Operator training is critical in
transitioning project upgrades to
operation with minimum disruption
Juan Jorge
Aurecon Regional Manager – South America
Project Value Still Being Destroyed!
• Many corporations have implemented front end loading studies
• Despite recent improvements in front end loading only 2.5% of projects meet
budget and schedule targets (PWC 2012)
• 69% of projects don’t make budget
• 57% of projects don’t make schedule
• Current measures are not totally effective!
Up to 30% of project value being
destroyed in project delivery!
Value Depletion Due to Poor
Operational Readiness (Deloitte)
Critical Issues in Operational Support
• Operational, financial and risk assumptions surrounding the existing operation may not be
valid after the upgrade.
• A requirement to continue production while the upgrades are carried out.
• Interfacing with existing equipment requires additional effort with regard to the position and
condition of existing plant.
• Matching the performance (and current condition) of existing equipment, or modifying its
operating regime, to ensure that it can support the performance of the new plant being
installed.
• Translating Original Equipment Manufacturer (OEM) manuals into a format which is
acceptable to operations personnel and aligned to CMMS.
• Interfacing with current operational restrictions, statutory requirements.
• Aligning with and supporting the cultural and behavioural expectations of the operation
A Systematic Approach
• Operational readiness must be linked to each project stage
• Operational elements must be assessed and prioritised
Identification of Focus Areas
• A targeted audit tool can be used to assess weaknesses and omissions
• Operational elements must be assessed and prioritised for targeted delivery
Functional Elements of Targeted Areas
• Targeted areas from the audit will need to organised into functional elements
Systems and operator training developed to meet industry standards
Elements Divided into Deliverables
• The functional elements can be further broken down into deliverables
• Operations person responsible for each deliverable identified (RACI)
• Appropriate persons trained in relevant elements
Importance of Experienced Coaches
• Focus on knowledge transfer not rote learning
• Focus on experienced trainers who can provide
practical examples
• Training needs to be practical and tailored to
culture and stage of operator development
• Trainers who can use the principles of
knowledge transfer and not just learning
methods
Importance of Operator Involvement
• Operator understanding of the design basis and operational principles
used in design;
• Planned upgrade maintenance needs and regimes understood so that
down time for “trial and error” is minimised;
• The design provides for efficient operational requirements and
maintenance by taking such requirements into account
• Operators have “ownership” of the final design and installation through
understanding and participating in the design decisions, and inevitable
trade-offs between costs and “nice-to-haves”.
Change Control – Systems and People
• Essential link between engineering and operational stages
• Normally poorly done
• Change register should provide link between design phase and operational phase
• Can use an independent committee to vet changes notices
• Change management processes for people aligned to project phases and the “new
state”
Case Study 1 – Coal Mine Indonesia
 Good upgrade planning/ engineering and
debottlenecking
X Let Down by lack of operator re-training and new
operating systems for upgraded facilities
Case Study 1 – Coal Mine Indonesia
Situation
•Established open cut coal mine Required increase in throughput from
17Mtpa to 35Mtpa
•Debottlenecking required to eliminate production restrictions
•Debottlenecking involved cooperation with OEMs
•13 km Overland Conveyor (OLC) was upgraded through speed increase to
8.7m/s
•Main commissioning / operational issue was instability in the OLC
•Operators had not been trained in the operating differences with respect to
new conveyor
Case Study 1 – Coal Mine Indonesia
What happened in practice
•Ramping up to full operational throughput rate loading onto the OLC
•Dealing with OLC instabilities when they start to occur
What would have been better
•Planning and management of maintenance shutdowns to minimise the time
between starting and stopping the OLC
•Management of stockpiling and machines at the mine and port to maximise
utilisation and minimise starting and stopping of the conveyor
Case Study 1 – Coal Mine Indonesia
Outcomes – Lessons Learned
•Output increased to the upgrade capacity over an extended six month
period
•Shutdowns and planned maintenance function could have been much more
organised pre-commissioning of the OLC
•Additional modelling and further training on how the OLC affected
operations downstream would have led to a more rapid improvement
•Change of operational approach over time to direct load coal from crusher
to ship as much of the time as possible for maximum efficiency
Situation
•Greenfield coal fired 1400MW power
station in Malaysia
•Requirement to commission plant over a
short time
•Company requirement to develop a new
operating culture – similar to a self directed
team style
•Operator selection not based on any
previous power station experience
Training and mentoring leading to fast track
commissioning and ramp up to operations
Case Study 2 – Jimah Power Station
Case Study 2 – Jimah Power Station
Solution
•The operators trained in power station operation in
four separate sessions
•The operators engaged early during construction
process
• The operators and maintenance personnel were heavily involved in the writing
and translation of the OEM manuals and in deciding operating methodology
• External assistance was used as required to overview the team development
of policy and procedures and to assist in commissioning
• A mentoring program was established and it was withdrawn gradually as
• competencies and culture grew
Case Study 2 –Jimah Power Station
Outcome
•Commissioning of the station took place to schedule and with no major
mishaps
•The operating culture has grown under the mentoring scheme
•Reviews were carried out for the first few years to assess progress and
ensure embedding
•The degree of mentoring has been cut back to occasional visits to provide
targeted development
Case Study 3 –Nickel Mine Koniambo
Situation
•Greenfield fluidised bed power station in New
Caledonia
•Operating personnel selected from local
population – requirement to move to self
sufficiency
•External assistance in framing operating
procedures into ESI Generation Training Package
•Local personnel part of the team developing
procedures and training for start up
Maximised benefit of local personnel through up
skilling in advance of commissioning and proactive
knowledge transfer programme
Case Study 3 –Nickel Mine Koniambo
Solution
•External assistance in building the training
framework and training requirements
•External consultants worked with local
personnel well ahead of commissioning to
develop the work packages
•Training packages were delivered with external
assistance
•External ongoing support on a required basis to
support the work
Case Study 3 –Nickel Mine Koniambo
Outcomes
•Maximised the rate and extent of knowledge transfer from expatriate staff
to internal staff and enable self-sufficiency
•Cultural differences, language, attitudes, numeracy and literacy
requirements were identified and the staff development process tailored to
suit
•Rapid local engagement and self-sufficiency
•Value-for-money in terms of set up and through-life-support
•Integrated operations processes and procedures
Conclusions
Brownfield upgrades require systematic and integrated operational readiness to optimise
results:
•Well-defined framework outlining the essential elements of operational support and the
interface with the project delivery stages.
•Auditing tool to assess weaknesses in operational aspects of the project
•A strong operational support system with the necessary.
•Strong integrated lead teams and disciplined change processes.
•Systems must be flexible and they must cater for the prevailing or desired workplace culture,
level of maturity and organisational structure.
•The operational support mechanism must span the entire project timeframe and they must
continue to support the operational staff post implementation.

