Chapter 8
Project Operation and Maintenance
(in developing countries)
(4 hours)
Prof. Dr. Hari Krishna Shrestha
Center for Postgraduate Studies
Nepal Engineering College
Changunarayan Municipality, Kathmandu
Importance of O&M
• Hundreds of projects around the world demonstrate how the newly built
infrastructure deteriorates after the project’s termination. Therefore, it is
imperative to plan for operation and maintenance (O&M)…
• O&M activities encompass technical, managerial, social, financial and
institutional issues. O&M is a crucial element of sustainability, and a frequent
cause of failure of service facilities in the past. Many failures are not technical
ones. They may result from poor planning, inadequate cost recovery, or the
outreach inadequacies of centralised agencies (LSHTM/WEDC 1998).
• O&M has been neglected in the past, or been discussed and introduced only
after a project was completed. Delay in applying O&M has adversely affected
the credibility of the investments made, the functioning of the services, the
well-being of rural populations, and the development of further projects.
• Importance of O&M has gained considerable visibility over the past few years,
and it appears that policy-makers and project designers are now more
conscious of the direct links between improved O&M practices and the
sustainability of project services. There is also greater recognition of the need
to approach these projects in a comprehensive way, encompassing not only the
design and construction but also post-construction activities (BRIKKE 2000).
Source: http://www.sswm.info/category/planning-process-tools/ensuring-sustainability/tools-ensure-
sustainability/ensure-sustain-4
Construction Project Operation
• Construction Project is executed to create something new to achieve a specific
objective.
• Operation begins once the construction phase is completed.
• Operations are the ongoing execution of activities that produce the same
output, or provide a repetitive service.
• Operation is necessary to maintain and sustain the system and achieve the goals.
• Operations are permanent in nature, and their only constraint is to make profit
for the organization.
• O&M refers to all of the activities needed to run a project/scheme, except for
the construction of new facilities. The overall aim of O&M is to ensure:
• efficiency, • effectiveness and • sustainability
of project facilities (adapted from CASTRO 2009).
Operation consists of:
• Smooth running of a project without any unplanned interruptions throughout its
lifespan.
• overseeing, designing, and redesigning daily operations
• managing process that converts inputs into outputs.
Objective of Project Operation
• To have regular expected level of goods and services from the
project
• At the right time (effectively)
• In reliable and sustainable manner (involves technical,
financial, social and environmental issues)
• With least cost (efficiently)
Potential Thesis Topic:
Analysis of Operation Model of Middle Marsyangdi HEP (or any other institute/project/line
agency)
How is it run on day to day basis? Does it have an operation manual (OM), and does it
cover all aspects of operation (technical, human resource, finance, social, environmental,
public relation, legal? Is the OM followed? Are the staff members aware of OM, and the
way to use it? How often the OM is updated, who updates it, are they trained? Does it
require updating? What are the weaknesses and strengths in the manual? How can the HEP
be made more efficient by improving the manual? Is the MM HEP’s OM very different than
manuals of other similar projects? What lessors can be learned from comparative analysis
of different manuals?
Will the MM HEP support preparation of your thesis, if it does not have OM yet?
Poor Project Operation can result in Project failure
Reasons for poor project operation:
• Lack of clear goals, objectives
• Goal incompatibility – conflict in objectives
• Lack of required technical skill
• Poor management skill
• Poor quality materials used in the project
• Material sizes used are not readily available
• Lack of updated operation manual or improper
manual use
Operational Activities
• Planning the operation
• Implementing the plan
• Monitoring the operation
• Adjustment of the plan in response to
monitoring
Potential thesis topic: Trend of operation cost in
irrigation/hydropower/micro-hydro/water supply projects of Nepal;
Factors affecting operation costs in infrastructure development
projects in Nepal
Operation cost comparison in private vs. government vs.
community managed HP/WS/Sanitation/Irrigation/Housing projects
Maintenance
• Maintenance involves the technical
activities, planned or reactive, which
are needed to keep the system working.
Maintenance requires skills, tools and
spare parts (Carter 2009).
• Includes all actions which have the
objective of retaining or restoring an
item in or to a state in which it can
perform its required functions.
• Reduces the deterioration of asset and
prolongs its life, reduces operating cost,
pushes back need of much expensive
rehabilitation and reconstruction.
