Construction Issues:
                           EPC Contracting and
                            FIDIC Silver Book
            Francis Ho                              An Update on Real Estate Laws in
            Senior Associate, King & Spalding LLP   the UAE and Saudi Arabia
            Email: fho@kslaw.com                    Radisson Blu Media City Hotel,
            Tel: +971 2 652 3426                    Dubai, UAE
            Mob: +971 50 557 0446                   31 January – 1 February 2010




428006 v1
EPC Contracts
        §  Engineering, procurement and construction contracts are most
            common form of contract used in major international infrastructure
            projects
        §  An EPC Contractor s obligations typically include:
        §  Turnkey responsibility to deliver:
              §  a complete facility
              §  for a guaranteed price
              §  by a guaranteed date
              §  which must perform to a specified level
        §  Because EPC Contracts involve Contractor taking a high level of
            risk they are, to some extent, resisted by contractors (partially due
            to high insurance costs). That said, they are still the dominant
            model because sponsors and lenders prefer certainty they offer

428006 v1                                                                           2
FIDIC Silver Book
        §  FIDIC – International Federation of Consulting
            Engineers
        §  Standard Forms of Contract widely used in international
            engineering and construction projects
        §  Range of contracts – White, Red, Yellow, Orange and
            Silver Books
        §  Silver book – Turnkey contract which departs from usual
            balance of risk allocation in FIDIC contracts




428006 v1                                                             3
Basic Contractual Structure
                           of a Power Project
                                Government
      Equity Support                              Concession                  Financing and
        Agreement                                 Agreement                 Security Agreements

            Sponsors            Project Co                          Lenders


             EPC                Longterm                    Fuel Supply
                                                                                   PPA
            Contract           O&M Contract                  Agreement


          EPC             O&M Contractor                        Fuel             Offtaker
        Contractor        (often a Sponsor)                    Supplier

                                               Direct Agreement
    Note: Contractors often become one of sponsors in large projects now although ordinarily
    sell down their interest after financial close as they wish to free up their capital for other
    projects                                                                                         4
428006 v1
Bankability
        §  EPC contracts must have risk allocation that satisfies Lenders
        §  Lenders focus on ability (or more particularly the lack of) Contractor to
            claim:
             §  Additional costs; and/or
             §  Extensions of time
        §  Lenders also look to Contractor s security (e.g. parent company
            guarantees/bank guarantees securing Contractor s performance)
        §  The less comfortable Lenders are with the above, the more equity the
            Sponsors will be required to contribute
        §  Lenders will also need to be satisfied with technical risk
        §  Price is a general bankability issue also (but a broader project issue)
        §  Engineering, procurement and construction contracts are most common
            form of contract used



428006 v1                                                                               5
General Bankability Issues in
                    Construction Contracts
        §  Fixed completion date (Silver Book Art. 8.2)
        §  Fixed completion price (Silver Book Arts. 4.11 and 14.1)
        §  No or limited technology risk (Silver Book Arts. 5.8, 7.5, 9.1 and 11
            etc)
        §  Output guarantees (Silver Book – no performance LDs, rather
            obligations to remedy defects and/or reduction in contract price)
        §  Liquidated damages for both delay and performance
        §  Security from Contractor and/or its parent (Silver Book Art. 4.2)
        §  Large caps on liability – ideally none but often one is negotiated
            (Silver Book Art. 17.6)
        §  Restrictions on ability of Contractor to claim extensions of time and
            additional costs (Silver Book Arts. 13.1 and 13.4)
        §  An EPC Contract (and Silver Book with amendments) generally
            delivers above
428006 v1                                                                           6
Key Clauses in EPC Contracts and
                 Common Approaches (1)
        §  Single point of responsibility – Contractor is responsible for all design,
            engineering, procurement, construction, commissioning and testing
            activities. If EPC Contractor is a joint venture, liability/responsibility is joint
            and several (Silver Book Arts. 4.1 & 5 – fit for purpose )
        §  Fixed Contract Price – limited opportunities for Contractor to claim extra
            costs/time. Generally limited to directed variations to works (Silver Book
            Arts. 13.1, 14.1 and 20)
        §  Fixed completion date – guaranteed date for completion. Failure to meet
            this date will attract LDs. In order for these to be enforceable they must be
            a genuine pre-estimate of the loss that the project company will suffer if the
            power station is not completed on time (Silver Book Arts. 8.2, 13 and 20)
        §  Note: Additionally extension of time clause must provide for an EOT to be
            granted where Contractor is delayed due to act/omissions of owner/project
            company (Silver Book Art. 8.4(c))



