GDAS PM Professions:
PMP Study Group
                                           Session #10: Risk Management




Monique Howard
January 8, 2009

© 2005 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice
1.   In your project, you can use all the following tools and techniques for risk response
     planning EXCEPT:

1.   Strategies for negative risks or threats
2.   Contingent response planning
3.   Strategy for threat and opportunities
4.   Strategy for residual risks
1.   In your project, you can use all the following tools and techniques for risk response
     planning EXCEPT:

1.   Strategies for negative risks or threats
2.   Contingent response planning
3.   Strategy for threat and opportunities
4.   Strategy for residual risks




Correct Choice: 4

Justification:   Figure 11-14

Reference: PMBOK Third Edition, Page Number: 260
2. You are the project manager in an automobile manufacturing company. A vendor was
    sending you the machine parts required in your manufacturing process,but the parts did
    not reach in time because of heavy rains. You had anticipated this risk and planned for it in
    your risk response plan. So, as per your risk response plan, you started using machine
    parts which had been supplied one year ago and were not utilized at that time. However,
    this has subjected your project to a new risk - that the machine parts which were not used
    for one year might be having higher level of defects.

This new risk can also be called:
1. Unidentifiable Risk
2. Unmanageable Risk
3. Secondary Risk
4. Residual Risk
2. You are the project manager in an automobile manufacturing company. A vendor was
    sending you the machine parts required in your manufacturing process,but the parts did
    not reach in time because of heavy rains. You had anticipated this risk and planned for it in
    your risk response plan. So, as per your risk response plan, you started using machine
    parts which had been supplied one year ago and were not utilized at that time. However,
    this has subjected your project to a new risk - that the machine parts which were not used
    for one year might be having higher level of defects.

This new risk can also be called:
1. Unidentifiable Risk
2. Unmanageable Risk
3. Secondary Risk
4. Residual Risk



Correct Choice: 3

Justification:   Secondary risks that arise as a direct outcome of implementing a risk response.

Reference: PMBOK Third Edition, Page Number: 264
3. In your project, you have identified important risks, and planned appropriate responses to the
       risks. Some risks e.g. possibility of natural disasters have been documented and accepted
       in your risk management plan. If there are risks that remain after you have taken these
       steps, then such risks are called:

1.   Unidentifiable Risks
2.   Residual Risks
3.   Secondary Risks
4.   Accepted Risks
4. Risk Management Planning is the process of deciding how to approach and plan the risk
    management activities for a project. It is important to plan for the risk management
    processes that follow to ensure that the level, type, and visibility of risk management are
    commensurate with both the risk and importance of the project to the organization. The
    output of Risk Management Planning is:

1.   Risks
2.   Risk Management Plan
3.   Risk Ranking of the Project
4.   Planning Meetings
3. In your project, you have identified important risks, and planned appropriate responses to the
       risks. Some risks e.g. possibility of natural disasters have been documented and accepted
       in your risk management plan. If there are risks that remain after you have taken these
       steps, then such risks are called:

1.    Unidentifiable Risks
2.    Residual Risks
3.    Secondary Risks
4.    Accepted Risks




Correct Choice: 2

Justification: Residual risks that are expected to remain after planned responses have been taken, as well as those which have
been deliberately accepted.

Reference: PMBOK Third Edition, Page Number: 264
4. Risk Management Planning is the process of deciding how to approach and plan the risk
    management activities for a project. It is important to plan for the risk management
    processes that follow to ensure that the level, type, and visibility of risk management are
    commensurate with both the risk and importance of the project to the organization. The
    output of Risk Management Planning is:

1.   Risks
2.   Risk Management Plan
3.   Risk Ranking of the Project
4.   Planning Meetings



Correct Choice: 2

Justification:   Figure 11-3

Reference: PMBOK Third Edition, Page Number: 242
5. In your project, you have identified a list of identified risks, a list of potential responses
     and root causes of risks. You should document this information in the :

1.   Risk Management Plan
2.   Risk Database
3.   Project Plan
4.   Risk Register
5. In your project, you have identified a list of identified risks, a list of potential responses
     and root causes of risks. You should document this information in the :

1.   Risk Management Plan
2.   Risk Database
3.   Project Plan
4.   Risk Register




 Correct Choice:      4

 Justification:    The risk register includes a list of identified risks, a list of potential responses, root causes of risk, and updated risk
 categories.

