PIPE JACKING
1
Internet Document
Pipe Jacking – Ritchie-Wiki.
Available online at http://www.ritchiewiki.com/wiki/index.php/Pipe_Jacking, checked on 2/4/2017.
Internet Document
Pipe Jacking Association Homepage.
Available online at http://pipejacking.org/, checked on 2/8/2017.
Internet Document
Welcome to Civil and Environmental Engineering at the University of Waterloo.
Available online at https://uwaterloo.ca/civil-environmental-engineering/, checked on 2/8/2017.
Internet Document
Ongoing & Upcoming Trenchless Projects in India
(2016). Available online at http://www.indstt.com/trenchless_projects.html, updated on 12/17/2016, checked on 2/8/2017.
Reference:
CONTENTS
•Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
2
INTRODUCTION
• Pipe Jacking is the oldest method of trenchless technology.
• Pipes are pushed through the ground behind the shield
using powerful jacks.
• Simultaneously excavation takes place within the shield.
• This process is continued until the pipeline is completed.
• The method provides a flexible, structural, watertight,
finished pipeline as the tunnel is excavated.
• Thrust wall is provided for the reaction of the jacks.
3
Contd.
4
Figure 1: Pipe jacking process (a) Jacks are pushing pipe
(b) Installation of pipeline under a runway.
(a) (b)
Source: www.pipejacking.org Source: www.pipejacking.org
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
5
BRIEF HISTORY
• First mentioned in 1910, USA by Richardson & Mayo.
• In 60s, used in UK and APJA(American Pipe Jacking
Association) is formed.
• In 70s, process is industrialized in Japan.
• In 80s, developed in Europe.
(i) 1800mm dia trenchless pipe is laid for 460m in London,1982.
(ii) 560m in water bearing sand and gravel, Byles, 1983.
• Komatsu introduced first fully automated machine in
1975 – IRONMOLE
• Today pipe jacking is remotely operated.
6
INDIAN HISTORY
• First project is of 3.5km in 1998, Mumbai.
• In Cuttack 10km is constructed for sewer using
trenchless method.
• Other projects of less than 8km is completed in Goa,
Hyderabad, Kolkata, Delhi, Assam etc.
• A total of around 100km is build so far using trenchless
methods so far.
Ongoing projects-
• 55km of interceptor sewer along 3 major drains for
reduction of pollution in Yamuna river at New Delhi.
7
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
8
METHODOLOGY
9
PLANNING
PROCEDURE
SPECIFIC FEATURE
PROCESS BASED ON SOIL
PIPE JACKING FORCE
FAILURE
SOLUTION
PLANING
• Understand the site history and potential obstructions.
• Look at old aerial photos.
• Conduct a geotechnical program.
• Locate all existing utilities.
• Minimize costs.
• Develop the best cross section.
• Use the right materials.
10
PROCEDURE
• The thrust pit and the reception pit are excavated at the
required places.
• Then the thrust wall is set up in the thrust pit according
to the requirement.
• In case of mechanized excavations, a very large pit is
required.
• But in case of manual excavation, a small pit is enough.
• Thrust ring is provided to ensure the even distribution of
stress along the circumference of the pipe.
11
Contd.
• The number of jacks vary upon the frictional resistance
of the soil, strength of pipes etc.,
• The size of the reception pit is to be big enough to
receive the jacking shield.
• To maintain the accuracy of alignment a steerable shield
is used during the pipe jacking.
• In case of small and short distance excavations, ordinary
survey method is sufficient.
• But in case of long excavations, remote sensing and
other techniques can be used.
12
Contd.
13
Figure 2a: Pipe Jacking Arrangement
Source: http://www-civ.eng.cam.ac.uk
Contd.
14
Figure 2b: Labelled arrangement of pipe jacking
Source: www.google.com
SPECIFIC FEATURES
• Simple cyclic procedure.
• Utilizes thrust from hydraulic jacks to force the pipe forward
• Person have to enter in pipe for excavation.
• Excavation can be manual or by machine.
• Excavation takes place in front of an articulated shield.
> Designed for worker safety.
> Shield guided with individually controlled hydraulic jacks.
• Practically limited to dia. greater than or equal to 1075mm.
• Pipe installation process occurs from entrance and exit
shaft.