Objectives of Project Maintenance
• Increase economic life
• Maximize availability and reliability of all assets
• Extend life of asset
• Prevent system deterioration (structural, mechanical)
• Ensure operational readiness of all the
equipment/components
• Reduce services and problem in management by
reducing frequency and cost of rehabilitation
• Minimize frequency and severity of interruptions in
operation process.
• Enhance personnel safety
• Reduce project downtime
• Better project operation
Planned versus Emergency Maintenance
Planned (Preventive and Corrective) Maintenance
• Routine maintenance: small and simple maintenance works,
carried on regular basis, not requiring forecast and assessment of
specific nature.
• Recurrent maintenance: generally higher interval of time than
routine maintenance; may need identification and preparation of
cost estimate.
• Periodic maintenance: maintenance works carried out in intervals
of years. Normally larger maintenance, using skilled human
resource; identification and preparation of cost estimate needed
before starting.
Emergency (Reactive) maintenance: carried out immediately after
unwanted/unplanned incident or after public complaint; can be
due to natural or human induced disasters.
A stitch in time saves nine.
Preventive and Corrective Maintenance
• Preventive maintenance: includes work that is planned and carried out
on a regular basis to maintain and keep the infrastructure in good
condition, such as network inspection, flushing of the well, cleaning and
greasing of mechanical parts and replacement of items with a limited
lifespan. It sometimes also includes minor repairs and replacement as
dictated by the routine examinations.
• Preventive maintenance is conducted before a breakdown occurs.
• Preventive maintenance is effective in preventing age (or fatigue) related
failures.
• Corrective maintenance: replacing or repairing something that was
done incorrectly or that needs to be changed; an example is the
reallocation of a pipe route or replacement of a faulty pump.
• Corrective maintenance is conducted after a breakage has occurred.
Normally more costly than preventive maintenance because
failure/breakdown itself causes multiple damage in other parts also.
Preventive maintenance is conducted to keep equipment working and/or extend the life of
the equipment.
Corrective maintenance (repair) is conducted to get equipment working again.
Types of Maintenance
Maintenance
Planned
Preventive
Routine Recurrent Periodic
Predictive Corrective
Shutdown Breakdown
Unplanned/
Reactive
Emergency
planned corrective: Regular budget allocation (cumulative) for sudden project shut down;
projected downtime in hydropower or water supply projects, overhaul or replace bridge
after its service life, replace major components after design life.
Planned Maintenance Management System
• Restoration of asset is a challenge which can
be achieved by a planned maintenance
management system (PMMS), comprising of a
series of interdependent routine, recurrent,
periodic and emergency activities.
• The key to ensuring effective maintenance is
to make certain that responsibilities are
clearly defined and maintenance personnel
have the tools and skills to do their job
effectively. It is also essential to schedule
preventive maintenance.
Can you develop PMMS for your organization, as an output of your thesis?
Functional Status of the Projects
S.N Status Criteria No of
Schemes
Covered
HHs
Coverage
(%)
1 Well managed projects 7,464 373,295 17.91
2 Minor repaired required 16,935 809,996 38.85
3 Major repair required 4,375 246,481 11.82
4 To be rehabilitated 4,967 437,800 21.00
5 To be reconstructed 3,438 189,756 9.10
6 Projects not possible for re-
operation
467 27,008 1.30
7 Others 15 530 0.03
Total 38,307 2,084,866 100
Source: Nationwide Coverage and Functionality Status of Water Supply and Sanitation in
Nepal, Final Report, National Management Information Project (NMIP), Department of
Water Supply and Sewerage (DWSS), Panipokhari, Kathmandu, March 2011
Design aspect of O&M
• Ease of O&M should be made an integral part
of project design
• Design optimization to reduce O&M cost
• Level of technology chosen in the design
should be suitable for easier O&M (rural vs.
urban, local vs. central)
• Project components/parts chosen in the
design should be available for O&M
• Standardization of equipments/parts will ease
O&M
Community Management for O&M
For the projects owned and operated by community:
• community ownership and management approach
facilitates effective O&M
• End-users directly responsible for the O&M
• “owner’s manual” prepared by the contractor and
engineer at the onset of the planning process, keeping
the community O&M in focus:
– schedule and procedures for maintenance
– methods to carry out tasks such as bookkeeping, paying
employees, collecting bills (utility management),
inspection, refurbishments, replacement of parts, etc.