 Reference: PMBOK Third Edition, Page Number: 249
6. Risk management helps in maximizing the probability and consequences of positive
    events and minimizing the probability and consequences of adverse events to project
    objectives. Risk Response Planning helps in this context because it:

1.   helps in deciding how to approach and plan the risk management activities.
2.   develops procedures and techniques to enhance opportunities and reduce threats to project
     objectives.
3.   determines which risks might affect the project and documents their characteristics.
4.   monitors residual risks, identifies new risks and executes risk reduction plans.
6. Risk management helps in maximizing the probability and consequences of positive
    events and minimizing the probability and consequences of adverse events to project
    objectives. Risk Response Planning helps in this context because it:

1.   helps in deciding how to approach and plan the risk management activities.
2.   develops procedures and techniques to enhance opportunities and reduce threats to project
     objectives.
3.   determines which risks might affect the project and documents their characteristics.
4.   monitors residual risks, identifies new risks and executes risk reduction plans.



Correct Choice:     2

Justification:    Risk response planning - developing options and actions to enhance opportunities, and reducing threats to project
objectives.

Reference: PMBOK Third Edition, Page Number: 237

pmstudy.com comments:
* Option 1: This is Risk Management Planning
* Option 3: This is Risk Identification
* Option 4: This is Risk Monitoring and Control
7. Utility function is a commonly used technique to find out the tolerance of a project manager
    towards risk. Some project managers are more averse to risk than others. All of the
    following are different classifications of tolerance for risk EXCEPT:

1.   Risk Averter
2.   Risk Seeker
3.   Risk Mitigator
4.   Risk Neutral
7. Utility function is a commonly used technique to find out the tolerance of a project manager
    towards risk. Some project managers are more averse to risk than others. All of the
    following are different classifications of tolerance for risk EXCEPT:

1.   Risk Averter
2.   Risk Seeker
3.   Risk Mitigator
4.   Risk Neutral




 Correct Choice: 3

 Justification:




 Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 906
8. As part of the Risk Management Process, you just created an overall risk ranking of the
    project and a list of prioritized risks, identified which risks need additional analysis and
    determined trends in risk analysis results. What should you do next?

1.   Analyze the effect of risk events and assign a numerical rating to those risks.
2.   Create a list of identified risks.
3.   Determine the fundamental conditions or events that may give rise to identified risk (root causes of
     risk).
4.   Make a list of potential responses to the risks.
8. As part of the Risk Management Process, you just created an overall risk ranking of the
    project and a list of prioritized risks, identified which risks need additional analysis and
    determined trends in risk analysis results. What should you do next?

1.   Analyze the effect of risk events and assign a numerical rating to those risks.
2.   Create a list of identified risks.
3.   Determine the fundamental conditions or events that may give rise to identified risk (root causes of
     risk).
4.   Make a list of potential responses to the risks.


Correct Choice: 1

Justification: Tasks like creating an overall risk ranking of the project, which includes a list of prioritized risks, identifying which
risks need additional analysis and determining trends in risk analysis results - are all outputs of Qualitative Risk Analysis (PMBOK
Page 253). So, the next step is to perform Quantitative Risk Analysis (i.e. analyze the effect of risk events and assign a numerical
rating to those risks) - (PMBOK Page 254)

Please note that Option 2, Option 3 and Option 4 refer to outputs from Risk Identification Phase which has already been completed
(PMBOK Page 249)

Reference: pmstudy.com notes as mentioned above
9. You are in the process of developing options, and determining actions to enhance
    opportunities and reduce threats to the project`s objectives. What should you be
    doing next?

1.   Determining which risks might affect the project and documenting their
     characteristics.
2.   Identifying, analyzing and planning for newly arising risks.
3.   Deciding how to approach and conduct risk management activities for the project.
4.   Assessing the priority of identified risks using their probability of occurring.
9. You are in the process of developing options, and determining actions to enhance
    opportunities and reduce threats to the project`s objectives. What should you be
    doing next?

1.   Determining which risks might affect the project and documenting their
     characteristics.
2.   Identifying, analyzing and planning for newly arising risks.
3.   Deciding how to approach and conduct risk management activities for the project.
4.   Assessing the priority of identified risks using their probability of occurring.


 Correct Choice: 2

 Justification:
 "Developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives" - this is Risk
 Response Planning; PMBOK Page 260

 "Identifying, analyzing and planning for newly arising risks" - this is Risk Monitoring and Control - PMBOK Page 264. Please note that
 this happens after Risk Response Planning and is the correct answer

 The other options happen before Risk Response Planning:

 Determining which risks might affect the project and documenting their characteristics (Risk Identification, PMBOK Page 246)
 Deciding how to approach and conduct risk management activities for the project (Risk Management Planning - PMBOK Page 242)
 Assessing the priority of identified risks using their probability of occurring (Qualitative Risk Analysis - PMBOK Page 249)


 Reference: pmstudy.com notes as mentioned above
10. You are in the build phase of the project. But it has run into several unanticipated
    problems. Several risks have surfaced which you had not anticipated earlier. The project
    is over-budget and behind schedule. What should you do?

