 Network Techniques: Bar Chart, Mile stone chart,
 work break down
 Structure and preparation of networks.
 Network techniques like PERT and CPM.
 In construction Management, Project Monitoring and resource
allocations through network techniques.
1
 BY MODASSAR ANSARI
 3RD Year
 Department of civil Engineering
 SUBJECT- Construction Technology And Management
 SUBJECT CODE-NCE 603
2
 Gives Pictorial Representation of Activities.
 Activities begin at EST and show their EFT, FF,
TF, Durations, etc.
 Arrows at the relative ends to show dependency.
 Status Line Concept
 Unable to show complete interdependency
between Activities.
 Time-scaled Network Diagrams show complete
interdependency between Activities.
3
 A work breakdown structure (WBS), in project
management and systems engineering, is a deliverable-
oriented decomposition of a project into smaller components
 Dividing complex projects to simpler and manageable tasks is
the process identified as Work Breakdown Structure (WBS).
 Usually, the project managers use this method for simplifying
the project execution. In WBS, much larger tasks are broken
down to manageable chunks of work.
4
 Accurate and readable project organization.
 Accurate assignment of responsibilities to the project team.
 Indicates the project milestones and control points.
 Helps to estimate the cost, time and risk.
 Illustrate the project scope, so the stakeholders can have a
better understanding of the same.
5
 The preceding sections have dealt
comprehensively with the critical path
 method. As a review, these are the steps to
follow in determining a schedule:
 Complete the CPM network diagram.
 Label each activity with its proper description.
 Check network logic.
 Estimate activity durations.
 Identify each event with a unique node number
6
 Determine the early event times by implementing the forward
pass computations.
 Determine the late event times by implementing the backward
pass computations.
 Compute total, free, and independent float, and identify the
critical activities on the network.
 Calculate calendar dates for event and activity times.
 If project duration is not suitable, either revise the network or
reschedule
 the start/completions of the event & activities, and once again
go through Steps 5-8.
7
 If the project duration, starts, and finishes of activities are
suitable,
 arrange the activities in the desired sequence, and tabulate
activity
 identification, description, duration, early and late starts, early
and late finishes, and floats.
 Finally, identify the critical activities.
8
 Includes processes required to ensure that the
project is completed within the approved budget.
 Processes involved are:
A. Resource Planning
B. Cost Estimating
C. Cost Budgeting
D. Cost Control
9
Involves determining what physical resources
(people, equipment, materials etc) and what
quantities of each should be used to perform project
activities.
10
1. Work Breakdown Structure:
A deliverable-oriented grouping of project elements that
organizes and defines the total scope of the project. It
Identifies the project elements that will need resources.
2. Historical Information
3. Scope Statement:
Contains the project justification and the project
objectives.
11
 Work Breakdown Structure
 Resource Requirement
 Resource Rates:
scheduled or non-scheduled
 Activity Duration Estimates
 Historical Information
 Chart of Accounts
12
 Analogous Estimating / Top-down Estimating:
Using the actual cost of a previous, similar project as the
basis for estimating the cost of the current project. It is less
costly but less accurate. (Rough-cost Estimate)
 Parametric Modeling:
Using project characteristics (parameters) in a
mathematical model to predict project costs.
13
 Cost Baseline
A time-phased budget that will be used to measure and
monitor cost performance on the project. It is
developed by summing estimated costs by period and
is usually displayed in the form of an S-curve.
14
Cost Control is concerned with
(a) Influencing the factors which create changes to the
cost baseline to ensure that changes are beneficial.
(b) Determining that the cost baseline has changed
(c) Managing the actual changes when and as they occur
15
An element of work performed during the course
of a project.
An amount of work that can be identified so that
we know what it involves and can recognize,
when it starts and finishes.
An activity normally has an expected duration, an
expected cost, and expected resource
requirements
16
 In the process of planning alternatives are examined and the
best alternative is chosen. The goal of planning is to minimize
resource use (cost) while satisfactorily completing the task .
Efficient use of equipments , material , labor and ensuring
