SWAT EMERALD MINES
BY
Arif khan
7th semester
Department of Mining Engineering
UET Peshawar
2
Introduction
Location
Geology
Previous working
Proposed working plan
Mine supporting facilities
Production chart
Summary of expenditure
Contents3
Introduction
 Mingora Emerald deposit known as Swat Emerald mines
 cover an area of about 182 Acres
 Mining start in 1958 under the Wali of swat Miangul Abdul HaqJahanzeb
 After 1969 PIDC run the Mine up to 1972
 Provincial government , PMDC & GC run the Mine up to 1995
 In Sep1996 the Mine was hands over to EMERALD MINING COMPANY
 In 2009 the Mine was taken by local Taliban
 Now Mine is handed over to M/S FAZAl KHALIQ & Company
4
PIDC (Pakistan industrial Development Corporation)
GC (Gemstone corporation)
Location
 Alternate names Mingora mine , Fizagat mine
 Situated in the close proximity of Mingora town in district swat
 At a distance of about 130 miles to the northeast of Peshawar
 200 miles northwest of Islamabad
 The Mines are closed to the main Swat highway
 Nearest to Railway station Durgai about 50 miles to the southwest
5
Geology
 Emerald is a gemstone and its formula is 𝐵𝑒3 𝐴𝑙2(𝑠𝑖𝑂3)6
 Swat Emerald Mines area comprised of
 Low-grade Chlorite-Mica schist’s: youngest units , grayish green color
 Amphibolites: underlie the chlorite-mica schist , black to green in color
 Carbonate-tale schist: underlie the amphibolites, Emerald rich
 Dykes: two types older dykes , younger dykes
 Serpentinites: two types older serpentinites , younger
 Quartz Vein: two types Quartz-calcite-talc-mica veins, Quartz-talc vein
6
Previous working
 world good class emeralds are being explored since 1958 from Swat mine
 most of the emerald recovered from Mine No.1 and Mine No.2 areas
 The Swat Emerald mine is divided as
 Mine No.1: divided into two faces , Islamia , Farooq , 80 feet, not finished
 Mine No.2 : two working faces , North and South face, fault line is present
 Sarkan Area: It is on top of Mine No 1,2 ,main fault line is passing through it
 Caral Trench: It is close to Mine No.1, hard rock composes of quartz
7
Proposed working plan
 In 2012 M/s karim and company proposed a working plan to Government
 Following short term plan will be carried out at Mine1, Mine2 ,Mine3 area
 Mine 1: Debries produced during illegal mining/rainfall which have buried the
mineralized body should be cleared in 3 months
 Mine2:- The debries removal work would be started from the South and North
faces of M2 to clear in 5 months
 Sarkan area: It is the extreme north of the Swat Emerald Mine and the present adit
should need proper timbering
 Sarkan:- This area is badly affected by the fault line and the cracks developed will
have to be removed through Mine machinery
8
Mine supporting facilities
 following supporting facilities are available
 Work shop: contain hand electric drill machine or a column mounted drill machine,
electric grinding machines, a small welding unit
 Store: contain maintenance tools and equipment's electric fittings, buildings and
maintenance store clothing/uniform etc
 Lamp Room: Room will be used as a storage and maintenance of lamps
 First Aid Room: contain safety and mine rescue kits along with first ointment and
equipment is kept ready for emergency
 Canteen
9
Production chart10
1 carat = 0.2gm
Summary of expenditure
 For 10 years from DEC 2010 to DEC 2020
 A Capital Expenditure ……………………………………………… 2,20,30000
 B Revenue Expenditure……………………………………………. 5,47,20000
 C Operating Expenses……………………………………………….. 1,34,76,100
 Total = A+B+C
 Total =9,02,26100
11
Questions ?
12

More Related Content

PPT
Ch 03 igneous textures
PPTX
Geothermometry in economic geology
PDF
Silica sand - Business Opportunities
PPTX
Contact metamorpic textures
PPT
Kimberlites
PPT
Inundation
PDF
Cours -_ gmdss
PPT
Topic 4: Mine wastes
Ch 03 igneous textures
Geothermometry in economic geology
Silica sand - Business Opportunities
Contact metamorpic textures
Kimberlites
Inundation
Cours -_ gmdss
Topic 4: Mine wastes

What's hot (20)

