PPTX
Project Execution
PDF
Microsoft Project and Portfolio Management
PPT
Integrated Master Schedule
Pdf primavera tutorial
Project Schedule Management
Methods of delay analysis
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Fast Tracking a Project and Project Crashing.ppt
Work breakdown structures
Introduction To Primavera (P6)
BIM Execution plan
Project Scheduling & Controls
Planning_and_scheduling.pptx
Promo_Epc project rule of credit and progress measurement
Project Time Management - PMBOK 5th Edition
Primavara
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Project Management using MS Project 2010
Wbs Building Use This
MS Project
Project Execution
Microsoft Project and Portfolio Management
Integrated Master Schedule
Ad

Viewers also liked (8)

PDF
Build an integrated master plan and integrated master
PDF
What You Should Be Doing with Your Master Schedule
PDF
In Pursuit of Reliable Schedules
PDF
101116 Risk-based Planning & Scheduling (My SAIT Slides)
PDF
Integrated Master Plan and Integrated Master Schedule
PDF
Project Control Handbook
PDF
FTA Construction Management Handbook - 2012
PDF
080613 Mega-Project Schedule Integration & Management RCF Method-1
Build an integrated master plan and integrated master
What You Should Be Doing with Your Master Schedule
In Pursuit of Reliable Schedules
101116 Risk-based Planning & Scheduling (My SAIT Slides)
Integrated Master Plan and Integrated Master Schedule
Project Control Handbook
FTA Construction Management Handbook - 2012
080613 Mega-Project Schedule Integration & Management RCF Method-1
Ad

Similar to Schedule levels-as-presented 02-may11 (20)

PPT
unit-vpart-2.ppt
PPTX
Petze.lara
PDF
Improving Project Performance in the DOE
PDF
Improving DOE Project Performance Using the DOD Integrated Master Plan
PDF
Acumen presentation (final)
PDF
Lecture 2 30-01-2020.pdf
PDF
Vonnie simonsen
PDF
Vonnie simonsen
PPT
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
PDF
Week 9 Lecture.pdf software project management
PPTX
PMNM101 Lesson 2 2022.pptx
PDF
Construction Project Schedule Example- Residential Building
DOCX
PositioningPositioning of Product or ServiceParis based weig.docx
PPTX
Pmi Project Management Core Problems Uet Dec 22 09
PPTX
PMIS Presentation ........................
PDF
Dlpks Cwmf Technical Briefing
PDF
Define the Project
PDF
Project Management Skills unit-4 Notes
PPTX
Team Final_Scope Management
unit-vpart-2.ppt
Petze.lara
Improving Project Performance in the DOE
Improving DOE Project Performance Using the DOD Integrated Master Plan
Acumen presentation (final)
Lecture 2 30-01-2020.pdf
Vonnie simonsen
Vonnie simonsen
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
Week 9 Lecture.pdf software project management
PMNM101 Lesson 2 2022.pptx
Construction Project Schedule Example- Residential Building
PositioningPositioning of Product or ServiceParis based weig.docx
Pmi Project Management Core Problems Uet Dec 22 09
PMIS Presentation ........................
Dlpks Cwmf Technical Briefing
Define the Project
Project Management Skills unit-4 Notes
Team Final_Scope Management

More from PMA Consultants (20)

