SlideShare a Scribd company logo
Project Value Delivery
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Best Practices for
Large Complex
Projects Control
Jeremie Averous
Senior Managing Partner
V0 – March 2015
Contents
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Large Complex Projects
Best Practices
• Introduction: Specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 3
• Be Focused on the right
things – Convergence
Monitoring
• Be in Control while
remaining Agile
• Address Complexity
• Create Space for
Responding to the
Unexpected
Section
1
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 5
What is Complexity?
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 6
Complex System = System with many
independent components and strong
interactions
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 7
Complicated vs Complex
Section
2
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 9
Project Team Best Practices
• Strong Project governance
• Strong Project Manager authority / specialized
disciplines providing resources
• Project Leadership not just Management
• An effective, integrated team with full-time
contributors in a separate open-space
• Effective teambuilding and operating practices
• The Project Execution Plans are developed and
revisited as a group during workshops at project
start-up
• To the extent practical ensure alignment between
individual capabilities and interests and project goals
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 10
Why?
• Diminish complexity
– Improve contributors’ alignment
• Strength of Project Sponsorship & governance
• Familiarization, alignment workshops
• Incentive schemes
– Minimize the number of contributors and
interfaces
• Integrated work package / subcontractors
• Integrated teams
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 11
Integrated teams
• High Authority Level of Project Manager
• Most people are allocated full time to a project
• The project-team is collocated in an open-plan
space to facilitate communication
• They do what it takes for the project
– recognition of need to contribute outside formal role
description for overall success
• A Matrix organization is
implemented within the
project with delivery
responsibility
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 12
Project Governance
• Proper project governance is often lacking on large
projects
– Project sponsor should understand specifics of large
projects,
– Project sponsorship should be strong and present,
– Project execution strategy and decision-making key points
for management should be well defined (gates),
– Utilization of contingency reserves process should be clear,
– Will to invest to prevent future costs or manage risks.
…You need to
build an
effective
integrated
team to find
the solution in
complexity
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 15
A team where blaming starts
=
100% project failure
Section
3
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 17
The Three Fundamental Questions
WHERE ARE WE?
(ARE WE ON COURSE?)
WHERE ARE WE GOING?
WHAT DO WE NEED TO DO TO BE
BACK ON COURSE?
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 18
Project Control Best Practices
• Project Control is implemented as a specific senior role
reporting to the PM – does not exist as such in smaller
projects
• Project Control to ensure consistency between cost,
schedule, risk and contracts at the adequate level of
detail
– Breakdown structures
– Forecasts / Earned Value Management
– Contingency, reserves, allowances
• Project Control sets up the relevant measurement and
reporting processes & systems
• Project Control is not just about compliance - it needs to
be the strategic advisor for the PMT
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 19
Large projects typical organization
Project
managerProject
Control
manager
Package
Manager 1
HSE, Q
Package
Manager 2
Package
Manager 3
Engineering
Manager
Procurement
manager
Construction
manager
Commissioning
Manager
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 20
What is Project Controls?
Project Control is about building
information sensors, and making
sense of the information.
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 21
Project Breakdown detail level
(Cost Model, Schedule)
Breakdown detail
Too little detail
will not allow
to grasp
the project drivers
Too much detail
drowns the team
and removes agility
Effectiveness
Optimal
Cost /
Schedule
Detail
Range
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 22
Too much detail!
= Not enough time for
analysis!
Section
4
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 24
Project Cost Control Best Practices
• Fully distinct from Accounting
• Focus on commitments and Project-end forecast
• Actual Cost (VOWD) is evaluated independently of
invoicing
• Breakdown structures are owned by Project Control and
coordinated with Procurement and Construction
contracting strategies
• A full Project Cost Model is maintained (in source
currency, time-phased, by work package)
• Issues / events are reported immediately in the forecast
• Sensitivities are provided in addition to the (prudent)
forecast
• Data integrity is maintained, all variances remain
traceable
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 25
Common “maturity’ observations
when no strong Cost Management
• Costs for internal resources as actual costs instead
of standard rates
– Extreme complication of cost tracking
• Commitments are not tracked – only invoicing
– Invoicing without commitments
– Poor control on project bottom line because of
invoicing delays
• Poor consistency with project execution strategy
and forecast schedule
• No support to PM in scenario planning
• No sensitivities available
Section
5
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 33
Project Schedule Best Practices
• Limit the detail of the Project Integrated Schedule – use a
proper scheduling hierarchy
• Use the Convergence Planning / monitoring method +
communicate focus to the team
• Float and Buffers are owned by the PM
