Process Analysis
2

OBJECTIVES

• Process Analysis
• Process Flowcharting
• Types of Processes
• Process Performance Metrics
3

Process Analysis Terms


Process: Is any part of an organization that
takes inputs and transforms them into outputs



Cycle Time: Is the average successive time
between completions of successive units



Utilization: Is the ratio of the time that a
resource is actually activated relative to the
time that it is available for use
Process Flowcharting
Defined


Process flowcharting is the use of a diagram to
present the major elements of a process



The basic elements can include tasks or
operations, flows of materials or customers,
decision points, and storage areas or queues



It is an ideal methodology by which to begin
analyzing a process

4
5

PROCESS ANALYSIS
Standard Symbols used for Flowcharting
Symbol

Activity
Operation

Transportation
or Movement
Inspection
Delay/Temporary
Storage

Definition of Activity
Modification of an object

Change in location of an
Item
Examination of an Object
(Qlty/Qty parameters)
Retention of an Object in a
location awaiting next
activity
6

Decision Point
(Awaiting decision
on further Action)

Storage

Combined
Activity

Location awaiting
next activity

Items in stored
condition (no
unauthorized
removal)

Two activities
occur
simultaneously
•

PROCESS ANALYSIS – Key
Terms
What is a process?
A process is any part of an organization that takes Inputs and transforms
them into Outputs

•

Cycle time
(unit item)

•

•

the elapsed time between starting and completing a job
(Average time between completion of units)

Run time

is the time required to produce a batch of parts
(for the batch) (this is calculated by multiplying the time required to
produce each unit by the batch size)

Set-up time
(for the m/c)

is the time required to prepare a m/c to produce an item

7
•

Operation time

is the sum of set-up time and runtime for a batch
of parts that are run on a m/c

(for the Batch)

•

Thro’put time
( for the Unit)

the time that the unit spends actually being
worked plus the time spent waiting in

aQ

•

Thro’put Rate

•

Value Added time

(for the Batch)

(for the unit)

•

Thro’put Ratio

is the Output rate that the process is expected to
produce over a period of time
the time in which useful work is actually being
done on the unit
Process Velocity :
the ratio of the total thro’put time to the value added
time

8
9

•

Make-to-order

•

Make-to-stock

•

Hybrid

(Either Unit or
Batch)

(Either Unit or
Batch)

(Unit or Batch )

A process that is activated only in response to an
actual order

A process that produces standard products that are
stored in finished Goods Inventory : the product is
quickly delivered to the customer

Combines the feature of both make-to-order and
make-to-stock
(A generic product is made and customised in a final
process to meet actual orders)
Make-to-Order

customer
Customer Order
Product
Production
Make-to-Stock
Forecast orders

customer

Production

Customer Order
Product

Finished Goods
Inventory

Product
Assemble-to-Order
Forecast orders

customer

Production of
Subassemblies
Customer order

Product

Assembly
of the Order

Subassembly
Inventory
of Subassemblies
13



Efficiency



Productivity



Utilization



Little’s Law

Actual Output
Standard Output

Output
Input
Time activated
Time available

(definition as follows)

Thro’put time = Work-in-Proccess
Thro’put Rate
14

Example: Flowchart of
Student Going to School
Go to
school
today?

No
Abstain

Yes

Drive to
school

Walk to
class
15

Types of Processes
Single-stage Process
Stage 1

Multi-stage Process
Stage 1

Stage 2

Stage 3
16

Other Process Terminology
(Continued)


Bottleneck
– Occurs when the limited capacity of a process
causes work to pile up or become unevenly
distributed in the flow of a process
– If an employee works too slow in a multi-stage
process, work will begin to pile up in front of
that employee. In this case the employee
represents the limited capacity causing the
bottleneck.