– What to do? When to do? How to do? Whom to contact?
Contact numbers…
Capacity Building for O&M
• Correct, unambiguous information at the right
time required for proper operation
• Training of “how to use correctly”, and do’s and
don’ts for proper operation
• training on technical matters, accounting and
simple financial management, basic contract
procedures, and monitoring and reporting
• Training to local officials
• Training to local technicians and O&M crew
• ToT to NGOs
Organizing and Planning O&M
• Organising for O&M does not represent a huge
task, but it does require certain level of planning,
commitment and monitoring. The aspects to be
organised are:
• What: the activity which is to be carried out
• When: the frequency of this activity
• Who: the human resources required for the task
• With what: what are the logistical support
(materials, spare parts, tools and equipments)
needed.
Potential thesis topic:
Trend of maintenance cost in irrigation/hydropower/micro-hydro/water supply
projects of Nepal;
Factors affecting maintenance costs in infrastructure development projects in Nepal
Maintenance cost comparison in private vs. government vs. community managed
projects
Example table for the type of tools which have to be developed
to support the O&M of a new infrastructure. The example relates
to the O&M of a septic tank (adapted from CASTRO 2009):
O&M Manual
O&M manual is a living document. It should be flexible to accommodate changes,
periodically updated based on experience and as organization matures.
O&M manual may include topics such as:
• Installation and configuration operations and associated definitions
• System maintenance, updates and upgrade policies, procedures, and schedules
• Proper and improper handling and maintenance of different types of equipment
• Database scheme, network typology, and flowcharts used to illustrate items such
as system design, data communications, program logic, and the relationship
between network nodes.
• Instructions for opening/closing and starting/stopping applications, devices, and
services under various conditions
• Procedure and sequences describing backup routines, media type, storage
locations, and schedules
• Security controls for staff, facilities, infrastructure and emergency response
procedures
• Frequently asked questions and troubleshooting techniques for common issues
• Roles, responsibilities and contact information for key personnel and support staff
• Other miscellaneous and/or relevant items
Characteristics of O&M Manual
• Easy: to understand, easy language, unambiguous
• Accessibility: stakeholders should have easy access
(hardcopy/softcopy, website)
• Jargon: no jargon, not loaded with abbreviations
• Regulations: related regulations, acts should be provided
• Manuals: multiple copies of the manuals, department-wise manuals
• Style: consistent style, text, sectioning
• Author/Editor: author and editors to be different persons
• Align: align with policies and procedures of organization
• Update: should be updated based on experience
• Educate: Train stakeholders and staff, continually reinforce O&M
practices
• Lessons: review previously used O&M, learn lessons from O&M
implementers, and update
Activities in preparation of an O&M Manual
• Identify the types of O&M required
• Identify information sources and information to be used in the
manual
• Identify and engage appropriate stakeholders and subject matter
experts (SME)
• Identify and incorporate SME inputs
• Develop each O&M manual
• Obtain approval from stakeholders and publish manual
• Test, train and exercise to reinforce and validate manual
• Prepare personnel through training and awareness campaign
• Document lessons learned and incorporate them in updated O&M
manual
• Treat O&M manual as living document and update them regularly,
to remain current with operational and system changes
Some common types of O&M Manual
• Product installation and maintenance manuals
• System description, operations, backup and recovery manuals
• Data and software administration manuals
• Human resources and personnel manual
• Help desk support manuals
