MRP EXERCISE
2nd Part.
BRIEFLY REMAINDER OF WHAT MRP
IS AND ITS CHARACTERISTICS
MRP is a dependent demand technique that uses a bill of-material, inventory, expected receipts, and a master
production Schedule to determine material requirement.
• In order to apply this method it will be needed to know:
1. What is to be made and when.
2. Materials and parts required to make the product.
3.What is in stock.
4. What is on order, also called expected receipts.
5. How long it takes to get various components.
MRP
Order
Proposal Stock Sales
Customer
order
Production
order
Forecast
Historical
of sales
NET MATERIAL REQUIREMENT
PLAN (ELEMENTS)
• Gross requirement: is the independent demand
quantity for each ítem (given).
• Schedule requirement: orders that have been placed
but not yet completed (given).
• Availabilities: estimate amount of inventory
available each week after gross requirement have been
satisfied.
• Planned Order Receipts: quantity determined to be
required for receipt at the beginning of a time period.
• Planned Order Releases: amount of order planned
in each time period.
NET MATERIAL REQUIREMENT
PLAN (FORMULAS)
Net Requirement = Gross Requirement – (availability + Schedule orders).
Optimal Quantity Order =
Q* = 2DS
H
where D= Annual usage.
S= Set-up cost.
H= Holding cost.
LOT SIZING TECHNIQUES
• Lot for lot.- Produced exactly what is required.
No: if set-up cost is significant high
or
unable to implement JIT (Just In Time).
• Constant or Fixed Order Quantity. Specify a number of units arbitrarily to be ordered each time, an
order is placed for a particular ítem.
• Economic Order Quantity. A specific number of units, that will minimise the combined cost of
order (acquiring and carrying inventory.
PROBLEM Nº 5 (problem definition)
• A company manufactures products A and H and the following information is available:
Products A and
H
Period
8 9 10 11 12
Gross
requirement of
A
100 50 150
Gross
requirements of
H
100 50
Item On hand inventory Lead time Components
A 0 1 B (1); C (1)
B 100 2 D(1); E(1)
C 25 1 F(1); G(1)
D 50 1
E 75 2
F 75 2
G 75 1
H 0 1 J (1), K (1), C(1)
J 100 2 E(1), F(1)
C 25 1 F(1), G(1)
K 100 2 E(1); G(1)
1. Elaborate the product tree structure and represent the level code.
2. Besides the units required of A and H, there exists a demand of 30 units for item E (sold as repair element)
in week 10. Modify the Gross materials requirement plan to reflect this change and elaborate the Net Material
Requirement Plan.
PROBLEM Nº5 (SOLUTION)
 Product tree and representation of the level code.
1st level
2nd
level
Product A Product H
B C CKJ
D E F G E F E G F G
PROBLEM Nº5 (SOLUTION)
 There exists a demand of 30 units for item E in week 10, construct the MRP Table.
NOTE: It has to been started from the top to the bottom.
-The Gross requirement (GRP) for these to
table will be directly subtracted from the
exercise.
Always the GRP of the ítem from the top
will be directly given.
-The lead time in both ítem: 1 week.
PROBLEM Nº5 (SOLUTION)
• For Product A is required ítem B and C:
-The Gross requirement in ítem B will be
subtracted from the orders planned of product
A. In the case of ítem C, the GRP will included
the order planned for product H.
-Availability is given by the exercise (there no
safety stock in this exercise).
-Lead time is two week for ítem B, and one
week for ítem C.
PROBLEM Nº5 (SOLUTION)
• For product H is required ítem J, K and C.
-The Gross requirement of both ítems will
be taken from the planned order of product
H.
-Availability: given.
-Net req : gross req. Availabilies.
-Lead time: ítem J (2 weeks); ítem K (2
weeks).
PROBLEM Nº5 (SOLUTION)
• 2nd level : Item B is composed by ítem D and E.