428006 v1                                                                                         7
Key Clauses in EPC Contracts and
                Common Approaches (2)
        §  Performance Guarantees: Project Co s revenue will come from revenue
            from project. This is important to service project debt. It is vital then that
            facility performs in respect of output, efficiency and reliability. This is
            purpose of the Performance Liquidated Damages payable by the
            Contractor if performance requirements are not met. (Silver Book does not
            provide for performance liquidated damages – see e.g. Art. 9.4. Can be
            amended as required.)
        §  Performance Liquidated Damages must also be genuine pre-estimate of
            loss. They are usually calculated on net present value (less expenses)
            calculation of revenue foregone over the project
        §  E.g. in case of a power station what this might mean is if plant output is 5
            MW less than required performance liquidated damages will be designed
            to compensate project company for that loss of revenue for life of project
            by being unable to sell that 5 MW



428006 v1                                                                                    8
Key Clauses in EPC Contracts and
                Common Approaches (3)
        §  Caps on liability: most EPC Contractors will baulk at unlimited
            liability. Market is generally a cap at 100% of the Contract Price.
            Sub-caps of 20% of Contract Price on delay and performance
            liquidated damages also common (Silver Book – LOL is dealt with
            in Special Conditions – see Art. 17.6)
        §  Consequential damages are also generally excluded. Profit also
            often expressly excluded (Silver Book Art. 17.6)
        §  There may be some exceptions to those caps (e.g. wilful
            misconduct, breach of patent rights)
        §  Security – EPC Contract will require that performance security be
            supplied by the Contractor in respect of its obligations under EPC
            Contract (Silver Book Art. 4.2)



428006 v1                                                                         9
Key Clauses in EPC Contracts and
                Common Approaches (4)
        §  Market security includes:
             §  Bank guarantee for between 5-15% of Contract Price
             §  Retention (withholding of 5-15%) of each payment under EPC
                 contract (Silver Book Arts. 4.2 and 14.3(c) and Annex F)
             §  Advance Payment Guarantee – if an advance payment is made
                 (Silver Book Art. 4.2 and Annex E)
             §  Parent Company Guarantee – to secure Contractor s
                 performance if it does not perform (Silver Book Art. 4.2 and
                 Annex A)
        Variations
        §  Project Co must have right to order variations/agree to suggested
            variations – clause must contemplate omission of work as well as
            pricing (Silver Book Arts. 3.5 and 13)

428006 v1                                                                       10
Key Clauses in EPC Contracts and
                Common Approaches (5)
        Defects Liability
        §  Contractors required to repair defects 12-24 months following
            completion of performance testing – can be one period or tiered
            (Silver Book Art. 11)
        Intellectual Property
        §  Contractor must warrant it has the rights regarding any proposed
            LP. Also note there is often an indemnity for breach (Silver Book
            Art. 17.5)
        Force Majeure
        §  Parties excused from performance for certain Force Majeure events
            (Silver Book Art. 19)
        Suspension
        §  Project Co has this right (Silver Book Arts. 8.8 to 8.12)

428006 v1                                                                       11
Termination
        §  Contractor has very limited rights e.g. non-payment/
            extended suspension, material breach by employer
            (Silver Book Art. 16.2)

        §  Project company has much broader rights. This will be
            tied with third party agreements. Can terminate:
             §  For convenience (Silver Book Art. 15.5)
             §  For breach/insolvency, otherwise (Silver Book Art.
                 15.2)



428006 v1                                                             12
Power-specific Clauses in EPC
                        Contracts
        §  General interface issues:
            §  Commencement and completion dates
            §  LDs amounts and trigger points (NB: Silver Book does not
                provide for performance liquidated damages and will need
                adaptation)
            §  Caps on liability
            §  Indemnities
            §  Entitlements to extensions of time
            §  Force Majeure (Silver Book fairly wide, beyond a Party s
                Control and could not reasonably have been provided against
                before entering into the Contract )
            §  Third party interfaces
            §  Intellectual Property

