JLL REAL VALUE METHOD: CHANGE ORDERS
JLL’S VALUE PROPOSITION FOR CHANGE ORDERS
Given the increasing technical and management complexities of building development projects, it has become
clear that delivering consistent expertise in a manner that is transparent and measurable is a major challenge. The
JLL Real Value Method brings an updated value proposition to the change order management process which
reflects forward thinking and approaches that have become more common in product delivery in high-skilled,
knowledge-based industries including aerospace (at NASA), healthcare, and real estate project management.
These methods—especially those outlined by Atul Gawande, a Harvard Medical School surgeon and MacArthur
Foundation “genius prize” recipient, in his acclaimed text Checklist Manifesto—have been adapted to the best
practices, experience and knowledge of JLL to produce a guide for project managers on development projects with
high change order volume. The JLL method promises the following value proposition:
Offer demonstrable value (quantified value and/or tangible value)
Present audit-style review, explanations, and clarity that stand on their own
Understand source of change order and apply knowledge to minimize future changes
Calculate and confirm rates, hours, and material billings
Give client confidence in the change order review process and JLL interpretation of changes
Expedite change order review with use of checklists and automated calculation templates
STEP 1: VENDOR CONTRACT KNOWLEDGE
Before reviewing change orders for a vendor it is important to familiarize yourself with the key terms in the
contract documentation, particularly those terms that relate to changes, schedule, and scope. The traditional
review process involves simply becoming knowledgeable of the terms in this documentation. The problem with the
traditional method is that after review tens of change orders over several months, the recall of specific detailed
language often becomes hazy. Even frequent reference of the contract documentation leaves a high potential for
missing key language that could be useful in responding to change orders.
The JLL Real Value method, however, follows a check-list routine whereby the project managers prepare a
checklist of the most important contractual terms for a vendor typically involved in change order processing. This
check-list is categorized by terms relating to (1) changes, (2) schedule, and (3) scope. The likely contract documents
to source terms from include: the CM agreement, the 3A pages, Form 36 pages, specifications, and closing notes.
Noting the source and article number/letter of the term in the checklist is necessary. This checklist typically should
not be more than 3 pages total.
Once a project manager has put together a summary check-list of terms for a vendor, that sheet should be used to
review each change order. Any pertinent terms informing the decision on a change order should be cited in a sheet
attached to the final reviewed change order with Key References. Terms can quickly be copied and pasted from
the checklist to this final review sheet.
Jones Lang LaSalle | Real Value in a Changing World
2
BENEFITS
Less likelihood of project manager over-looking or forgetting relevant contract knowledge when reviewing a
change order.
The client has tangible documentation that demonstrates that project managers have in fact carefully
reviewed and considered specific contract terms.
Final change order decisions appear less arbitrary
It is much easier for project managers to negotiate change orders when they can immediately cite the contract
language that informed their decision-making process.
Figure 1: Example of COR review checklist
STEP 2: COMPLETE THE CHANGE ORDER REVIEW SHEET
Every change order should have a change order review sheet with audit-style findings, a short description and
explanation of the rationale behind the decision. The Change Order Review Sheet (1 page max) should have the
following sections:
Change Order proposed cost vs. JLL recommended cost after review
Notes:
Jones Lang LaSalle | Real Value in a Changing World
3
o A one-sentence opinion on JLL recommended value for the change order;
o A one-sentence description of the change order request;
o 2-4 sentence description of the rationale behind the decision-making process, citing the guiding
contractual sources or highlighting any discrepancies.
o A one-sentence note on whether the rates and calculations are correct (and citing any errors if they
exist).
Key References—Copy and pasted abridged terms from the contract terms checklist OR the actual contract
documents if the guiding contract source was atypical and not listed in the checklist.
Sign-off—signature of project manager approving the change order review
Figure 2: Example of Change Order Review Sheet
Jones Lang LaSalle | Real Value in a Changing World
4
STEP 3: CREATE AN AUTOMATED RATES AND CALCULATION SPREADSHEET FOR A VENDOR
To further expedite the review process and reduce potential calculation errors, prepare a spreadsheet with
correct rates which can be used to quickly check calculations for change orders. Attach this document to the
Change Order Review Sheet to back up findings. Additionally, daily construction reports or other project
documents used to review the number of labor hours and the change proposal request should be attached as
back-up documentation to the change proposal.
Figure 3: Change Proposal Calculation Template
In the end, the Change Order Review Sheet, the Calculation Template, and other supporting documentation are
attached to the change order document as tangible back-up documentation and support for the decision.