NOTE: Item E is also required for ítem J and K. Additionally in week 10, extra demand of 30.
ItemE 1 2 3 4 5 6 7 8 9 10 11 12
Grossreq. 50 100 150 30
Plannedreceipt
Availability 75 75 75 75 75 75 75 25
Netreq. 75 150 30
Plannedorderorder 75 150 30
Plannedorderrelease 75 150 30
PERIOD
-Gross req. : For ítem D was subtracted from
orders planned in ítem B, and for ítem E was
subtracted form orders planned in ítem B, J, and K,
and the extra demand in week 10 of 30 units.
-Availabilities : given.
-Net req: Gross req. Availabilities.
-Lead time: 2 weeks for both ítems.
Item D 1 2 3 4 5 6 7 8 9 10 11 12
Grossreq. 50 150
Planned receipt
Availability 50 50 50 50 50 50 50
Netreq. 0 150
Planned orderorder 0 150
Planned orderrelease 150
PERIOD
PROBLEM Nº5 (SOLUTION)
• The remainder ítems are F and G:
ItemF 1 2 3 4 5 6 7 8 9 10 11 12
Grossreq. 50 100 100 50 150
Plannedreceipt
Availability 75 75 75 75 75 75 25
Netreq. 75 100 50 150
Plannedorderorder 75 100 50 150
Plannedorderrelease 75 100 50 150
PERIOD
ItemG 1 2 3 4 5 6 7 8 9 10 11 12
Grossreq. 50 100 100 50 150
Plannedreceipt
Availability 75 75 75 75 75 75 25
Netreq. 75 100 50 150
Plannedorderorder 75 100 50 150
Plannedorderrelease 75 100 50 150
PERIOD
-Gross req: ítem F will be subtracted from
planned order of ítem C (x2), J and K. And for
ítem G from planned orders of ítem C (x2), and
J.
-Availabilities: given.
-Net req: Gross req. Availabilities.
-Lead time: ítem F (2 weeks); ítem G (1 week).
PROBLEM Nº 7 (SOLUTION)
• A company that manufactures product X and Y has the following information:
Products X and Y Period
4 5 6 7
Gross
requirement of X
50 150
Gross
requirement of Y
100 50
Item On hand
inventory
Lead Time Components
X 0 1 A (1), B (1)
Y 0 1 B(1), F (1)
A 100 2 C(1), D(1)
B 25 1 E(1), F (1)
C 50 1
D 75 2
E 75 1
F 115 1
You are asked to:
1. Elaborate the product tree structure and represent the level code.
2. Besides the requirements for X and Y, there exits also a demand of 30 units for item D (sold externally) in week
5. Modify the Gross Requirement to reflect this change and elaborate the Net Requirement Plan
PROBLEM Nº 7 (SOLUTION)
• 1. Elaborate the product tree structure and represent the level code.
X Y
A B B F
DC E F E F
PROBLEM Nº 7 (SOLUTION)
 There exists an extra demand of 30 units (ítem D). Additionally all ítem follows the lot-for-lot
technique, excepts ítem F, which follows optimal order quantity technique. Order cost =140
m.u , holding cost: 1 m.u
ITEM X 1 2 3 4 5 6 7
GROSS REQ. 50 150
PLANNED RECEIPT
AVAILABILITY
NET REQ. 50 150
PLANNED ORD R. 50 150
PLANNED ORD. RE 50 150
WEEKS
ITEM Y 1 2 3 4 5 6 7
GROSS REQ. 100 50
PLANNED RECEIPT
AVAILABILITY
NET REQ. 100 50
PLANNED ORD R. 100 50
PLANNED ORD. RE 100 50
WEEKS
-The Gross requirement (GRP) for these
to table will be directly subtracted from the
exercise.
Always the GRP of the ítem from the top
will be directly given.
-The lead time in both ítem: 1 week.
PROBLEM Nº 7 (SOLUTION)
• For product X is required ítem A and B.