coordinated effort are the basic aim . The outcome of planning
is predetermined course of action. Thus, the planning creates
an orderly sequence of events, defines strategies to be
followed in carrying forth the plan and describes ultimate
disposition of the result. Putting the various activity of the
project in the sequence on the time frame is the process of
scheduling . Scheduling is required for continuous checking of
the project (control), for resource mobilization , to minimize
the cost and use of resources optimally.
17
 Various scheduling techniques have been employed to plan the
activity in sequence in project management . In construction
project , bar chart and critical path method (CPM) have been
widely used . During the planning process , a manager builds
the facilities on paper , thus identities each of the various tasks
and time .During construction , these predetermined course of
action form the basis for monitoring and the checking the
progress of the work . Following steps are followed during
planning , scheduling and control .
18
 Identifying and defining activity
 Defining activity interdependence
 Estimate time and resources for each activity
 Constructing the network,
 Calculations on network for project time earliest start and
finish of activity, resource requirement, etc,
 Project control and project review .
19
 In the network, it is important to know the criticality of the
activity, time available to perform the activity provided date of
completion of a project. In the previous section we have
already talked about various method of obtaining activity
duration. We shall be interested in the question that
 How early we can start the activity.
 How much we can delay the activity such that target date of
completion of project is not affected
 What the time available to perform the activity.
20
 Early start time
 Early finish time
 Latest start time
 Latest finish time
21
 It is the earliest time by which an activity can started.
 Let tij be the activity between events i and j. Let T E
i is the
earliest expected time of the event i then
 Earliest start time is equal is to
EST = T E
i
22
 The earliest finish time of an activity is the time by which an
activity can be finished earliest. The earliest finish time of an
activity is earliest start time plus activity duration.
EFT = EST + activity duration
23
 The latest finish time is the time by which an activity must be
finished such that completion of the project is not delayed the
latest finish time of an activity between events i and j is the
latest allowable event time of
LFT= T L
j
24
 The latest start time is the time by which an activity
must start such that completion of project is not
delayed. The latest start time of an activity between
events i and j is latest finish time minus activity
duration.
LST = LFT – activity duration
25
 In the last reading we have discuss that in the project with art
interested in time available to execute particular task(activity)
during the project period. We shall introduce the concept float
which tells us how much an activity can fluctuate without
affecting the completion of a project. We shall introduce
following float
 Total float.
 Free float.
 Independent float.
 Interfering float.
26
 Total float is the maximum time available during which an
activity can fluctuate. It is maximum time available minus
activity duration. The maximum time available in the
difference between latest finish time minus earliest start
time.
Maximum time available to execute the work = LFT – EST
total float = maximum time avalable – activity duration
= LFT – EST - t ij
= LST – EST
27
 Free float is the time available to fluctuate the activity without
the affecting the succeeding activity. The mean of without
affecting succeeding activity is that the activity must finish
before the earliest occurrence of the head event.
Time available = T E
i – EST
Free float = Time available – activity duration
= T E
i – EST - T E
ij
Free float = T E
i – EFT
28
 It is the time available to fluctuate if the preceding
activities get completed as late as possible and succeeding
activities get started as early as possible.
Hence time available = Te
i – TL
i
Independent float =Minimum time available – activity
duration
= T E
i – T L
i - T E
ij
29
 Interfering float is defined as difference
between total float and free float.
I.F=T.F-F.F
30
 Find critical path
31
3
2 7
4
1 86
5
8-10-12
3-7-9 8-10-12
4-6-8
3-5-6
7-10-15
5-8-12
 Path A 1-2-7-8
 Path B 1-2-6-8
 Path C 1-3-6-8
 Path D 1-4-5-6-8
32
Path Optimistic time Most likely time Pessimistic time
Path A 1-2-7-8 19 26 35
Path B 1-2-6-8 17 26 40
Path C 1-3-6-8 18 27 36
Path D 1-4-5-6-8 19 28 39
 Expected time for each activity
33
6
4 PLo
E
ttt
t