• Avoid ‘virtual float’ generation by constraining delivery
on fixed dates
• Implement float monitoring / trending (evolution of float
from one update to the next)
• Avoid having different schedules for different
stakeholders
• Prefer to increase the schedule robustness and
resilience instead of minimizing the critical path.
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 35
Best Practice Schedule Vision
Integrated Project Schedule
1,500 – 2,500 activities
Convergence
Plan
~ 100-200
deliverables
MOREDETAILS
MOREFOCUS
Document
List &
detailed
engineering
schedule
SCM
Detailed
Plan
Construction
Sub-
contractor’s
schedules
Commi-
ssioning
Plan /
schedule
Installation
Plan
Simplified Project Schedule
200-400
Activities
(Schedule Risk Analysis)
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 37
Convergence processFor Complex Projects, the focus needs to be on
convergence
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 38
Convergence process
Simple Project Complex Project
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 39
Convergence process
Project Performance Driver
(or, what kills a project)
Simple project Large project
Efficiency Convergence
Potential upside/
downside±10%
+20%
- 30, -50, -100%
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 40
Most
Projects fail
because of a
small piece
missing…
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 41
Convergence
Plan Example
Section
6
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 43
Project Risk Best Practices
• Opportunity and Risks, and ratings to be discussed as a team
• Focused action-taking. Prioritize ruthlessly and focus effort
• The earlier, the better for action-taking
• Use all opportunities of contractual relationships to transfer risk
• Do not confuse allowances, contingency, management
reserves
• Schedule risk analysis focus on improving schedule resilience
• Monte Carlo methods are conventional and their limits must
be understood (e.g. low probability risk, independence
assumptions)
• Most of the project risk is related to schedule slippage & lack
of convergence, and consequential impacts
• Prevention of major accidents is essential – industrial risk
management
• In case of major event, create a separate task-force to
minimize consequential impact on project execution
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 44
Advanced Risk Management
approaches
• Industrial Risk Management
– Specific methods to prevent major catastrophic
events (low probability, high consequences)
• Portfolio risk management
– Manage dependencies between projects
(resources etc) and consequential effects
• Minimize complexity
• Ensure there is a way to escape the project if it goes
bad – contractual T&C
– Limit of liability, termination clause etc
• Proper contingency calculation and Senior
Management ownership
Section
7
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 48
Systems
• Large project = lots of data to control
– Manual systems are overwhelmed, high error rate
• Need to:
– manage inter-office remote work, remote sites
– guarantee data correctness and accurate
reporting
• What minimum systems?
– Document control & Correspondence control
– Cost control (different from accounting)
– Commitments & approvals
• SCM
• Logistics
• Travel, HR
• Timesheets
– Scheduling & convergence planning
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 49
Project Systems Best Practices
• Minimize risks of mistakes by having systems that synchronize or
are shared/ accessible between different sites & worksite (new
trend = in addition, go mobile) and across the full process cycles
(e.g. site commitments)
• Single integrated systems (~ERP) often less effective in terms of
control and efficiency than a suite of specialized systems with
checks at the interface; and in addition longer and more
expensive to set-up
• All action-tracking systems to be coordinated to allow real
prioritization across the board
• Reporting to be as automated as possible to leave space for
actual analysis work (new trend = real time dashboards)
• Leverage systems to create performance indicators and reports
• Ensure shared breakdown structures and consistent references
across the entire contracting levels
Conclusion
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 51
Moving into Larger, more Complex
Projects
• Management by “efficient”
hierarchical departments
• Purely rational approaches
• Following an immutable baseline
plan
(a.k.a the Stalinist approach)
…DON’T WORK!
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 52
So, is your organization is ready for
large projects?
Key indicators:
• Strength of project managers vs department heads
• Project leadership capabilities and effective teams
• Office lay-out – really integrated teams
• Cost mindset vs investment mindset at
management level
• Strength of project governance process
• Strength of IT systems for project data management
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 53
• Be Focused on the right
things – Convergence
Monitoring
• Be in Control while
remaining Agile
• Address Complexity
• Create Space for
Responding to the
Unexpected
LEAD!
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 54
This presentation summarizes key best practices for
Large Complex Projects.
More information is available on our White Papers and
other documents on www.ProjectValueDelivery.com
…as well as in our handbooks!
W e E m p o w e r O r g a n i z a t i o n s
T o b e R e l i a b l y S u c c e s s f u l i n
E x e c u t i n g L a r g e , C o m p l e x P r o j e c t s
Discover more on
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery
Project Soft Power
Unleashing Value
from Your
Large, Complex
Projects
Project Health Check
Project Coaching
Organizational maturity
Team effectivenessIntercultural leadership
Advanced project trainingProject Startup support
Project Recovery
Advanced risk management
Project Control and Reporting
Support systems integration
Convergence planning
Remote sites integration
Leadership development