PDF
Practical Application of Value Engineering in Capital Projects
PDF
Project Cost & Schedule Integration Lessons Learnt
PDF
PANDEMIC RESILIENTSCHOOLS
PDF
BioPharma Projects: Essentials in Project Controls
PDF
How to Implement a Project Management Information System
PDF
Top Five Metrics for Measuring Schedule Reliability
PDF
What are the disadvantages of Gantt charts?
PDF
BIM and VDC for Megaproject Construction Projects
PDF
Setting up Filters & Layouts in P6
PDF
How to Choose a Project Delivery Method
PDF
Risk Management Processes from Jerry Klanac
PDF
Project Controls Processes
PDF
Work Breakdown Structure Planning in NetPoint
PDF
How to Import/Export a Schedule between NetPoint and Microsft Excel
PDF
Smarter Planning with Microsoft Excel
PDF
Leveraging NetPoint & Excel for Template-Based Project Planning
PDF
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
PDF
The Value of Project Risk Management
PDF
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
PDF
P6 tips tricks-client
Practical Application of Value Engineering in Capital Projects
Project Cost & Schedule Integration Lessons Learnt
PANDEMIC RESILIENTSCHOOLS
BioPharma Projects: Essentials in Project Controls
How to Implement a Project Management Information System
Top Five Metrics for Measuring Schedule Reliability
What are the disadvantages of Gantt charts?
BIM and VDC for Megaproject Construction Projects
Setting up Filters & Layouts in P6
How to Choose a Project Delivery Method
Risk Management Processes from Jerry Klanac
Project Controls Processes
Work Breakdown Structure Planning in NetPoint
How to Import/Export a Schedule between NetPoint and Microsft Excel
Smarter Planning with Microsoft Excel
Leveraging NetPoint & Excel for Template-Based Project Planning
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
The Value of Project Risk Management
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
P6 tips tricks-client

Recently uploaded (20)

PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
Tata consultancy services case study shri Sharda college, basrur
PPT
Chapter four Project-Preparation material
PDF
Comments on Crystal Cloud and Energy Star.pdf
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
NEW - FEES STRUCTURES (01-july-2024).pdf
PPTX
DMT - Profile Brief About Business .pptx
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
Principles of Marketing, Industrial, Consumers,
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
ICG2025_ICG 6th steering committee 30-8-24.pptx
Daniels 2024 Inclusive, Sustainable Development
Tata consultancy services case study shri Sharda college, basrur
Chapter four Project-Preparation material
Comments on Crystal Cloud and Energy Star.pdf
Belch_12e_PPT_Ch18_Accessible_university.pptx
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
Charisse Litchman: A Maverick Making Neurological Care More Accessible
Deliverable file - Regulatory guideline analysis.pdf
Module 2 - Modern Supervison Challenges - Student Resource.pdf
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
NEW - FEES STRUCTURES (01-july-2024).pdf
DMT - Profile Brief About Business .pptx
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Principles of Marketing, Industrial, Consumers,
Lecture 3344;;,,(,(((((((((((((((((((((((
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Probability Distribution, binomial distribution, poisson distribution
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics

Schedule levels-as-presented 02-may11

  • 2. Scheduling a Project At Different Levels Gui Ponce de Leon PhD, PE, PMP, LEED AP Philip Spittler PMP PMA Consultants, LLC May 2, M 2 2011 02 May 11 2
  • 4. Scheduling a Project at the Right Level at the Right Time Level, An important consideration in planning and scheduling During management planning When executive and senior managers are involved Project-level schedules prevail Schedules become detailed as the planning horizon switches from the whole of the project to stages or phases With assumptions tested and information firmed-up Management can engage in detailed planning Various participants have different levels of interest Some consensus but yet to reach standard status y 02 May 11 4
  • 5. Protocols Considered Jelen’s schedule levels The CII schedule levels Guide to the Forensic Scheduling Body of Knowledge Part I (FSBOK Guide) AACE International Recommended Practice No. 37R-06 Schedule Levels of Detail─As Applied in Engineering, Procurement and Construction (RP 37) ( ) The Chartered Institute of Building Guide to Good Practice in the Management of Time in Complex Projects (CIOB Guide) Mosaic’s Schedule Levels─Major Projects DOE Schedule Planning and Development Guide 1.8 02 May 11 5
  • 6. Jelen s Jelen’s Levels 02 May 11 6
  • 7. Varying Interpretations of Level 2 Schedules in Construction S h d l i C t ti 02 May 11 7
  • 8. Recent Developments RP 37 describes a 5-level method based on schedule level requirements, levels of interest and the intended use of each schedule level This RP 37 method is based on Stephenson’s levels The CIOB Guide advocates five schedule reporting levels le els Levels 1 - 3 accomplished through summarizations Activity duration ranges vary within a schedule based on planning h i l i horizon Neither the PMBOK Guide nor The Practice Standard for Scheduling deals with schedule levels Weaver/Mosaic offers a hierarchy of Level 1–5 schedules, from summary- to detailed- level schedules Activity duration ranges may vary either based on schedule y g y y level or planning horizon within a schedule 02 May 11 8
  • 9. The CSI Approach to Construction WBS Hierarchy The Construction Specifications Institute publishes the MasterFormat, a master list th t classifies project work M t F t t li t that l ifi j t k by deliverables and components and by construction practices General Requirements Division 01 Facility Construction Divisions 02-19 Facility Services Divisions 20-29 Site and Infrastructure Divisions 30-39 Process Equipment Divisions 40-49 The MasterFormat is one scheme that can be used to organize the project WBS, detail cost accounts and activity codes 02 May 11 9
  • 10. Guide to the Forensic Scheduling Body of Knowledge A schedule hierarchy for coherent summary and detailed detailed- level schedules intended for mega contracts and major contracts, but scalable to other contracts; it advocates: Network-based Network based level 1 4 schedules 1–4 Maintaining the Level 1 schedule and Level 2 schedule─both in time-scaled network format─current for the duration of the project Limiting rolling wave planning techniques to Level 4 schedules Suitable to top-down and roll-up integration Top-down─base a lower-level schedule on the next higher level Roll-up─carry re-baselining and updating to higher levels By way of example, the hierarchy is aligned with the MasterFormat approach to construction WBS hierarchies 02 May 11 10
  • 11. FSBOK Guide Level 1 Executive Schedule E ti S h d l General Intent and Format Establishes Contractual Milestones (if Included with the Request for Bids) or Demonstrates Conformance to Contractual and Other Milestones (if Included with the Bid and/or the Contract) Time-Scaled Network Diagram─Commonly One g y Sheet Kept Current with Level 2 Compares t RP 37 L C to Level 1 Wi k i et al. L l 1, Wickwire t l Level 1 l and Mosaic Level 1 02 May 11 11
  • 12. FSBOK Guide Level 1 Executive Schedule E ti S h d l Scheduling Objective Portrays Controlling, Summary-Level Activity(ies) Between Milestones at CSI Division Grouping Level Key Procurement Scope and Overall Commissioning Sequence Included Empirical Mega Construction Activity Duration: 20% to 40% of Contract, Generally 6 to 18 Months Empirical Major Construction Activity Duration: 10% p j y to 30% of Contract, Generally 3 to 12 Months 02 May 11 12
  • 13. FSBOK Guide Level 2 M Management S h d l t Schedule General Intent and Format Project Manager Input and Sign-Off Developed with the Bid or Before Mobilization Time-scaled Network Diagram Establishes the Critical Path, Near-Critical Paths and Key Target Dates for the Initial (Rev. 0) Progress Schedule Conforms to the Construction Plan, Including Constructability, Targeted Means and Methods, Craft Levels and Shared-Resource Dependencies Mostly Finish-to-Start Logic Ties Roll-Up of Level 3 Re-Baselining and Updating Compares to RP 37 Level 2 and Mosaic Level 2 02 May 11 13