Pacing
– Refers to the fixed timing of the movement of
items through the process
17

Other Types of Processes


Make-to-order
– Activated only in response to an actual order
– Both work-in-process and finished goods
inventory kept to a minimum



Make-to-stock
– Process activated to meet expected or
forecast demand
– Customer orders are served from target
stocking level
Process Performance
Metrics

18



Operation time = Setup time + Run time



Throughput time = Average time for a unit to
move through the system



Velocity = Throughput time
Value-added time
Process Performance
Metrics (Continued)


Cycle time = Average time between
completion of units



Throughput rate =
1
.
Cycle time



Efficiency = Actual output
Standard Output

19
Process Performance Metrics
(Continued)



Productivity = Output
Input



Utilization = Time Activated
Time Available

20
Cycle Time Example

21

Suppose you had to produce 600 units in 80
Suppose you had to produce 600 units in 80
hours to meet the demand requirements of a
hours to meet the demand requirements of a
product. What is the cycle time to meet this
product. What is the cycle time to meet this
demand requirement?
demand requirement?
Answer: There are 4,800 minutes (60
Answer: There are 4,800 minutes (60
minutes/hour x 80 hours) in 80 hours. So the
minutes/hour x 80 hours) in 80 hours. So the
average time between completions would have
average time between completions would have
to be: Cycle time = 4,800/600 units = 8 minutes.
to be: Cycle time = 4,800/600 units = 8 minutes.
22

Process Throughput Time
Reduction


Perform activities in parallel



Change the sequence of activities



Reduce interruptions
23

Question Bowl
Which of the following are possible
examples of “cycle times”?
a. Time for each television to come off an
assembly line.
b. Time it takes for a stock purchase
c. Time it takes for an instructor to grade
an exam
d. Time it takes to complete an automobile
e. All of the above

Answer: e. All of the above
24

Question Bowl
Which of the following are used as
symbols in a Process Flowchart?
a. Decision points
b. Blocking
c. Starving
d. Bottleneck
e. All of the above
Answer: a. Decision points (A diamond
shaped symbol.)
25

Question Bowl
Which type of process is configured as
follows?
1

2

Single-stage process
b. Multi-stage process
c. Make-to-order process
d. Make-to-stock process
e. All of the above
Answer: b. Multi-stage process
a.

3
26

Question Bowl

a.
b.
c.
d.
e.

When an assembly line employee is waiting
for a unit of work to come down the line so
they can stop being idle and get back to
work, it is an example of which of the
following process terms?
Buffering
Blocking
Starving
Bottleneck
All of the above

Answer: c. Starving
27

Question Bowl

a.
b.
c.
d.
e.

When a company waits until they have an
order for their product in hand before
beginning any production for that order, we
can characterize their operation as which of
the following processes?
Single-stage process
Multi-stage process
Make-to-order process
Make-to-stock process
All of the above

Answer: c. Make-to-order process
28

Question Bowl

a.
b.
c.
d.
e.

If the Run Time for a batch of parts is 45 minutes
on a machine, and the Setup Time is 65 minutes,
which of the following is the Operation Time?
75 minutes
110 minutes
Only 45 minutes
65/45 minutes or 1.44 hours
Can not be computed on the data above
Answer: b. 110 minutes ( Operation Time is the sum of
Run Time and Setup Time, or 65 + 45 = 110 minutes)
29

Question Bowl
If the standard expected phone calls for a
telephone marketers is 24 per hour, and one
telephone marketer did 27 per hour, which of
the following can be used to describe their
Answer: c. 112.5%
Efficiency?
(Ratio of actual
a.
88.8%
performance/expected performance,
b.
100%
or (27/24) x 100 = 110 minutes)
c.
d.
e.

112.5%
Well over 150%
Can not computed on the information given.
30

Solved Problems – OPERATIONS MANAGEMENT
(Class of 2010)
Q5. A processor makes 2 components, A and B, which are then packed together as final product
(each product sold contains one A and one B). The processor can do only one component at a
time: either it can make As or it can make Bs. There is a setup time when switching from A to
B
Current plans are to make 100 units of component A, then 100 units of component B, and then
100 units of A and 100 units of B to be packed to be supplied as 100 units of Final Product
The setup and runtimes for each component are given below:-

Component

Setup / Changeover
Time

Run Time / Unit

A

5 min

0.2 min

B

10 min

0.1 min

Assume that packaging of 2 components is totally automated and takes only 2 seconds / unit
of the final product. The packaging time is small enough that you can ignore it. What is the
average hourly output in terms of no. of units of packaged products (which includes 1 of A
and 1 of B)
31

