SlideShare a Scribd company logo
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
0. Introduction
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control Costs
Lecture 07 : Project Cost Management (1/18)
Contents
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (2/18)
Introduction
Direct vs. Indirect Cost
1. Direct Cost: Directly attributable to project work. ‫المشروع‬ ‫بأعمال‬ ‫مباشرة‬ ‫تتأثر‬
2. Indirect cost: Such as overhead, benefits, and costs incurred for more than
project like equipments. ‫المشاريع‬ ‫بين‬ ‫المشتركة‬ ‫التكاليف‬ ‫و‬ ‫االرباح‬ ‫و‬ ‫العامة‬ ‫النفقات‬ ‫مثل‬
Fixed vs. Variable Cost
1. Fixed cost: Costs that are not changed with production such as setup cost
and rental cost ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫ال‬ ‫تكاليف‬
2. Variable cost: Costs that are changed with production such as material and
labors. ‫الخام‬ ‫المواد‬ ‫و‬ ‫العمالة‬ ‫تكاليف‬ ‫مثل‬ ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫التي‬ ‫التكاليف‬
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (3/18)
Introduction
Definitions :
 Life Cycle Cost : Looking at the whole life cost.
(Ex: Don’t pay less for lower quality then pay more for maintenance.
‫المنتج‬ ‫حياة‬ ‫دورة‬ ‫تكاليف‬:‫المنتج‬ ‫عمر‬ ‫مراحل‬ ‫جميع‬ ‫في‬ ‫التكاليف‬ ‫دراسة‬ ‫يتم‬
‫مثال‬:‫الصيانة‬ ‫و‬ ‫التشغيل‬ ‫مراحل‬ ‫في‬ ً‫ا‬‫كثير‬ ‫تدفع‬ ‫ثم‬ ‫ضعيفة‬ ‫جودة‬ ‫معايير‬ ‫باختيار‬ ‫بالتوفير‬ ‫تقوم‬ ‫ال‬
 Value Analysis (value engineering) : Finding a less costly way to perform
the same work. ‫القيمة‬ ‫تحليل‬:‫األعمال‬ ‫نفس‬ ‫النجاز‬ ‫تكلفة‬ ‫اقل‬ ‫طرق‬ ‫ايجاد‬ ‫عن‬ ‫عبارة‬
Lecture 07 : Project Cost Management (4/18)
1.Plan Cost Management (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7.1 Plan Cost Management
Inputs :
 Project Management Plan
 Project Charter
 Enterprise Environmental Factors
 Organizational Process Assets
Tools and Techniques :
 Expert Judgment
 Analytical Techniques
 Meetings
Outputs :
 Cost Management Plan
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Analytical Techniques
• Strategic options to fund the project
o Self-funding,
o Funding with equity, (Ex: Stocks) ‫التمويل‬‫خالل‬ ‫من‬‫باألسهم‬ ‫كما‬ ‫المشاركة‬
o Funding with debt (Ex: Bonds) ‫بالسندات‬ ‫كما‬ ‫االقتراض‬ ‫خالل‬ ‫من‬ ‫التمويل‬
• Project resources Finance
o Making,
o Purchasing,
o Renting (Short Term),
o Leasing (Long Term).
• Financial analysis techniques:
o payback period,
o Return on investment (value),
o Internal rate of return,
o Net present value.
Lecture 07 : Project Cost Management (5/18)
1.Plan Cost Management (Planning)
TT
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Cost Management Plan : ‫التكاليف‬ ‫إدارة‬ ‫خطة‬
• Establish the criteria for planning, structuring, estimating, budgeting, and
control project cost. ‫المشروع‬ ‫تكاليف‬ ‫مراقبة‬ ‫و‬ ‫موازنة‬ ‫و‬ ‫تقدير‬ ‫و‬ ‫هيكلة‬ ‫و‬ ‫تخطيط‬ ‫معايير‬ ‫تأسيس‬
• Cost management plan may includes: ‫على‬ ‫الخطة‬ ‫تحتوي‬ ‫ان‬ ‫يمكن‬
1. Units of measure ( ex: staff hours) ‫القياس‬ ‫وحدات‬
2. Level of Precision (rounding up or down, ex: $125.3  $125)
3. Level of Accuracy (ex: ± 5%)
4. Organizational Links (with accounting systems)
5. Control thresholds ( level at which an action needs to be taken)
6. Rules of performance measurement (Procedures)
7. Reporting formats
Lecture 07 : Project Cost Management (6/18)
1.Plan Cost Management (Planning)
O
Lecture 07 : Project Cost Management (7/18)
2.Estimate Costs (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7 . 2 E s t i m a t e C o s t s
Inputs :
 Cost Management Plan ■ Scope Baseline
 Human Resource Management Plan ■ Project Schedule
 Risk Register ■ Enterprise Environmental Factors
 Organizational Process Assets
Tools and Techniques :
 Expert Judgment ■ Analogous Estimating
 Parametric Estimating ■ Bottom-Up Estimating
 Three-Point Estimates ■ Reserve Analysis
 Cost of Quality ■ Project Management Software
 Group Decision-Making Techniques ■ Vendor Bid Analysis
Outputs :
 Activity Cost Estimates
 Basis of Estimates
 Project Document Updates
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (8/18)
2.Estimate Costs (Planning)
Cost of Quality:
• All costs incurred in preventing nonconformance, apprising, or rework. This
will be illustrated later in Quality Management.