15
16
Figure 3: Manual and Machine Excavation
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
PROCESS BASED ON SOIL
Unstable soil
• Face excavated simultaneously with the jacking operation.
• Minimize over excavation and the risk of face collapse.
• After pipe jacked into place hydraulic rams are retracted
and another pipe length is installed.
Stable soil
• Face excavation may precede the jacking operation.
• All spoils removed through the inside of the pipe to the
jacking pit.
17
PIPE JACKING FORCE
• Force on jacked pipe includes:
> Pipe dead weight.
> Penetration resistance or face pressure.
> Soil-pipe friction.
• Other forces like:
> Curvature forces.
> Soil dead load.
> Railway or highway live load.
• Jacking force must not exceed allowable pipe
compressive strength .
18
19
Figure 4: Face Resistance
Source: www.youtube.com
20
Figure 5: Skin friction and face resistance
Source: www.youtube.com
21
Figure 6: Total force is greater than permissible limit
Source: www.youtube.com
22
Figure 7: Force distribution with intermediate jack
Intermediate jack
Source: www.youtube.com
FAILURE
• Pipe generally fails from the corner first.
• Maximum force is acting at the edges due to:
> Uneven distribution of jacking force from one pipe to another.
> Unavoidable curvature.
> Elastic forces from pressure transfer rings at joints.
23
Figure 8: Failure of pipe
Source: www.youtube.comSource: www.youtube.com
24
Figure 9: Failure of pipe
Source: www.youtube.com
POSSIBLE SOLUTION
Solution
Open cut/dig and replace Trenchless
25
Tunnel &
Replace
Jacking Pipe
Tunnel Liner
Plate
Slip-lining
Jacking Pipe
Plastic liner
Lining-Rehab
Cured in
place
Shotcrete
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
26
APPLICATION
• Larger Diameter Pipe (1050 mm and up).
• Lengths can range from 3 to over 200m.
• Sewers, and drainage construction.
• Gas and water mains.
• Oil pipelines.
• Industrial pipelines.
• Telecommunication.
• Pedestrian subways (access tunnels).
27
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
28
STANDARDS
29
• BS 6164: 2011 – Code of practice for health and safety in
tunnelling in the construction industry.
• BS EN 16191 – Tunnelling machinery safety requirements
Table 1: Standards for pipe jacking
Source: www.pipejacking.org
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
30
EQUIPMENT/COMPONENT
• Jacking Pit.
• Jack.
• Pipe.
• Thrust Ring.
• Thrust wall.
• Lubricant.
• Intermediate Jack.
• Cutting-head.
• Pressure Transfer Ring etc.
31
JACKING PIT
32
• Jacking pit size is function of Length of pipe segments,
Pipe diameter, Shield dimensions, Thrust wall design,
Jack size, Pressure rings and Guide rail systems.
• Pit should be shored using Timber or steel piling.
• Placement of concrete slab on the floor is recommended.
(a) (b)
Figure 10: Typical Jacking Pit(a) and (b)
Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
JACK AND PIPE
• Number and capacity of jack is a
function of pipe size, length, skin
friction, intermediate jacks etc.
It is suggested to provide even
number of jacks.
• Pipe should be light weighted,
smooth and strong enough to
withstand all the forces.
33
Figure 11a: Jack
Figure 11b: RCP Pipe
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
THRUST RING AND THRUST WALL
• Thrust ring distributes force
from jack head to pipe edges
equally.
A spacer is optional.
• Thrust wall is provided behind
the jack to transfer back thrust
of jack to earth and preventing
jack to sink.
34
Figure 12a: Thrust Ring
Figure 12b: Thrust Wall
Source: www.google.com
Source: www.google.com
LUBRICANT AND INTERMEDIATE JACK
• Lubrication is provided at
outer edges of pipe using
lubricant injection ports at
proper interval.
• Intermediate jack is provided
in between the entry and exit
shaft. Number of intermediate
jack depend on pipe length
and jack capacity.
IJ must match pipe diameter.
35
Figure 13a: Lubricant injection port
Figure 13b: Intermediate Jack
Source: www.civil.uwaterloo.ca
Source: www.civil.uwaterloo.ca
CUTTING-HEAD AND
PRESSURE TRANSFER RING
• Cutting-head or cutter is located at
the front of pipe line. It cuts down
the soil ahead using mechanical
motion into smaller fragments.