ITEM A 1 2 3 4 5 6 7
GROSS REQ. 50 150
PLANNED RECEIPT
AVAILABILITY 100 100 100 100 50 50
NET REQ. 100
PLANNED ORD R. 100
PLANNED ORD. RE 100
WEEKS
ITEM B 1 2 3 4 5 6 7
GROSS REQ. 100 50 50 150
PLANNED RECEIPT
AVAILABILITY 25 25 25
NET REQ. 75 50 50 150
PLANNED ORD R. 75 50 50 150
PLANNED ORD. RE 75 50 50 150
WEEKS
-The Gross requirement in ítem A will be
subtracted from the orders planned of product
X. In the case of ítem B, the GRP will include
the order planned for product X and Y.
-Availability is given by the exercise (there no
safety stock in this exercise).
-Lead time is two week for ítem A, and one
week for ítem B.
PROBLEM Nº 7 (SOLUTION)
• Item F Special characteristic (follows a fixed order quantity technique).
ITEM F 1 2 3 4 5 6 7
GROSS REQ. 75 150 50 200
PLANNED RECEIPT
AVAILABILITY 115 115 40 10 80
NET REQ. 110 40 120
PLANNED ORD R. 120 120 120
PLANNED ORD. RE 120 120 120
WEEKS -The Gross requirement in ítem F
will be subtracted from the orders
planned of product H, from ítem B
(x2).
-Availability is given by the exercise
(there no safety stock in this
exercise).
-Lead time is two week for ítem B,
and one week for ítem C.
 The planned order will be the one that minimize the cost of
holding inventories. Optimal quantity =
Q = ROOT ((2 X Ce x D) / Cp x Ɵ )
Q=ROOT (( 2 x 140 x 120) / 1 x 7) = 120
PROBLEM Nº 7 (SOLUTION)
• 2nd level : For making ítem A is required ítem C and D.
ITEM C 1 2 3 4 5 6 7
GROSS REQ. 100
PLANNED RECEIPT
AVAILABILITY 50 50 50 50
NET REQ. 50
PLANNED ORD R. 50
PLANNED ORD. RE 50
WEEKS
ITEM D 1 2 3 4 5 6 7
GROSS REQ. 100 30
PLANNED RECEIPT
AVAILABILITY 75 75 75 75
NET REQ. 25 30
PLANNED ORD R. 25 30
PLANNED ORD. RE 25 30
WEEKS
-Gross req: ítem C will be subtracted from
planned order of ítem A. And for ítem D
from planned orders of ítem A.
-Availabilities: given.
-Net req: Gross req. Availabilities.
-Lead time: ítem C (1 weeks); ítem D (2
week).
PROBLEM Nº 7 (SOLUTION)
• For making ítem B is required ítem E.
ITEME 1 2 3 4 5 6 7
GROSSREQ. 75 50 50 150
PLANNEDRECEIPT
AVAILABILITY 75 75
NETREQ. 50 50 150
PLANNEDORDR. 50 50 150
PLANNEDORD.RE 50 50 150
WEEKS
-Gross req: ítem E will be subtracted from
planned order of ítem B (x2).
-Availabilities: given.
-Net req: Gross req. Availabilities.
-Lead time: ítem E (1 week).
SOLVED PROBLEM (problem definition)
• The demand for item A in weeks 8, 10, and 11 are 50, 75, and 100 units,
respectively. Consider the following data.