More Related Content

PDF
Practical Project Cost Control for Large Complex Projects
PDF
Schedule Updates
PDF
Project Duration Estimation
PDF
Resource Optimization of Construction Project Using Primavera P6
PDF
construction project planing
PDF
Loading cost in primavera schedule using resources and expenses r01
PPTX
6.5 Resource Leveling and Resource Smoothing
PDF
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Practical Project Cost Control for Large Complex Projects
Schedule Updates
Project Duration Estimation
Resource Optimization of Construction Project Using Primavera P6
construction project planing
Loading cost in primavera schedule using resources and expenses r01
6.5 Resource Leveling and Resource Smoothing
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting

What's hot (20)

PPTX
Enterprise Project Structure (EPS)
PPT
Project managment ppt
PPTX
03 Construction Project Planning and Scheduling
PPT
Critical path method (cpm)
PPT
8. (lecture 6) Project Cost Control.ppt
PDF
Understanding p6 dates
PPTX
Project Scheduling
PPTX
Chapter 4
PDF
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
PPTX
Project Management Office Roles Functions And Benefits
PPTX
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
PPTX
Earned value management for Beginners
PDF
PMP: Key Concepts
PPTX
Ms project 2016 overview
PPTX
Smart project management - Best Practices to Manage Project effectively
PDF
Advanced project scheduling: proper practices for integrated project schedules
PPSX
introduction to financial monitoring
PDF
Introduction to Project Management
PDF
Project management
PPTX
Project management
Enterprise Project Structure (EPS)
Project managment ppt
03 Construction Project Planning and Scheduling
Critical path method (cpm)
8. (lecture 6) Project Cost Control.ppt
Understanding p6 dates
Project Scheduling
Chapter 4
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Project Management Office Roles Functions And Benefits
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
Earned value management for Beginners
PMP: Key Concepts
Ms project 2016 overview
Smart project management - Best Practices to Manage Project effectively
Advanced project scheduling: proper practices for integrated project schedules
introduction to financial monitoring
Introduction to Project Management
Project management
Project management
Ad

Viewers also liked (6)

PDF
Project Value Delivery methodology and interventions
PDF
How Governance Makes or Breaks a Project
PDF
Organizational Transformation Best Practices (Project-Driven Businesses)
PDF
Large Complex Projects (PMI-MY presentation Sept 2012)
PPTX
Project Soft Power
PDF
Specifics of Managing Large, Complex Projects
Project Value Delivery methodology and interventions
How Governance Makes or Breaks a Project
Organizational Transformation Best Practices (Project-Driven Businesses)
Large Complex Projects (PMI-MY presentation Sept 2012)
Project Soft Power
Specifics of Managing Large, Complex Projects
Ad

Similar to PVD Project Control Best Practices for Large Projects (20)