• Pressure transfer ring is used in
between of two pipe at joints, it
distribute the pressure to
succeeding pipe equally. It is made
either of cork or synthetic material.
36
Figure 14b: Pressure Transfer Ring
Figure 14a: Cutter-head
Source: www.youtube.com
Source: www.google.com
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
37
CLASSIFICATION
38
PipeJackingcanbeclassified
onthebasisof:
Pipe Material
Cutter-head
Excavation
Technique
39
(a) Reinforced Concrete (b) Vitrified Clay (c) Ductile Iron
(d) Fibreglass (e) Steel (f) Composite
Figure 15: Classification on basis of pipe material(a)-(f)
Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca
Source: www.google.comSource: www.google.comSource: www.hobas.com
Source: www.google.com
40
(d) Backacters
(a) Open Face Cutter Booms
(e) Pressurized Slurry
(b) Tunnel Boring Machine (c) Earth Pressure Balance
Figure 16: Classification on basis of Cutter-head(a)-(e)
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
41
(a) Manual Excavation (b) Machine Excavation
(c) Conveyer belt Excavation (d) Slurry Excavation
Figure 17: Classification on basis of excavation technique(a)-(d)
Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca
Source: www.google.comSource: www.google.com
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
0
42
ALTERNATIVE METHODS
Trenchless
Piping
Non-steering
Methods
Steering
Methods
43
• Moling/Piercing
• Pipe Ramming
• Auger Boring
• Pipe Jacking
• Micro-tunneling
• Horizontal
directional drilling
Generic Size and Length
• Method Size(inch) Length(ft)
Moling 2” - 12” 150’
Ramming 8” - 72” 300’
Auger Bore 8” - 60” 250’
Pilot Tube 6” - 42” 300’
Pipe Jacking >42” 1,000’
Micro-tunneling 12” - 42” 1,500’
HDD 2” - 48” 6,500’
Tunneling >60” Any length
Table 2: Compatibility of different methods 41
Source: www.pipejacking.org
45
(a) Auger Boring (b) Pilot Tube (c) Horizontal Direction Drilling
(d) Micro-tunneling (e) Pipe Ramming
Figure 18: Alternative methods(a)-(e)
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
CONTENTS
• Introduction
• Brief History
• Methodology
• Application
• Standards
• Equipment/Component
• Classification
• Alternative methods
• Pros & Cons
46
ADVANTAGE
• It avoids the excavation of trenches.
• Quick set-up, timely finish of projects.
• Good quality control and good grade of pipe used.
• Can be remotely operated.
• Versatile in various ground conditions.
• Cost efficient for large length pipe.
• Small surface settlements.
• Reduces disruption to existing services.
• Environment friendly.
• Less spoil.
47
DISADVANTAGE
• Costly for small lengths.
• Skilled personal is required.
• Dewatering of tunnel path is usually required.
• Not feasible for nature of soil changes drastically.
• Hard rock/Bed rock or very big boulders should not be
present in the path line.
48
CLOSING THOUGHTS
• Methods still evolving.
• Many hybrid methods emerging.
• Will never replace traditional open-cut methods;
however, they complement each other.
New idea
• To identify potential obstructions we can install a
GPR(Ground Penetrating Radar) at cutting head.