• User Manuals
• Emergency and safety manual
• Quick reference guide
• Job aids
• Run book
Source: CDC Unified Process Practices Guide, 2008, O&M Manual, Department of
Health and Human Services, USA
Let us assign presentation topic. Presentation to be prepared and made in Nov 28 & 30,
2016. Report in MS Word format, by Dec. 7, 2016. (Tentative)

More Related Content

PDF
05 Project Monitoring & Cost Control
PPTX
Construction Management in Developing Countries, Lecture 5
PDF
Construction Project management
PPT
09. Project Cost Management
PPTX
Construction phases
PPTX
Construction project management
PPT
050 Intergrating Constructability with Lean Construction
PPTX
Project life cycle
05 Project Monitoring & Cost Control
Construction Management in Developing Countries, Lecture 5
Construction Project management
09. Project Cost Management
Construction phases
Construction project management
050 Intergrating Constructability with Lean Construction
Project life cycle

What's hot (20)

PPT
2.project lifecycle
PDF
Project Resource Management
PPT
Construction scheduling & Cost control
PPT
Project Planning Scheduling
PPTX
Introduction to Project Management
PPTX
Project Management Process and Its Phases
PPTX
ppt for primevera
PPT
Project Planning
PPTX
Introduction to Lean Construction
PDF
Basics of project management
PPT
Project Definition
PDF
02 Construction Projects
PDF
Introduction to Project Management
PDF
Project management in construction
PDF
Scheduling by using microsoft project 2013
PPTX
Brief introduction to project management and project management tools
PPTX
Project management and control
PDF
Topic 14 - Project Team Management.pdf
PPTX
Ms project 2016 overview
DOCX
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
2.project lifecycle
Project Resource Management
Construction scheduling & Cost control
Project Planning Scheduling
Introduction to Project Management
Project Management Process and Its Phases
ppt for primevera
Project Planning
Introduction to Lean Construction
Basics of project management
Project Definition
02 Construction Projects
Introduction to Project Management
Project management in construction
Scheduling by using microsoft project 2013
Brief introduction to project management and project management tools
Project management and control
Topic 14 - Project Team Management.pdf
Ms project 2016 overview
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
Ad

Viewers also liked (20)

PPTX
Construction Management in Developing Countries, Lecture 7
PPTX
My presentaion
PPTX
Construction Management in Developing Countries, Lecture 4
PPTX
Construction Management in Developing Countries, Lecture 3
PPT
素材天下 Sucaitianxia.com ppt1511
PPT
Tourism Manitoba Presentation
DOCX
Reserva yasuni ttt.
PPT
Mr. walden culture project..christain sherman
PPT
Unidad iii.curso online.nathalie
PPTX
Aggus Bahamonde
PPTX
CoCooN-CCMCC Research Project Mid Term Review
PPT
素材天下 Sucaitianxia.com ppt1394
PDF
Chapter 1 december 2015
RTF
Economics
PPT
Computer is every where
PDF
Balikesir University - Mobile Technologies Presentation
PPTX
Engineering Professional Practice Pokhara University
PPTX
Construction Management in Developing Countries Lecture 1
PDF
Chapter 6 case studies relatd to practice of engineering profession
PPT
Construction Management in Developing Countries, Lecture 2
Construction Management in Developing Countries, Lecture 7
My presentaion
Construction Management in Developing Countries, Lecture 4
Construction Management in Developing Countries, Lecture 3
素材天下 Sucaitianxia.com ppt1511
Tourism Manitoba Presentation
Reserva yasuni ttt.
Mr. walden culture project..christain sherman
Unidad iii.curso online.nathalie
Aggus Bahamonde
CoCooN-CCMCC Research Project Mid Term Review
素材天下 Sucaitianxia.com ppt1394
Chapter 1 december 2015
Economics
Computer is every where
Balikesir University - Mobile Technologies Presentation
Engineering Professional Practice Pokhara University
Construction Management in Developing Countries Lecture 1
Chapter 6 case studies relatd to practice of engineering profession
Construction Management in Developing Countries, Lecture 2
