The document summarizes a scenario where Fields Developments plc (Fields) hired Nova Construction SA (Nova) to construct an integrated water and power plant in Dubai. The project is substantially behind schedule. Fields wishes to claim 12 weeks of liquidated damages from Nova due to delays, totaling €12,480,000. However, Nova may be insolvent. The document asks whether Fields can claim the damages from Nova's performance bond. It provides the relevant contract clause and bond language for review. Fields must determine if there are any weaknesses in the documents affecting its ability to claim, and what procedural steps it needs to take to do so assuming it is entitled under the bond.