Vendor Bid Analysis:
• Analysis of cost estimate based on responsive bids from qualified vendors.
Cost Estimates:
Costs are estimated for all resources such as:
• Direct Cost (Labor, materials, equipment, services, facilities, IT)
• Cost of financing (interest), inflation allowance, exchange rates.
• Contingency reserve.
• Insurance fees.
• Taxes
• Overhead (Site overhead and main office)
TT
O
TT
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (9/18)
2.Estimate Costs (Planning)
Basis of Estimates :
• Supporting documentation which provides understanding of how the cost
estimate was derived.
• This may includes:
• Assumptions.
• Constraints.
• Ranges of accuracy (ex:± 5%).
• Confidence level of the final cost estimate.
O
Lecture 07 : Project Cost Management (10/18)
3.Determine Budget (Planning)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7 . 3 D e t e r m i n e B u d g e t
Inputs :
 Cost Management Plan ■ Scope Baseline
 Activity Cost Estimates ■ Basis of Estimates
 Project Schedule ■ Resource Calendars
 Risk Register ■ Agreements
 Organizational Process Assets
Tools and Techniques :
 Cost Aggregation
 Reserve Analysis
 Expert Judgment
 Historical Relationships
 Funding Limit Reconciliation ‫توفيق‬
Outputs :
 Cost Baseline
 Project Funding Requirements
 Project Document Updates
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (11/18)
3.Determine Budget (Planning)
Cost Aggregation :
• Cost Estimates are aggregated within activities and rolled up to work
package then rolled up to control accounts then rolled up to entire project.
‫بالكامل‬ ‫المشروع‬ ‫الى‬ ‫ثم‬ ‫التحكم‬ ‫حسابات‬ ‫الى‬ ‫ثم‬ ‫العمل‬ ‫حزم‬ ‫الى‬ ‫األنشطة‬ ‫مستوى‬ ‫من‬ ‫التكاليف‬ ‫تجميع‬
Reserve Analysis :
1. Contingency Reserve : Allowances for
unplanned changes result from identified risks.
2. Management Reserve : Budgets reserved for
unplanned changes to scope and cost.
Cost estimates
Contingency Reserve
Management Reserve
CostBudget
CostBaseline
TT
TT
Historical Relationships:
• Historical Relationships involve the use of project characteristics
(parameters) to develop mathematical models to predict total project costs.
• This results in parametric estimates or analogous estimates.
TT
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Lecture 07 : Project Cost Management (12/18)
3.Determine Budget (Planning)
Funding Limit Reconciliation : ‫التمويل‬ ‫لقيود‬ ‫طبقا‬ ‫المعالجة‬
• Sometimes funds are not available when needed and you have to
reschedule the activities. ‫االنشطة‬ ‫جدولة‬ ‫اعادة‬ ‫الي‬ ‫يضطرك‬ ‫مما‬ ‫تمويل‬ ‫يوجد‬ ‫ال‬ ‫احيانا‬
• Expenditures should be reconciled with any funding limits
‫التمويل‬ ‫على‬ ‫موجودة‬ ‫قيود‬ ‫ألي‬ ‫طبقا‬ ‫االنفاق‬ ‫خطة‬ ‫توفيق‬ ‫و‬ ‫معالجة‬ ‫من‬ ‫بد‬ ‫ال‬
• Example : Funds for the project will be available on two batches :
$50 millions today and $40 millions in the beginning of the next year.
Cost Baseline : ‫التكلفة‬ ‫أساس‬ ‫خط‬
• The planned costs over project time. It’s used to
control cost performance in the project. ‫التكاليف‬
‫المخطط‬‫انفاقها‬‫عبر‬‫زمن‬‫المشروع‬
Project Funding Requirements : ‫المشروع‬ ‫تمويل‬ ‫متطلبات‬
• It can be derived from cost baseline. Funding
often occurs in incremental amounts.