428006 v1                                                                     13
Key Power Issues
        §  Grid Access
        §  EPC Contract must provide that Project Company provides Grid Access –
            this has 2 levels:
             §  (a) obligation to ensure that the infrastructure is in place; and
             §  (b) obligation to ensure that Contractor is permitted to export power
        §  Interfacing of commissioning and testing regimes (fuel for testing?)
        §  Consistency between testing/offtake/PPA regime? – important that they
            relate
        §  Interfacing of issues between the Offtaker and EPC Contractor
        §  Project company must control relationship with Offtaker (on-going
            relationship)
        §  Silver Book will require substantial modification – issues such as
            connection, metering, point of delivery and third party interfaces to be dealt
            with


428006 v1                                                                                    14
Key Performance Issues in Power
                       Projects (1)
        §  Liquidated Damages is main relevant provision governing
            performance
             §  Output LDs (how many mega watts produced)
             §  Heat rate (how much fuel burnt to produce required power
                 output)
        §  Delay liquidated damages
        Testing performance – most common approaches
        §  Functional Tests – pumps/conveyers/pressure vessels. Test
            functionality of parts at station but not whole station. Important as
            condition LDs will attach
        §  Emissions Tests – compliance against environmental requirements.
            Absolute obligation – generally not linked to LDs



428006 v1                                                                           15
Key Performance Issues in Power
                       Projects (2)
        §  Silver Book will require substantial modification to provide for
            performance liquidated damages and testing in power projects:
             §  Employer s remedy for defective plant accepted into service is
                 a reduction in the Contract Price; and
             §  Testing and commissioning provisions are generally defined
                 and require further definition – can use technical schedules
             §  Guarantee Tests – these are the ability of power station to meet
                 the performance criteria set out in Contract
             §  Generally these are set at maximum level of required
                 performance. Lender s input will be important in determining
                 this level. Lender s interest though will be that debt service
                 obligations are met – Sponsor s interest will be to get optimal
                 performances


428006 v1                                                                           16
Key Performance Issues in Power
                        Projects (3)
            §   Hand-over ought to occur after all performance tests are
                satisfied. This retains Sponsor s potential rights to both
                performance and delay damages
            §  Contractor s will often request a right to modify station in event
                performance guarantees are not met (EPC Contract must
                allocate costs for this eventuality)
            §  Silver Book provisions will need modification to be made
                applicable to project specific requirements (See Art. 9 of Silver
                Book)




428006 v1                                                                            17
Technical Issues
        §  Testing procedures ought to be set out in EPC Contract including:
             §  Testing Methodology (i.e. American Society of Mechanical
                 Engineers)
             §  Testing Equipment – (who must provide it, where will it be, how
                 sensitive)
             §  Tolerances – what is margin of error?
             §  Ambient Conditions – what atmospheric conditions are
                 assumed to be base case (testing results will need to be
                 adjusted to take into account any variance from these
                 conditions)
             §  If a multi-unit station individual unit tests and then whole of plant
                 testing
             §  Provision of fuel and consumables

428006 v1                                                                                18
To EPC or not to EPC?


       Advantages                                   Disadvantages

       1.  Bankable                                 1.    Higher Contract price than
       2.  Certainty (as far as that is possible)         alternative structure due to risk
       3.  Turnkey responsibility on the                  allocation (and built-in Contractor
           EPC Contractor                                 contingencies)
                                                    2.    Limited scope for Project Sponsor
                                                          to intervene if problems arise
                                                          during construction
                                                    3.    Not many players




428006 v1                                                                                       19
To Silver Book or not to Silver Book?
        §  Silver Book very general and requires modification for
            complex process driven projects
        §  No provision for lender or concession grantor step-in in
            project-financed (including PPP and BOT) deals
        §  Dispute resolution provisions require consideration –
            currently dispute adjudication board appointed (can be
            expensive)
        §  Performance liquidated damages against Contract Price
            reduction – lenders requirements and debt servicing
        §  Substantial modification required for project-financed
            deals

428006 v1                                                              20

More Related Content

PDF
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
PDF
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
PDF
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
PDF
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
PPSX
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
PPTX
Ppt on fidic claims
PPTX
#FIDIC Understanding Basics# By SN Panigrahi
PPT
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Ppt on fidic claims
#FIDIC Understanding Basics# By SN Panigrahi
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...