Ad

Similar to Construction Management in Developing Countries, Lecture 8 (20)

PPTX
Chapter 8 Project Operation and Maintenance in Developing Countries 2024.pptx
DOC
Resume David Young
PPT
Operational Readiness and Importance of Operator Training
PDF
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
PPTX
Module_2_Industrial_Maintenance_Manageme.pptx
PPT
Rework Reduction in Construction Project
PPTX
MAINTENANCE MANAGEMENT.pptx
PPTX
Building Maintenance Program for engineers.pptx
PPT
Lecture-3-Introduction to Maintenance Management.ppt
PPTX
Module_2_Industrial_Maintenance_Manageme.pptx
DOC
JackmcdowellCV
PPTX
5076_362_3_92207TribologyMaintenance.pptx
PDF
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
PPTX
Property Management Lecture 4.pptx
DOC
Resume201512111001update
DOC
CV D. Maimbolwa
PDF
ICT 4109.pdf
PPTX
System Project initiation and planning.pptx
PDF
Duffield institutions and better infrastructure 2
PDF
Duffield institutions and better infrastructure 2
Chapter 8 Project Operation and Maintenance in Developing Countries 2024.pptx
Resume David Young
Operational Readiness and Importance of Operator Training
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Module_2_Industrial_Maintenance_Manageme.pptx
Rework Reduction in Construction Project
MAINTENANCE MANAGEMENT.pptx
Building Maintenance Program for engineers.pptx
Lecture-3-Introduction to Maintenance Management.ppt
Module_2_Industrial_Maintenance_Manageme.pptx
JackmcdowellCV
5076_362_3_92207TribologyMaintenance.pptx
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
Property Management Lecture 4.pptx
Resume201512111001update
CV D. Maimbolwa
ICT 4109.pdf
System Project initiation and planning.pptx
Duffield institutions and better infrastructure 2
Duffield institutions and better infrastructure 2

More from Hari Krishna Shrestha (20)

PDF
Chapter 5_Hydrograph Analysis, Unit Hydrograph.pdf
PDF
Chapter 4 Surface Runoff and Flow Measurement 2024.pdf
PDF
Chapter 3_Hydrological Losses Apr2024.pdf
PPTX
Chapter 2 Physical Hydrology Evapotranspiration Factors2024.pptx
PPTX
Engineering Hydrology Chapter 1 Hydrological Cycle, Water Balance and Data Av...
PDF
Chapter 1-Concept of National Development_Nov2024.pdf
PPTX
Chapter 10 Project Evaluation and Auditing August2020.pptx
PPTX
Chapter 9 Society and Construction Project Management January 2024.pptx
PPTX
Chapter 7 Participatory Approach 2023.pptx
PPTX
Chapter 6 Choice of Technology 2024.pptx
PPTX
Chapter 5_Project Environment Jan 2024.pptx
PPTX
Chapter 4 Culture Attitudes and Beliefs May 2024.pptx
PPTX
Chapter 3 Needs of the developed and developing countries.pptx
PPTX
Chapter 2 Linkage between developed and developing countries Feb 2024.pptx
PPTX
Construction Management in Developing Countries, Chapter 4, Culture, Attitude...
PPTX
Construction Management in Developing Countries, Chapter 3, Needs of the deve...
PPTX
Construction Management in Developing Countries, Chapter 2, June 2020
PPTX
Construction Management in Developing Countries, Chapter 1, April2020
PPTX
Construction Management in Developing Countries, Lecture 10
PPTX
Construction Management in Developing Countries, Lecture 9
Chapter 5_Hydrograph Analysis, Unit Hydrograph.pdf
Chapter 4 Surface Runoff and Flow Measurement 2024.pdf
Chapter 3_Hydrological Losses Apr2024.pdf
Chapter 2 Physical Hydrology Evapotranspiration Factors2024.pptx
Engineering Hydrology Chapter 1 Hydrological Cycle, Water Balance and Data Av...
Chapter 1-Concept of National Development_Nov2024.pdf
Chapter 10 Project Evaluation and Auditing August2020.pptx
Chapter 9 Society and Construction Project Management January 2024.pptx
Chapter 7 Participatory Approach 2023.pptx
Chapter 6 Choice of Technology 2024.pptx
Chapter 5_Project Environment Jan 2024.pptx
Chapter 4 Culture Attitudes and Beliefs May 2024.pptx
Chapter 3 Needs of the developed and developing countries.pptx
Chapter 2 Linkage between developed and developing countries Feb 2024.pptx
Construction Management in Developing Countries, Chapter 4, Culture, Attitude...
Construction Management in Developing Countries, Chapter 3, Needs of the deve...
