Diploma Project Management
       Captain Cook College
                Sharon Boyle
   Presentation –An overview of Quality
    Management
   Check everyone has completed Cost
    ◦ SB CMP started last week & finish tomorrow
    ◦ Today & Friday – completed cost Friday 23 August
   Come and SEE me individually if there is a
    problem
   http://www.youtube.com/watch?v=3HcTnZn_
    jOw&feature=endscreen
Quality unit 2012
   1. Determine quality requirements
   2. Implement quality assurance processes
   3. Implement project quality improvements
   Quality objectives
    ◦ negotiated trade-offs between cost, schedule and
      performance
    ◦ requirements from a higher project authority
    ◦ requirements from the client and other
      stakeholders
    ◦ those quality aspects which may impact on
      customer satisfaction
   Quality management plan includes
    ◦   authorisations
    ◦   responsibilities for quality control
    ◦   continuous improvement
    ◦   established processes
    ◦   quality assurance
   benchmarking
   brainstorming
   charting processes
   control charts
   defining control
   flowcharts
   group work activities
   processes that limit and/or indicate variation
   undertaking benefit/cost analysis
    ◦ & lots more which are project specific
   http://www.youtube.com/watch?v=oq1Zi_V4
    KyE
   On-going through out project
   Causes identified recommend actions
   Quality control
    ◦ monitoring conformance with specifications
    ◦ monitoring of regular inspections by internal or
      external agents
    ◦ recommending ways to eliminate causes of
      unsatisfactory performance of products or
      processes
   Review processes
    ◦ implement agreed changes
    ◦ throughout the project life cycle
    ◦ ensure continuous quality improvement
   Review project outcomes against
    performance criteria
   Assess the effectiveness of quality
    management processes and procedures
   Identify and document lessons learned
   Recommend improvements
   http://www.youtube.com/watch?v=u-5C72-
    bgyU
   http://www.youtube.com/watch?v=u-5C72-
    bgyU
   Let’s talk about the balance of the day.
   Options – everyone needs to be doing either:
   Reading the notes re Quality Management in
    preparation for assessment items
   OR
   Completing Cost
   To complement the fishbone diagram, you
    can use Pareto diagrams.
   Fishbone or Ishikawa shows relationships –
    root &
   Pareto diagram shows the size of the various
    issues/problems & where to focus effort for
    greatest reward.
   A Pareto diagram is a simple bar chart that ranks
    related measures in decreasing order of
    occurrence
   Vilfredo Pareto
    ◦ Italian economist and sociologist
    ◦ study in Europe in the early 1900s on wealth and
      poverty.
   His findings included
    ◦ wealth was concentrated in the hands of the few and
    ◦ poverty in the hands of the many.
    ◦ significant few things will generally make up 80% of the
      whole,
    ◦ the trivial many will make up about 20%.
Quality unit 2012
Quality unit 2012
   Thursday 30 August –
    ◦ Intro & reading notes
    ◦ Tidying up the last of Cost
    ◦ Starting assessment items 1 & 2.
   Friday 31 August
    ◦ Complete
      Assessment Item 1.
      Assessment Item 2.
   Written/Oral – do the replacement questions
   New Project - do NOT do existing project in LMS
   Next week – 6 & 7 September
    ◦ the impact of variations on Quality
    ◦ New Project assessment
Quality unit 2012
   Why important?
   What can go wrong?
   Relationship to other aspects of project
    management?
   The establishes an orderly and effective
    procedure for
    ◦   tracking the submission,
    ◦   coordination, review, evaluation,
    ◦   categorization, and
    ◦   approval for release of all changes to the project’s
        baselines.
Element                                           Description
   Date       The date the CR was created
   CR#        Assigned by the Change Manager
   Title      A brief description of the change request
Description   Description of the desired change, the impact, or benefits of a change should also be
              described

Submitter     Name of the person completing the CR Form and who can answer questions regarding
              the suggested change

  Phone       Phone number of the submitter
  E-Mail      Email of the submitter
 Product      The product that the suggested change is for
 Version      The product version that the suggested change is for
  Priority    A code that provides a recommended categorization of the urgency of the requested
              change (High, Medium, Low)
Priority                                            Description

  High       <Insert the definition the project assigns to a high priority CR>

Medium       <Insert the definition the project assigns to a medium priority CR>

  Low        <Insert the definition the project assigns to a low priority CR>

<priority>   <Insert the definition the project assigns to this level of priority CR>
Change requests are evaluated and assigned one or
more of the following change types:
        Type                                        Description

