SlideShare a Scribd company logo
Line Layout and Workstation Identification        Presented  byAayushKad (91061)AnkitKasera (91069)AnujMangal(91073)Rahul Gupta(91099)RuchiVarma(91103)
MRPAssumes infinite capacity in the manufacturing process/department.Orders are periodically issued as per master schedule.Uses Bill of Materials to get dependency in demand.
Imbalance in LineAdditional orders often requested.Release orders in advance.Causes shortages leading to expediting activities.Late orders or overtime.Increased Inventory as buffer.
Lean ManufacturingLittle or no type of muda (waste)Differentiate between Value adding and Non value adding steps
Line Layout and Workstation Identification
Line balancing with Lean ManufacturingUtilize only the resources necessary to meet customer demand.
Pull based production system.
All resources located at one place.
Eliminate the need for batching or grouping the resources.
Product manufactured one unit at a time.Lean ManufacturingSequence of events (SOE) labor and machine times divided into parts equal to a Takt time.Reduces inventory and cycle time.
Steps to implementCalculate Resource RequirementsDefining Resource AttributesPhysical layout of resourcesMaintaining workstation balance
1. Calculating Resource Requirements# Resources = Standard Time SOE/TaktNumeratorSum of all labor and machine categories of work individually.Includes non value adding time like dynamic setups.Denominator    Takt=   Work minutes per shift * No. of shifts                          Throughput volume per day
Sequence of Events (Labor)∑ All Times = 8.05
Multi Product Line    When one process used for producing more than one product we use a weighted standard time as follows:Standard Time Weighted (STW) = ∑Vc*SOE Standard Time/∑Vc
STW=3585/130 = 27.6 minutesTakt Time= 7 hours x 60 minutes x 1 shift  = 420  =3.23 minutes                          Total Process F Volume            130Resources = 27.6/3.23=9 approx
2.  Defining ResourcesDefine physical attributes of individual resources.SOE labor time results in number of people required.The number of resources calculated for future must be in proportion to current resources and volume.
2.  Defining ResourcesPhysical location from which work to be performed must also be defined including space for supporting equipment.Thus, number of physical workstations also determined.For each workstation, its attributes and dimensions on the shop floor must be defined.Reduce excess workstation space.
Balancing a Machine to Takt Time Build additional inventory equal to:Cycle Time of Machine = Units of Inventory        Process Takt TimeEg: A machine process requires 60 minutes to travel the conveyer length in a tunnel and Takt time is 3.23 minutes.      Inventory = 60/3.23=19 units.     Additional 19 hooks will be added and spaced such that each unit takes 60 minutes on conveyer and exit tunnel every 3.23 minutes.
3. Physical Layout of ResourcesReduce Move and Wait time.Use paper simulation as it involves:Team ParticipationLow CostWork upstream.Leave space for material movement.Keep environment and safety needs in mind.
4. Assigning Tasks for Each WorkstationAfter the resources have been determined and processes balanced, define the exact work quality inspection at each workstation.Use SOE to document the sequence of tasks.Summation of time of work tasks should be equal to Takt time.
In-Process Kanban Signaling MethodologyIPKs are used to remove the imbalancesIPK provides a temporary “parking space”IPK signals the next unitNo stack up“Pull” system is evidentIt controls speed of the lineFIFO priority sequencing of customer ordersSales order configuration document attached to configure-to-order custom products
Discipline For Workstation BalanceNest BuildingStash CacheI’m SpecialThe Better IdeaSpeed Trumps Takt- 1 unit at a timeManagement Indifference to Warning SignsSilence is AcceptanceLean Manufacturing – A Way Of Life
Balance By Workstation

More Related Content

PPTX
Line balancing
PDF
Kanban siom
PPT
Assembly Line Balancing
PPT
Line balancing ppt By Wakil Kumar
PPT
Ch5 process+analysis
PPTX
Equipment Availability Analysis
PPTX
Equipment Availability Analysis
Line balancing
Kanban siom
Assembly Line Balancing
Line balancing ppt By Wakil Kumar
Ch5 process+analysis
Equipment Availability Analysis
Equipment Availability Analysis