What's hot (20)

PPTX
P3 Fundamentals Seminar - P3 Agreements
PDF
Fidic contract
PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PDF
Fidic comparison red yellow - silver book
PDF
Fidic contracts management introduction
PDF
Standard Forms of Construction Contracts
PDF
Fundamentals of Construction Contracts - English, ver. 2021
PDF
Claims 20.1 (Flow chart)
PPTX
Build,Operate,Own,Transfer (BOOT)
PPTX
fidic , jct and nec contracts
PDF
Assignment - FIDIC Contract
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PPT
Contract Management
PDF
time bar clauses
PPT
Effective contract administration may 2014
PDF
110801Proposed Fidic Contract Framework For Complex Epc Projects
DOCX
Construction lawprint-final-update-21112017
PDF
Extension of Time (EoT) in Construction Project presentation
PPTX
Project Finance Session 02
PPTX
FIDIC-Relevant to Time Management
P3 Fundamentals Seminar - P3 Agreements
Fidic contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Fidic comparison red yellow - silver book
Fidic contracts management introduction
Standard Forms of Construction Contracts
Fundamentals of Construction Contracts - English, ver. 2021
Claims 20.1 (Flow chart)
Build,Operate,Own,Transfer (BOOT)
fidic , jct and nec contracts
Assignment - FIDIC Contract
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Contract Management
time bar clauses
Effective contract administration may 2014
110801Proposed Fidic Contract Framework For Complex Epc Projects
Construction lawprint-final-update-21112017
Extension of Time (EoT) in Construction Project presentation
Project Finance Session 02
FIDIC-Relevant to Time Management
Ad

Viewers also liked (17)

PPT
Fidic yellow vs silver
PPT
Fidic flow charts final
PPTX
PPT
Fidic law1
PDF
FIDIC variation, claim & dispute - CYLFEx workshop
PDF
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
PDF
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
PDF
Fidic conditions of subcontract agreement
PPTX
A Case Study based on FIDIC and PAM Form 2006
PDF
Update Delay Analysis
PDF
Methods of delay analysis
PPTX
Construction Delay Analysis, Simplified
PPTX
Extension of time Analysis
PDF
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
PDF
SlideShare 101
PDF
Fi dic silver book
PDF
101313812 دورة-فيديك
Fidic yellow vs silver
Fidic flow charts final
Fidic law1
FIDIC variation, claim & dispute - CYLFEx workshop
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Fidic conditions of subcontract agreement
A Case Study based on FIDIC and PAM Form 2006
Update Delay Analysis
Methods of delay analysis
Construction Delay Analysis, Simplified
Extension of time Analysis
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
SlideShare 101
Fi dic silver book
101313812 دورة-فيديك
Ad

Similar to FIDIC SIlver Book in Power Projects (20)

PDF
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
PDF
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
PPTX
Werksmans Construction & Engineering Seminar - Deon Griessel presentation
PPT
Wind power epc o&m april 2013
PPTX
4GOVEaasdfgggtkfwseyRNMENT CONTRACTS33.pptx
PPT
Session 9 Bouillon Presentation. ppt.ppt
PPTX
EPC and other types of contracts
PPT
Feed Oil and Gas projects and operations upstream and all value chain
PPTX
Contracts PPT.pptx
PDF
1999 FIDIC Guide for Consulting Engineers
PDF
Epc contracts-in-the-power-sector
PPT
Awareness PPT - Fidic_slide_s_show 2015.ppt
PDF
FIDIC Webinar_201503181_SEKAJM_FINAL.pdf
PPTX
Epc contracts.
PPTX
05 Contract Management.pptx . DEFINITION
PPTX
Limiting the Offshore EPC Contractor's Risks and Liabiltities, Busan korea 19...
PPTX
Limiting the Offshore EPC Contractor's Risks and Liabiltities, Busan korea 19...
PPTX
Limiting the Offshore EPC Contractor's Risks and Liabilities
PPTX
400618115-180522-FIDIC-2017-Edition-Workshop-May-2018.pptx
PDF
The working of the Dispute Adjudication Board (DAB)
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Werksmans Construction & Engineering Seminar - Deon Griessel presentation
Wind power epc o&m april 2013
4GOVEaasdfgggtkfwseyRNMENT CONTRACTS33.pptx
Session 9 Bouillon Presentation. ppt.ppt
EPC and other types of contracts
Feed Oil and Gas projects and operations upstream and all value chain
Contracts PPT.pptx
1999 FIDIC Guide for Consulting Engineers
Epc contracts-in-the-power-sector
Awareness PPT - Fidic_slide_s_show 2015.ppt
FIDIC Webinar_201503181_SEKAJM_FINAL.pdf
Epc contracts.
05 Contract Management.pptx . DEFINITION
Limiting the Offshore EPC Contractor's Risks and Liabiltities, Busan korea 19...
Limiting the Offshore EPC Contractor's Risks and Liabiltities, Busan korea 19...
Limiting the Offshore EPC Contractor's Risks and Liabilities
400618115-180522-FIDIC-2017-Edition-Workshop-May-2018.pptx
The working of the Dispute Adjudication Board (DAB)