  • 14. FSBOK Guide Level 2 M Management S h d l t Schedule Scheduling Objective Driving Path for Structures & Major P D i i P th f St t M j Process S t Systems at CSI t Division Level (e.g., Earthwork, Foundations, Framing, etc.) May Subdivide Into Area Grouping or Tier Grouping Constructability and Normal Adverse Weather-Validated Long-Lead Equipment & Material Procurements and Critical Commissioning Sequences Empirical Construction Activity Duration: Mega contracts: 10% to 20% of Contract, Generally 3 to 9 Months Major Contracts: 5% to15% of Contract, Generally 2 to 6 Months Lower end is for activities for which hard logic applies Upper limit is for activities scoping bulk commodities 02 May 11 14
  • 15. FSBOK Guide Level 3 P Progress S h d l Schedule General Intent and Format Site/Construction Manager Input and Sign-Off Time-scaled Network Diagram or Bar Chart with Logic Drives the Updating Process Integrates Vendor Design, Fab/Delivery, Construction, System Completion and Commissioning May be Craft Loaded (Typically, Critical Crafts) and Rely on Critical Shared-Resource Dependencies (e.g., Shared Crane) ) Activity Cost Loading, if Contractually Required Compares to RP 37 Level 3, Wickwire et al. Level 2 and Mosaic Level 3 02 May 11 15
  • 16. FSBOK Guide Level 3 P Progress S h d l Schedule Scheduling Objective Grouping of CSI Divisions in Areas or Elevations for Structures and Major Process Systems Level 2 Earthwork, Foundation, Framing etc Subdivided Earthwork Foundation Framing, etc. into Component Chunks Normal Adverse Weather-Validated Detailed Delivery Sequences and Integrated, Detailed Commissioning Sequence Formula Mega Construction Activity Duration: 2% to 5% g y of Contract, Generally 3 to 12 Weeks Formula Major Construction Activity Duration: 1% to 3% of Contract, 2 to 6 Weeks Contract 02 May 11 16
  • 17. FSBOK Guide Level 4 W ki S h d l Working Schedules General Intent and Format Supervision Input and Sign-Off Developed Before Starting a Phase or Area Often Developed as Separate Schedules p p Time-scaled Network Diagrams or Bar Charts with Logic Coordinated with Field Supervision (Contractor) and Subcontractor Input Trade Coordination May be Craft Loaded and Detail Crew Movements and other Means & Methods May be Done on a Rolling Wave Basis (e.g., Every 3 Months) Compares to RP 37 Level 4, Wickwire et al. Level 3 and Mosaic L M i Level 4 l 02 May 11 17
  • 18. FSBOK Guide Level 4 W ki S h d l Working Schedules Scheduling Objective Groups CSI Sections Within Elevation or Area for Structure or Process System Level 3 Earthwork, Foundation, Framing Enclosure MEP Earthwork Foundation Framing, Enclosure, & Process Installations Subdivided into Fragnets; Activities Biased Towards a Subcontractor or Trade Normal Ad N l Adverse W th V lid t d Weather-Validated Working-Level Detail in Procurement and Commissioning Formula Mega Construction Activity Duration: 1% to 3% g y of Contract, Generally 2 to 6 Weeks Formula Major Construction Activity Duration: 1% to 2% of Contract, Generally 2 to 4 Weeks Contract 02 May 11 18
  • 19. FSBOK Guide Level 5 L k Ah d S h d l Look-Ahead Schedule General Intent and Format Subdivide Progress and Upcoming Level 3 or Level 4 Activities into Tasks for the Next 2 to 3 Weeks Developed by Crew Foreman Typically in Bar Charts or Similar Format Tasks are Crew Loaded Reviewed in Site Progress Meetings g g Compares to RP 37 Level 5 and Mosaic Level 5 02 May 11 19
  • 20. FSBOK Guide Level 5 L k Ah d S h d l Look-Ahead Schedule Scheduling Objective Work Assigned to Crews Broken Down by Specific Components, Based y p p on Verification That Work Can Proceed and That Materials, Design Documentation and Other Installation Information are Packaged and Made Available to Crew Foremen Task Duration: From a Few Days to Three y Weeks 02 May 11 20
  • 21. FSBOK Guide Advocates Network- Based Level 1 4 S h d l B dL l 1-4 Schedules Absent Contrary Contractual Language: y g g Level 2 schedules and Level 3 schedules are appropriate forecasting tools to evaluate: Timely performance Delay and disruption, and Time extension requests Whether When Wh such ih issues arise, or i Where the evaluation is undertaken post-completion 02 May 11 21
  • 22. FSBOK Guide View of Level 2S h d l Schedules g A Relevant and Reliable Forecasting Tool if: In a time-scaled network format It portrays the contractor’s plan at contract award at an appropriate granularity t i t l it It remains current and in conformance to the contract It establishes the critical/near-critical paths based: On contract dates On the construction plan, e.g., means and methods, etc. On normal adverse weather On key deliveries 02 May 11 22
  • 23. FSBOK Guide View of Level 3S h d l Schedules As Source Document for Forensic Modeling g Depending on the analysis method used, a Level 3 schedule may be overly detailed, particularly where not relevant to the facts of the case t l t t th f t f th Forensic analysis using a Level 3 schedule may divert attention to non issues and detract from the non-issues issues in dispute without gaining analysis accuracy Where this compromises analysis accuracy, an p y y, acceptable protocol is to generate a reliable summarization of the Level 3 schedule 02 May 11 23