       Scope        Change affecting scope

        Time        Change affecting time

      Duration      Change affecting duration

        Cost        Change affecting cost

     Resources      Change affecting resources

     Deliverables   Change affecting deliverables

       Product      Change affecting product

     Processes      Change affecting process

       Quality      Change affecting quality
   The impacts on the project and the
    appropriate actions.
   The appropriate documentation which has
    been completed for the example variation.
   A summary of the variation approval and
    documentation process.
   Master of Ceremonies suddenly taken ill two
    weeks before event and will not be available
    for the event. A strong suggestion from
    Councillors to get a professional.
   The Council access officer wants to know how
    the event is to cater meet council’s Universal
    access policy.
   List the impacts on the project and the
    appropriate actions.
   The ground appears to be unstable and
    potentially unsuitable for construction.
   List the impacts on the project and the
    appropriate actions.
   48 hours from arrival of new robot
    welder, notice arrives that there will be a
    delay of 2 weeks.
   List the impacts on the project and the
    appropriate actions.

More Related Content

DOCX
2.08 quality management 1
PPTX
Project management basics variations and change control
PPSX
Changes in construction
DOCX
Change control and variations
DOC
PPTX
Hidden Horrors of Shoddy ( Poor Quality) Construction
PPTX
P iron triangle 2
DOC
Project client signoff template v2.0
2.08 quality management 1
Project management basics variations and change control
Changes in construction
Change control and variations
Hidden Horrors of Shoddy ( Poor Quality) Construction
P iron triangle 2
Project client signoff template v2.0

What's hot (20)

PPSX
Changes in construction projects
PDF
Cost Control Process for Construction
PDF
(Student assignment) riordan manufacturing process improvement final
PDF
ShekharResume
PDF
Construction quality control site inspection training (2) pages-deleted
PDF
Project Performance Analysis And Delivery Methods - Quantitative Analysis
PPT
06 pert cpm
PDF
Pmp cost chapter 7
PDF
Quality control IN CONSTRUCTION
PPT
Quality control in construction
DOC
Project closure template v3.0
PPTX
Triple constraint
DOCX
Bsbpmg505 manage project quality
PPT
Subcontractor Scheduling
PDF
Nabeeltd_CV_QCs
PPTX
Ch4 project management process
PPSX
Nqa 1 Is It Really Expensive
PPTX
NQA-1-2012 Changes That Support DOE Nuclear Facility Safety
PDF
Pmp quality chapter 8
PPTX
Construction phases
Changes in construction projects
Cost Control Process for Construction
(Student assignment) riordan manufacturing process improvement final
ShekharResume
Construction quality control site inspection training (2) pages-deleted
Project Performance Analysis And Delivery Methods - Quantitative Analysis
06 pert cpm
Pmp cost chapter 7
Quality control IN CONSTRUCTION
Quality control in construction
Project closure template v3.0
Triple constraint
Bsbpmg505 manage project quality
Subcontractor Scheduling
Nabeeltd_CV_QCs
Ch4 project management process
Nqa 1 Is It Really Expensive
NQA-1-2012 Changes That Support DOE Nuclear Facility Safety
Pmp quality chapter 8
Construction phases
Ad

Viewers also liked (9)

PPTX
Ppt
PPTX
Catch up clarification dip pm 27 sept
PPTX
Time unit 2012 nov 12 part 1
PPTX
Risk management
PPTX
Procurement part 1.
PPTX
Cost unit 2012 part 2
PPT
Bsbmkg502 b session ib
PPTX
Quality unit 2012 part 1. day 1 - 31 jan
PPT
Templates without questions
Ppt
Catch up clarification dip pm 27 sept
Time unit 2012 nov 12 part 1
Risk management
Procurement part 1.
Cost unit 2012 part 2
Bsbmkg502 b session ib
Quality unit 2012 part 1. day 1 - 31 jan
Templates without questions
Ad

Similar to Quality unit 2012 (20)

PPTX
Quality unit 2012 2
PPT
How the change control process affects project quality
PPTX
Change management
PPTX
Project management assignment slides
PPTX
Scope part 1 day 1
PPSX
Information Technology Project Management
PPTX
The Project Charter Ensuring Quality
PDF
Oleksandr Osypenko: Управління обсягом (Scope) (UA)
DOC
Template quality management-plan2
 