PATH ACTIVITY to tL tP tE ∑tE
A
1-2 6 8 11 8.17
26.342-7 8 10 12 10
7-8 5 8 12 8.17
B
1-2 6 8 11 8.17
26.832-6 4 8 14 8.33
6-8 7 10 15 10.33
C
1-3 3 7 9 6.67
273-6 8 10 12 10
6-8 7 10 15 10.33
D
1-4 5 7 10 7.17
28.33
4-5 4 6 8 6
5-6 3 5 6 4.83
6-8 7 10 15 10.33
Path ‘D’ is critical path
34

More Related Content

DOC
The Techniques Used In Project Managament
PPT
Critical path method (cpm)
ODP
Critical path method
PPTX
Critical Path Method (CPM) & Network Analysis
PPT
Program Evaluation and Review Technique
PDF
pert chart guide for dummies
PPTX
The Critical Path Method
PPTX
The Techniques Used In Project Managament
Critical path method (cpm)
Critical path method
Critical Path Method (CPM) & Network Analysis
Program Evaluation and Review Technique
pert chart guide for dummies
The Critical Path Method

What's hot (20)

PDF
Network analysis cpm module3
DOCX
Economics of project evaluation cpm module2
PPTX
How Project Network Diagram's Can Help You Become A Better Project Manager
PPTX
Industrial engineering unit 2 new
PPT
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PDF
Assignment project scheduling
PDF
Critical Path Analysis
PPT
Planning, scheduling and resource allocation
PPTX
Wbs & Bar chart for Civil engg
PPTX
Construction scheduling
PDF
CPM and PERT
PDF
Project Scheduling and Control Projects
PPT
PDF
Scheduling and Financial Analysis of a High Rise Building
PPTX
Project Management Through Gantt & Pert Chart
PPT
Critical Path Method
PPTX
CPM, Network Analysis A-O-A, A-O-N, Resource management
PPTX
Unit 02 unit – ii project planning and scheduling
PPTX
The Critical Path Method
Network analysis cpm module3
Economics of project evaluation cpm module2
How Project Network Diagram's Can Help You Become A Better Project Manager
Industrial engineering unit 2 new
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
Assignment project scheduling
Critical Path Analysis
Planning, scheduling and resource allocation
Wbs & Bar chart for Civil engg
Construction scheduling
CPM and PERT
Project Scheduling and Control Projects
Scheduling and Financial Analysis of a High Rise Building
Project Management Through Gantt & Pert Chart
Critical Path Method
CPM, Network Analysis A-O-A, A-O-N, Resource management
Unit 02 unit – ii project planning and scheduling
The Critical Path Method
Ad

Viewers also liked (20)

PPT
Nce403 mod unit2
PPTX
Nce403 mod unit3
PPT
Nce403 mod unit5
PPT
Nce403 mod unit4
PPTX
Nce603 mod unit1
PPTX
Nce603 mod unit3
PPT
Nce 403 mod unit1
PDF
AN INTRODUCTION ON LITERATURE OF SMART CITY
PDF
Diffusion of Innovation
PPTX
死ぬときに周りの人になんて言われて送られたいですか?
PDF
Israel primeiros oito anos de filatelia_5
DOCX
article sistem informasi manajemen ahmad khotib,Bagaskoro Sabastian, Bayu Aji...
DOC
CB2016 jan 2017
PPTX
Indifference Curves
PPT
Nce603 mod unit4
PPT
Nce603 mod unit5
PPTX
Vinderhoutewandeling 2017
PPT
Nce403 mod unit2
DOC
продукт субботиной сп дс зол к. гбоу оош №19
DOCX
Resumen economia xix.doc
Nce403 mod unit2
Nce403 mod unit3
Nce403 mod unit5
Nce403 mod unit4
Nce603 mod unit1
Nce603 mod unit3
Nce 403 mod unit1
AN INTRODUCTION ON LITERATURE OF SMART CITY
Diffusion of Innovation
死ぬときに周りの人になんて言われて送られたいですか?
Israel primeiros oito anos de filatelia_5
article sistem informasi manajemen ahmad khotib,Bagaskoro Sabastian, Bayu Aji...
CB2016 jan 2017
Indifference Curves
Nce603 mod unit4
Nce603 mod unit5
Vinderhoutewandeling 2017
Nce403 mod unit2
продукт субботиной сп дс зол к. гбоу оош №19
Resumen economia xix.doc
Ad