More Related Content

DOCX
CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS
DOCX
Change control and variations
PPTX
1539781398299 tech writing
DOCX
Project cost control management
PDF
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
PDF
Project controls outlined
CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS
Change control and variations
1539781398299 tech writing
Project cost control management
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project controls outlined

What's hot (18)

PPSX
Changes in construction
PDF
9. project procurement management
PPTX
Training _ZK _Rev3_Final
PDF
Control procurement
PDF
Tiffany
PDF
Cost Control Process for Construction
PDF
Project Management Definitions
PDF
Project Controls Processes
PPTX
VERTEX Construction Claim Visuals - AACE Northeast Total Cost Management Sym...
PDF
Project Cost & Schedule Integration Lessons Learnt
PPTX
Quality unit 2012
PPSX
Project Control System
PPTX
Operations & engineering presentation to sales meeting
PPT
CSCM Chapter 9 sl as cscm
PDF
BioPharma Projects: Essentials in Project Controls
DOC
Project change request template v2.0
DOCX
Project Management 2nd assignment
Changes in construction
9. project procurement management
Training _ZK _Rev3_Final
Control procurement
Tiffany
Cost Control Process for Construction
Project Management Definitions
Project Controls Processes
VERTEX Construction Claim Visuals - AACE Northeast Total Cost Management Sym...
Project Cost & Schedule Integration Lessons Learnt
Quality unit 2012
Project Control System
Operations & engineering presentation to sales meeting
CSCM Chapter 9 sl as cscm
BioPharma Projects: Essentials in Project Controls
Project change request template v2.0
Project Management 2nd assignment
Ad

Similar to JLL Change Order process (20)

DOCX
6 I need the overall earned value analysis.  (That is, overall i.docx
PPTX
Cost unit 2012 part 2
PDF
Pm600 1103 a-02-schwappach-loren-p4-t3
PDF
Project Change Management-Pankaj K Sinha
PDF
Engineering change management webinar april 2013
DOCX
Change control and variations
PPT
Large Capital Projects CAI NJ 2011
PPT
The Bid Proccess
PPT
TMC PowerPoint for CAI NJ 2011 revised 10-31
PPT
Ensuring a Successful Bid Process
PDF
HOW TO ESTABLISH AN EFFECTIVE CHANGE MANAGEMENT
PPT
Project Management Change Management.ppt
PPTX
Effective Change Management
DOC
Change Management Plan
PPT
Projects Better Faster Cheaper
PPT
BRVillari,AmecL11.ppt
PPTX
Change Management - UC Berkeley Extension
DOCX
Change management plan_template
PPTX
Engineering Change Management - Overview and Best Practices
PPTX
Fire alarm ppt_presentation_to_suppliers_november_2015
6 I need the overall earned value analysis.  (That is, overall i.docx
Cost unit 2012 part 2
Pm600 1103 a-02-schwappach-loren-p4-t3
Project Change Management-Pankaj K Sinha
Engineering change management webinar april 2013
Change control and variations
Large Capital Projects CAI NJ 2011
The Bid Proccess
TMC PowerPoint for CAI NJ 2011 revised 10-31
Ensuring a Successful Bid Process
HOW TO ESTABLISH AN EFFECTIVE CHANGE MANAGEMENT
Project Management Change Management.ppt
Effective Change Management
Change Management Plan
Projects Better Faster Cheaper
BRVillari,AmecL11.ppt
Change Management - UC Berkeley Extension
Change management plan_template
Engineering Change Management - Overview and Best Practices
Fire alarm ppt_presentation_to_suppliers_november_2015
Ad