DOC
Project change request template v2.0
PDF
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
DOC
Change Management Plan
ODP
Guidelines for Managing Projects
PPT
Final Class Presentation on Project Audit and Closure.ppt
PDF
Do it, sf state project lifecycle management (plm) v1.19 091012
PPTX
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
PPTX
CAPM Exam preparation - series 1
PPT
ICB Competence, Project Standards
PPTX
Is your project not going well this will help you get it back on track
PDF
Module 12 Monitoring and Control I
Quality unit 2012 2
How the change control process affects project quality
Change management
Project management assignment slides
Scope part 1 day 1
Information Technology Project Management
The Project Charter Ensuring Quality
Oleksandr Osypenko: Управління обсягом (Scope) (UA)
Template quality management-plan2
 
Project change request template v2.0
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
Change Management Plan
Guidelines for Managing Projects
Final Class Presentation on Project Audit and Closure.ppt
Do it, sf state project lifecycle management (plm) v1.19 091012
SYSTEM LIFE CYCLE_DurgaPrasad_TA Assignemnt 02
CAPM Exam preparation - series 1
ICB Competence, Project Standards
Is your project not going well this will help you get it back on track
Module 12 Monitoring and Control I

More from Skript (20)

PPTX
Quality unit 2012 part 1. day 1 - 31 jan
PPTX
Cost unit 2013 part 2. 24 jan
PPTX
Cost unit 2013 part 1. 18 jan
PPTX
Cost unit 2013 part 1. 17 jan
PPTX
Hr unit 2012 part 1
PPTX
Time unit 2012 nov part 2
PPTX
Hr unit 2
PPTX
Time unit 2012 nov part 2.
PPTX
Quality unit 2012
PPT
Table of contents_1_without_questions
PPT
Table of contents_3_without_questions
PPT
Table of contents_2_without_questions
PPT
Mail merge 2_without_questions
PPT
Mail merge 1_without_questions
PPT
Headers footers without_questions
PPT
Headers footers document_selection_without_questions
PPT
Bullets numbering lists_without_questions
PPT
Backgrounds borders effects_without_questions
PPT
Bsbled401 a develop_teams_and_individuals_sah 2012
PPTX
Scope part 2 day 1
Quality unit 2012 part 1. day 1 - 31 jan
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 1. 18 jan
Cost unit 2013 part 1. 17 jan
Hr unit 2012 part 1
Time unit 2012 nov part 2
Hr unit 2
Time unit 2012 nov part 2.
Quality unit 2012
Table of contents_1_without_questions
Table of contents_3_without_questions
Table of contents_2_without_questions
Mail merge 2_without_questions
Mail merge 1_without_questions
Headers footers without_questions
Headers footers document_selection_without_questions
Bullets numbering lists_without_questions
Backgrounds borders effects_without_questions
Bsbled401 a develop_teams_and_individuals_sah 2012
Scope part 2 day 1

Recently uploaded (20)

PDF
Nidhal Samdaie CV - International Business Consultant
PDF
Roadmap Map-digital Banking feature MB,IB,AB
DOCX
Business Management - unit 1 and 2
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
How to Get Funding for Your Trucking Business
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
IFRS Notes in your pocket for study all the time
PDF
MSPs in 10 Words - Created by US MSP Network
PPTX
5 Stages of group development guide.pptx
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Nidhal Samdaie CV - International Business Consultant
Roadmap Map-digital Banking feature MB,IB,AB
Business Management - unit 1 and 2
Euro SEO Services 1st 3 General Updates.docx
How to Get Funding for Your Trucking Business
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
IFRS Notes in your pocket for study all the time
MSPs in 10 Words - Created by US MSP Network
5 Stages of group development guide.pptx
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
Power and position in leadershipDOC-20250808-WA0011..pdf
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
BsN 7th Sem Course GridNNNNNNNN CCN.pdf