  • 24. FSBOK Guide View of Level 4 and L d Level 1 S h d l l Schedules The subdivisions of Level 3 schedule activities existing in a Level 4 schedule are often suitable bases for time impact analysis at the fragnet level A Level 1 schedule i a time-scaled network f L l h d l in i l d k format that is coherent with the Level 2 schedule is a valid source for a forensic demonstrative provided: demonstrative, It portrays controlling summary activities between milestones at the CSI Division Grouping Level or equivalent indenture in another WBS scheme It includes critical procurement activities, commissioning activities and, possibly, schedule reserve 02 May 11 24
  • 25. Example of a Level 1 Schedule 02 May 11 25
  • 26. Schedule Granularity vs. Schedule Density When the Wh th project i scheduled i multi-level schedules j t is h d l d in lti l l h d l For instance, where separate rolling wave Level 4 schedules are generated, it is practical to design Level 2 and Level 3 schedules with uniform activity duration ranges Where duration range is uniform for the duration of level 2-3 schedules, appropriate to the level in the hierarchy The Th term activity or schedule granularity i used rather than i i h d l l i is d h h schedule density CIOB Guide schedule density implies varying duration ranges within a schedule ithi h d l FSBOK Guide schedule granularity prescribes a uniform duration range for each schedule g 02 May 11 26
  • 27. Recapping the FSBOK Guide Hierarchy Main Points Network-based schedules at all levels but for look-ahead Better ensures relevant and reliable forecasting tools ALLevel 2 schedule k t current f th project d ti l h d l kept t for the j t duration promotes continuing executive and senior management involvement when re-baselining schedule performance Derive a lower-level schedule from the next higher-level Limit use of rolling wave planning techniques to Level 4 Hold schedule granularity uniform as opposed to varying schedule density with planning horizon Interplay between WBS and Schedule level 02 May 11 27
  • 28. The Downside of Schedules that Become Massive as D M i Density I it Increases When the schedule multiplies in the number of activities as schedule density increases from update to update, its usefulness as a relevant reliable forecasting tool degrades relevant, Schedule integrity is affected by data machinations the scheduler may have engaged in to attain realistic dates and critical paths Ever-growing multi-thousand activity schedules trend toward a highly-disordered schedule document 02 May 11 28
  • 29. FSBOK and CIOB Guidance on Activity Duration R A i i D i Ranges 02 May 11 29
  • 30. FSBOK Guide Schedule Hierarchy in Summary 02 May 11 30
  • 31. The Sayonara Conclusion The time has come to bid farewell to bar chart techniques for Level 1 and Level 2 schedules, as well as Level 4 schedules This will not only promote more coherent p planning, but will allow all contemporaneous g, p schedules to play a role in forensic scheduling 02 May 11 31
  • 32. The TMI Conclusion An alternative to working with Level 3 schedules that become massive as schedule density increases is to approach the scheduling of a project in a multi-level schedule sequence that involves Deriving a lower-level schedule from the next higher-level schedule Limiting reliance on rolling wave planning techniques to the network-based Level 4 schedules For any schedule in the hierarchy, maintaining granularity unniform, from beginning to end, better ensures a highly-ordered network of realistic dates and reasonable floats, ergo a relevant and reliable forecasting document 02 May 11 32
  • 33. The Less is More… You Had Me at Level 2 Conclusion The activity granularity designed into a Level 2 schedule is likely to yield a relevant and reliable source document for forensic schedule analysis Because of the activity granularity typically followed, a Level 3 schedule may detail paths not relevant to the facts of the case; analyzing non- non issues may detract from and confuse the issues in dispute without gaining analysis accuracy The d t il i Th detail in a Level 3 schedule used i f L l h d l d in forensic i schedule analysis should be made proportionate to the facts at issue by means of reliable summarizations 02 May 11 33
  • 34. The New Standard Conclusion Favor approaching the scheduling of a project in separate but coherent summary- and detailed-level schedules, each schedule with uniform granularity Note ─the principles discussed are adaptable to schedule level approaches that are based on pp one schedule designed at different levels of detail by varying schedule density based on planning horizon 02 May 11 34
  • 35. Thank You For Attending! 02 May 11 35