Construction Management in Developing Countries, Chapter 2, June 2020
Construction Management in Developing Countries, Chapter 1, April2020
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 9

Recently uploaded (20)

PPTX
Artificial Intelligence
PPTX
Nature of X-rays, X- Ray Equipment, Fluoroscopy
PDF
86236642-Electric-Loco-Shed.pdf jfkduklg
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Visual Aids for Exploratory Data Analysis.pdf
PDF
PPT on Performance Review to get promotions
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Abrasive, erosive and cavitation wear.pdf
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PPT
Total quality management ppt for engineering students
PDF
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PPTX
Fundamentals of Mechanical Engineering.pptx
PPTX
Current and future trends in Computer Vision.pptx
Artificial Intelligence
Nature of X-rays, X- Ray Equipment, Fluoroscopy
86236642-Electric-Loco-Shed.pdf jfkduklg
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Visual Aids for Exploratory Data Analysis.pdf
PPT on Performance Review to get promotions
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Abrasive, erosive and cavitation wear.pdf
III.4.1.2_The_Space_Environment.p pdffdf
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
Categorization of Factors Affecting Classification Algorithms Selection
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Total quality management ppt for engineering students
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
Fundamentals of Mechanical Engineering.pptx
Current and future trends in Computer Vision.pptx

Construction Management in Developing Countries, Lecture 8

  • 1. Chapter 8 Project Operation and Maintenance (in developing countries) (4 hours) Prof. Dr. Hari Krishna Shrestha Center for Postgraduate Studies Nepal Engineering College Changunarayan Municipality, Kathmandu
  • 2. Importance of O&M • Hundreds of projects around the world demonstrate how the newly built infrastructure deteriorates after the project’s termination. Therefore, it is imperative to plan for operation and maintenance (O&M)… • O&M activities encompass technical, managerial, social, financial and institutional issues. O&M is a crucial element of sustainability, and a frequent cause of failure of service facilities in the past. Many failures are not technical ones. They may result from poor planning, inadequate cost recovery, or the outreach inadequacies of centralised agencies (LSHTM/WEDC 1998). • O&M has been neglected in the past, or been discussed and introduced only after a project was completed. Delay in applying O&M has adversely affected the credibility of the investments made, the functioning of the services, the well-being of rural populations, and the development of further projects. • Importance of O&M has gained considerable visibility over the past few years, and it appears that policy-makers and project designers are now more conscious of the direct links between improved O&M practices and the sustainability of project services. There is also greater recognition of the need to approach these projects in a comprehensive way, encompassing not only the design and construction but also post-construction activities (BRIKKE 2000). Source: http://www.sswm.info/category/planning-process-tools/ensuring-sustainability/tools-ensure- sustainability/ensure-sustain-4
  • 3. Construction Project Operation • Construction Project is executed to create something new to achieve a specific objective. • Operation begins once the construction phase is completed. • Operations are the ongoing execution of activities that produce the same output, or provide a repetitive service. • Operation is necessary to maintain and sustain the system and achieve the goals. • Operations are permanent in nature, and their only constraint is to make profit for the organization. • O&M refers to all of the activities needed to run a project/scheme, except for the construction of new facilities. The overall aim of O&M is to ensure: • efficiency, • effectiveness and • sustainability of project facilities (adapted from CASTRO 2009). Operation consists of: • Smooth running of a project without any unplanned interruptions throughout its lifespan. • overseeing, designing, and redesigning daily operations • managing process that converts inputs into outputs.
  • 4. Objective of Project Operation • To have regular expected level of goods and services from the project • At the right time (effectively) • In reliable and sustainable manner (involves technical, financial, social and environmental issues) • With least cost (efficiently) Potential Thesis Topic: Analysis of Operation Model of Middle Marsyangdi HEP (or any other institute/project/line agency) How is it run on day to day basis? Does it have an operation manual (OM), and does it cover all aspects of operation (technical, human resource, finance, social, environmental, public relation, legal? Is the OM followed? Are the staff members aware of OM, and the way to use it? How often the OM is updated, who updates it, are they trained? Does it require updating? What are the weaknesses and strengths in the manual? How can the HEP be made more efficient by improving the manual? Is the MM HEP’s OM very different than manuals of other similar projects? What lessors can be learned from comparative analysis of different manuals? Will the MM HEP support preparation of your thesis, if it does not have OM yet?