49

More Related Content

PPT
1.1 box jacking
PPTX
Curso de formación de riesgo eléctrico
PPTX
Environment lab instruments
PPTX
Tunnel constructions
PPTX
Construccion de pozos de agua
PPTX
Air transport
PPTX
Tunneling
PPT
Construction of diaphragm wall
1.1 box jacking
Curso de formación de riesgo eléctrico
Environment lab instruments
Tunnel constructions
Construccion de pozos de agua
Air transport
Tunneling
Construction of diaphragm wall

What's hot (20)

PPTX
Sheet pile presentation
PPTX
Types of failure in rigid pavements
PPT
Sinking of well foundation
PPTX
Dewatering by well point system
PDF
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
PDF
Plate load test
PPTX
PDF
Ground improvement technique
PPT
Deck slab bridge
PDF
Construction methods and equipments
PPT
Earth moving equipments
PPTX
Earth work equipment
PPTX
Soil Nailing
PPTX
Well Foundation
PPTX
Bridge components
PPT
Tunnelling methods
PPTX
7. TUNNEL ENGINEERING
PPTX
Dewatering techniques
PDF
8. Road Construction Technology.pdf
PPTX
BALANCED CANTILEVER BRIDGE
Sheet pile presentation
Types of failure in rigid pavements
Sinking of well foundation
Dewatering by well point system
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
Plate load test
Ground improvement technique
Deck slab bridge
Construction methods and equipments
Earth moving equipments
Earth work equipment
Soil Nailing
Well Foundation
Bridge components
Tunnelling methods
7. TUNNEL ENGINEERING
Dewatering techniques
8. Road Construction Technology.pdf
BALANCED CANTILEVER BRIDGE
Ad

Viewers also liked (20)

PPTX
PPTX
Trenchless technolgy
PPTX
PPT ON TRENCHLESS TECHNOLOGY
DOCX
Trenchless technology
PDF
Diaphragm Wall Presentation By Gagan
PPTX
TRENCHLESS TECHNOLOGY
PPT
Trenchless technology
PPT
grouting and guniting
PPSX
Microtunneling presentation 2014
PPTX
reliability analysis in adjustment computation
PPTX
Interlocking pavement
PPT
TBRR Workshop, University of Washington
PPTX
NAVIC (Navigation with Indian Constellation)
PPT
Working of digital camera
PPTX
Irnss ppt.
PPTX
IRNSS ISRO
PDF
Indian satellite based navigation system description and implementation status
PPTX
IRNSS by Anish Raj Goyal
PPTX
PPTX
Indian Regional Navigational Satellite System (IRNSS)
Trenchless technolgy
PPT ON TRENCHLESS TECHNOLOGY
Trenchless technology
Diaphragm Wall Presentation By Gagan
TRENCHLESS TECHNOLOGY
Trenchless technology
grouting and guniting
Microtunneling presentation 2014
reliability analysis in adjustment computation
Interlocking pavement
TBRR Workshop, University of Washington
NAVIC (Navigation with Indian Constellation)
Working of digital camera
Irnss ppt.
IRNSS ISRO
Indian satellite based navigation system description and implementation status
IRNSS by Anish Raj Goyal
Indian Regional Navigational Satellite System (IRNSS)
Ad

Similar to Pipe Jacking (20)

PPTX
Trenchless technology
PDF
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
PDF
TRENCHLESS-TECHNOLOGY.pdf
PPTX
Trenchless Technology for Laying Underground pipes.
PPTX
TRENCHLESS TECHNOLOGY WITHOUT DIGGING THE GROUND.pptx
PPTX
UMAID IQBAL SEMINAR.pptx
PDF
Trenchless Technology a Review
PPTX
Shotcrete technology
PDF
Blue mountains cascade dam- Horizontal direction drill
PPTX
presentation on shotcrete technology
PPTX
transtech.pptx
PPTX
A brief overview of drilling and blasting process for tunnel excavation used ...
PPTX
Dcl hdd presentation 9 2-2014
PPTX
trenchless technology
PPT
Trenchless technology
PDF
Stripping of liners from pipes using hdd technology (2007)
PPTX
SDP Presentation.pptx
PDF
Trenchless Technologies for New Pipe Installations
PPTX
Final Project Presentation
ODP
A Complete Guide on Directional Boring
Trenchless technology
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
TRENCHLESS-TECHNOLOGY.pdf
Trenchless Technology for Laying Underground pipes.
TRENCHLESS TECHNOLOGY WITHOUT DIGGING THE GROUND.pptx
UMAID IQBAL SEMINAR.pptx
Trenchless Technology a Review
Shotcrete technology
Blue mountains cascade dam- Horizontal direction drill
presentation on shotcrete technology
transtech.pptx
A brief overview of drilling and blasting process for tunnel excavation used ...
Dcl hdd presentation 9 2-2014
trenchless technology
Trenchless technology
Stripping of liners from pipes using hdd technology (2007)
SDP Presentation.pptx
Trenchless Technologies for New Pipe Installations
Final Project Presentation
A Complete Guide on Directional Boring

Recently uploaded (20)

PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PDF
IGGE1 Understanding the Self1234567891011
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
Uderstanding digital marketing and marketing stratergie for engaging the digi...
