The document discusses lessons learned from over 500 modular data center implementations around the world. Key lessons include: (1) Good modular design allows deferring up to 50% of electrical and mechanical capacity costs until needed, saving millions compared to retrofitting; (2) Plans should account for unpredictability over 10-30 years and support 3-5x power density growth; (3) No single cooling approach is optimal for all sizes and densities, requiring tailored solutions.