PMI Processes
(Edition 5 + Const)
CONTRACT
PJCT Work Statement
Enter[rise Environment
Org Process
INITIATING
PLANNING

INTEGRATION

SCOPE

PROJECT CHARTER
Selection methd
PMIS
Expert Judgment
PM Methodology
PJCT MNGMNT PLAN
PM Method
PMIS
Expert Judgment

CLOSING

QUALITY

HR

COMMUNICATIONS /
STAKEHOLDER

RISK

Safety
Environment

PROCUREMENT
Claims Management

ID STAKEHOLDERS

PLAN SCOPE
MNGMNT

SCOPE DEFINITION
Product Analysis
Alternatives
Judgment
Stakeholder analysis
CREATE WBS
WBS Templates
Decomposition

MONITORING &
CONTROL

COST
Financial

COLLECT RQMNTS
PM plan
Matrix

EXECUTION

TIME

ACTIVITY
DEFINITION
Decomposition
Templates
Rolling Wave Plan
Judgement
ACTIVITY
SEQUENCE
Precedence / Arrow
diagram, Network
Diagram
Dependencies
ACT RESOURCE EST
Judgment
Alternatives
Published data
Bottom up estimate
ACT DURATION
Analogous estimate
Parametric
3 point
Reserve analysis
SCHEDULE DVLP
Network, CPM, what
if?, resource level,
Leads & Lags

COST ESTIMATE
Analogous estimate,
Resource costs,
Bottom Up,
Parametric, Cost of
quality, Tenders/bids
COST BUDGET
Cost aggregation
Reserve analysis
Parametric estimates,
Funding Limit
reconciliation

QUALITY PLANNING
Cost benefit analysis’
Benchmarking,
Experiments, Cost of
Quality, Metrics /
checklists

INTEGRATED
CHANGE CONTROL
PM Methodology
PMIS
Expert Judgment
CLOSE PROJECT
PM Methodology,
PMIS, Judgment

COST CONTROL
Cost change control,
Performance
measurement,
Forecasting, Variance
management

QUALITY CONTROL
Cause & effect
Control charts
Flowcharts
Histogram
Pareto charts
Run charts/trends
Scatter diagram
Inspection & samples

ACQUIRE TEAM
Pre-assignment,
Negotiation,
Acquisition, Virtual
DEVELOP TEAM
General Management,
Training, Teams,
Rules, Collocate
MANAGE TEAM
Observations &
conversations,
Appraisals, Training,
Issues Log, Conflict
management (Part of
Execution)

SCOPE CONTROL
Change Control
Variance Analysis
Configuration Mngmnt
Repalnning

Inspection

SCHEDULE
CONTROL
Progress Reports
Change Control
Performance Measure
PM Software
Variance,
Comparison Charts

RISK MNGMNT PLAN
Planning meeting &
analysis, Enterprise
standards

PLAN
STAKEHOLDER
MANAGEMENT

QUALITY
ASSURANCE
Audits, Process
analysis, QC Tools

SCOPE
VERIFICATION

COMMS PLANNING
Comms requirements,
Comms technology

RISK ID
Document review
Checklist analysis
Assumptions analysis
Brainstorming, Delphi,
Interviews, Diagrams
QUAL ANALYSIS
Probability & Impact
(Low/Med/High)
assessment matrix,
category / priority
QUANT ANALYSIS
Simulations, data
gathering, Monte Carlo

MANAGE COMMS
(INFORMATION
DISTRIBUTION)
Comms skills, Info
gather, store, distribute
MANAGE
S’HOLDERS
Issues logs,
experience, meetings
PERFORMANCE
REPORTS
Presentations
Meetings
Time & Cost reports
Performance gathering

CONDUCT
PROCUREMENT
Bidder conference
Advertise, prequal
Selection criteria,
negotiations,
independent estimates
RISK MONITORING &
CONTROL
Risk assessment
Audits
Variance & Trend
Reserve Analysis

CONTRACT
ADMINISTRATION
Change Control
Inspections & audits
Payment system
Performance
Claims admin
Records Mngmnt
IT tools
Letters by condition of
contract for evaluation
of contract difficulties
etc.