‫دفعات‬ ‫على‬ ‫تكون‬ ‫ما‬ ‫غالبا‬ ‫و‬ ‫التكلفة‬ ‫أساس‬ ‫خط‬ ‫من‬ ‫استنتاجها‬ ‫يمكن‬
TT
O
O
Lecture 07 : Project Cost Management (13/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
C o s t M a n a g e m e n t
7 . 4 C o n t r o l C o s t s
Inputs :
 Project Management Plan
 Project Funding Requirements
 Work Performance Information Data
 Organizational Process Assets
Tools and Techniques :
 Earned Value Management
 Forecasting
 To Complete Performance Index (TCPI)
 Performance Reviews
 Project Management Software
 Reserve Analysis
Outputs :
 Work Performance Information ■ Cost Forecasts
 Project Management Plan Updates ■ Change Requests
 Organizational Process Assets Updates ■ Project Document Updates
Lecture 07 : Project Cost Management (14/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Earned Value Management : ‫المكتسبة‬ ‫القيمة‬ ‫ادارة‬
• Planned Value (PV) = Budgeted cost for work scheduled (BCWS)
‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫تنفيذها‬ ‫المخطط‬ ‫األعمال‬ ‫قيمة‬
• Earned value (EV) = Budgeted cost for work performed (BCWP)
‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫فعلية‬ ‫اعمال‬ ‫تنفيذ‬ ‫من‬ ‫المكتسبة‬ ‫القيمة‬
• Actual Cost (AC) = Actual cost for work performed (ACWP)
‫تنفيذها‬ ‫تم‬ ‫التي‬ ‫لالعمال‬ ‫الفعلية‬ ‫التكاليف‬
• Schedule Variance (SV) = EV – PV ‫انحراف‬(‫تباين‬)‫الزمني‬ ‫الجدول‬
• Cost Variance (CV) = EV – AC ‫التكلفة‬ ‫انحراف‬
• Schedule Performance Index (SPI) = EV / PV ‫الزمني‬ ‫الجدول‬ ‫أداء‬ ‫مؤشر‬
• Cost Performance Index (CPI) = EV / AC ‫التكلفة‬ ‫أداء‬ ‫مؤشر‬
Behind Schedule ‫متأخر‬‫الجدول‬ ‫عن‬SV < 0
On Schedule ‫الجدول‬ ‫مع‬SV = 0
Ahead of Schedule ‫الجدول‬ ‫سابق‬SV > 0
Over Budget ‫الميزانية‬ ‫تعدى‬CV < 0
On Budget ‫الميزانية‬ ‫مع‬CV = 0
Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CV > 0
Behind ScheduleSPI < 1
On ScheduleSPI = 1
Ahead of ScheduleSPI > 1
Over Budget ‫الميزانية‬ ‫تعدى‬CPI < 1
On Budget ‫الميزانية‬ ‫مع‬CPI = 1
Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CPI > 1
TT
Lecture 07 : Project Cost Management (15/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Example :
PV (BCWS) =1000x120 = 120,000.00
EV (BCWP) =1000x130 = 130,000.00
AC (ACWP) =1200*130 = 156,000.00
Variance :
SV = EV - PV = 130'000 - 120'000 = 10'000 (Ahead of Schedule)
CV = EV - AC = 130'000 - 156'000 = -26'000 (Over Budget)
Performance Index
SPI = EV / PV = 130'000 / 120'000 = 1.083 (Ahead of Schedule)
CVI = EV / AC = 130'000 / 156'000 = 0.833 (Over Budget)
Cost/Unit Quantity
Budget 1000 120
Actual 1200 130
Lecture 07 : Project Cost Management (16/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Time
Cost
Lecture 07 : Project Cost Management (17/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
Forecasting : ‫معايير‬ ‫خالل‬ ‫من‬ ‫التوقع‬
• Estimate at Completion (EAC) = Actual Cost+ Estimate to Complete (ETC).