Answer. In order to make final goods, we have to assemble both component A and
component B.
So, let us find out the final operation time for both the components :

Component A
Operation Time = Setuptime + Runtime (for batch)
= 5 + [ (0.2 × 100)]
= 25 minutes



Component B
Operation Time = Setuptime + Runtime (for batch)
= 10 + [ (0.1 × 100)]
= 20 minutes
32



So, Total Operation Time for 100 nos. of Finished Products ( Excluding Packaging
Time)
= 25 + 20
= 45 minutes / 100 pcs



Now, to find out Average output per Hour
In 45 minutes - - - - - - 100 nos
60 minutes
------ ?
= 60 × 100 = 133.34 units
45

Therefore Average Output per Hour = 134 units

More Related Content

PPT
Ch5 process analysis
PPT
Litttle knowledge of lean concept helps
PPTX
Operation management problems
PPT
Line balancing and its formulation
PPT
Line balancing
PPTX
Process design
PPTX
Jonson"s Rule Production scheduling
PPTX
Line balance
Ch5 process analysis
Litttle knowledge of lean concept helps
Operation management problems
Line balancing and its formulation
Line balancing
Process design
Jonson"s Rule Production scheduling
Line balance

What's hot (13)

DOCX
Sap material movement types
PPTX
Line Layout and Workstation Identification
PDF
Job shop scheduling
PDF
ALD Vacuum Systems Inc. - Integrated Heat Treating
PDF
Job Shop Scheduling with Setup Times Release times and Deadlines
PDF
All Movement Types SAP by www.abaper.weebly.com
PPTX
Line balancing
PPTX
MRP exercises
PPTX
Simulation of New World Energy PV Panel Production Facility
PPTX
Line balancing and heuristics
PDF
Flow shop scheduling problem, processing time associated with probabilities i...
PPTX
MRP
Sap material movement types
Line Layout and Workstation Identification
Job shop scheduling
ALD Vacuum Systems Inc. - Integrated Heat Treating
Job Shop Scheduling with Setup Times Release times and Deadlines
All Movement Types SAP by www.abaper.weebly.com
Line balancing
MRP exercises
Simulation of New World Energy PV Panel Production Facility
Line balancing and heuristics
Flow shop scheduling problem, processing time associated with probabilities i...
MRP
Ad

Viewers also liked (19)

DOCX
Supplier ankita
PDF
research report
PDF
634741590184634755
PDF
634953131803473592
PDF
634926580024019075
PDF
research report
PPTX
Process+analysis
PPTX
India before after vat
PPT
Om lect 09(r3-jul 11)_quality management_basics_mms_sies
PPT
The+open+economy+&+exchange+rates
PPT
Ch4 product design
PPT
Allotment of shares total
PDF
Deflation
PDF
Porter five forces model
DOCX
A simple note on prospectus
PPT
Fiscalpolicy
PPT
Law of special contracts
PPTX
Manufacturing+process+selection+and+design.ppt
PPT
Porters5forcesclasspresentation 100616023636-phpapp01
Supplier ankita
research report
634741590184634755
634953131803473592
634926580024019075
research report
Process+analysis
India before after vat
Om lect 09(r3-jul 11)_quality management_basics_mms_sies
The+open+economy+&+exchange+rates
Ch4 product design
Allotment of shares total
Deflation
Porter five forces model
A simple note on prospectus
Fiscalpolicy
Law of special contracts
Manufacturing+process+selection+and+design.ppt
Porters5forcesclasspresentation 100616023636-phpapp01
Ad

Similar to Ch5 process+analysis (20)