JLL Change Order process

  • 1. Jones Lang LaSalle | Real Value in a Changing World 1 JLL REAL VALUE METHOD: CHANGE ORDERS JLL’S VALUE PROPOSITION FOR CHANGE ORDERS Given the increasing technical and management complexities of building development projects, it has become clear that delivering consistent expertise in a manner that is transparent and measurable is a major challenge. The JLL Real Value Method brings an updated value proposition to the change order management process which reflects forward thinking and approaches that have become more common in product delivery in high-skilled, knowledge-based industries including aerospace (at NASA), healthcare, and real estate project management. These methods—especially those outlined by Atul Gawande, a Harvard Medical School surgeon and MacArthur Foundation “genius prize” recipient, in his acclaimed text Checklist Manifesto—have been adapted to the best practices, experience and knowledge of JLL to produce a guide for project managers on development projects with high change order volume. The JLL method promises the following value proposition: Offer demonstrable value (quantified value and/or tangible value) Present audit-style review, explanations, and clarity that stand on their own Understand source of change order and apply knowledge to minimize future changes Calculate and confirm rates, hours, and material billings Give client confidence in the change order review process and JLL interpretation of changes Expedite change order review with use of checklists and automated calculation templates STEP 1: VENDOR CONTRACT KNOWLEDGE Before reviewing change orders for a vendor it is important to familiarize yourself with the key terms in the contract documentation, particularly those terms that relate to changes, schedule, and scope. The traditional review process involves simply becoming knowledgeable of the terms in this documentation. The problem with the traditional method is that after review tens of change orders over several months, the recall of specific detailed language often becomes hazy. Even frequent reference of the contract documentation leaves a high potential for missing key language that could be useful in responding to change orders. The JLL Real Value method, however, follows a check-list routine whereby the project managers prepare a checklist of the most important contractual terms for a vendor typically involved in change order processing. This check-list is categorized by terms relating to (1) changes, (2) schedule, and (3) scope. The likely contract documents to source terms from include: the CM agreement, the 3A pages, Form 36 pages, specifications, and closing notes. Noting the source and article number/letter of the term in the checklist is necessary. This checklist typically should not be more than 3 pages total. Once a project manager has put together a summary check-list of terms for a vendor, that sheet should be used to review each change order. Any pertinent terms informing the decision on a change order should be cited in a sheet attached to the final reviewed change order with Key References. Terms can quickly be copied and pasted from the checklist to this final review sheet.
  • 2. Jones Lang LaSalle | Real Value in a Changing World 2 BENEFITS Less likelihood of project manager over-looking or forgetting relevant contract knowledge when reviewing a change order. The client has tangible documentation that demonstrates that project managers have in fact carefully reviewed and considered specific contract terms. Final change order decisions appear less arbitrary It is much easier for project managers to negotiate change orders when they can immediately cite the contract language that informed their decision-making process. Figure 1: Example of COR review checklist STEP 2: COMPLETE THE CHANGE ORDER REVIEW SHEET Every change order should have a change order review sheet with audit-style findings, a short description and explanation of the rationale behind the decision. The Change Order Review Sheet (1 page max) should have the following sections: Change Order proposed cost vs. JLL recommended cost after review Notes:
  • 3. Jones Lang LaSalle | Real Value in a Changing World 3 o A one-sentence opinion on JLL recommended value for the change order; o A one-sentence description of the change order request; o 2-4 sentence description of the rationale behind the decision-making process, citing the guiding contractual sources or highlighting any discrepancies. o A one-sentence note on whether the rates and calculations are correct (and citing any errors if they exist). Key References—Copy and pasted abridged terms from the contract terms checklist OR the actual contract documents if the guiding contract source was atypical and not listed in the checklist. Sign-off—signature of project manager approving the change order review Figure 2: Example of Change Order Review Sheet
  • 4. Jones Lang LaSalle | Real Value in a Changing World 4 STEP 3: CREATE AN AUTOMATED RATES AND CALCULATION SPREADSHEET FOR A VENDOR To further expedite the review process and reduce potential calculation errors, prepare a spreadsheet with correct rates which can be used to quickly check calculations for change orders. Attach this document to the Change Order Review Sheet to back up findings. Additionally, daily construction reports or other project documents used to review the number of labor hours and the change proposal request should be attached as back-up documentation to the change proposal. Figure 3: Change Proposal Calculation Template In the end, the Change Order Review Sheet, the Calculation Template, and other supporting documentation are attached to the change order document as tangible back-up documentation and support for the decision.