‫المشروع‬ ‫نهاية‬ ‫في‬ ‫المتوقعة‬ ‫القيمة‬=‫اآلن‬ ‫حتى‬ ‫الفعلية‬ ‫القيمة‬+‫المشروع‬ ‫النهاء‬ ‫المتوقع‬
• There are various methods to calculate the Estimate to Complete (ETC)
‫المشروع‬ ‫النهاء‬ ‫المتوقعة‬ ‫القيمة‬ ‫لحساب‬ ‫طرق‬ ‫عدة‬ ‫يوجد‬
1- At the budgeted rate :
EAC = AC + (BAC – EV)
2- Considering CPI :
EAC = AC + [ (BAC – EV) / CPI ] = AC + BAC/CPI – EV/CPI
= AC + BAC/CPI – AC = BAC / CPI
3- Considering CPI and SPI :
EAC = AC + [ (BAC – EV) / (CPI x SPI) ]
TT
Lecture 07 : Project Cost Management (18/18)
4.Control Costs (M/C)
PMP Lectures Prepared By: Eng. Mohamed
ElSaadany
To Complete Performance Index (TCPI) : ‫المشروع‬ ‫إلكمال‬ ‫المطلوبة‬ ‫للقيمة‬ ‫اآلداء‬ ‫مؤشر‬
• It’s the cost performance that must be achieved on the remaining work to
meet a specified goal like BAC or EAC ‫القادمة‬ ‫الفترة‬ ‫في‬ ‫تحقيقه‬ ‫المطلوب‬ ‫المالي‬ ‫االداء‬
• It represents the ratio between remaining works and remaining funds.
‫المتبقي‬ ‫التمويل‬ ‫قيمة‬ ‫و‬ ‫المتبقية‬ ‫االعمال‬ ‫قيمة‬ ‫بين‬ ‫النسبة‬ ‫تمثل‬
• TCPI = (BAC-EV) / (BAC – AC)
Or TCPI = (BAC-EV) / (EAC – AC) “If the BAC is no longer valid”
• Ex :
BAC = 500’000.00 , EV = 200’000.00, AC= 250’000.00
TCPI = (300’000.00 ) / (250’000.00) = 1.2
TT
Performance Reviews :
• Variance at completion (VAC) = BAC – EAC
• Trend Analysis: Graphical analysis examines project performance over time.
• EVM
TT

More Related Content

PPTX
PMP Preparation - 06 Time Management
PPTX
PMP Preparation - 05 Scope Management
PDF
PDF
Time Impact Analysis
PPTX
Project portfolio management
PDF
Baseline Schedules 2
PDF
Criterium epc project risks (5.28.13)
PDF
Project Risk Management
PMP Preparation - 06 Time Management
PMP Preparation - 05 Scope Management
Time Impact Analysis
Project portfolio management
Baseline Schedules 2
Criterium epc project risks (5.28.13)
Project Risk Management

What's hot (20)

PPSX
Pmp presentation chapter 1 to 7
PDF
FIDIC variation, claim & dispute - CYLFEx workshop
PDF
Project Risk Management
PDF
مقدمة عن إدارة التكاليف والشهادات الاحترافية
PPTX
Forensic schedule analysis acesss
PDF
Project Management Concepts
PPTX
Enterprise Project Structure (EPS)
PPTX
Earned Value Management - Leading & Misleading in Project Control
PPTX
Project Cost Management
PPTX
Project management
PDF
PVD Project Control Best Practices for Large Projects
PPTX
Introduction to project management
PPTX
Project risk management
PDF
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
PPTX
Project Monitoring and Control
PPT
Project risk management
PDF
Project Duration Estimation
PDF
Practitioner class 3: Contract strategy
PDF
Practical Project Cost Control for Large Complex Projects
PPTX
Project Cost Management
Pmp presentation chapter 1 to 7
FIDIC variation, claim & dispute - CYLFEx workshop
Project Risk Management
مقدمة عن إدارة التكاليف والشهادات الاحترافية
Forensic schedule analysis acesss
Project Management Concepts
Enterprise Project Structure (EPS)
Earned Value Management - Leading & Misleading in Project Control
Project Cost Management
Project management
PVD Project Control Best Practices for Large Projects
Introduction to project management
Project risk management
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Project Monitoring and Control
Project risk management
Project Duration Estimation
Practitioner class 3: Contract strategy
Practical Project Cost Control for Large Complex Projects
Project Cost Management
Ad

Similar to PMP Preparation - 07 Cost Management (20)

PPTX
day 3 PMP.pptx
PPTX
day 3-2 PMP.pptx
PDF
CCP Course - Introduction.pdf
PDF
PM Notebook - Chapter 7 - Cost Management
PDF
project Cost management
PPTX
cost Management V4
PDF
Chap 7.1 Plan Cost Management
PDF
PMP Chap 7 - Project Cost Management - Part 1
PPTX
Professional project cost management