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
Virtual and Augmented Reality in Current Scenario
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Share_Module_2_Power_conflict_and_negotiation.pptx
IGGE1 Understanding the Self1234567891011
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Uderstanding digital marketing and marketing stratergie for engaging the digi...
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
AI-driven educational solutions for real-life interventions in the Philippine...
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
History, Philosophy and sociology of education (1).pptx
LDMMIA Reiki Yoga Finals Review Spring Summer
Virtual and Augmented Reality in Current Scenario
A powerpoint presentation on the Revised K-10 Science Shaping Paper
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Chinmaya Tiranga quiz Grand Finale.pdf
What if we spent less time fighting change, and more time building what’s rig...
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
FORM 1 BIOLOGY MIND MAPS and their schemes
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf

Pipe Jacking

  • 1. PIPE JACKING 1 Internet Document Pipe Jacking – Ritchie-Wiki. Available online at http://www.ritchiewiki.com/wiki/index.php/Pipe_Jacking, checked on 2/4/2017. Internet Document Pipe Jacking Association Homepage. Available online at http://pipejacking.org/, checked on 2/8/2017. Internet Document Welcome to Civil and Environmental Engineering at the University of Waterloo. Available online at https://uwaterloo.ca/civil-environmental-engineering/, checked on 2/8/2017. Internet Document Ongoing & Upcoming Trenchless Projects in India (2016). Available online at http://www.indstt.com/trenchless_projects.html, updated on 12/17/2016, checked on 2/8/2017. Reference:
  • 2. CONTENTS •Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 2
  • 3. INTRODUCTION • Pipe Jacking is the oldest method of trenchless technology. • Pipes are pushed through the ground behind the shield using powerful jacks. • Simultaneously excavation takes place within the shield. • This process is continued until the pipeline is completed. • The method provides a flexible, structural, watertight, finished pipeline as the tunnel is excavated. • Thrust wall is provided for the reaction of the jacks. 3
  • 4. Contd. 4 Figure 1: Pipe jacking process (a) Jacks are pushing pipe (b) Installation of pipeline under a runway. (a) (b) Source: www.pipejacking.org Source: www.pipejacking.org
  • 5. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 5
  • 6. BRIEF HISTORY • First mentioned in 1910, USA by Richardson & Mayo. • In 60s, used in UK and APJA(American Pipe Jacking Association) is formed. • In 70s, process is industrialized in Japan. • In 80s, developed in Europe. (i) 1800mm dia trenchless pipe is laid for 460m in London,1982. (ii) 560m in water bearing sand and gravel, Byles, 1983. • Komatsu introduced first fully automated machine in 1975 – IRONMOLE • Today pipe jacking is remotely operated. 6
  • 7. INDIAN HISTORY • First project is of 3.5km in 1998, Mumbai. • In Cuttack 10km is constructed for sewer using trenchless method. • Other projects of less than 8km is completed in Goa, Hyderabad, Kolkata, Delhi, Assam etc. • A total of around 100km is build so far using trenchless methods so far. Ongoing projects- • 55km of interceptor sewer along 3 major drains for reduction of pollution in Yamuna river at New Delhi. 7
  • 8. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 8
  • 9. METHODOLOGY 9 PLANNING PROCEDURE SPECIFIC FEATURE PROCESS BASED ON SOIL PIPE JACKING FORCE FAILURE SOLUTION
  • 10. PLANING • Understand the site history and potential obstructions. • Look at old aerial photos. • Conduct a geotechnical program. • Locate all existing utilities. • Minimize costs. • Develop the best cross section. • Use the right materials. 10
  • 11. PROCEDURE • The thrust pit and the reception pit are excavated at the required places. • Then the thrust wall is set up in the thrust pit according to the requirement. • In case of mechanized excavations, a very large pit is required. • But in case of manual excavation, a small pit is enough. • Thrust ring is provided to ensure the even distribution of stress along the circumference of the pipe. 11
