The document describes procedures for updating construction schedules, including:
1) Setting the duration of completed activities to zero and identifying live activities currently in progress.
2) Setting the early start time of live activities to the update time and their remaining durations.
3) Changing durations of future activities as given in the update report and performing network analysis to prepare a new schedule.