  • 5. Poor Project Operation can result in Project failure Reasons for poor project operation: • Lack of clear goals, objectives • Goal incompatibility – conflict in objectives • Lack of required technical skill • Poor management skill • Poor quality materials used in the project • Material sizes used are not readily available • Lack of updated operation manual or improper manual use
  • 6. Operational Activities • Planning the operation • Implementing the plan • Monitoring the operation • Adjustment of the plan in response to monitoring Potential thesis topic: Trend of operation cost in irrigation/hydropower/micro-hydro/water supply projects of Nepal; Factors affecting operation costs in infrastructure development projects in Nepal Operation cost comparison in private vs. government vs. community managed HP/WS/Sanitation/Irrigation/Housing projects
  • 7. Maintenance • Maintenance involves the technical activities, planned or reactive, which are needed to keep the system working. Maintenance requires skills, tools and spare parts (Carter 2009). • Includes all actions which have the objective of retaining or restoring an item in or to a state in which it can perform its required functions. • Reduces the deterioration of asset and prolongs its life, reduces operating cost, pushes back need of much expensive rehabilitation and reconstruction.
  • 8. Objectives of Project Maintenance • Increase economic life • Maximize availability and reliability of all assets • Extend life of asset • Prevent system deterioration (structural, mechanical) • Ensure operational readiness of all the equipment/components • Reduce services and problem in management by reducing frequency and cost of rehabilitation • Minimize frequency and severity of interruptions in operation process. • Enhance personnel safety • Reduce project downtime • Better project operation
  • 9. Planned versus Emergency Maintenance Planned (Preventive and Corrective) Maintenance • Routine maintenance: small and simple maintenance works, carried on regular basis, not requiring forecast and assessment of specific nature. • Recurrent maintenance: generally higher interval of time than routine maintenance; may need identification and preparation of cost estimate. • Periodic maintenance: maintenance works carried out in intervals of years. Normally larger maintenance, using skilled human resource; identification and preparation of cost estimate needed before starting. Emergency (Reactive) maintenance: carried out immediately after unwanted/unplanned incident or after public complaint; can be due to natural or human induced disasters. A stitch in time saves nine.
  • 10. Preventive and Corrective Maintenance • Preventive maintenance: includes work that is planned and carried out on a regular basis to maintain and keep the infrastructure in good condition, such as network inspection, flushing of the well, cleaning and greasing of mechanical parts and replacement of items with a limited lifespan. It sometimes also includes minor repairs and replacement as dictated by the routine examinations. • Preventive maintenance is conducted before a breakdown occurs. • Preventive maintenance is effective in preventing age (or fatigue) related failures. • Corrective maintenance: replacing or repairing something that was done incorrectly or that needs to be changed; an example is the reallocation of a pipe route or replacement of a faulty pump. • Corrective maintenance is conducted after a breakage has occurred. Normally more costly than preventive maintenance because failure/breakdown itself causes multiple damage in other parts also. Preventive maintenance is conducted to keep equipment working and/or extend the life of the equipment. Corrective maintenance (repair) is conducted to get equipment working again.
  • 11. Types of Maintenance Maintenance Planned Preventive Routine Recurrent Periodic Predictive Corrective Shutdown Breakdown Unplanned/ Reactive Emergency planned corrective: Regular budget allocation (cumulative) for sudden project shut down; projected downtime in hydropower or water supply projects, overhaul or replace bridge after its service life, replace major components after design life.
  • 12. Planned Maintenance Management System • Restoration of asset is a challenge which can be achieved by a planned maintenance management system (PMMS), comprising of a series of interdependent routine, recurrent, periodic and emergency activities. • The key to ensuring effective maintenance is to make certain that responsibilities are clearly defined and maintenance personnel have the tools and skills to do their job effectively. It is also essential to schedule preventive maintenance. Can you develop PMMS for your organization, as an output of your thesis?