Quality unit 2012

  • 1. Diploma Project Management Captain Cook College Sharon Boyle
  • 2. Presentation –An overview of Quality Management  Check everyone has completed Cost ◦ SB CMP started last week & finish tomorrow ◦ Today & Friday – completed cost Friday 23 August  Come and SEE me individually if there is a problem
  • 3. http://www.youtube.com/watch?v=3HcTnZn_ jOw&feature=endscreen
  • 5. 1. Determine quality requirements  2. Implement quality assurance processes  3. Implement project quality improvements
  • 6. Quality objectives ◦ negotiated trade-offs between cost, schedule and performance ◦ requirements from a higher project authority ◦ requirements from the client and other stakeholders ◦ those quality aspects which may impact on customer satisfaction
  • 7. Quality management plan includes ◦ authorisations ◦ responsibilities for quality control ◦ continuous improvement ◦ established processes ◦ quality assurance
  • 8. benchmarking  brainstorming  charting processes  control charts  defining control  flowcharts  group work activities  processes that limit and/or indicate variation  undertaking benefit/cost analysis ◦ & lots more which are project specific
  • 9. http://www.youtube.com/watch?v=oq1Zi_V4 KyE
  • 10. On-going through out project  Causes identified recommend actions  Quality control ◦ monitoring conformance with specifications ◦ monitoring of regular inspections by internal or external agents ◦ recommending ways to eliminate causes of unsatisfactory performance of products or processes
  • 11. Review processes ◦ implement agreed changes ◦ throughout the project life cycle ◦ ensure continuous quality improvement  Review project outcomes against performance criteria  Assess the effectiveness of quality management processes and procedures  Identify and document lessons learned  Recommend improvements
  • 12. http://www.youtube.com/watch?v=u-5C72- bgyU
  • 13. http://www.youtube.com/watch?v=u-5C72- bgyU
  • 14. Let’s talk about the balance of the day.  Options – everyone needs to be doing either:  Reading the notes re Quality Management in preparation for assessment items  OR  Completing Cost
  • 15. To complement the fishbone diagram, you can use Pareto diagrams.  Fishbone or Ishikawa shows relationships – root &  Pareto diagram shows the size of the various issues/problems & where to focus effort for greatest reward.
  • 16. A Pareto diagram is a simple bar chart that ranks related measures in decreasing order of occurrence  Vilfredo Pareto ◦ Italian economist and sociologist ◦ study in Europe in the early 1900s on wealth and poverty.  His findings included ◦ wealth was concentrated in the hands of the few and ◦ poverty in the hands of the many. ◦ significant few things will generally make up 80% of the whole, ◦ the trivial many will make up about 20%.
  • 19. Thursday 30 August – ◦ Intro & reading notes ◦ Tidying up the last of Cost ◦ Starting assessment items 1 & 2.  Friday 31 August ◦ Complete  Assessment Item 1.  Assessment Item 2.  Written/Oral – do the replacement questions  New Project - do NOT do existing project in LMS  Next week – 6 & 7 September ◦ the impact of variations on Quality ◦ New Project assessment
  • 21. Why important?  What can go wrong?  Relationship to other aspects of project management?
  • 22. The establishes an orderly and effective procedure for ◦ tracking the submission, ◦ coordination, review, evaluation, ◦ categorization, and ◦ approval for release of all changes to the project’s baselines.
  • 23. Element Description Date The date the CR was created CR# Assigned by the Change Manager Title A brief description of the change request Description Description of the desired change, the impact, or benefits of a change should also be described Submitter Name of the person completing the CR Form and who can answer questions regarding the suggested change Phone Phone number of the submitter E-Mail Email of the submitter Product The product that the suggested change is for Version The product version that the suggested change is for Priority A code that provides a recommended categorization of the urgency of the requested change (High, Medium, Low)
  • 24. Priority Description High <Insert the definition the project assigns to a high priority CR> Medium <Insert the definition the project assigns to a medium priority CR> Low <Insert the definition the project assigns to a low priority CR> <priority> <Insert the definition the project assigns to this level of priority CR>
  • 25. Change requests are evaluated and assigned one or more of the following change types: Type Description Scope Change affecting scope Time Change affecting time Duration Change affecting duration Cost Change affecting cost Resources Change affecting resources Deliverables Change affecting deliverables Product Change affecting product Processes Change affecting process Quality Change affecting quality
  • 26. The impacts on the project and the appropriate actions.  The appropriate documentation which has been completed for the example variation.  A summary of the variation approval and documentation process.
  • 27. Master of Ceremonies suddenly taken ill two weeks before event and will not be available for the event. A strong suggestion from Councillors to get a professional.  The Council access officer wants to know how the event is to cater meet council’s Universal access policy.  List the impacts on the project and the appropriate actions.
  • 28. The ground appears to be unstable and potentially unsuitable for construction.  List the impacts on the project and the appropriate actions.
  • 29. 48 hours from arrival of new robot welder, notice arrives that there will be a delay of 2 weeks.  List the impacts on the project and the appropriate actions.

Editor's Notes

  • #10: Its international It’s a standard for all projectsBut there is a considerable paper trail &amp; system embedded into the organisation.For this to be truly successful the company/organisation has to be committed to on-going implementation. Usually something smaller and more tailored is required for a project because of its limited time and resources. The organization&apos;s company quality management may provide sufficient guidance for the project – the first place to start.