Chapter two
Developing supply plan
Activity 2.1. Individual Reflection
Instruction: Recall your previous practice
What procedures have you used while developing a
supply plan?
Time allowed: 5 minute
Formula MOS
MOS is calculated using the following formula
To compute AMC, at least three to six months of continuous consumption quantity of a product
is needed.
Months of stock (MOS) = stock on hand or order (SOH or SOO)/Average monthly consumption
(AMC)
Activity on MOS
Funding/budget gap analysis
• If sufficient funding is available, the final quantity to procure for each
product will be the same as the quantity to order
• if funding is insufficient, the quantification team will need to determine
whether additional resources can be mobilized
• When it is impossible to mobilize additional resources to procure the full
quantities of products required or the forecasted quantity will need to be
reduced
Scheduling delivery of ordered pharmaceuticals
all the quantities required might not necessary be delivered at a time for the
reasons;
• Insufficient storage capacity,
• Seasonality of some diseases,
• Available fund covers portion of the required quantity and
• The stock on hand quantity is greater than the set maximum stock level.
 To accompany these, the arrival of products must be scheduled so that medicines
are sustainably available.
Scheduling delivery of ordered pharmaceuticals
Scheduling depends on
• the in house tender process,
• supplier/manufacturing lead time,
• method of transport,
• length of time for port clearance,
• quality assurance procedures (pre- and post-shipment) and some other possible conditions.
The supplier/manufacturing lead time can vary for each product and must be
monitored as part of supplier performance.
When lead times are underestimated, the likely results are shortages and more
expensive emergency purchases.
Scheduling delivery of ordered pharmaceuticals
Timely ordering is achieved through efficient pipeline monitoring, which includes
• Monitoring stock balances, in terms of quantities and MOS (aggregate of stock at all levels or
national stock level)
• Comparing stock balances to maximum and minimum stock levels
• Identifying potential pipeline problems (quantities needed, stock-outs, balances below
minimum or above maximum)
Flexible procurement contracts with suppliers are recommended, so that
shipment quantities can be adjusted to respond to
• uptake in services,
• fluctuations in patient demand,
• existing stock levels, and
• rates of consumption of products.
2.3. Using supply plan
Well-developed supply plan have numerous benefits in facilitating the
establishment of a resilient supply of products.
The benefits are multi-dimensional when considering the involved stakeholders.
Mangers
• To identify the funding needs and gaps for procurement of the required products
• Leverage the sources, amounts, and timing of funding commitments to maximize the use of
available resources
• Advocate for additional resources, when needed
• To monitor and evaluate the process
Using supply plan
Supply planners
• To coordinate procurements and shipment delivery schedules to ensure a continuous supply
of commodities
• For easily identification specific matters if problems exists
• To communicate with manufacturers and suppliers for timely delivery
Donors
• Will have clear picture of the funding amount
• Recognize the existence of funding gap
• To evaluate whether their funding disbursement meets the right target
• Gives insight where to provide financial or/and technical support
Reviewing and updating the supply planning

More Related Content

PPTX
Managemnt of SP_Chapter 1.pptx_Supply Planing Courrse
PPT
Latest Learning and Resources for iCCM_Briggs
PPTX
Material mangement (1).pptx
PPTX
Material management
PPTX
Module 3 - Aggregate Planning Tacticts2.pptx
PPTX
INVENTORYCONTROL. definition and methods
DOC
Inventory management for remote healthcare
PDF
21-Inventory Management-2.pdf
Managemnt of SP_Chapter 1.pptx_Supply Planing Courrse
Latest Learning and Resources for iCCM_Briggs
Material mangement (1).pptx
Material management
Module 3 - Aggregate Planning Tacticts2.pptx
INVENTORYCONTROL. definition and methods
Inventory management for remote healthcare
21-Inventory Management-2.pdf

Similar to Managemnt of SP_Chapter 2.pptx: Sp Training (20)

PPTX
supply chain management in hospitality and tourism industry
PPTX
Safety stock
PPTX
Material and Inventory management By Nitin Shekapure
PPTX
MATERIALS MANAGEMENT
DOCX
Pom unit 3
PDF
Inventory management
PPTX
Chap7.pptx
PPT
Finance 22 1- BSA Budgeting and Finance.ppt
PPTX
PHC LECTURE 6.pptx
PPTX
Capacity management
PPTX
Inventory Management , MRP, JIT and SCM
PPTX
RDF Quantification-Orientation material for 2014.pptx
PPTX
Models of inventory control
PDF
Inventory management a detailed presentation
PPTX
Materail Management
PDF
Aggregate planning using transportation method a case study in cable industry
PPTX
INVENTORY MANAGEMENT & CONTROL (NISHA SS).pptx
PPT
Planning & Procurement of Spares Accessories Consumables.ppt
PPTX
Material Managament in Hospital.pptx
PPT
Abc analysis
supply chain management in hospitality and tourism industry
Safety stock
Material and Inventory management By Nitin Shekapure
MATERIALS MANAGEMENT
Pom unit 3
Inventory management
Chap7.pptx
Finance 22 1- BSA Budgeting and Finance.ppt
PHC LECTURE 6.pptx
Capacity management
Inventory Management , MRP, JIT and SCM
RDF Quantification-Orientation material for 2014.pptx
Models of inventory control
Inventory management a detailed presentation
Materail Management
Aggregate planning using transportation method a case study in cable industry
INVENTORY MANAGEMENT & CONTROL (NISHA SS).pptx
Planning & Procurement of Spares Accessories Consumables.ppt
Material Managament in Hospital.pptx
Abc analysis
Ad