PPTX
PMP Preparation - 08 Quality Management
PPT
FINAL PROJECT COST MANAGEMENT STUDENT COPY.ppt
PPTX
Part (1 1)
PDF
07.cost management updated
PDF
07 project cost management
PPTX
Lecture 06 project_cost_management
PDF
8. implementation (2) cost management
PPTX
Cost management
PPTX
Project Cost Management - PMBOK6
PPT
P ex cost management-1
PPTX
7.0 Project Cost Management Overview
day 3 PMP.pptx
day 3-2 PMP.pptx
CCP Course - Introduction.pdf
PM Notebook - Chapter 7 - Cost Management
project Cost management
cost Management V4
Chap 7.1 Plan Cost Management
PMP Chap 7 - Project Cost Management - Part 1
Professional project cost management
PMP Preparation - 08 Quality Management
FINAL PROJECT COST MANAGEMENT STUDENT COPY.ppt
Part (1 1)
07.cost management updated
07 project cost management
Lecture 06 project_cost_management
8. implementation (2) cost management
Cost management
Project Cost Management - PMBOK6
P ex cost management-1
7.0 Project Cost Management Overview
Ad

More from Mohamed ElSaadany, PMP, CCP, PMI-RMP, SCE-PE (11)

PDF
مكتب إدارة المشاريع. الفرص والتحديات
PPTX
A lecture on CCP Certificate
PDF
Construction KPIs & Dashboards
PPTX
PMP Preparation - 10 Communication Management
PPTX
PMP Preparation - 11 Risk Management
PPTX
PMP Preparation - 09 Human Resource Management
PPTX
PPTX
PMP Preparation - 03 Framework
PPTX
PMP Preparation - 01 Get Ready
PPTX
Project Management Applications Using Google Documents
مكتب إدارة المشاريع. الفرص والتحديات
A lecture on CCP Certificate
Construction KPIs & Dashboards
PMP Preparation - 10 Communication Management
PMP Preparation - 11 Risk Management
PMP Preparation - 09 Human Resource Management
PMP Preparation - 03 Framework
PMP Preparation - 01 Get Ready
Project Management Applications Using Google Documents

Recently uploaded (20)

PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PPTX
Cell Types and Its function , kingdom of life
PDF
Complications of Minimal Access Surgery at WLH
PPTX
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
RMMM.pdf make it easy to upload and study
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
Institutional Correction lecture only . . .
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PPTX
Week 4 Term 3 Study Techniques revisited.pptx
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
Basic Mud Logging Guide for educational purpose
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Business Ethics Teaching Materials for college
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
Cell Types and Its function , kingdom of life
Complications of Minimal Access Surgery at WLH
Introduction_to_Human_Anatomy_and_Physiology_for_B.Pharm.pptx
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
RMMM.pdf make it easy to upload and study
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
TR - Agricultural Crops Production NC III.pdf
Institutional Correction lecture only . . .
Anesthesia in Laparoscopic Surgery in India
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
Week 4 Term 3 Study Techniques revisited.pptx
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Basic Mud Logging Guide for educational purpose
Final Presentation General Medicine 03-08-2024.pptx
Business Ethics Teaching Materials for college

PMP Preparation - 07 Cost Management

  • 1. PMP Lectures Prepared By: Eng. Mohamed ElSaadany 0. Introduction 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget 4. Control Costs Lecture 07 : Project Cost Management (1/18) Contents