Viewers also liked (8)

PDF
O ambiente e o layout
PDF
Doc.Igor_9
PDF
Estudo layout empresa
DOCX
Lean Manufacturing Exam Questions Mar 2011
PDF
13 - Tipos de Processos x Arranjo Físico
PDF
Case Study - Lean Implementation (Manufacturing)
PDF
Lean Manufacturing Implementation - Case Study
PPT
Lean presentation ppt
O ambiente e o layout
Doc.Igor_9
Estudo layout empresa
Lean Manufacturing Exam Questions Mar 2011
13 - Tipos de Processos x Arranjo Físico
Case Study - Lean Implementation (Manufacturing)
Lean Manufacturing Implementation - Case Study
Lean presentation ppt
Ad

Similar to Line Layout and Workstation Identification (20)

PPTX
Fundamentals of Lean
PDF
5 Steps to implementing Lean
PPT
PPT
Generic Lean Overview For Future Employer Of Alan S Desrocher
PDF
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
PDF
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PPTX
2.IE Presentation.pptx
PDF
synopsis
PPTX
Value Stream Mapping ( Lean manufacturing )
PDF
Line Balancing and facility optimization of Machine Shop with Work Study and ...
PDF
LEAN STANDARDIZED WORK TOOL
PPTX
Lean Introduction.pptx
PDF
Volume 2-issue-6-2177-2185
PDF
Volume 2-issue-6-2177-2185
PDF
Schneider Case Study Challenge
PPTX
Lean-Dennis-summary-notes.ppt LEAN MANUFACTURINGx
PPTX
Lean in fishing net
PPT
MANT 265 S01.ppt
PPT
Process Selection and Facility layout.ppt
PDF
Implementation of Lean Manufacturing Principles in Foundries
Fundamentals of Lean
5 Steps to implementing Lean
Generic Lean Overview For Future Employer Of Alan S Desrocher
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
2.IE Presentation.pptx
synopsis
Value Stream Mapping ( Lean manufacturing )
Line Balancing and facility optimization of Machine Shop with Work Study and ...
LEAN STANDARDIZED WORK TOOL
Lean Introduction.pptx
Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185
Schneider Case Study Challenge
Lean-Dennis-summary-notes.ppt LEAN MANUFACTURINGx
Lean in fishing net
MANT 265 S01.ppt
Process Selection and Facility layout.ppt
Implementation of Lean Manufacturing Principles in Foundries
Ad

More from Ashutosh Kumar Jha (20)

PPTX
Virgin mobile
PDF
Gillette report 2
PPTX
Gillette final
PDF
Nokia Supply Chain Management
PDF
Marlboro Brand Equity
PDF
Taj trapezium
PDF
Environmental issue pertaining to a business sudha gramodyog
PPTX
Taj Trapezium
PDF
Mandatory investment in csr
PDF
IBM B2B segments
PPTX
Kanban strategies
PPTX
Lean manufacturing
PPTX
Operations management - Kortek electronics (india) pvt
DOCX
Tata JLR acquisition case study
PPTX
Eureka forbes
DOCX
Nokia distribution network delhi ncr
PPTX
Group7 nokia
DOCX
TQM - SPC Tools Report
PPTX
TQM - SPC Tools
PPTX
Corporate Financel
Virgin mobile
Gillette report 2
Gillette final
Nokia Supply Chain Management
Marlboro Brand Equity
Taj trapezium
Environmental issue pertaining to a business sudha gramodyog
Taj Trapezium
Mandatory investment in csr
IBM B2B segments
Kanban strategies
Lean manufacturing
Operations management - Kortek electronics (india) pvt
Tata JLR acquisition case study
Eureka forbes
Nokia distribution network delhi ncr
Group7 nokia
TQM - SPC Tools Report
TQM - SPC Tools
Corporate Financel