Answer: (a) and (b)
(a) Draw the product tree for item A (b) Indicate the low-level code for each item
Answer (c):
MRP records for each item are as follows:
Answer (c):
MRP records for each item are as follows:
Answer (c):
MRP records for each item are as follows:1
3
2
Answer (c):
MRP records for each item are as follows:
11
Answer (c):
MRP records for each item are as follows:
2
Answer (c):
MRP records for each item are as follows:
3
MRP exercises

More Related Content

PPTX
Materials requirements planning
PPTX
Materials requirement planning
PPT
Material requirement planning presentation
PPT
Material Requirement Planning (MRP)
PPTX
PPT
Scheduling
PPTX
MRP,MRP-II,JIT
PPT
Material Resource Planning
Materials requirements planning
Materials requirement planning
Material requirement planning presentation
Material Requirement Planning (MRP)
Scheduling
MRP,MRP-II,JIT
Material Resource Planning

What's hot (20)

PPTX
Production Planning & Control
PPT
Aggregate Production Planning
PPTX
Material Requirement Planning (mrp)
PPT
Aggregate Planning
PDF
Quality Function Deployment PPT Slide Template
PPTX
Material requirement planning - Production and Operation Management
PPTX
Master Production Scheduling (MPS)
PPTX
MRP, MPS, Bill of Material, Numericals
PPTX
Material requirement planning (mrp1)
PPTX
Assignment on MRP Calculation
PPT
Job Design and Work Measurement
PPTX
Capacity planning
PPTX
Line balancing
PPT
Lean Manufacturing and Principles
PPTX
Quality Function Deployment
PPT
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
PPT
Capacity planning
PPTX
Presentation aggregate planning
PDF
8. chapter 7 work study (time and motion study)
Production Planning & Control
Aggregate Production Planning
Material Requirement Planning (mrp)
Aggregate Planning
Quality Function Deployment PPT Slide Template
Material requirement planning - Production and Operation Management
Master Production Scheduling (MPS)
MRP, MPS, Bill of Material, Numericals
Material requirement planning (mrp1)
Assignment on MRP Calculation
Job Design and Work Measurement
Capacity planning
Line balancing
Lean Manufacturing and Principles
Quality Function Deployment
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
Capacity planning
Presentation aggregate planning
8. chapter 7 work study (time and motion study)
Ad

Similar to MRP exercises (20)

PDF
Mrpexercise 150427045220-conversion-gate01
PPTX
Mrp exercise nº7
PDF
PDF
PPTX
Operations Management Classroom Presentation
PPT
Material requirement Process in Production
PPT
PPT
5 MRP.ppt
PPTX
samer amale mrp presentation
PPT
MRP in English
PPT
Ch16 mrp
PDF
A Simple Case Study of Material Requirement Planning
PPTX
MRP
PDF
Material requirement planning Q&A
DOC
Materials Management
PDF
Lecture 12_Enterprise Resourse Planning.pdf
PPT
Mrp task 1
PPT
Mrp task 1
PPTX
MRP and ERP
Mrpexercise 150427045220-conversion-gate01
Mrp exercise nº7
Operations Management Classroom Presentation
Material requirement Process in Production
5 MRP.ppt
samer amale mrp presentation
MRP in English
Ch16 mrp
A Simple Case Study of Material Requirement Planning
MRP
Material requirement planning Q&A
Materials Management
Lecture 12_Enterprise Resourse Planning.pdf
Mrp task 1
Mrp task 1
MRP and ERP
Ad

Recently uploaded (20)

PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
Deliverable file - Regulatory guideline analysis.pdf
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
Digital Marketing & E-commerce Certificate Glossary.pdf.................
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
Amazon (Business Studies) management studies
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PPT
Chapter four Project-Preparation material
PDF
How to Get Business Funding for Small Business Fast
PPTX
Lecture (1)-Introduction.pptx business communication
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Belch_12e_PPT_Ch18_Accessible_university.pptx
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Roadmap Map-digital Banking feature MB,IB,AB
340036916-American-Literature-Literary-Period-Overview.ppt
2025 Product Deck V1.0.pptxCATALOGTCLCIA
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
Deliverable file - Regulatory guideline analysis.pdf
unit 1 COST ACCOUNTING AND COST SHEET
Daniels 2024 Inclusive, Sustainable Development
Digital Marketing & E-commerce Certificate Glossary.pdf.................