PPTX
ch5-processanalysis-131122013048-phpapp02 (1).pptx
PPT
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
PPT
Sususueueuueueeudusiieid8d8eiiriidr3.ppt
PPT
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
PPT
1 and 2 pom.pptdqwekuhtgegweb1226yer71rf 1rrfof
PPT
Process analysis
PPT
Topic 5 - Process Analysis.ppt nsjeiehrh3hw
PPT
Chap005
PPT
Chap005
PPT
Mba ii pmom_unit-1.4 process design, analysis & selection a
PPT
Process Analysis
PPTX
process design and analysis oprations and supply chain management
PPTX
ITlecture5.pptx
PPT
ch05-Flows.ppt
PPTX
Buspro infosheet6
PPTX
Flow queue analysis co4.pptx business process management
PDF
Brief introduction to CAD and CAM – Manufacturing planning, Manufacturing con...
PDF
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
PDF
What is Throughput Time?
PPT
5271197.ppt
ch5-processanalysis-131122013048-phpapp02 (1).pptx
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
Sususueueuueueeudusiieid8d8eiiriidr3.ppt
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
1 and 2 pom.pptdqwekuhtgegweb1226yer71rf 1rrfof
Process analysis
Topic 5 - Process Analysis.ppt nsjeiehrh3hw
Chap005
Chap005
Mba ii pmom_unit-1.4 process design, analysis & selection a
Process Analysis
process design and analysis oprations and supply chain management
ITlecture5.pptx
ch05-Flows.ppt
Buspro infosheet6
Flow queue analysis co4.pptx business process management
Brief introduction to CAD and CAM – Manufacturing planning, Manufacturing con...
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
What is Throughput Time?
5271197.ppt

More from videoaakash15 (20)

PDF
Articlesof association
DOCX
Allotment shares
PPTX
Allotment of shares vamsi
DOC
2448661 issue-of-shares
PPT
87099 19849-book bulding process
DOCX
Ultravires. cons.notice & indoor
PPT
The contract act
DOC
Procedure for incorporating a public limited company
DOC
Notes on wto etc
DOC
Mms la12corsout
DOCX
Minor as a member of a limited company
DOC
Mergers and amalgamations
PDF
Legal environment of business
DOCX
It act,2000 note
DOC
Ipr notes
DOC
Introduction to legal frame work
DOC
Exhaus comp old form
DOCX
DOCX
Assgnment my ans.
Articlesof association
Allotment shares
Allotment of shares vamsi
2448661 issue-of-shares
87099 19849-book bulding process
Ultravires. cons.notice & indoor
The contract act
Procedure for incorporating a public limited company
Notes on wto etc
Mms la12corsout
Minor as a member of a limited company
Mergers and amalgamations
Legal environment of business
It act,2000 note
Ipr notes
Introduction to legal frame work
Exhaus comp old form
Assgnment my ans.

Recently uploaded (20)

PDF
Review of recent advances in non-invasive hemoglobin estimation
PDF
Approach and Philosophy of On baking technology
PDF
Chapter 3 Spatial Domain Image Processing.pdf
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PDF
Electronic commerce courselecture one. Pdf
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
NewMind AI Weekly Chronicles - August'25 Week I
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
Machine learning based COVID-19 study performance prediction
PPT
Teaching material agriculture food technology
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
Spectroscopy.pptx food analysis technology
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PPTX
MYSQL Presentation for SQL database connectivity
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
Review of recent advances in non-invasive hemoglobin estimation
Approach and Philosophy of On baking technology
Chapter 3 Spatial Domain Image Processing.pdf
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Mobile App Security Testing_ A Comprehensive Guide.pdf
Electronic commerce courselecture one. Pdf
Agricultural_Statistics_at_a_Glance_2022_0.pdf
NewMind AI Weekly Chronicles - August'25 Week I
Building Integrated photovoltaic BIPV_UPV.pdf
Unlocking AI with Model Context Protocol (MCP)
Advanced methodologies resolving dimensionality complications for autism neur...
Machine learning based COVID-19 study performance prediction
Teaching material agriculture food technology
Encapsulation_ Review paper, used for researhc scholars
Spectroscopy.pptx food analysis technology
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
The Rise and Fall of 3GPP – Time for a Sabbatical?
MYSQL Presentation for SQL database connectivity
Reach Out and Touch Someone: Haptics and Empathic Computing