Close / Lessons learnt

CONTRACT
CLOSURE
Claims Resolution

CONTROL
STAKEHOLDER
ENGAGEMENT
As executed
programme

/mnt/temp/unoconv/20131109050852/pmiprocessespmbok5-131108230851-phpapp02.doc

PLAN
PROCUREMENT
Standard forms,
Judgement

RISK RESPONSE
Strategic for +ve & -ve
Contingency
Scenario

DIRECT & MANAGE
EXECUTION
PM Methodology
PMIS

MONITORING &
CONTROL
PM Methodology
PMIS
Earned Value
Expert Judgment

HR PLANNING
Org charts, Job
Descriptions,
Networking,
Organisation Theory,
RACI Chart

Close Financial

Close Quality / Safety
Assurance

Close Team

More Related Content

PPTX
BWB PMP pres to Non-Profit PMs 2013
PDF
PRINCE2 Timeline Slides
PDF
Vineeth Prince2 Practitioner e-Cert
PPT
Knowledge Transfer With Scrum
PDF
PRINCE2 Practitioner Exam Guide - by Ashish Dhoke (projectingIT)
PPT
Comparing PRINCE2 and the PMBok
PDF
Prince2 Practitioner Certificate - Robert Loranc
BWB PMP pres to Non-Profit PMs 2013
PRINCE2 Timeline Slides
Vineeth Prince2 Practitioner e-Cert
Knowledge Transfer With Scrum
PRINCE2 Practitioner Exam Guide - by Ashish Dhoke (projectingIT)
Comparing PRINCE2 and the PMBok
Prince2 Practitioner Certificate - Robert Loranc

Viewers also liked (11)

PPTX
Pmbok5 data flow diagram in english MS-VISIO
PPTX
Pmp brain-dump
PDF
PRINCE2 Foundation Course Material
PDF
Interpersonal Skills For Project Managers
PDF
PRINCE2 Foundation Training Manual by Frank Turley
PDF
Learn the SECRETS to passing your PRINCE2 Practitioner exam with flying colou...
PPT
Learning pmp formulas the easy way
PDF
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PDF
PMP - Process 42 Chart Matrix
PDF
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
Pmbok5 data flow diagram in english MS-VISIO
Pmp brain-dump
PRINCE2 Foundation Course Material
Interpersonal Skills For Project Managers
PRINCE2 Foundation Training Manual by Frank Turley
Learn the SECRETS to passing your PRINCE2 Practitioner exam with flying colou...
Learning pmp formulas the easy way
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PMP - Process 42 Chart Matrix
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
Ad

Similar to Pmi processes pmbok5 (20)

DOC
Pmi processes pmbok6 jan 2019
PPTX
Mastering T&T analysis in PMP - PMBOK Ver5
PDF
Project Management
PPTX
Lean six-sigma-project-charter-template
PDF
Technology Alignment Framework
PDF
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
PPT
Project Management, Planning And Analysis Tools
PPTX
Pmp doc data_as per pmp - copy
PDF
PMP ITTOs Quick Review
PDF
PMP CAPM Study Guide-Cost Management
PPTX
Triple Constraints of Projects: Scope, Cost & Schedule
PPTX
PMP.pptx
PPTX
Estimation - The next level - and beyond
PDF
PMP CAPM Study Guide Time Management
PPTX
Augmenting IT strategy with Enterprise architecture assessment
PPTX
Mastering ITTO DataFlow PMP - PMBOK Version 5
PPT
Pm training (planning and tracking) - Project Leader Ramp-Up
PPTX
PRP - 21st Century Program/Project Management
PPT
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
PPT
Project management methodology pmo example (short sanitised)
Pmi processes pmbok6 jan 2019
Mastering T&T analysis in PMP - PMBOK Ver5
Project Management
Lean six-sigma-project-charter-template
Technology Alignment Framework
SOC-2 Framework - Plan, Budget, Design, Integrate & Audit Security Controls
Project Management, Planning And Analysis Tools
Pmp doc data_as per pmp - copy
PMP ITTOs Quick Review
PMP CAPM Study Guide-Cost Management
Triple Constraints of Projects: Scope, Cost & Schedule
PMP.pptx
Estimation - The next level - and beyond
PMP CAPM Study Guide Time Management
Augmenting IT strategy with Enterprise architecture assessment
Mastering ITTO DataFlow PMP - PMBOK Version 5
Pm training (planning and tracking) - Project Leader Ramp-Up
PRP - 21st Century Program/Project Management
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Project management methodology pmo example (short sanitised)
Ad

More from Malcolm Peart (20)

PDF
Micromanagement.pdf
PDF
Decisions- a flow approach
PDF
Problem solving decisions
PPTX
Troubled projects recovery
PPTX
Project planning
DOC
Four disciplines of execution notes
PPT
Letter writing
DOC
Leadership essay peart
PPT
Letter writing
PDF
Tunnelling process for Safety in design and construction
PPTX
Project management stakeholder feb 2018
DOC
PMI four reasons for failure
DOC
E mail protocol 020807
PDF
Eternal triangle - PM Areas, Risk & influence
PDF
Passing blame & evading responsibility
DOC
Letter writing
PDF
Failing projects downward spiral
PPT
Risk management - A short course
PPT
Report Writing - A Project Management Perspective
DOC
Claim aide memoire
Micromanagement.pdf
Decisions- a flow approach
Problem solving decisions
Troubled projects recovery
Project planning
Four disciplines of execution notes
Letter writing
Leadership essay peart
Letter writing
Tunnelling process for Safety in design and construction
Project management stakeholder feb 2018
PMI four reasons for failure
E mail protocol 020807
Eternal triangle - PM Areas, Risk & influence
Passing blame & evading responsibility
Letter writing
Failing projects downward spiral
Risk management - A short course
Report Writing - A Project Management Perspective
Claim aide memoire