  • 12. Contd. • The number of jacks vary upon the frictional resistance of the soil, strength of pipes etc., • The size of the reception pit is to be big enough to receive the jacking shield. • To maintain the accuracy of alignment a steerable shield is used during the pipe jacking. • In case of small and short distance excavations, ordinary survey method is sufficient. • But in case of long excavations, remote sensing and other techniques can be used. 12
  • 13. Contd. 13 Figure 2a: Pipe Jacking Arrangement Source: http://www-civ.eng.cam.ac.uk
  • 14. Contd. 14 Figure 2b: Labelled arrangement of pipe jacking Source: www.google.com
  • 15. SPECIFIC FEATURES • Simple cyclic procedure. • Utilizes thrust from hydraulic jacks to force the pipe forward • Person have to enter in pipe for excavation. • Excavation can be manual or by machine. • Excavation takes place in front of an articulated shield. > Designed for worker safety. > Shield guided with individually controlled hydraulic jacks. • Practically limited to dia. greater than or equal to 1075mm. • Pipe installation process occurs from entrance and exit shaft. 15
  • 16. 16 Figure 3: Manual and Machine Excavation Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 17. PROCESS BASED ON SOIL Unstable soil • Face excavated simultaneously with the jacking operation. • Minimize over excavation and the risk of face collapse. • After pipe jacked into place hydraulic rams are retracted and another pipe length is installed. Stable soil • Face excavation may precede the jacking operation. • All spoils removed through the inside of the pipe to the jacking pit. 17
  • 18. PIPE JACKING FORCE • Force on jacked pipe includes: > Pipe dead weight. > Penetration resistance or face pressure. > Soil-pipe friction. • Other forces like: > Curvature forces. > Soil dead load. > Railway or highway live load. • Jacking force must not exceed allowable pipe compressive strength . 18
  • 19. 19 Figure 4: Face Resistance Source: www.youtube.com
  • 20. 20 Figure 5: Skin friction and face resistance Source: www.youtube.com
  • 21. 21 Figure 6: Total force is greater than permissible limit Source: www.youtube.com
  • 22. 22 Figure 7: Force distribution with intermediate jack Intermediate jack Source: www.youtube.com
  • 23. FAILURE • Pipe generally fails from the corner first. • Maximum force is acting at the edges due to: > Uneven distribution of jacking force from one pipe to another. > Unavoidable curvature. > Elastic forces from pressure transfer rings at joints. 23 Figure 8: Failure of pipe Source: www.youtube.comSource: www.youtube.com
  • 24. 24 Figure 9: Failure of pipe Source: www.youtube.com
  • 25. POSSIBLE SOLUTION Solution Open cut/dig and replace Trenchless 25 Tunnel & Replace Jacking Pipe Tunnel Liner Plate Slip-lining Jacking Pipe Plastic liner Lining-Rehab Cured in place Shotcrete
  • 26. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 26
  • 27. APPLICATION • Larger Diameter Pipe (1050 mm and up). • Lengths can range from 3 to over 200m. • Sewers, and drainage construction. • Gas and water mains. • Oil pipelines. • Industrial pipelines. • Telecommunication. • Pedestrian subways (access tunnels). 27
  • 28. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 28
  • 29. STANDARDS 29 • BS 6164: 2011 – Code of practice for health and safety in tunnelling in the construction industry. • BS EN 16191 – Tunnelling machinery safety requirements Table 1: Standards for pipe jacking Source: www.pipejacking.org
  • 30. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 30
  • 31. EQUIPMENT/COMPONENT • Jacking Pit. • Jack. • Pipe. • Thrust Ring. • Thrust wall. • Lubricant. • Intermediate Jack. • Cutting-head. • Pressure Transfer Ring etc. 31
  • 32. JACKING PIT 32 • Jacking pit size is function of Length of pipe segments, Pipe diameter, Shield dimensions, Thrust wall design, Jack size, Pressure rings and Guide rail systems. • Pit should be shored using Timber or steel piling. • Placement of concrete slab on the floor is recommended. (a) (b) Figure 10: Typical Jacking Pit(a) and (b) Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 33. JACK AND PIPE • Number and capacity of jack is a function of pipe size, length, skin friction, intermediate jacks etc. It is suggested to provide even number of jacks. • Pipe should be light weighted, smooth and strong enough to withstand all the forces. 33 Figure 11a: Jack Figure 11b: RCP Pipe Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 34. THRUST RING AND THRUST WALL • Thrust ring distributes force from jack head to pipe edges equally. A spacer is optional. • Thrust wall is provided behind the jack to transfer back thrust of jack to earth and preventing jack to sink. 34 Figure 12a: Thrust Ring Figure 12b: Thrust Wall Source: www.google.com Source: www.google.com