1.   Create updates to risk response plan
2.   Create a revised project plan
3.   Perform risk response audits
4.   Perform updated risk identification and analysis
10. You are in the build phase of the project. But it has run into several unanticipated
    problems. Several risks have surfaced which you had not anticipated earlier. The project
    is over-budget and behind schedule. What should you do?

1.   Create updates to risk response plan
2.   Create a revised project plan
3.   Perform risk response audits
4.   Perform updated risk identification and analysis




Correct Choice: 4

Justification: Results from an earned value analysis may indicate potential deviation of the project at completion from cost and
schedule targets. When a project deviates significantly from the baseline, updated risk identification and analysis should be
performed.

Reference: pmstudy.com notes as mentioned above
11. In your project, there is:

    * 50% probability of $ 40,000 profit
    * 50% probability of $ 25,000 loss

What is the expected profit in your project?
1. $ 32,500
2. $ 25,000
3. $ 7,500
4. - $ 7,500 (i.e. loss of $ 7,500)
11. In your project, there is:

     * 50% probability of $ 40,000 profit
     * 50% probability of $ 25,000 loss

What is the expected profit in your project?
1. $ 32,500
2. $ 25,000
3. $ 7,500
4. - $ 7,500 (i.e. loss of $ 7,500)



Correct Choice: 3

Justification:
Expected Profit = Sum of (Probability X Profit) (for each alternative)
= (0.50 x $ 40,000) + (0.50 x - $ 25,000)
= $ 20,000 - $ 12,500
= $ 7,500 profit

Reference: pmstudy.com notes as mentioned above
12. In risk response planning, you are in the process of developing options, and determining
      actions to reduce threats to your project`s objectives. When you show the results of your
      risk response planning to your project sponsor, she is not comfortable with the risks in
      the project and she suggests that the project scope should be decreased. This is an
      example of :


1.   Inappropriate risk management because it is having a direct impact on your project scope
2.   Risk Avoidance
3.   Risk Mitigation
4.   Risk Transfer
12. In risk response planning, you are in the process of developing options, and determining
      actions to reduce threats to your project`s objectives. When you show the results of your
      risk response planning to your project sponsor, she is not comfortable with the risks in
      the project and she suggests that the project scope should be decreased. This is an
      example of :


1.    Inappropriate risk management because it is having a direct impact on your project scope
2.    Risk Avoidance
3.    Risk Mitigation
4.    Risk Transfer


Correct Choice: 2

Justification: Risk avoidance involves changing the project management plan to elimiate the threat posed by an adverse risk.... or
to relax the objective that is in jeopardy, such as extending the schedule or reducing scope.

Reference: PMBOK Third Edition, Page Number: 261
13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which
      the data about risks is useful for risk management. What could be a potential next
      step?

1.   Perform a structured review of project plans and assumptions, both at the total project and detailed
     scope levels
2.   Develop checklists for identifying risks based on historical information and knowledge that has
     been accumulated from previous similar projects
3.   Conduct planning meetings to develop the risk management plan
4.   Conduct interviews to quantify the probability and consequences of risks on project activities
13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which
      the data about risks is useful for risk management. What could be a potential next
      step?

1.     Perform a structured review of project plans and assumptions, both at the total project and detailed
       scope levels
2.     Develop checklists for identifying risks based on historical information and knowledge that has
       been accumulated from previous similar projects
3.     Conduct planning meetings to develop the risk management plan
4.     Conduct interviews to quantify the probability and consequences of risks on project activities



Correct Choice: 4

Justification:    Risk data quality analysis is a tool for Qualitative Risk Analysis.

* Option 4 refers to "Interviewing" which is a tool and technique for Quantitative Risk Analysis. Quantitative Risk Analysis is conducted
after Qualitatitive Risk Analysis
* Option 1 refers to "Documentation Reviews" which is a tool and technique for Risk Identification. Risk Identification is conducted
before Qualitatitive Risk Analysis
* Option 2 refers to "Checklists" which is a tool and technique for Risk Identification. Risk Identification is conducted before Qualitatitive
Risk Analysis
* Option 3 refers to "Planning Meetings" which is a tool and technique for Risk Management Planning. Risk Management Planning is
conducted before Qualitatitive Risk Analysis