More from Francis Ho (20)

PDF
COP26: Eating for the Planet
PDF
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
PDF
City of London Law Society - Construction Law Committee - Response to Retenti...
PDF
How will Brexit impact on Construction?
PDF
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
PDF
Construction Insolvency
PDF
The Management of Complex Contracts
PDF
Key Developments in Emerging Markets
PDF
Using Two-Stage Tendering Effectively
PDF
Managing the Risks of Delay in Construction Projects
PDF
It Pays to Be Right: Payment in Construction Contracts
PDF
Adjudication: Tips, Traps and Tactics
PDF
Contractual Options for Procuring Major Projects in the UK
PDF
Introductory Note on International Construction Contracts
PDF
Works Insurance and Latent Defects Insurance
PDF
Third Party Rights and Why They Matter
PDF
A Practical Guide to the Construction (Design and Management) Regulations 2015
PDF
Construction Dispute Resolution and Avoidance in a Boom Market
PDF
Letters of Intent
PDF
Collateral Warranties and Third Party Rights
COP26: Eating for the Planet
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Construction Law Committee - Response to Retenti...
How will Brexit impact on Construction?
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Construction Insolvency
The Management of Complex Contracts
Key Developments in Emerging Markets
Using Two-Stage Tendering Effectively
Managing the Risks of Delay in Construction Projects
It Pays to Be Right: Payment in Construction Contracts
Adjudication: Tips, Traps and Tactics
Contractual Options for Procuring Major Projects in the UK
Introductory Note on International Construction Contracts
Works Insurance and Latent Defects Insurance
Third Party Rights and Why They Matter
A Practical Guide to the Construction (Design and Management) Regulations 2015
Construction Dispute Resolution and Avoidance in a Boom Market
Letters of Intent
Collateral Warranties and Third Party Rights

Recently uploaded (20)