Pmi processes pmbok5

  • 1. PMI Processes (Edition 5 + Const) CONTRACT PJCT Work Statement Enter[rise Environment Org Process INITIATING PLANNING INTEGRATION SCOPE PROJECT CHARTER Selection methd PMIS Expert Judgment PM Methodology PJCT MNGMNT PLAN PM Method PMIS Expert Judgment CLOSING QUALITY HR COMMUNICATIONS / STAKEHOLDER RISK Safety Environment PROCUREMENT Claims Management ID STAKEHOLDERS PLAN SCOPE MNGMNT SCOPE DEFINITION Product Analysis Alternatives Judgment Stakeholder analysis CREATE WBS WBS Templates Decomposition MONITORING & CONTROL COST Financial COLLECT RQMNTS PM plan Matrix EXECUTION TIME ACTIVITY DEFINITION Decomposition Templates Rolling Wave Plan Judgement ACTIVITY SEQUENCE Precedence / Arrow diagram, Network Diagram Dependencies ACT RESOURCE EST Judgment Alternatives Published data Bottom up estimate ACT DURATION Analogous estimate Parametric 3 point Reserve analysis SCHEDULE DVLP Network, CPM, what if?, resource level, Leads & Lags COST ESTIMATE Analogous estimate, Resource costs, Bottom Up, Parametric, Cost of quality, Tenders/bids COST BUDGET Cost aggregation Reserve analysis Parametric estimates, Funding Limit reconciliation QUALITY PLANNING Cost benefit analysis’ Benchmarking, Experiments, Cost of Quality, Metrics / checklists INTEGRATED CHANGE CONTROL PM Methodology PMIS Expert Judgment CLOSE PROJECT PM Methodology, PMIS, Judgment COST CONTROL Cost change control, Performance measurement, Forecasting, Variance management QUALITY CONTROL Cause & effect Control charts Flowcharts Histogram Pareto charts Run charts/trends Scatter diagram Inspection & samples ACQUIRE TEAM Pre-assignment, Negotiation, Acquisition, Virtual DEVELOP TEAM General Management, Training, Teams, Rules, Collocate MANAGE TEAM Observations & conversations, Appraisals, Training, Issues Log, Conflict management (Part of Execution) SCOPE CONTROL Change Control Variance Analysis Configuration Mngmnt Repalnning Inspection SCHEDULE CONTROL Progress Reports Change Control Performance Measure PM Software Variance, Comparison Charts RISK MNGMNT PLAN Planning meeting & analysis, Enterprise standards PLAN STAKEHOLDER MANAGEMENT QUALITY ASSURANCE Audits, Process analysis, QC Tools SCOPE VERIFICATION COMMS PLANNING Comms requirements, Comms technology RISK ID Document review Checklist analysis Assumptions analysis Brainstorming, Delphi, Interviews, Diagrams QUAL ANALYSIS Probability & Impact (Low/Med/High) assessment matrix, category / priority QUANT ANALYSIS Simulations, data gathering, Monte Carlo MANAGE COMMS (INFORMATION DISTRIBUTION) Comms skills, Info gather, store, distribute MANAGE S’HOLDERS Issues logs, experience, meetings PERFORMANCE REPORTS Presentations Meetings Time & Cost reports Performance gathering CONDUCT PROCUREMENT Bidder conference Advertise, prequal Selection criteria, negotiations, independent estimates RISK MONITORING & CONTROL Risk assessment Audits Variance & Trend Reserve Analysis CONTRACT ADMINISTRATION Change Control Inspections & audits Payment system Performance Claims admin Records Mngmnt IT tools Letters by condition of contract for evaluation of contract difficulties etc. Close / Lessons learnt CONTRACT CLOSURE Claims Resolution CONTROL STAKEHOLDER ENGAGEMENT As executed programme /mnt/temp/unoconv/20131109050852/pmiprocessespmbok5-131108230851-phpapp02.doc PLAN PROCUREMENT Standard forms, Judgement RISK RESPONSE Strategic for +ve & -ve Contingency Scenario DIRECT & MANAGE EXECUTION PM Methodology PMIS MONITORING & CONTROL PM Methodology PMIS Earned Value Expert Judgment HR PLANNING Org charts, Job Descriptions, Networking, Organisation Theory, RACI Chart Close Financial Close Quality / Safety Assurance Close Team