Similar to Nce603 mod unit2 (20)

PPTX
PERT and CPM
PPTX
project management-cpm and pert methods for managers
PDF
CPM AND PERT
PDF
Cpm n pert
PPT
Construction scheduling & Cost control
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
PPTX
Network Analysis- CPM ppt..pptx
PDF
pert and crm examples full class course.pdf
PPTX
Chapter 3.pptx
DOCX
PPT
Pert & Cpm
PDF
project managment lesson mechanical engineering
PPTX
Chapter 5-Project Management.pptx
PPTX
MEE 3164 Lecture 8 TMEE 3164 Lecture 8 T..pptx
DOCX
Ii. pert cpm
PPTX
PERT-CPM : PROJECT MANAGEMENT TOOLS
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PDF
Construction Project management
PPT
Network analysis cpm module3 ppt
PPTX
Projectmanagement anupama-Amit Payal
PERT and CPM
project management-cpm and pert methods for managers
CPM AND PERT
Cpm n pert
Construction scheduling & Cost control
Project Management: NETWORK ANALYSIS - CPM and PERT
Network Analysis- CPM ppt..pptx
pert and crm examples full class course.pdf
Chapter 3.pptx
Pert & Cpm
project managment lesson mechanical engineering
Chapter 5-Project Management.pptx
MEE 3164 Lecture 8 TMEE 3164 Lecture 8 T..pptx
Ii. pert cpm
PERT-CPM : PROJECT MANAGEMENT TOOLS
Project Management Techniques ( CPM & PERT Techniques )
Construction Project management
Network analysis cpm module3 ppt
Projectmanagement anupama-Amit Payal

Recently uploaded (20)

PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
web development for engineering and engineering
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
OOP with Java - Java Introduction (Basics)
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Geodesy 1.pptx...............................................
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
DOCX
573137875-Attendance-Management-System-original
PDF
Digital Logic Computer Design lecture notes
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
R24 SURVEYING LAB MANUAL for civil enggi
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
web development for engineering and engineering
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Operating System & Kernel Study Guide-1 - converted.pdf
OOP with Java - Java Introduction (Basics)
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Geodesy 1.pptx...............................................
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Embodied AI: Ushering in the Next Era of Intelligent Systems
Model Code of Practice - Construction Work - 21102022 .pdf
Foundation to blockchain - A guide to Blockchain Tech
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
573137875-Attendance-Management-System-original
Digital Logic Computer Design lecture notes
Automation-in-Manufacturing-Chapter-Introduction.pdf
CYBER-CRIMES AND SECURITY A guide to understanding

