Lisa is the project manager updating her project's risk register. She should include a level of detail in the risk responses that corresponds to the priority ranking of each risk. This will allow for an appropriate level of planning for high priority risks without overplanning for lower priority risks.
Jenny uncovered new risk events during quantitative analysis. She should enter these new risks into the risk register so they can be properly monitored and addressed.
The risk management plan will define who will share information on project risks with stakeholders, as it is responsible for communicating how risks will be identified, analyzed, and monitored throughout the project lifecycle.