More Related Content

PDF
Manufacturing Excellence - Visual Factory
PDF
Takt Time.pdf
PPT
5 why training 21 oct2010
PDF
5 Steps to implementing Lean
PPTX
Oee (overall equipment effectifness)
PPTX
Process Safety Management in Design, Construction & Commissioning | Lalit K...
PPTX
Fault Tree Analysis FTA Training
PPTX
Total productive maintenance(TPM)
Manufacturing Excellence - Visual Factory
Takt Time.pdf
5 why training 21 oct2010
5 Steps to implementing Lean
Oee (overall equipment effectifness)
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Fault Tree Analysis FTA Training
Total productive maintenance(TPM)

What's hot (20)

PPT
Copq benefits of correct measurement (for slideshare)
PPTX
Kaizen presentation for workers
PPTX
Corrective Action And Root Cause Analysis
PPTX
PRESENTASI KAIZEN.pptx
PDF
TPM for lean manufacturing | lean tools
PDF
Failure Mode & Effect Analysis
PPTX
PPTX
FMEA Introduction.ppt
PDF
Single minute exchange of dies - quick changeover
PDF
Cleaning Methodology and Validation
PPSX
Trouble Shooting of Chemical Process Industry
PPT
My machine camp
PDF
Overall Equipment Effectiveness
PDF
Gemba Kaizen for Lean manufacturing | Chap1:Kaizen Basic Education | lean t...
PPTX
Control-Plan-Training with Example for .pptx
PDF
Conquering the Cost of Poor Quality
PDF
Payload Core Product Line Accelerates ADC Clinical Timelines
PDF
Henkaten Fundamentals - English.pdf
Copq benefits of correct measurement (for slideshare)
Kaizen presentation for workers
Corrective Action And Root Cause Analysis
PRESENTASI KAIZEN.pptx
TPM for lean manufacturing | lean tools
Failure Mode & Effect Analysis
FMEA Introduction.ppt
Single minute exchange of dies - quick changeover
Cleaning Methodology and Validation
Trouble Shooting of Chemical Process Industry
My machine camp
Overall Equipment Effectiveness
Gemba Kaizen for Lean manufacturing | Chap1:Kaizen Basic Education | lean t...
Control-Plan-Training with Example for .pptx
Conquering the Cost of Poor Quality
Payload Core Product Line Accelerates ADC Clinical Timelines
Henkaten Fundamentals - English.pdf
Ad

Similar to Operational Readiness and Importance of Operator Training (20)