Nce603 mod unit2

  • 1.  Network Techniques: Bar Chart, Mile stone chart,  work break down  Structure and preparation of networks.  Network techniques like PERT and CPM.  In construction Management, Project Monitoring and resource allocations through network techniques. 1
  • 2.  BY MODASSAR ANSARI  3RD Year  Department of civil Engineering  SUBJECT- Construction Technology And Management  SUBJECT CODE-NCE 603 2
  • 3.  Gives Pictorial Representation of Activities.  Activities begin at EST and show their EFT, FF, TF, Durations, etc.  Arrows at the relative ends to show dependency.  Status Line Concept  Unable to show complete interdependency between Activities.  Time-scaled Network Diagrams show complete interdependency between Activities. 3
  • 4.  A work breakdown structure (WBS), in project management and systems engineering, is a deliverable- oriented decomposition of a project into smaller components  Dividing complex projects to simpler and manageable tasks is the process identified as Work Breakdown Structure (WBS).  Usually, the project managers use this method for simplifying the project execution. In WBS, much larger tasks are broken down to manageable chunks of work. 4
  • 5.  Accurate and readable project organization.  Accurate assignment of responsibilities to the project team.  Indicates the project milestones and control points.  Helps to estimate the cost, time and risk.  Illustrate the project scope, so the stakeholders can have a better understanding of the same. 5
  • 6.  The preceding sections have dealt comprehensively with the critical path  method. As a review, these are the steps to follow in determining a schedule:  Complete the CPM network diagram.  Label each activity with its proper description.  Check network logic.  Estimate activity durations.  Identify each event with a unique node number 6
  • 7.  Determine the early event times by implementing the forward pass computations.  Determine the late event times by implementing the backward pass computations.  Compute total, free, and independent float, and identify the critical activities on the network.  Calculate calendar dates for event and activity times.  If project duration is not suitable, either revise the network or reschedule  the start/completions of the event & activities, and once again go through Steps 5-8. 7
  • 8.  If the project duration, starts, and finishes of activities are suitable,  arrange the activities in the desired sequence, and tabulate activity  identification, description, duration, early and late starts, early and late finishes, and floats.  Finally, identify the critical activities. 8
  • 9.  Includes processes required to ensure that the project is completed within the approved budget.  Processes involved are: A. Resource Planning B. Cost Estimating C. Cost Budgeting D. Cost Control 9
  • 10. Involves determining what physical resources (people, equipment, materials etc) and what quantities of each should be used to perform project activities. 10
  • 11. 1. Work Breakdown Structure: A deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. It Identifies the project elements that will need resources. 2. Historical Information 3. Scope Statement: Contains the project justification and the project objectives. 11
  • 12.  Work Breakdown Structure  Resource Requirement  Resource Rates: scheduled or non-scheduled  Activity Duration Estimates  Historical Information  Chart of Accounts 12
  • 13.  Analogous Estimating / Top-down Estimating: Using the actual cost of a previous, similar project as the basis for estimating the cost of the current project. It is less costly but less accurate. (Rough-cost Estimate)  Parametric Modeling: Using project characteristics (parameters) in a mathematical model to predict project costs. 13
  • 14.  Cost Baseline A time-phased budget that will be used to measure and monitor cost performance on the project. It is developed by summing estimated costs by period and is usually displayed in the form of an S-curve. 14
  • 15. Cost Control is concerned with (a) Influencing the factors which create changes to the cost baseline to ensure that changes are beneficial. (b) Determining that the cost baseline has changed (c) Managing the actual changes when and as they occur 15
  • 16. An element of work performed during the course of a project. An amount of work that can be identified so that we know what it involves and can recognize, when it starts and finishes. An activity normally has an expected duration, an expected cost, and expected resource requirements 16
  • 17.  In the process of planning alternatives are examined and the best alternative is chosen. The goal of planning is to minimize resource use (cost) while satisfactorily completing the task . Efficient use of equipments , material , labor and ensuring coordinated effort are the basic aim . The outcome of planning is predetermined course of action. Thus, the planning creates an orderly sequence of events, defines strategies to be followed in carrying forth the plan and describes ultimate disposition of the result. Putting the various activity of the project in the sequence on the time frame is the process of scheduling . Scheduling is required for continuous checking of the project (control), for resource mobilization , to minimize the cost and use of resources optimally. 17