Reconciliation AND MEMORANDUM RECONCILATION
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Amazon (Business Studies) management studies
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
Chapter four Project-Preparation material
How to Get Business Funding for Small Business Fast
Lecture (1)-Introduction.pptx business communication
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...

MRP exercises

  • 2. BRIEFLY REMAINDER OF WHAT MRP IS AND ITS CHARACTERISTICS MRP is a dependent demand technique that uses a bill of-material, inventory, expected receipts, and a master production Schedule to determine material requirement. • In order to apply this method it will be needed to know: 1. What is to be made and when. 2. Materials and parts required to make the product. 3.What is in stock. 4. What is on order, also called expected receipts. 5. How long it takes to get various components. MRP Order Proposal Stock Sales Customer order Production order Forecast Historical of sales
  • 3. NET MATERIAL REQUIREMENT PLAN (ELEMENTS) • Gross requirement: is the independent demand quantity for each ítem (given). • Schedule requirement: orders that have been placed but not yet completed (given). • Availabilities: estimate amount of inventory available each week after gross requirement have been satisfied. • Planned Order Receipts: quantity determined to be required for receipt at the beginning of a time period. • Planned Order Releases: amount of order planned in each time period.
  • 4. NET MATERIAL REQUIREMENT PLAN (FORMULAS) Net Requirement = Gross Requirement – (availability + Schedule orders). Optimal Quantity Order = Q* = 2DS H where D= Annual usage. S= Set-up cost. H= Holding cost.
  • 5. LOT SIZING TECHNIQUES • Lot for lot.- Produced exactly what is required. No: if set-up cost is significant high or unable to implement JIT (Just In Time). • Constant or Fixed Order Quantity. Specify a number of units arbitrarily to be ordered each time, an order is placed for a particular ítem. • Economic Order Quantity. A specific number of units, that will minimise the combined cost of order (acquiring and carrying inventory.
  • 6. PROBLEM Nº 5 (problem definition) • A company manufactures products A and H and the following information is available: Products A and H Period 8 9 10 11 12 Gross requirement of A 100 50 150 Gross requirements of H 100 50 Item On hand inventory Lead time Components A 0 1 B (1); C (1) B 100 2 D(1); E(1) C 25 1 F(1); G(1) D 50 1 E 75 2 F 75 2 G 75 1 H 0 1 J (1), K (1), C(1) J 100 2 E(1), F(1) C 25 1 F(1), G(1) K 100 2 E(1); G(1) 1. Elaborate the product tree structure and represent the level code. 2. Besides the units required of A and H, there exists a demand of 30 units for item E (sold as repair element) in week 10. Modify the Gross materials requirement plan to reflect this change and elaborate the Net Material Requirement Plan.
  • 7. PROBLEM Nº5 (SOLUTION)  Product tree and representation of the level code. 1st level 2nd level Product A Product H B C CKJ D E F G E F E G F G
  • 8. PROBLEM Nº5 (SOLUTION)  There exists a demand of 30 units for item E in week 10, construct the MRP Table. NOTE: It has to been started from the top to the bottom. -The Gross requirement (GRP) for these to table will be directly subtracted from the exercise. Always the GRP of the ítem from the top will be directly given. -The lead time in both ítem: 1 week.
  • 9. PROBLEM Nº5 (SOLUTION) • For Product A is required ítem B and C: -The Gross requirement in ítem B will be subtracted from the orders planned of product A. In the case of ítem C, the GRP will included the order planned for product H. -Availability is given by the exercise (there no safety stock in this exercise). -Lead time is two week for ítem B, and one week for ítem C.
  • 10. PROBLEM Nº5 (SOLUTION) • For product H is required ítem J, K and C. -The Gross requirement of both ítems will be taken from the planned order of product H. -Availability: given. -Net req : gross req. Availabilies. -Lead time: ítem J (2 weeks); ítem K (2 weeks).