Ch5 process+analysis

  • 2. 2 OBJECTIVES • Process Analysis • Process Flowcharting • Types of Processes • Process Performance Metrics
  • 3. 3 Process Analysis Terms  Process: Is any part of an organization that takes inputs and transforms them into outputs  Cycle Time: Is the average successive time between completions of successive units  Utilization: Is the ratio of the time that a resource is actually activated relative to the time that it is available for use
  • 4. Process Flowcharting Defined  Process flowcharting is the use of a diagram to present the major elements of a process  The basic elements can include tasks or operations, flows of materials or customers, decision points, and storage areas or queues  It is an ideal methodology by which to begin analyzing a process 4
  • 5. 5 PROCESS ANALYSIS Standard Symbols used for Flowcharting Symbol Activity Operation Transportation or Movement Inspection Delay/Temporary Storage Definition of Activity Modification of an object Change in location of an Item Examination of an Object (Qlty/Qty parameters) Retention of an Object in a location awaiting next activity
  • 6. 6 Decision Point (Awaiting decision on further Action) Storage Combined Activity Location awaiting next activity Items in stored condition (no unauthorized removal) Two activities occur simultaneously
  • 7. • PROCESS ANALYSIS – Key Terms What is a process? A process is any part of an organization that takes Inputs and transforms them into Outputs • Cycle time (unit item) • • the elapsed time between starting and completing a job (Average time between completion of units) Run time is the time required to produce a batch of parts (for the batch) (this is calculated by multiplying the time required to produce each unit by the batch size) Set-up time (for the m/c) is the time required to prepare a m/c to produce an item 7
  • 8. • Operation time is the sum of set-up time and runtime for a batch of parts that are run on a m/c (for the Batch) • Thro’put time ( for the Unit) the time that the unit spends actually being worked plus the time spent waiting in aQ • Thro’put Rate • Value Added time (for the Batch) (for the unit) • Thro’put Ratio is the Output rate that the process is expected to produce over a period of time the time in which useful work is actually being done on the unit Process Velocity : the ratio of the total thro’put time to the value added time 8
  • 9. 9 • Make-to-order • Make-to-stock • Hybrid (Either Unit or Batch) (Either Unit or Batch) (Unit or Batch ) A process that is activated only in response to an actual order A process that produces standard products that are stored in finished Goods Inventory : the product is quickly delivered to the customer Combines the feature of both make-to-order and make-to-stock (A generic product is made and customised in a final process to meet actual orders)
  • 12. Assemble-to-Order Forecast orders customer Production of Subassemblies Customer order Product Assembly of the Order Subassembly Inventory of Subassemblies
  • 13. 13  Efficiency  Productivity  Utilization  Little’s Law Actual Output Standard Output Output Input Time activated Time available (definition as follows) Thro’put time = Work-in-Proccess Thro’put Rate
  • 14. 14 Example: Flowchart of Student Going to School Go to school today? No Abstain Yes Drive to school Walk to class
  • 15. 15 Types of Processes Single-stage Process Stage 1 Multi-stage Process Stage 1 Stage 2 Stage 3
  • 16. 16 Other Process Terminology (Continued)  Bottleneck – Occurs when the limited capacity of a process causes work to pile up or become unevenly distributed in the flow of a process – If an employee works too slow in a multi-stage process, work will begin to pile up in front of that employee. In this case the employee represents the limited capacity causing the bottleneck.  Pacing – Refers to the fixed timing of the movement of items through the process
  • 17. 17 Other Types of Processes  Make-to-order – Activated only in response to an actual order – Both work-in-process and finished goods inventory kept to a minimum  Make-to-stock – Process activated to meet expected or forecast demand – Customer orders are served from target stocking level
  • 18. Process Performance Metrics 18  Operation time = Setup time + Run time  Throughput time = Average time for a unit to move through the system  Velocity = Throughput time Value-added time
  • 19. Process Performance Metrics (Continued)  Cycle time = Average time between completion of units  Throughput rate = 1 . Cycle time  Efficiency = Actual output Standard Output 19
  • 20. Process Performance Metrics (Continued)  Productivity = Output Input  Utilization = Time Activated Time Available 20