  • 13. Functional Status of the Projects S.N Status Criteria No of Schemes Covered HHs Coverage (%) 1 Well managed projects 7,464 373,295 17.91 2 Minor repaired required 16,935 809,996 38.85 3 Major repair required 4,375 246,481 11.82 4 To be rehabilitated 4,967 437,800 21.00 5 To be reconstructed 3,438 189,756 9.10 6 Projects not possible for re- operation 467 27,008 1.30 7 Others 15 530 0.03 Total 38,307 2,084,866 100 Source: Nationwide Coverage and Functionality Status of Water Supply and Sanitation in Nepal, Final Report, National Management Information Project (NMIP), Department of Water Supply and Sewerage (DWSS), Panipokhari, Kathmandu, March 2011
  • 14. Design aspect of O&M • Ease of O&M should be made an integral part of project design • Design optimization to reduce O&M cost • Level of technology chosen in the design should be suitable for easier O&M (rural vs. urban, local vs. central) • Project components/parts chosen in the design should be available for O&M • Standardization of equipments/parts will ease O&M
  • 15. Community Management for O&M For the projects owned and operated by community: • community ownership and management approach facilitates effective O&M • End-users directly responsible for the O&M • “owner’s manual” prepared by the contractor and engineer at the onset of the planning process, keeping the community O&M in focus: – schedule and procedures for maintenance – methods to carry out tasks such as bookkeeping, paying employees, collecting bills (utility management), inspection, refurbishments, replacement of parts, etc. – What to do? When to do? How to do? Whom to contact? Contact numbers…
  • 16. Capacity Building for O&M • Correct, unambiguous information at the right time required for proper operation • Training of “how to use correctly”, and do’s and don’ts for proper operation • training on technical matters, accounting and simple financial management, basic contract procedures, and monitoring and reporting • Training to local officials • Training to local technicians and O&M crew • ToT to NGOs
  • 17. Organizing and Planning O&M • Organising for O&M does not represent a huge task, but it does require certain level of planning, commitment and monitoring. The aspects to be organised are: • What: the activity which is to be carried out • When: the frequency of this activity • Who: the human resources required for the task • With what: what are the logistical support (materials, spare parts, tools and equipments) needed. Potential thesis topic: Trend of maintenance cost in irrigation/hydropower/micro-hydro/water supply projects of Nepal; Factors affecting maintenance costs in infrastructure development projects in Nepal Maintenance cost comparison in private vs. government vs. community managed projects
  • 18. Example table for the type of tools which have to be developed to support the O&M of a new infrastructure. The example relates to the O&M of a septic tank (adapted from CASTRO 2009):
  • 19. O&M Manual O&M manual is a living document. It should be flexible to accommodate changes, periodically updated based on experience and as organization matures. O&M manual may include topics such as: • Installation and configuration operations and associated definitions • System maintenance, updates and upgrade policies, procedures, and schedules • Proper and improper handling and maintenance of different types of equipment • Database scheme, network typology, and flowcharts used to illustrate items such as system design, data communications, program logic, and the relationship between network nodes. • Instructions for opening/closing and starting/stopping applications, devices, and services under various conditions • Procedure and sequences describing backup routines, media type, storage locations, and schedules • Security controls for staff, facilities, infrastructure and emergency response procedures • Frequently asked questions and troubleshooting techniques for common issues • Roles, responsibilities and contact information for key personnel and support staff • Other miscellaneous and/or relevant items
  • 20. Characteristics of O&M Manual • Easy: to understand, easy language, unambiguous • Accessibility: stakeholders should have easy access (hardcopy/softcopy, website) • Jargon: no jargon, not loaded with abbreviations • Regulations: related regulations, acts should be provided • Manuals: multiple copies of the manuals, department-wise manuals • Style: consistent style, text, sectioning • Author/Editor: author and editors to be different persons • Align: align with policies and procedures of organization • Update: should be updated based on experience • Educate: Train stakeholders and staff, continually reinforce O&M practices • Lessons: review previously used O&M, learn lessons from O&M implementers, and update
  • 21. Activities in preparation of an O&M Manual • Identify the types of O&M required • Identify information sources and information to be used in the manual • Identify and engage appropriate stakeholders and subject matter experts (SME) • Identify and incorporate SME inputs • Develop each O&M manual • Obtain approval from stakeholders and publish manual • Test, train and exercise to reinforce and validate manual • Prepare personnel through training and awareness campaign • Document lessons learned and incorporate them in updated O&M manual • Treat O&M manual as living document and update them regularly, to remain current with operational and system changes
  • 22. Some common types of O&M Manual • Product installation and maintenance manuals • System description, operations, backup and recovery manuals • Data and software administration manuals • Human resources and personnel manual • Help desk support manuals • User Manuals • Emergency and safety manual • Quick reference guide • Job aids • Run book Source: CDC Unified Process Practices Guide, 2008, O&M Manual, Department of Health and Human Services, USA Let us assign presentation topic. Presentation to be prepared and made in Nov 28 & 30, 2016. Report in MS Word format, by Dec. 7, 2016. (Tentative)