PPTX
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
PPTX
Transitioning from Project to Operations in CSG to LNG
PDF
LanningJeffreyresumerev
PPTX
Construction Management in Developing Countries, Lecture 8
DOC
CV D. Maimbolwa
DOC
JackmcdowellCV
DOC
Abhinav Aditya
DOC
Sean_Hougham_Resume
PPTX
Chapter 8 Project Operation and Maintenance in Developing Countries 2024.pptx
POTX
Case studies: Predictive maintenance in the petrochemical industry
DOC
Anuraj panicker
DOC
Anuraj Panicker
DOC
Resume of Mohamed Sajid Maqba_2016
PDF
The study of Perpetual Evolution_Group 5_ Final Project_PPT.pdf
PPTX
Presentationresume minggu 1
DOC
Manoj kulkarni.docx
PPTX
Operations management
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Transitioning from Project to Operations in CSG to LNG
LanningJeffreyresumerev
Construction Management in Developing Countries, Lecture 8
CV D. Maimbolwa
JackmcdowellCV
Abhinav Aditya
Sean_Hougham_Resume
Chapter 8 Project Operation and Maintenance in Developing Countries 2024.pptx
Case studies: Predictive maintenance in the petrochemical industry
Anuraj panicker
Anuraj Panicker
Resume of Mohamed Sajid Maqba_2016
The study of Perpetual Evolution_Group 5_ Final Project_PPT.pdf
Presentationresume minggu 1
Manoj kulkarni.docx
Operations management
Ad

Recently uploaded (20)

PPTX
Understanding_Digital_Forensics_Presentation.pptx
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Electronic commerce courselecture one. Pdf
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
cuic standard and advanced reporting.pdf
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PDF
KodekX | Application Modernization Development
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PPTX
Big Data Technologies - Introduction.pptx
PPTX
MYSQL Presentation for SQL database connectivity
PDF
NewMind AI Weekly Chronicles - August'25 Week I
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
Machine learning based COVID-19 study performance prediction
Understanding_Digital_Forensics_Presentation.pptx
20250228 LYD VKU AI Blended-Learning.pptx
Electronic commerce courselecture one. Pdf
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
cuic standard and advanced reporting.pdf
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
KodekX | Application Modernization Development
Diabetes mellitus diagnosis method based random forest with bat algorithm
Big Data Technologies - Introduction.pptx
MYSQL Presentation for SQL database connectivity
NewMind AI Weekly Chronicles - August'25 Week I
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Per capita expenditure prediction using model stacking based on satellite ima...
Mobile App Security Testing_ A Comprehensive Guide.pdf
The Rise and Fall of 3GPP – Time for a Sabbatical?
Network Security Unit 5.pdf for BCA BBA.
Machine learning based COVID-19 study performance prediction