  • 21. Cycle Time Example 21 Suppose you had to produce 600 units in 80 Suppose you had to produce 600 units in 80 hours to meet the demand requirements of a hours to meet the demand requirements of a product. What is the cycle time to meet this product. What is the cycle time to meet this demand requirement? demand requirement? Answer: There are 4,800 minutes (60 Answer: There are 4,800 minutes (60 minutes/hour x 80 hours) in 80 hours. So the minutes/hour x 80 hours) in 80 hours. So the average time between completions would have average time between completions would have to be: Cycle time = 4,800/600 units = 8 minutes. to be: Cycle time = 4,800/600 units = 8 minutes.
  • 22. 22 Process Throughput Time Reduction  Perform activities in parallel  Change the sequence of activities  Reduce interruptions
  • 23. 23 Question Bowl Which of the following are possible examples of “cycle times”? a. Time for each television to come off an assembly line. b. Time it takes for a stock purchase c. Time it takes for an instructor to grade an exam d. Time it takes to complete an automobile e. All of the above Answer: e. All of the above
  • 24. 24 Question Bowl Which of the following are used as symbols in a Process Flowchart? a. Decision points b. Blocking c. Starving d. Bottleneck e. All of the above Answer: a. Decision points (A diamond shaped symbol.)
  • 25. 25 Question Bowl Which type of process is configured as follows? 1 2 Single-stage process b. Multi-stage process c. Make-to-order process d. Make-to-stock process e. All of the above Answer: b. Multi-stage process a. 3
  • 26. 26 Question Bowl a. b. c. d. e. When an assembly line employee is waiting for a unit of work to come down the line so they can stop being idle and get back to work, it is an example of which of the following process terms? Buffering Blocking Starving Bottleneck All of the above Answer: c. Starving
  • 27. 27 Question Bowl a. b. c. d. e. When a company waits until they have an order for their product in hand before beginning any production for that order, we can characterize their operation as which of the following processes? Single-stage process Multi-stage process Make-to-order process Make-to-stock process All of the above Answer: c. Make-to-order process
  • 28. 28 Question Bowl a. b. c. d. e. If the Run Time for a batch of parts is 45 minutes on a machine, and the Setup Time is 65 minutes, which of the following is the Operation Time? 75 minutes 110 minutes Only 45 minutes 65/45 minutes or 1.44 hours Can not be computed on the data above Answer: b. 110 minutes ( Operation Time is the sum of Run Time and Setup Time, or 65 + 45 = 110 minutes)
  • 29. 29 Question Bowl If the standard expected phone calls for a telephone marketers is 24 per hour, and one telephone marketer did 27 per hour, which of the following can be used to describe their Answer: c. 112.5% Efficiency? (Ratio of actual a. 88.8% performance/expected performance, b. 100% or (27/24) x 100 = 110 minutes) c. d. e. 112.5% Well over 150% Can not computed on the information given.
  • 30. 30 Solved Problems – OPERATIONS MANAGEMENT (Class of 2010) Q5. A processor makes 2 components, A and B, which are then packed together as final product (each product sold contains one A and one B). The processor can do only one component at a time: either it can make As or it can make Bs. There is a setup time when switching from A to B Current plans are to make 100 units of component A, then 100 units of component B, and then 100 units of A and 100 units of B to be packed to be supplied as 100 units of Final Product The setup and runtimes for each component are given below:- Component Setup / Changeover Time Run Time / Unit A 5 min 0.2 min B 10 min 0.1 min Assume that packaging of 2 components is totally automated and takes only 2 seconds / unit of the final product. The packaging time is small enough that you can ignore it. What is the average hourly output in terms of no. of units of packaged products (which includes 1 of A and 1 of B)
  • 31. 31 Answer. In order to make final goods, we have to assemble both component A and component B. So, let us find out the final operation time for both the components : Component A Operation Time = Setuptime + Runtime (for batch) = 5 + [ (0.2 × 100)] = 25 minutes  Component B Operation Time = Setuptime + Runtime (for batch) = 10 + [ (0.1 × 100)] = 20 minutes
  • 32. 32  So, Total Operation Time for 100 nos. of Finished Products ( Excluding Packaging Time) = 25 + 20 = 45 minutes / 100 pcs  Now, to find out Average output per Hour In 45 minutes - - - - - - 100 nos 60 minutes ------ ? = 60 × 100 = 133.34 units 45 Therefore Average Output per Hour = 134 units