Line Layout and Workstation Identification

  • 1. Line Layout and Workstation Identification Presented byAayushKad (91061)AnkitKasera (91069)AnujMangal(91073)Rahul Gupta(91099)RuchiVarma(91103)
  • 2. MRPAssumes infinite capacity in the manufacturing process/department.Orders are periodically issued as per master schedule.Uses Bill of Materials to get dependency in demand.
  • 3. Imbalance in LineAdditional orders often requested.Release orders in advance.Causes shortages leading to expediting activities.Late orders or overtime.Increased Inventory as buffer.
  • 4. Lean ManufacturingLittle or no type of muda (waste)Differentiate between Value adding and Non value adding steps
  • 6. Line balancing with Lean ManufacturingUtilize only the resources necessary to meet customer demand.
  • 8. All resources located at one place.
  • 9. Eliminate the need for batching or grouping the resources.
  • 10. Product manufactured one unit at a time.Lean ManufacturingSequence of events (SOE) labor and machine times divided into parts equal to a Takt time.Reduces inventory and cycle time.
  • 11. Steps to implementCalculate Resource RequirementsDefining Resource AttributesPhysical layout of resourcesMaintaining workstation balance
  • 12. 1. Calculating Resource Requirements# Resources = Standard Time SOE/TaktNumeratorSum of all labor and machine categories of work individually.Includes non value adding time like dynamic setups.Denominator Takt= Work minutes per shift * No. of shifts Throughput volume per day
  • 13. Sequence of Events (Labor)∑ All Times = 8.05
  • 14. Multi Product Line When one process used for producing more than one product we use a weighted standard time as follows:Standard Time Weighted (STW) = ∑Vc*SOE Standard Time/∑Vc
  • 15. STW=3585/130 = 27.6 minutesTakt Time= 7 hours x 60 minutes x 1 shift = 420 =3.23 minutes Total Process F Volume 130Resources = 27.6/3.23=9 approx
  • 16. 2. Defining ResourcesDefine physical attributes of individual resources.SOE labor time results in number of people required.The number of resources calculated for future must be in proportion to current resources and volume.
  • 17. 2. Defining ResourcesPhysical location from which work to be performed must also be defined including space for supporting equipment.Thus, number of physical workstations also determined.For each workstation, its attributes and dimensions on the shop floor must be defined.Reduce excess workstation space.
  • 18. Balancing a Machine to Takt Time Build additional inventory equal to:Cycle Time of Machine = Units of Inventory Process Takt TimeEg: A machine process requires 60 minutes to travel the conveyer length in a tunnel and Takt time is 3.23 minutes. Inventory = 60/3.23=19 units. Additional 19 hooks will be added and spaced such that each unit takes 60 minutes on conveyer and exit tunnel every 3.23 minutes.
  • 19. 3. Physical Layout of ResourcesReduce Move and Wait time.Use paper simulation as it involves:Team ParticipationLow CostWork upstream.Leave space for material movement.Keep environment and safety needs in mind.
  • 20. 4. Assigning Tasks for Each WorkstationAfter the resources have been determined and processes balanced, define the exact work quality inspection at each workstation.Use SOE to document the sequence of tasks.Summation of time of work tasks should be equal to Takt time.
  • 21. In-Process Kanban Signaling MethodologyIPKs are used to remove the imbalancesIPK provides a temporary “parking space”IPK signals the next unitNo stack up“Pull” system is evidentIt controls speed of the lineFIFO priority sequencing of customer ordersSales order configuration document attached to configure-to-order custom products
  • 22. Discipline For Workstation BalanceNest BuildingStash CacheI’m SpecialThe Better IdeaSpeed Trumps Takt- 1 unit at a timeManagement Indifference to Warning SignsSilence is AcceptanceLean Manufacturing – A Way Of Life
  • 24. Techniques to Overcome ImbalancesLook for Work That Can Be EliminatedRelocate Work From Workstation to WorkstationAdd IPKs to the Imbalanced WorkstationsAdd ResourcesSequence Properly
  • 25. Designing 5 S Into The Line DesignSifting (Seiri) Removing Unnecessary ItemsSorting (Seiton) Identify and arrange: a place for everythingSweeping (Seiso) Maintain order, sweep and cleanStandardize (Seiketsu) Practice management disciplineSustain (Shitsuke) Reinforce and demonstrate leadership