Reference: pmstudy.com notes as mentioned above
14. You are the project manager of a project which involves oil-exploration in the ocean. Since
     you cannot plan for all eventualities, you establish a contingency reserve, including
     amounts of time, money or resources to handle known or unknown risks. This is an
     example of :


1.   Risk Avoidance
2.   Risk Transfer
3.   Active Risk Acceptance
4.   Improper Risk Planning since all risks should be identified and accounted for
14. You are the project manager of a project which involves oil-exploration in the ocean. Since
     you cannot plan for all eventualities, you establish a contingency reserve, including
     amounts of time, money or resources to handle known or unknown risks. This is an
     example of :


1.    Risk Avoidance
2.    Risk Transfer
3.    Active Risk Acceptance
4.    Improper Risk Planning since all risks should be identified and accounted for


Correct Choice: 3

Justification: The most common active acceptance strategy is to establish a contingency reserve, including amounts of time,
money or resources, to handle known-or even sometimes potential, unknown - threats or opportunities.

Reference: PMBOK Third Edition, Page Number: 263
15. Please refer to this Decision Tree which shows the analysis of profit/loss for the two
      alternatives (i.e. to build or buy).




What is the opportunity cost if the project manager decides to build instead of buy?
1.   $ 1,500        
2.   $ 3,500        
3.   $ 1,500        
4.   $ 5,000
Correct Choice: 2
Justification: Please refer to the diagram:




Profit of Build : $ 5,000
Profit of Buy : $ 3,500
Opportunity cost of Build = Profit you give up if you do not buy = $ 3,500


Reference: pmstudy.com notes as mentioned above
Wrap Up
     Conference#: 702-696-4520 or 866-409-2889
     Participant – 370670831

11     Procurement Management and Tips    January 22   2:00pm    Presenter:       https://
           & Tricks (PMBOK Chapters 12)                    EST
                                                                    www.rooms.hp.com/attend/default.aspx?key
                                                                    =EHHP87PUR6
                                                                 Participant:     https://
                                                                    www.rooms.hp.com/attend/default.aspx?key
                                                                    =EPFBPLUR8X

More Related Content

PPT
Session 5 gdas pmp study group presentation
PPT
Session 4 gdas pmp study group presentation
PPT
Session 6 gdas pmp study group presentation
PPT
Session 2 gdas pmp study group presentation
PDF
Pm study project risk management test
PPT
Session 3 gdas pmp study group presentation
PPT
Session 8 gdas pmp study group presentation
PDF
Pmi sp questions with answers
Session 5 gdas pmp study group presentation
Session 4 gdas pmp study group presentation
Session 6 gdas pmp study group presentation
Session 2 gdas pmp study group presentation
Pm study project risk management test
Session 3 gdas pmp study group presentation
Session 8 gdas pmp study group presentation
Pmi sp questions with answers

What's hot (19)

PDF
Risk 9-pm study project risk management-test
PDF
Risk 0-risk-guide book for pmi-rmp by amer elbaz
PDF
Risk 8- pm study question risk management
PDF
Risk 6 questions - 170
PDF
Risk 5 simplelearn-exam4-ans
PDF
Pmp test 03
PDF
PMP 1600 Questions by TechFAQ360
PDF
Pmp test 04
PDF
Pmstudy exam_1
PDF
Pmstudy exam 2
PDF
Risk 2 simplelearn-exam1-ans
PDF
Self test engine PSP-PMI-SP
PDF
Pmp test 01
PDF
Risk 4 simplelearn-exam3-ans
PDF
11 pmp risk management exam
PDF
Pmstudy exam 4
PDF
Pmp test 02
PDF
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Risk 9-pm study project risk management-test
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 8- pm study question risk management
Risk 6 questions - 170
Risk 5 simplelearn-exam4-ans
Pmp test 03
PMP 1600 Questions by TechFAQ360
Pmp test 04
Pmstudy exam_1
Pmstudy exam 2
Risk 2 simplelearn-exam1-ans
Self test engine PSP-PMI-SP
Pmp test 01
Risk 4 simplelearn-exam3-ans
11 pmp risk management exam
Pmstudy exam 4
Pmp test 02
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ad

Viewers also liked (20)