PDF
Under Construction Projects in Mumbai: A Smart Investment for Future Living
PDF
Binghatti Haven at Dubai Sports City -
PDF
Taormina Village At Wadi Al Safa By Reportage Properties
PDF
Binghatti Aquarise at Business Bay, Dubai – Binghatti Developers.pdf
PDF
Collaborating-for-a-Better-Future-Cross-Sector-Partnerships-in-Miami.pdf
PDF
2, 3, and 4 BHK Superior Apartment in Coimbatore
PDF
Lesson 9 _ the role of plantrdetrtbtvrcterxwctvyrbutynibvrtcewrxctv and anim...
PDF
Evolving Illinois Rental Market: Trends and Opportunities for Landlords
PDF
Skyvue Stellar at Sobha Hartland 2, Dubai – Sobha Group
PDF
M3M Infinum - Prime Business Hub in Noida
PDF
Why DJ Thielen is the #1 Choice for Real Estate Investing
PDF
Mansory Residences at Meydan City – AMAAL
PDF
Expert Advice on Property Development Finance for 2025.pdf
PDF
Embracing the Circular Economy: A Homeowners Guide to Sustainable Living
PDF
MSN Realty 4 BHK Luxury Apartments in Neopolis Hyderabad | Premium Homes with...
PDF
Top 5 Gemba Walks Apps with eAuditor Audits & Inspections
PDF
BAYZ 102 at Business Bay, Dubai – Danube Properties
PDF
Robin Pahuja – The Driving Force Among Gurgaon’s Top Real Estate Partners
PPTX
Celebrate Independence Day in Premium Apartments in Kerala
PDF
Wellness Villas in Hyderabad – Forest Nation
Under Construction Projects in Mumbai: A Smart Investment for Future Living
Binghatti Haven at Dubai Sports City -
Taormina Village At Wadi Al Safa By Reportage Properties
Binghatti Aquarise at Business Bay, Dubai – Binghatti Developers.pdf
Collaborating-for-a-Better-Future-Cross-Sector-Partnerships-in-Miami.pdf
2, 3, and 4 BHK Superior Apartment in Coimbatore
Lesson 9 _ the role of plantrdetrtbtvrcterxwctvyrbutynibvrtcewrxctv and anim...
Evolving Illinois Rental Market: Trends and Opportunities for Landlords
Skyvue Stellar at Sobha Hartland 2, Dubai – Sobha Group
M3M Infinum - Prime Business Hub in Noida
Why DJ Thielen is the #1 Choice for Real Estate Investing
Mansory Residences at Meydan City – AMAAL
Expert Advice on Property Development Finance for 2025.pdf
Embracing the Circular Economy: A Homeowners Guide to Sustainable Living
MSN Realty 4 BHK Luxury Apartments in Neopolis Hyderabad | Premium Homes with...
Top 5 Gemba Walks Apps with eAuditor Audits & Inspections
BAYZ 102 at Business Bay, Dubai – Danube Properties
Robin Pahuja – The Driving Force Among Gurgaon’s Top Real Estate Partners
Celebrate Independence Day in Premium Apartments in Kerala
Wellness Villas in Hyderabad – Forest Nation