  • 35. LUBRICANT AND INTERMEDIATE JACK • Lubrication is provided at outer edges of pipe using lubricant injection ports at proper interval. • Intermediate jack is provided in between the entry and exit shaft. Number of intermediate jack depend on pipe length and jack capacity. IJ must match pipe diameter. 35 Figure 13a: Lubricant injection port Figure 13b: Intermediate Jack Source: www.civil.uwaterloo.ca Source: www.civil.uwaterloo.ca
  • 36. CUTTING-HEAD AND PRESSURE TRANSFER RING • Cutting-head or cutter is located at the front of pipe line. It cuts down the soil ahead using mechanical motion into smaller fragments. • Pressure transfer ring is used in between of two pipe at joints, it distribute the pressure to succeeding pipe equally. It is made either of cork or synthetic material. 36 Figure 14b: Pressure Transfer Ring Figure 14a: Cutter-head Source: www.youtube.com Source: www.google.com
  • 37. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 37
  • 39. 39 (a) Reinforced Concrete (b) Vitrified Clay (c) Ductile Iron (d) Fibreglass (e) Steel (f) Composite Figure 15: Classification on basis of pipe material(a)-(f) Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca Source: www.google.comSource: www.google.comSource: www.hobas.com Source: www.google.com
  • 40. 40 (d) Backacters (a) Open Face Cutter Booms (e) Pressurized Slurry (b) Tunnel Boring Machine (c) Earth Pressure Balance Figure 16: Classification on basis of Cutter-head(a)-(e) Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
  • 41. 41 (a) Manual Excavation (b) Machine Excavation (c) Conveyer belt Excavation (d) Slurry Excavation Figure 17: Classification on basis of excavation technique(a)-(d) Source: www.civil.uwaterloo.caSource: www.civil.uwaterloo.ca Source: www.google.comSource: www.google.com
  • 42. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 0 42
  • 43. ALTERNATIVE METHODS Trenchless Piping Non-steering Methods Steering Methods 43 • Moling/Piercing • Pipe Ramming • Auger Boring • Pipe Jacking • Micro-tunneling • Horizontal directional drilling
  • 44. Generic Size and Length • Method Size(inch) Length(ft) Moling 2” - 12” 150’ Ramming 8” - 72” 300’ Auger Bore 8” - 60” 250’ Pilot Tube 6” - 42” 300’ Pipe Jacking >42” 1,000’ Micro-tunneling 12” - 42” 1,500’ HDD 2” - 48” 6,500’ Tunneling >60” Any length Table 2: Compatibility of different methods 41 Source: www.pipejacking.org
  • 45. 45 (a) Auger Boring (b) Pilot Tube (c) Horizontal Direction Drilling (d) Micro-tunneling (e) Pipe Ramming Figure 18: Alternative methods(a)-(e) Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org Source: http://rightofway.transportation.org
  • 46. CONTENTS • Introduction • Brief History • Methodology • Application • Standards • Equipment/Component • Classification • Alternative methods • Pros & Cons 46
  • 47. ADVANTAGE • It avoids the excavation of trenches. • Quick set-up, timely finish of projects. • Good quality control and good grade of pipe used. • Can be remotely operated. • Versatile in various ground conditions. • Cost efficient for large length pipe. • Small surface settlements. • Reduces disruption to existing services. • Environment friendly. • Less spoil. 47
  • 48. DISADVANTAGE • Costly for small lengths. • Skilled personal is required. • Dewatering of tunnel path is usually required. • Not feasible for nature of soil changes drastically. • Hard rock/Bed rock or very big boulders should not be present in the path line. 48
  • 49. CLOSING THOUGHTS • Methods still evolving. • Many hybrid methods emerging. • Will never replace traditional open-cut methods; however, they complement each other. New idea • To identify potential obstructions we can install a GPR(Ground Penetrating Radar) at cutting head. 49