PPT
Session 7 gdas pmp study group presentation
PPSX
PDF
01 project management framework
PDF
Pmp scope chapter 5
PDF
Pmp communication chapter 10
PDF
Pmp cost chapter 7
PDF
Pmp time chapter 6
PDF
Pmp integration chapter 4
PDF
Pmp quality chapter 8
PDF
Pmp risk chapter 11
PDF
PMP / Framework 1 2-3
PDF
Pmp stakeholder chapter 13
PDF
PDF
Pmp procurement chapter 12
PDF
Pmbok 4th edition chapter 12 - Project Procurement Management
PPT
Kpi for product manager
PDF
2015 Upload Campaigns Calendar - SlideShare
PPTX
What to Upload to SlideShare
PDF
Getting Started With SlideShare
Session 7 gdas pmp study group presentation
01 project management framework
Pmp scope chapter 5
Pmp communication chapter 10
Pmp cost chapter 7
Pmp time chapter 6
Pmp integration chapter 4
Pmp quality chapter 8
Pmp risk chapter 11
PMP / Framework 1 2-3
Pmp stakeholder chapter 13
Pmp procurement chapter 12
Pmbok 4th edition chapter 12 - Project Procurement Management
Kpi for product manager
2015 Upload Campaigns Calendar - SlideShare
What to Upload to SlideShare
Getting Started With SlideShare
Ad

Similar to Session 10 gdas pmp study group presentation (20)

PDF
Project risk management
PDF
Session 14 - Project Risk Management.pdf
PPTX
Day 5, 6 _ 7 - Project Risk Management.pptx
PDF
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
PPTX
The Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
PPTX
PMP (Project Management Professional) course prepares individuals
PDF
Beyond PMP: Risk Management
PPTX
Project risk management
PDF
Risk Management Best Practices
PPTX
Project risk management: Techniques and strategies
PDF
RISK TEMPLATE FORMATE GOOD-ALIU OLAB.pdf
PDF
07 managing risk
PPTX
A Guide to Risk Management
PPTX
Risk management
PPTX
Project of entrepreneurship
PPTX
Presentation Project managment
DOC
R I S K M A N A G E M E N T
PPTX
4554447637498498-Project-Risk-Management.pptx
PPT
Project Risk management
PDF
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Project risk management
Session 14 - Project Risk Management.pdf
Day 5, 6 _ 7 - Project Risk Management.pptx
2013 Geospatial Data and Project Management Track, Risk Management in Geospat...
The Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
PMP (Project Management Professional) course prepares individuals
Beyond PMP: Risk Management
Project risk management
Risk Management Best Practices
Project risk management: Techniques and strategies
RISK TEMPLATE FORMATE GOOD-ALIU OLAB.pdf
07 managing risk
A Guide to Risk Management
Risk management
Project of entrepreneurship
Presentation Project managment
R I S K M A N A G E M E N T
4554447637498498-Project-Risk-Management.pptx
Project Risk management
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd

More from Tu Nguyen, PMP®,PMI-RMP® (20)

PPSX
PPSX
PPSX
Arrow computation
PPSX
PPSX
Time cost-trade-off
PPSX
Time cost-control
PPSX
PDF
Ch 6 construction progress control
PDF
Ch 4 cash flow and investment appraisal
PDF
Ch 3 contract strategy
PDF
Ch 2 planning and scheduling
PDF
Ch 1 organization of construction projects
Arrow computation
Time cost-trade-off
Time cost-control
Ch 6 construction progress control
Ch 4 cash flow and investment appraisal
Ch 3 contract strategy
Ch 2 planning and scheduling
Ch 1 organization of construction projects

