This document contains a risk register for an overhead transmission line project with 16 identified risks. The top 3 risks are:
1) Changes to the approved foundation design after work has commenced could delay the project due to changes in scope.
2) Introduction of new software not specified in the contract could delay the project as it would require additional engineering work and study time.
3) Passing new comments on design revisions may lead to design delays and delays in execution if not properly managed.