FIDIC SIlver Book in Power Projects

  • 1. Construction Issues: EPC Contracting and FIDIC Silver Book Francis Ho An Update on Real Estate Laws in Senior Associate, King & Spalding LLP the UAE and Saudi Arabia Email: fho@kslaw.com Radisson Blu Media City Hotel, Tel: +971 2 652 3426 Dubai, UAE Mob: +971 50 557 0446 31 January – 1 February 2010 428006 v1
  • 2. EPC Contracts §  Engineering, procurement and construction contracts are most common form of contract used in major international infrastructure projects §  An EPC Contractor s obligations typically include: §  Turnkey responsibility to deliver: §  a complete facility §  for a guaranteed price §  by a guaranteed date §  which must perform to a specified level §  Because EPC Contracts involve Contractor taking a high level of risk they are, to some extent, resisted by contractors (partially due to high insurance costs). That said, they are still the dominant model because sponsors and lenders prefer certainty they offer 428006 v1 2
  • 3. FIDIC Silver Book §  FIDIC – International Federation of Consulting Engineers §  Standard Forms of Contract widely used in international engineering and construction projects §  Range of contracts – White, Red, Yellow, Orange and Silver Books §  Silver book – Turnkey contract which departs from usual balance of risk allocation in FIDIC contracts 428006 v1 3
  • 4. Basic Contractual Structure of a Power Project Government Equity Support Concession Financing and Agreement Agreement Security Agreements Sponsors Project Co Lenders EPC Longterm Fuel Supply PPA Contract O&M Contract Agreement EPC O&M Contractor Fuel Offtaker Contractor (often a Sponsor) Supplier Direct Agreement Note: Contractors often become one of sponsors in large projects now although ordinarily sell down their interest after financial close as they wish to free up their capital for other projects 4 428006 v1
  • 5. Bankability §  EPC contracts must have risk allocation that satisfies Lenders §  Lenders focus on ability (or more particularly the lack of) Contractor to claim: §  Additional costs; and/or §  Extensions of time §  Lenders also look to Contractor s security (e.g. parent company guarantees/bank guarantees securing Contractor s performance) §  The less comfortable Lenders are with the above, the more equity the Sponsors will be required to contribute §  Lenders will also need to be satisfied with technical risk §  Price is a general bankability issue also (but a broader project issue) §  Engineering, procurement and construction contracts are most common form of contract used 428006 v1 5
  • 6. General Bankability Issues in Construction Contracts §  Fixed completion date (Silver Book Art. 8.2) §  Fixed completion price (Silver Book Arts. 4.11 and 14.1) §  No or limited technology risk (Silver Book Arts. 5.8, 7.5, 9.1 and 11 etc) §  Output guarantees (Silver Book – no performance LDs, rather obligations to remedy defects and/or reduction in contract price) §  Liquidated damages for both delay and performance §  Security from Contractor and/or its parent (Silver Book Art. 4.2) §  Large caps on liability – ideally none but often one is negotiated (Silver Book Art. 17.6) §  Restrictions on ability of Contractor to claim extensions of time and additional costs (Silver Book Arts. 13.1 and 13.4) §  An EPC Contract (and Silver Book with amendments) generally delivers above 428006 v1 6
  • 7. Key Clauses in EPC Contracts and Common Approaches (1) §  Single point of responsibility – Contractor is responsible for all design, engineering, procurement, construction, commissioning and testing activities. If EPC Contractor is a joint venture, liability/responsibility is joint and several (Silver Book Arts. 4.1 & 5 – fit for purpose ) §  Fixed Contract Price – limited opportunities for Contractor to claim extra costs/time. Generally limited to directed variations to works (Silver Book Arts. 13.1, 14.1 and 20) §  Fixed completion date – guaranteed date for completion. Failure to meet this date will attract LDs. In order for these to be enforceable they must be a genuine pre-estimate of the loss that the project company will suffer if the power station is not completed on time (Silver Book Arts. 8.2, 13 and 20) §  Note: Additionally extension of time clause must provide for an EOT to be granted where Contractor is delayed due to act/omissions of owner/project company (Silver Book Art. 8.4(c)) 428006 v1 7
  • 8. Key Clauses in EPC Contracts and Common Approaches (2) §  Performance Guarantees: Project Co s revenue will come from revenue from project. This is important to service project debt. It is vital then that facility performs in respect of output, efficiency and reliability. This is purpose of the Performance Liquidated Damages payable by the Contractor if performance requirements are not met. (Silver Book does not provide for performance liquidated damages – see e.g. Art. 9.4. Can be amended as required.) §  Performance Liquidated Damages must also be genuine pre-estimate of loss. They are usually calculated on net present value (less expenses) calculation of revenue foregone over the project §  E.g. in case of a power station what this might mean is if plant output is 5 MW less than required performance liquidated damages will be designed to compensate project company for that loss of revenue for life of project by being unable to sell that 5 MW 428006 v1 8
  • 9. Key Clauses in EPC Contracts and Common Approaches (3) §  Caps on liability: most EPC Contractors will baulk at unlimited liability. Market is generally a cap at 100% of the Contract Price. Sub-caps of 20% of Contract Price on delay and performance liquidated damages also common (Silver Book – LOL is dealt with in Special Conditions – see Art. 17.6) §  Consequential damages are also generally excluded. Profit also often expressly excluded (Silver Book Art. 17.6) §  There may be some exceptions to those caps (e.g. wilful misconduct, breach of patent rights) §  Security – EPC Contract will require that performance security be supplied by the Contractor in respect of its obligations under EPC Contract (Silver Book Art. 4.2) 428006 v1 9