Session 10 gdas pmp study group presentation

  • 1. GDAS PM Professions: PMP Study Group Session #10: Risk Management Monique Howard January 8, 2009 © 2005 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice
  • 2. 1. In your project, you can use all the following tools and techniques for risk response planning EXCEPT: 1. Strategies for negative risks or threats 2. Contingent response planning 3. Strategy for threat and opportunities 4. Strategy for residual risks
  • 3. 1. In your project, you can use all the following tools and techniques for risk response planning EXCEPT: 1. Strategies for negative risks or threats 2. Contingent response planning 3. Strategy for threat and opportunities 4. Strategy for residual risks Correct Choice: 4 Justification: Figure 11-14 Reference: PMBOK Third Edition, Page Number: 260
  • 4. 2. You are the project manager in an automobile manufacturing company. A vendor was sending you the machine parts required in your manufacturing process,but the parts did not reach in time because of heavy rains. You had anticipated this risk and planned for it in your risk response plan. So, as per your risk response plan, you started using machine parts which had been supplied one year ago and were not utilized at that time. However, this has subjected your project to a new risk - that the machine parts which were not used for one year might be having higher level of defects. This new risk can also be called: 1. Unidentifiable Risk 2. Unmanageable Risk 3. Secondary Risk 4. Residual Risk
  • 5. 2. You are the project manager in an automobile manufacturing company. A vendor was sending you the machine parts required in your manufacturing process,but the parts did not reach in time because of heavy rains. You had anticipated this risk and planned for it in your risk response plan. So, as per your risk response plan, you started using machine parts which had been supplied one year ago and were not utilized at that time. However, this has subjected your project to a new risk - that the machine parts which were not used for one year might be having higher level of defects. This new risk can also be called: 1. Unidentifiable Risk 2. Unmanageable Risk 3. Secondary Risk 4. Residual Risk Correct Choice: 3 Justification: Secondary risks that arise as a direct outcome of implementing a risk response. Reference: PMBOK Third Edition, Page Number: 264
  • 6. 3. In your project, you have identified important risks, and planned appropriate responses to the risks. Some risks e.g. possibility of natural disasters have been documented and accepted in your risk management plan. If there are risks that remain after you have taken these steps, then such risks are called: 1. Unidentifiable Risks 2. Residual Risks 3. Secondary Risks 4. Accepted Risks
  • 7. 4. Risk Management Planning is the process of deciding how to approach and plan the risk management activities for a project. It is important to plan for the risk management processes that follow to ensure that the level, type, and visibility of risk management are commensurate with both the risk and importance of the project to the organization. The output of Risk Management Planning is: 1. Risks 2. Risk Management Plan 3. Risk Ranking of the Project 4. Planning Meetings
  • 8. 3. In your project, you have identified important risks, and planned appropriate responses to the risks. Some risks e.g. possibility of natural disasters have been documented and accepted in your risk management plan. If there are risks that remain after you have taken these steps, then such risks are called: 1. Unidentifiable Risks 2. Residual Risks 3. Secondary Risks 4. Accepted Risks Correct Choice: 2 Justification: Residual risks that are expected to remain after planned responses have been taken, as well as those which have been deliberately accepted. Reference: PMBOK Third Edition, Page Number: 264
  • 9. 4. Risk Management Planning is the process of deciding how to approach and plan the risk management activities for a project. It is important to plan for the risk management processes that follow to ensure that the level, type, and visibility of risk management are commensurate with both the risk and importance of the project to the organization. The output of Risk Management Planning is: 1. Risks 2. Risk Management Plan 3. Risk Ranking of the Project 4. Planning Meetings Correct Choice: 2 Justification: Figure 11-3 Reference: PMBOK Third Edition, Page Number: 242
  • 10. 5. In your project, you have identified a list of identified risks, a list of potential responses and root causes of risks. You should document this information in the : 1. Risk Management Plan 2. Risk Database 3. Project Plan 4. Risk Register
  • 11. 5. In your project, you have identified a list of identified risks, a list of potential responses and root causes of risks. You should document this information in the : 1. Risk Management Plan 2. Risk Database 3. Project Plan 4. Risk Register Correct Choice: 4 Justification: The risk register includes a list of identified risks, a list of potential responses, root causes of risk, and updated risk categories. Reference: PMBOK Third Edition, Page Number: 249
  • 12. 6. Risk management helps in maximizing the probability and consequences of positive events and minimizing the probability and consequences of adverse events to project objectives. Risk Response Planning helps in this context because it: 1. helps in deciding how to approach and plan the risk management activities. 2. develops procedures and techniques to enhance opportunities and reduce threats to project objectives. 3. determines which risks might affect the project and documents their characteristics. 4. monitors residual risks, identifies new risks and executes risk reduction plans.