  • 18.  Various scheduling techniques have been employed to plan the activity in sequence in project management . In construction project , bar chart and critical path method (CPM) have been widely used . During the planning process , a manager builds the facilities on paper , thus identities each of the various tasks and time .During construction , these predetermined course of action form the basis for monitoring and the checking the progress of the work . Following steps are followed during planning , scheduling and control . 18
  • 19.  Identifying and defining activity  Defining activity interdependence  Estimate time and resources for each activity  Constructing the network,  Calculations on network for project time earliest start and finish of activity, resource requirement, etc,  Project control and project review . 19
  • 20.  In the network, it is important to know the criticality of the activity, time available to perform the activity provided date of completion of a project. In the previous section we have already talked about various method of obtaining activity duration. We shall be interested in the question that  How early we can start the activity.  How much we can delay the activity such that target date of completion of project is not affected  What the time available to perform the activity. 20
  • 21.  Early start time  Early finish time  Latest start time  Latest finish time 21
  • 22.  It is the earliest time by which an activity can started.  Let tij be the activity between events i and j. Let T E i is the earliest expected time of the event i then  Earliest start time is equal is to EST = T E i 22
  • 23.  The earliest finish time of an activity is the time by which an activity can be finished earliest. The earliest finish time of an activity is earliest start time plus activity duration. EFT = EST + activity duration 23
  • 24.  The latest finish time is the time by which an activity must be finished such that completion of the project is not delayed the latest finish time of an activity between events i and j is the latest allowable event time of LFT= T L j 24
  • 25.  The latest start time is the time by which an activity must start such that completion of project is not delayed. The latest start time of an activity between events i and j is latest finish time minus activity duration. LST = LFT – activity duration 25
  • 26.  In the last reading we have discuss that in the project with art interested in time available to execute particular task(activity) during the project period. We shall introduce the concept float which tells us how much an activity can fluctuate without affecting the completion of a project. We shall introduce following float  Total float.  Free float.  Independent float.  Interfering float. 26
  • 27.  Total float is the maximum time available during which an activity can fluctuate. It is maximum time available minus activity duration. The maximum time available in the difference between latest finish time minus earliest start time. Maximum time available to execute the work = LFT – EST total float = maximum time avalable – activity duration = LFT – EST - t ij = LST – EST 27
  • 28.  Free float is the time available to fluctuate the activity without the affecting the succeeding activity. The mean of without affecting succeeding activity is that the activity must finish before the earliest occurrence of the head event. Time available = T E i – EST Free float = Time available – activity duration = T E i – EST - T E ij Free float = T E i – EFT 28
  • 29.  It is the time available to fluctuate if the preceding activities get completed as late as possible and succeeding activities get started as early as possible. Hence time available = Te i – TL i Independent float =Minimum time available – activity duration = T E i – T L i - T E ij 29
  • 30.  Interfering float is defined as difference between total float and free float. I.F=T.F-F.F 30
  • 31.  Find critical path 31 3 2 7 4 1 86 5 8-10-12 3-7-9 8-10-12 4-6-8 3-5-6 7-10-15 5-8-12
  • 32.  Path A 1-2-7-8  Path B 1-2-6-8  Path C 1-3-6-8  Path D 1-4-5-6-8 32 Path Optimistic time Most likely time Pessimistic time Path A 1-2-7-8 19 26 35 Path B 1-2-6-8 17 26 40 Path C 1-3-6-8 18 27 36 Path D 1-4-5-6-8 19 28 39
  • 33.  Expected time for each activity 33 6 4 PLo E ttt t  
  • 34. PATH ACTIVITY to tL tP tE ∑tE A 1-2 6 8 11 8.17 26.342-7 8 10 12 10 7-8 5 8 12 8.17 B 1-2 6 8 11 8.17 26.832-6 4 8 14 8.33 6-8 7 10 15 10.33 C 1-3 3 7 9 6.67 273-6 8 10 12 10 6-8 7 10 15 10.33 D 1-4 5 7 10 7.17 28.33 4-5 4 6 8 6 5-6 3 5 6 4.83 6-8 7 10 15 10.33 Path ‘D’ is critical path 34