Recently uploaded (20)

PPTX
COMMUNICATION SKILSS IN NURSING PRACTICE
PPTX
BLS, BCLS Module-A life saving procedure
PDF
Priorities Critical Care Nursing 7th Edition by Urden Stacy Lough Test Bank.pdf
PPTX
Basics of pharmacology (Pharmacology I).pptx
PPTX
Care Facilities Alcatel lucenst Presales
PDF
01. Histology New Classification of histo is clear calssification
PPTX
Medical aspects of impairment including all the domains mentioned in ICF
PPTX
unit1-introduction of nursing education..
PPTX
Vaginal Bleeding and Uterine Fibroids p
PDF
Structure Composition and Mechanical Properties of Australian O.pdf
PPTX
Immunity....(shweta).................pptx
PDF
Assessment of Complications in Patients Maltreated with Fixed Self Cure Acryl...
PPTX
SPIROMETRY and pulmonary function test basic
PPTX
Infection prevention and control for medical students
PDF
2E-Learning-Together...PICS-PCISF con.pdf
PPTX
Nursing Care Aspects for High Risk newborn.pptx
PPTX
Pulmonary Circulation PPT final for easy
PPTX
Trichuris trichiura infection
PDF
NUTRITION THROUGHOUT THE LIFE CYCLE CHILDHOOD -AGEING
PPTX
HEMODYNAMICS - I DERANGEMENTS OF BODY FLUIDS.pptx
COMMUNICATION SKILSS IN NURSING PRACTICE
BLS, BCLS Module-A life saving procedure
Priorities Critical Care Nursing 7th Edition by Urden Stacy Lough Test Bank.pdf
Basics of pharmacology (Pharmacology I).pptx
Care Facilities Alcatel lucenst Presales
01. Histology New Classification of histo is clear calssification
Medical aspects of impairment including all the domains mentioned in ICF
unit1-introduction of nursing education..
Vaginal Bleeding and Uterine Fibroids p
Structure Composition and Mechanical Properties of Australian O.pdf
Immunity....(shweta).................pptx
Assessment of Complications in Patients Maltreated with Fixed Self Cure Acryl...
SPIROMETRY and pulmonary function test basic
Infection prevention and control for medical students
2E-Learning-Together...PICS-PCISF con.pdf
Nursing Care Aspects for High Risk newborn.pptx
Pulmonary Circulation PPT final for easy
Trichuris trichiura infection
NUTRITION THROUGHOUT THE LIFE CYCLE CHILDHOOD -AGEING
HEMODYNAMICS - I DERANGEMENTS OF BODY FLUIDS.pptx
Ad

Managemnt of SP_Chapter 2.pptx: Sp Training

  • 2. Activity 2.1. Individual Reflection Instruction: Recall your previous practice What procedures have you used while developing a supply plan? Time allowed: 5 minute
  • 3. Formula MOS MOS is calculated using the following formula To compute AMC, at least three to six months of continuous consumption quantity of a product is needed. Months of stock (MOS) = stock on hand or order (SOH or SOO)/Average monthly consumption (AMC)
  • 5. Funding/budget gap analysis • If sufficient funding is available, the final quantity to procure for each product will be the same as the quantity to order • if funding is insufficient, the quantification team will need to determine whether additional resources can be mobilized • When it is impossible to mobilize additional resources to procure the full quantities of products required or the forecasted quantity will need to be reduced
  • 6. Scheduling delivery of ordered pharmaceuticals all the quantities required might not necessary be delivered at a time for the reasons; • Insufficient storage capacity, • Seasonality of some diseases, • Available fund covers portion of the required quantity and • The stock on hand quantity is greater than the set maximum stock level.  To accompany these, the arrival of products must be scheduled so that medicines are sustainably available.
  • 7. Scheduling delivery of ordered pharmaceuticals Scheduling depends on • the in house tender process, • supplier/manufacturing lead time, • method of transport, • length of time for port clearance, • quality assurance procedures (pre- and post-shipment) and some other possible conditions. The supplier/manufacturing lead time can vary for each product and must be monitored as part of supplier performance. When lead times are underestimated, the likely results are shortages and more expensive emergency purchases.
  • 8. Scheduling delivery of ordered pharmaceuticals Timely ordering is achieved through efficient pipeline monitoring, which includes • Monitoring stock balances, in terms of quantities and MOS (aggregate of stock at all levels or national stock level) • Comparing stock balances to maximum and minimum stock levels • Identifying potential pipeline problems (quantities needed, stock-outs, balances below minimum or above maximum) Flexible procurement contracts with suppliers are recommended, so that shipment quantities can be adjusted to respond to • uptake in services, • fluctuations in patient demand, • existing stock levels, and • rates of consumption of products.
  • 9. 2.3. Using supply plan Well-developed supply plan have numerous benefits in facilitating the establishment of a resilient supply of products. The benefits are multi-dimensional when considering the involved stakeholders. Mangers • To identify the funding needs and gaps for procurement of the required products • Leverage the sources, amounts, and timing of funding commitments to maximize the use of available resources • Advocate for additional resources, when needed • To monitor and evaluate the process
  • 10. Using supply plan Supply planners • To coordinate procurements and shipment delivery schedules to ensure a continuous supply of commodities • For easily identification specific matters if problems exists • To communicate with manufacturers and suppliers for timely delivery Donors • Will have clear picture of the funding amount • Recognize the existence of funding gap • To evaluate whether their funding disbursement meets the right target • Gives insight where to provide financial or/and technical support
  • 11. Reviewing and updating the supply planning