  • 13. 6. Risk management helps in maximizing the probability and consequences of positive events and minimizing the probability and consequences of adverse events to project objectives. Risk Response Planning helps in this context because it: 1. helps in deciding how to approach and plan the risk management activities. 2. develops procedures and techniques to enhance opportunities and reduce threats to project objectives. 3. determines which risks might affect the project and documents their characteristics. 4. monitors residual risks, identifies new risks and executes risk reduction plans. Correct Choice: 2 Justification: Risk response planning - developing options and actions to enhance opportunities, and reducing threats to project objectives. Reference: PMBOK Third Edition, Page Number: 237 pmstudy.com comments: * Option 1: This is Risk Management Planning * Option 3: This is Risk Identification * Option 4: This is Risk Monitoring and Control
  • 14. 7. Utility function is a commonly used technique to find out the tolerance of a project manager towards risk. Some project managers are more averse to risk than others. All of the following are different classifications of tolerance for risk EXCEPT: 1. Risk Averter 2. Risk Seeker 3. Risk Mitigator 4. Risk Neutral
  • 15. 7. Utility function is a commonly used technique to find out the tolerance of a project manager towards risk. Some project managers are more averse to risk than others. All of the following are different classifications of tolerance for risk EXCEPT: 1. Risk Averter 2. Risk Seeker 3. Risk Mitigator 4. Risk Neutral Correct Choice: 3 Justification: Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 906
  • 16. 8. As part of the Risk Management Process, you just created an overall risk ranking of the project and a list of prioritized risks, identified which risks need additional analysis and determined trends in risk analysis results. What should you do next? 1. Analyze the effect of risk events and assign a numerical rating to those risks. 2. Create a list of identified risks. 3. Determine the fundamental conditions or events that may give rise to identified risk (root causes of risk). 4. Make a list of potential responses to the risks.
  • 17. 8. As part of the Risk Management Process, you just created an overall risk ranking of the project and a list of prioritized risks, identified which risks need additional analysis and determined trends in risk analysis results. What should you do next? 1. Analyze the effect of risk events and assign a numerical rating to those risks. 2. Create a list of identified risks. 3. Determine the fundamental conditions or events that may give rise to identified risk (root causes of risk). 4. Make a list of potential responses to the risks. Correct Choice: 1 Justification: Tasks like creating an overall risk ranking of the project, which includes a list of prioritized risks, identifying which risks need additional analysis and determining trends in risk analysis results - are all outputs of Qualitative Risk Analysis (PMBOK Page 253). So, the next step is to perform Quantitative Risk Analysis (i.e. analyze the effect of risk events and assign a numerical rating to those risks) - (PMBOK Page 254) Please note that Option 2, Option 3 and Option 4 refer to outputs from Risk Identification Phase which has already been completed (PMBOK Page 249) Reference: pmstudy.com notes as mentioned above
  • 18. 9. You are in the process of developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives. What should you be doing next? 1. Determining which risks might affect the project and documenting their characteristics. 2. Identifying, analyzing and planning for newly arising risks. 3. Deciding how to approach and conduct risk management activities for the project. 4. Assessing the priority of identified risks using their probability of occurring.
  • 19. 9. You are in the process of developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives. What should you be doing next? 1. Determining which risks might affect the project and documenting their characteristics. 2. Identifying, analyzing and planning for newly arising risks. 3. Deciding how to approach and conduct risk management activities for the project. 4. Assessing the priority of identified risks using their probability of occurring. Correct Choice: 2 Justification: "Developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives" - this is Risk Response Planning; PMBOK Page 260 "Identifying, analyzing and planning for newly arising risks" - this is Risk Monitoring and Control - PMBOK Page 264. Please note that this happens after Risk Response Planning and is the correct answer The other options happen before Risk Response Planning: Determining which risks might affect the project and documenting their characteristics (Risk Identification, PMBOK Page 246) Deciding how to approach and conduct risk management activities for the project (Risk Management Planning - PMBOK Page 242) Assessing the priority of identified risks using their probability of occurring (Qualitative Risk Analysis - PMBOK Page 249) Reference: pmstudy.com notes as mentioned above
  • 20. 10. You are in the build phase of the project. But it has run into several unanticipated problems. Several risks have surfaced which you had not anticipated earlier. The project is over-budget and behind schedule. What should you do? 1. Create updates to risk response plan 2. Create a revised project plan 3. Perform risk response audits 4. Perform updated risk identification and analysis
  • 21. 10. You are in the build phase of the project. But it has run into several unanticipated problems. Several risks have surfaced which you had not anticipated earlier. The project is over-budget and behind schedule. What should you do? 1. Create updates to risk response plan 2. Create a revised project plan 3. Perform risk response audits 4. Perform updated risk identification and analysis Correct Choice: 4 Justification: Results from an earned value analysis may indicate potential deviation of the project at completion from cost and schedule targets. When a project deviates significantly from the baseline, updated risk identification and analysis should be performed. Reference: pmstudy.com notes as mentioned above