Operational Readiness and Importance of Operator Training

  • 1. Operator training is critical in transitioning project upgrades to operation with minimum disruption Juan Jorge Aurecon Regional Manager – South America
  • 2. Project Value Still Being Destroyed! • Many corporations have implemented front end loading studies • Despite recent improvements in front end loading only 2.5% of projects meet budget and schedule targets (PWC 2012) • 69% of projects don’t make budget • 57% of projects don’t make schedule • Current measures are not totally effective!
  • 3. Up to 30% of project value being destroyed in project delivery! Value Depletion Due to Poor Operational Readiness (Deloitte)
  • 4. Critical Issues in Operational Support • Operational, financial and risk assumptions surrounding the existing operation may not be valid after the upgrade. • A requirement to continue production while the upgrades are carried out. • Interfacing with existing equipment requires additional effort with regard to the position and condition of existing plant. • Matching the performance (and current condition) of existing equipment, or modifying its operating regime, to ensure that it can support the performance of the new plant being installed. • Translating Original Equipment Manufacturer (OEM) manuals into a format which is acceptable to operations personnel and aligned to CMMS. • Interfacing with current operational restrictions, statutory requirements. • Aligning with and supporting the cultural and behavioural expectations of the operation
  • 5. A Systematic Approach • Operational readiness must be linked to each project stage • Operational elements must be assessed and prioritised
  • 6. Identification of Focus Areas • A targeted audit tool can be used to assess weaknesses and omissions • Operational elements must be assessed and prioritised for targeted delivery
  • 7. Functional Elements of Targeted Areas • Targeted areas from the audit will need to organised into functional elements Systems and operator training developed to meet industry standards
  • 8. Elements Divided into Deliverables • The functional elements can be further broken down into deliverables • Operations person responsible for each deliverable identified (RACI) • Appropriate persons trained in relevant elements
  • 9. Importance of Experienced Coaches • Focus on knowledge transfer not rote learning • Focus on experienced trainers who can provide practical examples • Training needs to be practical and tailored to culture and stage of operator development • Trainers who can use the principles of knowledge transfer and not just learning methods
  • 10. Importance of Operator Involvement • Operator understanding of the design basis and operational principles used in design; • Planned upgrade maintenance needs and regimes understood so that down time for “trial and error” is minimised; • The design provides for efficient operational requirements and maintenance by taking such requirements into account • Operators have “ownership” of the final design and installation through understanding and participating in the design decisions, and inevitable trade-offs between costs and “nice-to-haves”.
  • 11. Change Control – Systems and People • Essential link between engineering and operational stages • Normally poorly done • Change register should provide link between design phase and operational phase • Can use an independent committee to vet changes notices • Change management processes for people aligned to project phases and the “new state”
  • 12. Case Study 1 – Coal Mine Indonesia  Good upgrade planning/ engineering and debottlenecking X Let Down by lack of operator re-training and new operating systems for upgraded facilities
  • 13. Case Study 1 – Coal Mine Indonesia Situation •Established open cut coal mine Required increase in throughput from 17Mtpa to 35Mtpa •Debottlenecking required to eliminate production restrictions •Debottlenecking involved cooperation with OEMs •13 km Overland Conveyor (OLC) was upgraded through speed increase to 8.7m/s •Main commissioning / operational issue was instability in the OLC •Operators had not been trained in the operating differences with respect to new conveyor
  • 14. Case Study 1 – Coal Mine Indonesia What happened in practice •Ramping up to full operational throughput rate loading onto the OLC •Dealing with OLC instabilities when they start to occur What would have been better •Planning and management of maintenance shutdowns to minimise the time between starting and stopping the OLC •Management of stockpiling and machines at the mine and port to maximise utilisation and minimise starting and stopping of the conveyor
  • 15. Case Study 1 – Coal Mine Indonesia Outcomes – Lessons Learned •Output increased to the upgrade capacity over an extended six month period •Shutdowns and planned maintenance function could have been much more organised pre-commissioning of the OLC •Additional modelling and further training on how the OLC affected operations downstream would have led to a more rapid improvement •Change of operational approach over time to direct load coal from crusher to ship as much of the time as possible for maximum efficiency
  • 16. Situation •Greenfield coal fired 1400MW power station in Malaysia •Requirement to commission plant over a short time •Company requirement to develop a new operating culture – similar to a self directed team style •Operator selection not based on any previous power station experience Training and mentoring leading to fast track commissioning and ramp up to operations Case Study 2 – Jimah Power Station
  • 17. Case Study 2 – Jimah Power Station Solution •The operators trained in power station operation in four separate sessions •The operators engaged early during construction process • The operators and maintenance personnel were heavily involved in the writing and translation of the OEM manuals and in deciding operating methodology • External assistance was used as required to overview the team development of policy and procedures and to assist in commissioning • A mentoring program was established and it was withdrawn gradually as • competencies and culture grew
  • 18. Case Study 2 –Jimah Power Station Outcome •Commissioning of the station took place to schedule and with no major mishaps •The operating culture has grown under the mentoring scheme •Reviews were carried out for the first few years to assess progress and ensure embedding •The degree of mentoring has been cut back to occasional visits to provide targeted development
  • 19. Case Study 3 –Nickel Mine Koniambo Situation •Greenfield fluidised bed power station in New Caledonia •Operating personnel selected from local population – requirement to move to self sufficiency •External assistance in framing operating procedures into ESI Generation Training Package •Local personnel part of the team developing procedures and training for start up Maximised benefit of local personnel through up skilling in advance of commissioning and proactive knowledge transfer programme
  • 20. Case Study 3 –Nickel Mine Koniambo Solution •External assistance in building the training framework and training requirements •External consultants worked with local personnel well ahead of commissioning to develop the work packages •Training packages were delivered with external assistance •External ongoing support on a required basis to support the work
  • 21. Case Study 3 –Nickel Mine Koniambo Outcomes •Maximised the rate and extent of knowledge transfer from expatriate staff to internal staff and enable self-sufficiency •Cultural differences, language, attitudes, numeracy and literacy requirements were identified and the staff development process tailored to suit •Rapid local engagement and self-sufficiency •Value-for-money in terms of set up and through-life-support •Integrated operations processes and procedures
  • 22. Conclusions Brownfield upgrades require systematic and integrated operational readiness to optimise results: •Well-defined framework outlining the essential elements of operational support and the interface with the project delivery stages. •Auditing tool to assess weaknesses in operational aspects of the project •A strong operational support system with the necessary. •Strong integrated lead teams and disciplined change processes. •Systems must be flexible and they must cater for the prevailing or desired workplace culture, level of maturity and organisational structure. •The operational support mechanism must span the entire project timeframe and they must continue to support the operational staff post implementation.