  • 2. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (2/18) Introduction Direct vs. Indirect Cost 1. Direct Cost: Directly attributable to project work. ‫المشروع‬ ‫بأعمال‬ ‫مباشرة‬ ‫تتأثر‬ 2. Indirect cost: Such as overhead, benefits, and costs incurred for more than project like equipments. ‫المشاريع‬ ‫بين‬ ‫المشتركة‬ ‫التكاليف‬ ‫و‬ ‫االرباح‬ ‫و‬ ‫العامة‬ ‫النفقات‬ ‫مثل‬ Fixed vs. Variable Cost 1. Fixed cost: Costs that are not changed with production such as setup cost and rental cost ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫ال‬ ‫تكاليف‬ 2. Variable cost: Costs that are changed with production such as material and labors. ‫الخام‬ ‫المواد‬ ‫و‬ ‫العمالة‬ ‫تكاليف‬ ‫مثل‬ ‫االنتاج‬ ‫مع‬ ‫تتغير‬ ‫التي‬ ‫التكاليف‬
  • 3. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (3/18) Introduction Definitions :  Life Cycle Cost : Looking at the whole life cost. (Ex: Don’t pay less for lower quality then pay more for maintenance. ‫المنتج‬ ‫حياة‬ ‫دورة‬ ‫تكاليف‬:‫المنتج‬ ‫عمر‬ ‫مراحل‬ ‫جميع‬ ‫في‬ ‫التكاليف‬ ‫دراسة‬ ‫يتم‬ ‫مثال‬:‫الصيانة‬ ‫و‬ ‫التشغيل‬ ‫مراحل‬ ‫في‬ ً‫ا‬‫كثير‬ ‫تدفع‬ ‫ثم‬ ‫ضعيفة‬ ‫جودة‬ ‫معايير‬ ‫باختيار‬ ‫بالتوفير‬ ‫تقوم‬ ‫ال‬  Value Analysis (value engineering) : Finding a less costly way to perform the same work. ‫القيمة‬ ‫تحليل‬:‫األعمال‬ ‫نفس‬ ‫النجاز‬ ‫تكلفة‬ ‫اقل‬ ‫طرق‬ ‫ايجاد‬ ‫عن‬ ‫عبارة‬
  • 4. Lecture 07 : Project Cost Management (4/18) 1.Plan Cost Management (Planning) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7.1 Plan Cost Management Inputs :  Project Management Plan  Project Charter  Enterprise Environmental Factors  Organizational Process Assets Tools and Techniques :  Expert Judgment  Analytical Techniques  Meetings Outputs :  Cost Management Plan
  • 5. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Analytical Techniques • Strategic options to fund the project o Self-funding, o Funding with equity, (Ex: Stocks) ‫التمويل‬‫خالل‬ ‫من‬‫باألسهم‬ ‫كما‬ ‫المشاركة‬ o Funding with debt (Ex: Bonds) ‫بالسندات‬ ‫كما‬ ‫االقتراض‬ ‫خالل‬ ‫من‬ ‫التمويل‬ • Project resources Finance o Making, o Purchasing, o Renting (Short Term), o Leasing (Long Term). • Financial analysis techniques: o payback period, o Return on investment (value), o Internal rate of return, o Net present value. Lecture 07 : Project Cost Management (5/18) 1.Plan Cost Management (Planning) TT
  • 6. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Cost Management Plan : ‫التكاليف‬ ‫إدارة‬ ‫خطة‬ • Establish the criteria for planning, structuring, estimating, budgeting, and control project cost. ‫المشروع‬ ‫تكاليف‬ ‫مراقبة‬ ‫و‬ ‫موازنة‬ ‫و‬ ‫تقدير‬ ‫و‬ ‫هيكلة‬ ‫و‬ ‫تخطيط‬ ‫معايير‬ ‫تأسيس‬ • Cost management plan may includes: ‫على‬ ‫الخطة‬ ‫تحتوي‬ ‫ان‬ ‫يمكن‬ 1. Units of measure ( ex: staff hours) ‫القياس‬ ‫وحدات‬ 2. Level of Precision (rounding up or down, ex: $125.3  $125) 3. Level of Accuracy (ex: ± 5%) 4. Organizational Links (with accounting systems) 5. Control thresholds ( level at which an action needs to be taken) 6. Rules of performance measurement (Procedures) 7. Reporting formats Lecture 07 : Project Cost Management (6/18) 1.Plan Cost Management (Planning) O
  • 7. Lecture 07 : Project Cost Management (7/18) 2.Estimate Costs (Planning) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7 . 2 E s t i m a t e C o s t s Inputs :  Cost Management Plan ■ Scope Baseline  Human Resource Management Plan ■ Project Schedule  Risk Register ■ Enterprise Environmental Factors  Organizational Process Assets Tools and Techniques :  Expert Judgment ■ Analogous Estimating  Parametric Estimating ■ Bottom-Up Estimating  Three-Point Estimates ■ Reserve Analysis  Cost of Quality ■ Project Management Software  Group Decision-Making Techniques ■ Vendor Bid Analysis Outputs :  Activity Cost Estimates  Basis of Estimates  Project Document Updates