  • 22. 11. In your project, there is: * 50% probability of $ 40,000 profit * 50% probability of $ 25,000 loss What is the expected profit in your project? 1. $ 32,500 2. $ 25,000 3. $ 7,500 4. - $ 7,500 (i.e. loss of $ 7,500)
  • 23. 11. In your project, there is: * 50% probability of $ 40,000 profit * 50% probability of $ 25,000 loss What is the expected profit in your project? 1. $ 32,500 2. $ 25,000 3. $ 7,500 4. - $ 7,500 (i.e. loss of $ 7,500) Correct Choice: 3 Justification: Expected Profit = Sum of (Probability X Profit) (for each alternative) = (0.50 x $ 40,000) + (0.50 x - $ 25,000) = $ 20,000 - $ 12,500 = $ 7,500 profit Reference: pmstudy.com notes as mentioned above
  • 24. 12. In risk response planning, you are in the process of developing options, and determining actions to reduce threats to your project`s objectives. When you show the results of your risk response planning to your project sponsor, she is not comfortable with the risks in the project and she suggests that the project scope should be decreased. This is an example of : 1. Inappropriate risk management because it is having a direct impact on your project scope 2. Risk Avoidance 3. Risk Mitigation 4. Risk Transfer
  • 25. 12. In risk response planning, you are in the process of developing options, and determining actions to reduce threats to your project`s objectives. When you show the results of your risk response planning to your project sponsor, she is not comfortable with the risks in the project and she suggests that the project scope should be decreased. This is an example of : 1. Inappropriate risk management because it is having a direct impact on your project scope 2. Risk Avoidance 3. Risk Mitigation 4. Risk Transfer Correct Choice: 2 Justification: Risk avoidance involves changing the project management plan to elimiate the threat posed by an adverse risk.... or to relax the objective that is in jeopardy, such as extending the schedule or reducing scope. Reference: PMBOK Third Edition, Page Number: 261
  • 26. 13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which the data about risks is useful for risk management. What could be a potential next step? 1. Perform a structured review of project plans and assumptions, both at the total project and detailed scope levels 2. Develop checklists for identifying risks based on historical information and knowledge that has been accumulated from previous similar projects 3. Conduct planning meetings to develop the risk management plan 4. Conduct interviews to quantify the probability and consequences of risks on project activities
  • 27. 13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which the data about risks is useful for risk management. What could be a potential next step? 1. Perform a structured review of project plans and assumptions, both at the total project and detailed scope levels 2. Develop checklists for identifying risks based on historical information and knowledge that has been accumulated from previous similar projects 3. Conduct planning meetings to develop the risk management plan 4. Conduct interviews to quantify the probability and consequences of risks on project activities Correct Choice: 4 Justification: Risk data quality analysis is a tool for Qualitative Risk Analysis. * Option 4 refers to "Interviewing" which is a tool and technique for Quantitative Risk Analysis. Quantitative Risk Analysis is conducted after Qualitatitive Risk Analysis * Option 1 refers to "Documentation Reviews" which is a tool and technique for Risk Identification. Risk Identification is conducted before Qualitatitive Risk Analysis * Option 2 refers to "Checklists" which is a tool and technique for Risk Identification. Risk Identification is conducted before Qualitatitive Risk Analysis * Option 3 refers to "Planning Meetings" which is a tool and technique for Risk Management Planning. Risk Management Planning is conducted before Qualitatitive Risk Analysis Reference: pmstudy.com notes as mentioned above
  • 28. 14. You are the project manager of a project which involves oil-exploration in the ocean. Since you cannot plan for all eventualities, you establish a contingency reserve, including amounts of time, money or resources to handle known or unknown risks. This is an example of : 1. Risk Avoidance 2. Risk Transfer 3. Active Risk Acceptance 4. Improper Risk Planning since all risks should be identified and accounted for
  • 29. 14. You are the project manager of a project which involves oil-exploration in the ocean. Since you cannot plan for all eventualities, you establish a contingency reserve, including amounts of time, money or resources to handle known or unknown risks. This is an example of : 1. Risk Avoidance 2. Risk Transfer 3. Active Risk Acceptance 4. Improper Risk Planning since all risks should be identified and accounted for Correct Choice: 3 Justification: The most common active acceptance strategy is to establish a contingency reserve, including amounts of time, money or resources, to handle known-or even sometimes potential, unknown - threats or opportunities. Reference: PMBOK Third Edition, Page Number: 263
  • 30. 15. Please refer to this Decision Tree which shows the analysis of profit/loss for the two alternatives (i.e. to build or buy). What is the opportunity cost if the project manager decides to build instead of buy? 1. $ 1,500         2. $ 3,500         3. $ 1,500         4. $ 5,000
  • 31. Correct Choice: 2 Justification: Please refer to the diagram: Profit of Build : $ 5,000 Profit of Buy : $ 3,500 Opportunity cost of Build = Profit you give up if you do not buy = $ 3,500 Reference: pmstudy.com notes as mentioned above
  • 32. Wrap Up Conference#: 702-696-4520 or 866-409-2889 Participant – 370670831 11 Procurement Management and Tips January 22 2:00pm Presenter: https:// & Tricks (PMBOK Chapters 12) EST www.rooms.hp.com/attend/default.aspx?key =EHHP87PUR6 Participant: https:// www.rooms.hp.com/attend/default.aspx?key =EPFBPLUR8X