  • 11. PROBLEM Nº5 (SOLUTION) • 2nd level : Item B is composed by ítem D and E. NOTE: Item E is also required for ítem J and K. Additionally in week 10, extra demand of 30. ItemE 1 2 3 4 5 6 7 8 9 10 11 12 Grossreq. 50 100 150 30 Plannedreceipt Availability 75 75 75 75 75 75 75 25 Netreq. 75 150 30 Plannedorderorder 75 150 30 Plannedorderrelease 75 150 30 PERIOD -Gross req. : For ítem D was subtracted from orders planned in ítem B, and for ítem E was subtracted form orders planned in ítem B, J, and K, and the extra demand in week 10 of 30 units. -Availabilities : given. -Net req: Gross req. Availabilities. -Lead time: 2 weeks for both ítems. Item D 1 2 3 4 5 6 7 8 9 10 11 12 Grossreq. 50 150 Planned receipt Availability 50 50 50 50 50 50 50 Netreq. 0 150 Planned orderorder 0 150 Planned orderrelease 150 PERIOD
  • 12. PROBLEM Nº5 (SOLUTION) • The remainder ítems are F and G: ItemF 1 2 3 4 5 6 7 8 9 10 11 12 Grossreq. 50 100 100 50 150 Plannedreceipt Availability 75 75 75 75 75 75 25 Netreq. 75 100 50 150 Plannedorderorder 75 100 50 150 Plannedorderrelease 75 100 50 150 PERIOD ItemG 1 2 3 4 5 6 7 8 9 10 11 12 Grossreq. 50 100 100 50 150 Plannedreceipt Availability 75 75 75 75 75 75 25 Netreq. 75 100 50 150 Plannedorderorder 75 100 50 150 Plannedorderrelease 75 100 50 150 PERIOD -Gross req: ítem F will be subtracted from planned order of ítem C (x2), J and K. And for ítem G from planned orders of ítem C (x2), and J. -Availabilities: given. -Net req: Gross req. Availabilities. -Lead time: ítem F (2 weeks); ítem G (1 week).
  • 13. PROBLEM Nº 7 (SOLUTION) • A company that manufactures product X and Y has the following information: Products X and Y Period 4 5 6 7 Gross requirement of X 50 150 Gross requirement of Y 100 50 Item On hand inventory Lead Time Components X 0 1 A (1), B (1) Y 0 1 B(1), F (1) A 100 2 C(1), D(1) B 25 1 E(1), F (1) C 50 1 D 75 2 E 75 1 F 115 1 You are asked to: 1. Elaborate the product tree structure and represent the level code. 2. Besides the requirements for X and Y, there exits also a demand of 30 units for item D (sold externally) in week 5. Modify the Gross Requirement to reflect this change and elaborate the Net Requirement Plan
  • 14. PROBLEM Nº 7 (SOLUTION) • 1. Elaborate the product tree structure and represent the level code. X Y A B B F DC E F E F
  • 15. PROBLEM Nº 7 (SOLUTION)  There exists an extra demand of 30 units (ítem D). Additionally all ítem follows the lot-for-lot technique, excepts ítem F, which follows optimal order quantity technique. Order cost =140 m.u , holding cost: 1 m.u ITEM X 1 2 3 4 5 6 7 GROSS REQ. 50 150 PLANNED RECEIPT AVAILABILITY NET REQ. 50 150 PLANNED ORD R. 50 150 PLANNED ORD. RE 50 150 WEEKS ITEM Y 1 2 3 4 5 6 7 GROSS REQ. 100 50 PLANNED RECEIPT AVAILABILITY NET REQ. 100 50 PLANNED ORD R. 100 50 PLANNED ORD. RE 100 50 WEEKS -The Gross requirement (GRP) for these to table will be directly subtracted from the exercise. Always the GRP of the ítem from the top will be directly given. -The lead time in both ítem: 1 week.