  • 10. Key Clauses in EPC Contracts and Common Approaches (4) §  Market security includes: §  Bank guarantee for between 5-15% of Contract Price §  Retention (withholding of 5-15%) of each payment under EPC contract (Silver Book Arts. 4.2 and 14.3(c) and Annex F) §  Advance Payment Guarantee – if an advance payment is made (Silver Book Art. 4.2 and Annex E) §  Parent Company Guarantee – to secure Contractor s performance if it does not perform (Silver Book Art. 4.2 and Annex A) Variations §  Project Co must have right to order variations/agree to suggested variations – clause must contemplate omission of work as well as pricing (Silver Book Arts. 3.5 and 13) 428006 v1 10
  • 11. Key Clauses in EPC Contracts and Common Approaches (5) Defects Liability §  Contractors required to repair defects 12-24 months following completion of performance testing – can be one period or tiered (Silver Book Art. 11) Intellectual Property §  Contractor must warrant it has the rights regarding any proposed LP. Also note there is often an indemnity for breach (Silver Book Art. 17.5) Force Majeure §  Parties excused from performance for certain Force Majeure events (Silver Book Art. 19) Suspension §  Project Co has this right (Silver Book Arts. 8.8 to 8.12) 428006 v1 11
  • 12. Termination §  Contractor has very limited rights e.g. non-payment/ extended suspension, material breach by employer (Silver Book Art. 16.2) §  Project company has much broader rights. This will be tied with third party agreements. Can terminate: §  For convenience (Silver Book Art. 15.5) §  For breach/insolvency, otherwise (Silver Book Art. 15.2) 428006 v1 12
  • 13. Power-specific Clauses in EPC Contracts §  General interface issues: §  Commencement and completion dates §  LDs amounts and trigger points (NB: Silver Book does not provide for performance liquidated damages and will need adaptation) §  Caps on liability §  Indemnities §  Entitlements to extensions of time §  Force Majeure (Silver Book fairly wide, beyond a Party s Control and could not reasonably have been provided against before entering into the Contract ) §  Third party interfaces §  Intellectual Property 428006 v1 13
  • 14. Key Power Issues §  Grid Access §  EPC Contract must provide that Project Company provides Grid Access – this has 2 levels: §  (a) obligation to ensure that the infrastructure is in place; and §  (b) obligation to ensure that Contractor is permitted to export power §  Interfacing of commissioning and testing regimes (fuel for testing?) §  Consistency between testing/offtake/PPA regime? – important that they relate §  Interfacing of issues between the Offtaker and EPC Contractor §  Project company must control relationship with Offtaker (on-going relationship) §  Silver Book will require substantial modification – issues such as connection, metering, point of delivery and third party interfaces to be dealt with 428006 v1 14
  • 15. Key Performance Issues in Power Projects (1) §  Liquidated Damages is main relevant provision governing performance §  Output LDs (how many mega watts produced) §  Heat rate (how much fuel burnt to produce required power output) §  Delay liquidated damages Testing performance – most common approaches §  Functional Tests – pumps/conveyers/pressure vessels. Test functionality of parts at station but not whole station. Important as condition LDs will attach §  Emissions Tests – compliance against environmental requirements. Absolute obligation – generally not linked to LDs 428006 v1 15
  • 16. Key Performance Issues in Power Projects (2) §  Silver Book will require substantial modification to provide for performance liquidated damages and testing in power projects: §  Employer s remedy for defective plant accepted into service is a reduction in the Contract Price; and §  Testing and commissioning provisions are generally defined and require further definition – can use technical schedules §  Guarantee Tests – these are the ability of power station to meet the performance criteria set out in Contract §  Generally these are set at maximum level of required performance. Lender s input will be important in determining this level. Lender s interest though will be that debt service obligations are met – Sponsor s interest will be to get optimal performances 428006 v1 16
  • 17. Key Performance Issues in Power Projects (3) §  Hand-over ought to occur after all performance tests are satisfied. This retains Sponsor s potential rights to both performance and delay damages §  Contractor s will often request a right to modify station in event performance guarantees are not met (EPC Contract must allocate costs for this eventuality) §  Silver Book provisions will need modification to be made applicable to project specific requirements (See Art. 9 of Silver Book) 428006 v1 17
  • 18. Technical Issues §  Testing procedures ought to be set out in EPC Contract including: §  Testing Methodology (i.e. American Society of Mechanical Engineers) §  Testing Equipment – (who must provide it, where will it be, how sensitive) §  Tolerances – what is margin of error? §  Ambient Conditions – what atmospheric conditions are assumed to be base case (testing results will need to be adjusted to take into account any variance from these conditions) §  If a multi-unit station individual unit tests and then whole of plant testing §  Provision of fuel and consumables 428006 v1 18
  • 19. To EPC or not to EPC? Advantages Disadvantages 1.  Bankable 1.  Higher Contract price than 2.  Certainty (as far as that is possible) alternative structure due to risk 3.  Turnkey responsibility on the allocation (and built-in Contractor EPC Contractor contingencies) 2.  Limited scope for Project Sponsor to intervene if problems arise during construction 3.  Not many players 428006 v1 19
  • 20. To Silver Book or not to Silver Book? §  Silver Book very general and requires modification for complex process driven projects §  No provision for lender or concession grantor step-in in project-financed (including PPP and BOT) deals §  Dispute resolution provisions require consideration – currently dispute adjudication board appointed (can be expensive) §  Performance liquidated damages against Contract Price reduction – lenders requirements and debt servicing §  Substantial modification required for project-financed deals 428006 v1 20