  • 8. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (8/18) 2.Estimate Costs (Planning) Cost of Quality: • All costs incurred in preventing nonconformance, apprising, or rework. This will be illustrated later in Quality Management. Vendor Bid Analysis: • Analysis of cost estimate based on responsive bids from qualified vendors. Cost Estimates: Costs are estimated for all resources such as: • Direct Cost (Labor, materials, equipment, services, facilities, IT) • Cost of financing (interest), inflation allowance, exchange rates. • Contingency reserve. • Insurance fees. • Taxes • Overhead (Site overhead and main office) TT O TT
  • 9. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (9/18) 2.Estimate Costs (Planning) Basis of Estimates : • Supporting documentation which provides understanding of how the cost estimate was derived. • This may includes: • Assumptions. • Constraints. • Ranges of accuracy (ex:± 5%). • Confidence level of the final cost estimate. O
  • 10. Lecture 07 : Project Cost Management (10/18) 3.Determine Budget (Planning) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7 . 3 D e t e r m i n e B u d g e t Inputs :  Cost Management Plan ■ Scope Baseline  Activity Cost Estimates ■ Basis of Estimates  Project Schedule ■ Resource Calendars  Risk Register ■ Agreements  Organizational Process Assets Tools and Techniques :  Cost Aggregation  Reserve Analysis  Expert Judgment  Historical Relationships  Funding Limit Reconciliation ‫توفيق‬ Outputs :  Cost Baseline  Project Funding Requirements  Project Document Updates
  • 11. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (11/18) 3.Determine Budget (Planning) Cost Aggregation : • Cost Estimates are aggregated within activities and rolled up to work package then rolled up to control accounts then rolled up to entire project. ‫بالكامل‬ ‫المشروع‬ ‫الى‬ ‫ثم‬ ‫التحكم‬ ‫حسابات‬ ‫الى‬ ‫ثم‬ ‫العمل‬ ‫حزم‬ ‫الى‬ ‫األنشطة‬ ‫مستوى‬ ‫من‬ ‫التكاليف‬ ‫تجميع‬ Reserve Analysis : 1. Contingency Reserve : Allowances for unplanned changes result from identified risks. 2. Management Reserve : Budgets reserved for unplanned changes to scope and cost. Cost estimates Contingency Reserve Management Reserve CostBudget CostBaseline TT TT Historical Relationships: • Historical Relationships involve the use of project characteristics (parameters) to develop mathematical models to predict total project costs. • This results in parametric estimates or analogous estimates. TT
  • 12. PMP Lectures Prepared By: Eng. Mohamed ElSaadany Lecture 07 : Project Cost Management (12/18) 3.Determine Budget (Planning) Funding Limit Reconciliation : ‫التمويل‬ ‫لقيود‬ ‫طبقا‬ ‫المعالجة‬ • Sometimes funds are not available when needed and you have to reschedule the activities. ‫االنشطة‬ ‫جدولة‬ ‫اعادة‬ ‫الي‬ ‫يضطرك‬ ‫مما‬ ‫تمويل‬ ‫يوجد‬ ‫ال‬ ‫احيانا‬ • Expenditures should be reconciled with any funding limits ‫التمويل‬ ‫على‬ ‫موجودة‬ ‫قيود‬ ‫ألي‬ ‫طبقا‬ ‫االنفاق‬ ‫خطة‬ ‫توفيق‬ ‫و‬ ‫معالجة‬ ‫من‬ ‫بد‬ ‫ال‬ • Example : Funds for the project will be available on two batches : $50 millions today and $40 millions in the beginning of the next year. Cost Baseline : ‫التكلفة‬ ‫أساس‬ ‫خط‬ • The planned costs over project time. It’s used to control cost performance in the project. ‫التكاليف‬ ‫المخطط‬‫انفاقها‬‫عبر‬‫زمن‬‫المشروع‬ Project Funding Requirements : ‫المشروع‬ ‫تمويل‬ ‫متطلبات‬ • It can be derived from cost baseline. Funding often occurs in incremental amounts. ‫دفعات‬ ‫على‬ ‫تكون‬ ‫ما‬ ‫غالبا‬ ‫و‬ ‫التكلفة‬ ‫أساس‬ ‫خط‬ ‫من‬ ‫استنتاجها‬ ‫يمكن‬ TT O O
  • 13. Lecture 07 : Project Cost Management (13/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany C o s t M a n a g e m e n t 7 . 4 C o n t r o l C o s t s Inputs :  Project Management Plan  Project Funding Requirements  Work Performance Information Data  Organizational Process Assets Tools and Techniques :  Earned Value Management  Forecasting  To Complete Performance Index (TCPI)  Performance Reviews  Project Management Software  Reserve Analysis Outputs :  Work Performance Information ■ Cost Forecasts  Project Management Plan Updates ■ Change Requests  Organizational Process Assets Updates ■ Project Document Updates