PDF
How to Manage the Transition from Small, Simple to Large Complex Projects
PDF
9_LCI_Business-Case-for-Lean_Standard-2021.pdf
PDF
Cost Estimation and Control on Projects: Addressing today's challenges
PDF
Megaprojects: Project Control as Strategic Director
PDF
The Business of Projects
PDF
Project Value Delivery methodology and interventions
PDF
Business Transformation Best Practices-Project Value Delivery.pdf
PDF
Large Complex Industrial Projects:Owner specific role and associated requirem...
PDF
09_quality_resource_mgt_eval_control.pdf
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPTX
PROJECT MANAGEMENT ESSENTIALS.pptx
PDF
Aconex connected cost webinar - drive project performance
PPTX
Environmental Engineering.pptx
PDF
PRESTO Change Management
PDF
GROUP PRESENTATION Construction Management .pdf
PDF
project introduction.pdf
PDF
PRESTO Change Management
PPT
FINAL PROJECT COST MANAGEMENT STUDENT COPY.ppt
PDF
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
PPTX
Week 4 - Managing System Projects in OOP.pptx
How to Manage the Transition from Small, Simple to Large Complex Projects
9_LCI_Business-Case-for-Lean_Standard-2021.pdf
Cost Estimation and Control on Projects: Addressing today's challenges
Megaprojects: Project Control as Strategic Director
The Business of Projects
Project Value Delivery methodology and interventions
Business Transformation Best Practices-Project Value Delivery.pdf
Large Complex Industrial Projects:Owner specific role and associated requirem...
09_quality_resource_mgt_eval_control.pdf
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PROJECT MANAGEMENT ESSENTIALS.pptx
Aconex connected cost webinar - drive project performance
Environmental Engineering.pptx
PRESTO Change Management
GROUP PRESENTATION Construction Management .pdf
project introduction.pdf
PRESTO Change Management
FINAL PROJECT COST MANAGEMENT STUDENT COPY.ppt
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
Week 4 - Managing System Projects in OOP.pptx

More from Jeremie Averous (6)

PDF
Dealing with Extra Long Duration Megaprojects
PDF
Advanced Scheduling for Large, Complex Industrial Projects
PDF
Project Value Delivery methodology and interventions
PDF
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
PDF
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
PDF
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Dealing with Extra Long Duration Megaprojects
Advanced Scheduling for Large, Complex Industrial Projects
Project Value Delivery methodology and interventions
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...

Recently uploaded (20)

PDF
Types of control:Qualitative vs Quantitative
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
How to Get Business Funding for Small Business Fast
PDF
How to Get Funding for Your Trucking Business
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PPTX
5 Stages of group development guide.pptx
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PPT
Data mining for business intelligence ch04 sharda
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
IFRS Notes in your pocket for study all the time
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPTX
Lecture (1)-Introduction.pptx business communication
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
Reconciliation AND MEMORANDUM RECONCILATION
Types of control:Qualitative vs Quantitative
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
HR Introduction Slide (1).pptx on hr intro
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
How to Get Business Funding for Small Business Fast
How to Get Funding for Your Trucking Business
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
5 Stages of group development guide.pptx
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Data mining for business intelligence ch04 sharda
Probability Distribution, binomial distribution, poisson distribution
IFRS Notes in your pocket for study all the time
Belch_12e_PPT_Ch18_Accessible_university.pptx
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
WRN_Investor_Presentation_August 2025.pdf
DOC-20250806-WA0002._20250806_112011_0000.pdf
Lecture (1)-Introduction.pptx business communication
Power and position in leadershipDOC-20250808-WA0011..pdf
Roadmap Map-digital Banking feature MB,IB,AB
Reconciliation AND MEMORANDUM RECONCILATION