  • 16. PROBLEM Nº 7 (SOLUTION) • For product X is required ítem A and B. ITEM A 1 2 3 4 5 6 7 GROSS REQ. 50 150 PLANNED RECEIPT AVAILABILITY 100 100 100 100 50 50 NET REQ. 100 PLANNED ORD R. 100 PLANNED ORD. RE 100 WEEKS ITEM B 1 2 3 4 5 6 7 GROSS REQ. 100 50 50 150 PLANNED RECEIPT AVAILABILITY 25 25 25 NET REQ. 75 50 50 150 PLANNED ORD R. 75 50 50 150 PLANNED ORD. RE 75 50 50 150 WEEKS -The Gross requirement in ítem A will be subtracted from the orders planned of product X. In the case of ítem B, the GRP will include the order planned for product X and Y. -Availability is given by the exercise (there no safety stock in this exercise). -Lead time is two week for ítem A, and one week for ítem B.
  • 17. PROBLEM Nº 7 (SOLUTION) • Item F Special characteristic (follows a fixed order quantity technique). ITEM F 1 2 3 4 5 6 7 GROSS REQ. 75 150 50 200 PLANNED RECEIPT AVAILABILITY 115 115 40 10 80 NET REQ. 110 40 120 PLANNED ORD R. 120 120 120 PLANNED ORD. RE 120 120 120 WEEKS -The Gross requirement in ítem F will be subtracted from the orders planned of product H, from ítem B (x2). -Availability is given by the exercise (there no safety stock in this exercise). -Lead time is two week for ítem B, and one week for ítem C.  The planned order will be the one that minimize the cost of holding inventories. Optimal quantity = Q = ROOT ((2 X Ce x D) / Cp x Ɵ ) Q=ROOT (( 2 x 140 x 120) / 1 x 7) = 120
  • 18. PROBLEM Nº 7 (SOLUTION) • 2nd level : For making ítem A is required ítem C and D. ITEM C 1 2 3 4 5 6 7 GROSS REQ. 100 PLANNED RECEIPT AVAILABILITY 50 50 50 50 NET REQ. 50 PLANNED ORD R. 50 PLANNED ORD. RE 50 WEEKS ITEM D 1 2 3 4 5 6 7 GROSS REQ. 100 30 PLANNED RECEIPT AVAILABILITY 75 75 75 75 NET REQ. 25 30 PLANNED ORD R. 25 30 PLANNED ORD. RE 25 30 WEEKS -Gross req: ítem C will be subtracted from planned order of ítem A. And for ítem D from planned orders of ítem A. -Availabilities: given. -Net req: Gross req. Availabilities. -Lead time: ítem C (1 weeks); ítem D (2 week).
  • 19. PROBLEM Nº 7 (SOLUTION) • For making ítem B is required ítem E. ITEME 1 2 3 4 5 6 7 GROSSREQ. 75 50 50 150 PLANNEDRECEIPT AVAILABILITY 75 75 NETREQ. 50 50 150 PLANNEDORDR. 50 50 150 PLANNEDORD.RE 50 50 150 WEEKS -Gross req: ítem E will be subtracted from planned order of ítem B (x2). -Availabilities: given. -Net req: Gross req. Availabilities. -Lead time: ítem E (1 week).
  • 20. SOLVED PROBLEM (problem definition) • The demand for item A in weeks 8, 10, and 11 are 50, 75, and 100 units, respectively. Consider the following data.
  • 21. Answer: (a) and (b) (a) Draw the product tree for item A (b) Indicate the low-level code for each item
  • 22. Answer (c): MRP records for each item are as follows:
  • 23. Answer (c): MRP records for each item are as follows:
  • 24. Answer (c): MRP records for each item are as follows:1 3 2
  • 25. Answer (c): MRP records for each item are as follows: 11
  • 26. Answer (c): MRP records for each item are as follows: 2
  • 27. Answer (c): MRP records for each item are as follows: 3