  • 14. Lecture 07 : Project Cost Management (14/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Earned Value Management : ‫المكتسبة‬ ‫القيمة‬ ‫ادارة‬ • Planned Value (PV) = Budgeted cost for work scheduled (BCWS) ‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫تنفيذها‬ ‫المخطط‬ ‫األعمال‬ ‫قيمة‬ • Earned value (EV) = Budgeted cost for work performed (BCWP) ‫محددة‬ ‫زمنية‬ ‫نقطة‬ ‫عند‬ ‫فعلية‬ ‫اعمال‬ ‫تنفيذ‬ ‫من‬ ‫المكتسبة‬ ‫القيمة‬ • Actual Cost (AC) = Actual cost for work performed (ACWP) ‫تنفيذها‬ ‫تم‬ ‫التي‬ ‫لالعمال‬ ‫الفعلية‬ ‫التكاليف‬ • Schedule Variance (SV) = EV – PV ‫انحراف‬(‫تباين‬)‫الزمني‬ ‫الجدول‬ • Cost Variance (CV) = EV – AC ‫التكلفة‬ ‫انحراف‬ • Schedule Performance Index (SPI) = EV / PV ‫الزمني‬ ‫الجدول‬ ‫أداء‬ ‫مؤشر‬ • Cost Performance Index (CPI) = EV / AC ‫التكلفة‬ ‫أداء‬ ‫مؤشر‬ Behind Schedule ‫متأخر‬‫الجدول‬ ‫عن‬SV < 0 On Schedule ‫الجدول‬ ‫مع‬SV = 0 Ahead of Schedule ‫الجدول‬ ‫سابق‬SV > 0 Over Budget ‫الميزانية‬ ‫تعدى‬CV < 0 On Budget ‫الميزانية‬ ‫مع‬CV = 0 Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CV > 0 Behind ScheduleSPI < 1 On ScheduleSPI = 1 Ahead of ScheduleSPI > 1 Over Budget ‫الميزانية‬ ‫تعدى‬CPI < 1 On Budget ‫الميزانية‬ ‫مع‬CPI = 1 Under Budget ‫الميزانية‬ ‫نطاق‬ ‫داخل‬CPI > 1 TT
  • 15. Lecture 07 : Project Cost Management (15/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Example : PV (BCWS) =1000x120 = 120,000.00 EV (BCWP) =1000x130 = 130,000.00 AC (ACWP) =1200*130 = 156,000.00 Variance : SV = EV - PV = 130'000 - 120'000 = 10'000 (Ahead of Schedule) CV = EV - AC = 130'000 - 156'000 = -26'000 (Over Budget) Performance Index SPI = EV / PV = 130'000 / 120'000 = 1.083 (Ahead of Schedule) CVI = EV / AC = 130'000 / 156'000 = 0.833 (Over Budget) Cost/Unit Quantity Budget 1000 120 Actual 1200 130
  • 16. Lecture 07 : Project Cost Management (16/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Time Cost
  • 17. Lecture 07 : Project Cost Management (17/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany Forecasting : ‫معايير‬ ‫خالل‬ ‫من‬ ‫التوقع‬ • Estimate at Completion (EAC) = Actual Cost+ Estimate to Complete (ETC). ‫المشروع‬ ‫نهاية‬ ‫في‬ ‫المتوقعة‬ ‫القيمة‬=‫اآلن‬ ‫حتى‬ ‫الفعلية‬ ‫القيمة‬+‫المشروع‬ ‫النهاء‬ ‫المتوقع‬ • There are various methods to calculate the Estimate to Complete (ETC) ‫المشروع‬ ‫النهاء‬ ‫المتوقعة‬ ‫القيمة‬ ‫لحساب‬ ‫طرق‬ ‫عدة‬ ‫يوجد‬ 1- At the budgeted rate : EAC = AC + (BAC – EV) 2- Considering CPI : EAC = AC + [ (BAC – EV) / CPI ] = AC + BAC/CPI – EV/CPI = AC + BAC/CPI – AC = BAC / CPI 3- Considering CPI and SPI : EAC = AC + [ (BAC – EV) / (CPI x SPI) ] TT
  • 18. Lecture 07 : Project Cost Management (18/18) 4.Control Costs (M/C) PMP Lectures Prepared By: Eng. Mohamed ElSaadany To Complete Performance Index (TCPI) : ‫المشروع‬ ‫إلكمال‬ ‫المطلوبة‬ ‫للقيمة‬ ‫اآلداء‬ ‫مؤشر‬ • It’s the cost performance that must be achieved on the remaining work to meet a specified goal like BAC or EAC ‫القادمة‬ ‫الفترة‬ ‫في‬ ‫تحقيقه‬ ‫المطلوب‬ ‫المالي‬ ‫االداء‬ • It represents the ratio between remaining works and remaining funds. ‫المتبقي‬ ‫التمويل‬ ‫قيمة‬ ‫و‬ ‫المتبقية‬ ‫االعمال‬ ‫قيمة‬ ‫بين‬ ‫النسبة‬ ‫تمثل‬ • TCPI = (BAC-EV) / (BAC – AC) Or TCPI = (BAC-EV) / (EAC – AC) “If the BAC is no longer valid” • Ex : BAC = 500’000.00 , EV = 200’000.00, AC= 250’000.00 TCPI = (300’000.00 ) / (250’000.00) = 1.2 TT Performance Reviews : • Variance at completion (VAC) = BAC – EAC • Trend Analysis: Graphical analysis examines project performance over time. • EVM TT