This document contains a series of questions and answers about project risk management processes and techniques:
1) It describes using decision tree analysis to evaluate options and determine which decision yields the greatest expected value when considering uncertainties.
2) Identify Risks is the process used to determine which risks may affect a project and document their characteristics.
3) Residual risks are risks that remain after risk responses have been implemented and deliberately accepted risks.
4) Contingency plans are planned in advance while workarounds are responses to unplanned risks that have occurred.
5) Establishing a contingency reserve for unplanned risks is an example of active risk acceptance.