PVD Project Control Best Practices for Large Projects

  • 1. Project Value Delivery © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Best Practices for Large Complex Projects Control Jeremie Averous Senior Managing Partner V0 – March 2015
  • 2. Contents © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Large Complex Projects Best Practices • Introduction: Specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 3. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 3 • Be Focused on the right things – Convergence Monitoring • Be in Control while remaining Agile • Address Complexity • Create Space for Responding to the Unexpected
  • 4. Section 1 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 5. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 5 What is Complexity?
  • 6. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 6 Complex System = System with many independent components and strong interactions
  • 7. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 7 Complicated vs Complex
  • 8. Section 2 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 9. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 9 Project Team Best Practices • Strong Project governance • Strong Project Manager authority / specialized disciplines providing resources • Project Leadership not just Management • An effective, integrated team with full-time contributors in a separate open-space • Effective teambuilding and operating practices • The Project Execution Plans are developed and revisited as a group during workshops at project start-up • To the extent practical ensure alignment between individual capabilities and interests and project goals
  • 10. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 10 Why? • Diminish complexity – Improve contributors’ alignment • Strength of Project Sponsorship & governance • Familiarization, alignment workshops • Incentive schemes – Minimize the number of contributors and interfaces • Integrated work package / subcontractors • Integrated teams
  • 11. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 11 Integrated teams • High Authority Level of Project Manager • Most people are allocated full time to a project • The project-team is collocated in an open-plan space to facilitate communication • They do what it takes for the project – recognition of need to contribute outside formal role description for overall success • A Matrix organization is implemented within the project with delivery responsibility
  • 12. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 12 Project Governance • Proper project governance is often lacking on large projects – Project sponsor should understand specifics of large projects, – Project sponsorship should be strong and present, – Project execution strategy and decision-making key points for management should be well defined (gates), – Utilization of contingency reserves process should be clear, – Will to invest to prevent future costs or manage risks.
  • 13. …You need to build an effective integrated team to find the solution in complexity
  • 14. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 15 A team where blaming starts = 100% project failure
  • 15. Section 3 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 16. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 17 The Three Fundamental Questions WHERE ARE WE? (ARE WE ON COURSE?) WHERE ARE WE GOING? WHAT DO WE NEED TO DO TO BE BACK ON COURSE?
  • 17. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 18 Project Control Best Practices • Project Control is implemented as a specific senior role reporting to the PM – does not exist as such in smaller projects • Project Control to ensure consistency between cost, schedule, risk and contracts at the adequate level of detail – Breakdown structures – Forecasts / Earned Value Management – Contingency, reserves, allowances • Project Control sets up the relevant measurement and reporting processes & systems • Project Control is not just about compliance - it needs to be the strategic advisor for the PMT
  • 18. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 19 Large projects typical organization Project managerProject Control manager Package Manager 1 HSE, Q Package Manager 2 Package Manager 3 Engineering Manager Procurement manager Construction manager Commissioning Manager
  • 19. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 20 What is Project Controls? Project Control is about building information sensors, and making sense of the information.
  • 20. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 21 Project Breakdown detail level (Cost Model, Schedule) Breakdown detail Too little detail will not allow to grasp the project drivers Too much detail drowns the team and removes agility Effectiveness Optimal Cost / Schedule Detail Range
  • 21. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 22 Too much detail! = Not enough time for analysis!
  • 22. Section 4 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 23. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 24 Project Cost Control Best Practices • Fully distinct from Accounting • Focus on commitments and Project-end forecast • Actual Cost (VOWD) is evaluated independently of invoicing • Breakdown structures are owned by Project Control and coordinated with Procurement and Construction contracting strategies • A full Project Cost Model is maintained (in source currency, time-phased, by work package) • Issues / events are reported immediately in the forecast • Sensitivities are provided in addition to the (prudent) forecast • Data integrity is maintained, all variances remain traceable
  • 24. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 25 Common “maturity’ observations when no strong Cost Management • Costs for internal resources as actual costs instead of standard rates – Extreme complication of cost tracking • Commitments are not tracked – only invoicing – Invoicing without commitments – Poor control on project bottom line because of invoicing delays • Poor consistency with project execution strategy and forecast schedule • No support to PM in scenario planning • No sensitivities available
  • 25. Section 5 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 26. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 33 Project Schedule Best Practices • Limit the detail of the Project Integrated Schedule – use a proper scheduling hierarchy • Use the Convergence Planning / monitoring method + communicate focus to the team • Float and Buffers are owned by the PM • Avoid ‘virtual float’ generation by constraining delivery on fixed dates • Implement float monitoring / trending (evolution of float from one update to the next) • Avoid having different schedules for different stakeholders • Prefer to increase the schedule robustness and resilience instead of minimizing the critical path.
  • 27. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 35 Best Practice Schedule Vision Integrated Project Schedule 1,500 – 2,500 activities Convergence Plan ~ 100-200 deliverables MOREDETAILS MOREFOCUS Document List & detailed engineering schedule SCM Detailed Plan Construction Sub- contractor’s schedules Commi- ssioning Plan / schedule Installation Plan Simplified Project Schedule 200-400 Activities (Schedule Risk Analysis)
  • 28. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 37 Convergence processFor Complex Projects, the focus needs to be on convergence
  • 29. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 38 Convergence process Simple Project Complex Project
  • 30. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 39 Convergence process Project Performance Driver (or, what kills a project) Simple project Large project Efficiency Convergence Potential upside/ downside±10% +20% - 30, -50, -100%
  • 31. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 40 Most Projects fail because of a small piece missing…
  • 32. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 41 Convergence Plan Example
  • 33. Section 6 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 34. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 43 Project Risk Best Practices • Opportunity and Risks, and ratings to be discussed as a team • Focused action-taking. Prioritize ruthlessly and focus effort • The earlier, the better for action-taking • Use all opportunities of contractual relationships to transfer risk • Do not confuse allowances, contingency, management reserves • Schedule risk analysis focus on improving schedule resilience • Monte Carlo methods are conventional and their limits must be understood (e.g. low probability risk, independence assumptions) • Most of the project risk is related to schedule slippage & lack of convergence, and consequential impacts • Prevention of major accidents is essential – industrial risk management • In case of major event, create a separate task-force to minimize consequential impact on project execution
  • 35. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 44 Advanced Risk Management approaches • Industrial Risk Management – Specific methods to prevent major catastrophic events (low probability, high consequences) • Portfolio risk management – Manage dependencies between projects (resources etc) and consequential effects • Minimize complexity • Ensure there is a way to escape the project if it goes bad – contractual T&C – Limit of liability, termination clause etc • Proper contingency calculation and Senior Management ownership
  • 36. Section 7 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 37. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 48 Systems • Large project = lots of data to control – Manual systems are overwhelmed, high error rate • Need to: – manage inter-office remote work, remote sites – guarantee data correctness and accurate reporting • What minimum systems? – Document control & Correspondence control – Cost control (different from accounting) – Commitments & approvals • SCM • Logistics • Travel, HR • Timesheets – Scheduling & convergence planning
  • 38. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 49 Project Systems Best Practices • Minimize risks of mistakes by having systems that synchronize or are shared/ accessible between different sites & worksite (new trend = in addition, go mobile) and across the full process cycles (e.g. site commitments) • Single integrated systems (~ERP) often less effective in terms of control and efficiency than a suite of specialized systems with checks at the interface; and in addition longer and more expensive to set-up • All action-tracking systems to be coordinated to allow real prioritization across the board • Reporting to be as automated as possible to leave space for actual analysis work (new trend = real time dashboards) • Leverage systems to create performance indicators and reports • Ensure shared breakdown structures and consistent references across the entire contracting levels
  • 39. Conclusion © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 40. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 51 Moving into Larger, more Complex Projects • Management by “efficient” hierarchical departments • Purely rational approaches • Following an immutable baseline plan (a.k.a the Stalinist approach) …DON’T WORK!
  • 41. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 52 So, is your organization is ready for large projects? Key indicators: • Strength of project managers vs department heads • Project leadership capabilities and effective teams • Office lay-out – really integrated teams • Cost mindset vs investment mindset at management level • Strength of project governance process • Strength of IT systems for project data management
  • 42. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 53 • Be Focused on the right things – Convergence Monitoring • Be in Control while remaining Agile • Address Complexity • Create Space for Responding to the Unexpected LEAD!
  • 43. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 54 This presentation summarizes key best practices for Large Complex Projects. More information is available on our White Papers and other documents on www.ProjectValueDelivery.com …as well as in our handbooks!
  • 44. W e E m p o w e r O r g a n i z a t i o n s T o b e R e l i a b l y S u c c e s s f u l i n E x e c u t i n g L a r g e , C o m p l e x P r o j e c t s Discover more on w w w . P r o j e c t V a l u e D e l i v e r y . c o m Project Value Delivery Project Soft Power Unleashing Value from Your Large, Complex Projects Project Health Check Project Coaching Organizational maturity Team effectivenessIntercultural leadership Advanced project trainingProject Startup support Project Recovery Advanced risk management Project Control and Reporting Support systems integration Convergence planning Remote sites integration Leadership development