DOC
Pasir kuarsa
PDF
Underground Mining System Question Pattern and Answer
PPTX
Gems color
PDF
Models and exploration methods for major gold deposit types
PPTX
Supergene deposit by rajat
PPTX
PETROGRAPHIC COMPOSITION AND DEPOSITIONAL ENVIRONMENTS OF CRETACEOUS COALS
PPTX
Sandur schist belt
PPT
Ch 10 magma generation
PDF
Dangers from surface & Underground water
PPTX
Mines vocational training rules 1966 short answer notes
PPTX
Unit operations in underground mining
PPT
Ch07 sedimentary rocks
PDF
METAMORPHIC DIFFERENTIATION
PPTX
Mine hazards(2162294)
PDF
Jurnal fasies gunung api dan aplikasinya
DOCX
Mining terminology
Pasir kuarsa
Underground Mining System Question Pattern and Answer
Gems color
Models and exploration methods for major gold deposit types
Supergene deposit by rajat
PETROGRAPHIC COMPOSITION AND DEPOSITIONAL ENVIRONMENTS OF CRETACEOUS COALS
Sandur schist belt
Ch 10 magma generation
Dangers from surface & Underground water
Mines vocational training rules 1966 short answer notes
Unit operations in underground mining
Ch07 sedimentary rocks
METAMORPHIC DIFFERENTIATION
Mine hazards(2162294)
Jurnal fasies gunung api dan aplikasinya
Mining terminology
Ad

More from Chulalongkorn University (16)

PPTX
Technical Report on the Konya, Ilgin Coal Project
PPT
Ventilationcontrol
PPTX
mechanically ventilation
PPTX
PPTX
Sources of heat
PPTX
Selection of ventilation system
PPTX
heat sources in mine
PPTX
PPTX
Importance of auxiliary ventilation
PPTX
Effect of airway characteristics on power consumption ibrahim
PPTX
Classification of mechanical ventilation devices presentation
PDF
solution of chap 1 operation research
PDF
Operations research 1_the_two-phase_simp
PPTX
Lecture 1 introduction to or
PPTX
Natural supports in mine
PPTX
Pakistan - swat valley
Technical Report on the Konya, Ilgin Coal Project
Ventilationcontrol
mechanically ventilation
Sources of heat
Selection of ventilation system
heat sources in mine
Importance of auxiliary ventilation
Effect of airway characteristics on power consumption ibrahim
Classification of mechanical ventilation devices presentation
solution of chap 1 operation research
Operations research 1_the_two-phase_simp
Lecture 1 introduction to or
Natural supports in mine
Pakistan - swat valley
Ad

Recently uploaded (20)

PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
PDF
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PPT
Chapter 1 - Introduction to Manufacturing Technology_2.ppt
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PPTX
Measurement Uncertainty and Measurement System analysis
PDF
Implantable Drug Delivery System_NDDS_BPHARMACY__SEM VII_PCI .pdf
PPTX
Information Storage and Retrieval Techniques Unit III
PPTX
Building constraction Conveyance of water.pptx
PPTX
A Brief Introduction to IoT- Smart Objects: The "Things" in IoT
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PDF
Abrasive, erosive and cavitation wear.pdf
PPTX
Management Information system : MIS-e-Business Systems.pptx
PPTX
Software Engineering and software moduleing
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Petroleum Refining & Petrochemicals.pptx
PDF
Computer organization and architecuture Digital Notes....pdf
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
August -2025_Top10 Read_Articles_ijait.pdf
Chapter 1 - Introduction to Manufacturing Technology_2.ppt
"Array and Linked List in Data Structures with Types, Operations, Implementat...
distributed database system" (DDBS) is often used to refer to both the distri...
Measurement Uncertainty and Measurement System analysis
Implantable Drug Delivery System_NDDS_BPHARMACY__SEM VII_PCI .pdf
Information Storage and Retrieval Techniques Unit III
Building constraction Conveyance of water.pptx
A Brief Introduction to IoT- Smart Objects: The "Things" in IoT
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
Abrasive, erosive and cavitation wear.pdf
Management Information system : MIS-e-Business Systems.pptx
Software Engineering and software moduleing
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Petroleum Refining & Petrochemicals.pptx
Computer organization and architecuture Digital Notes....pdf

Swat emerald mine

  • 1. 1
  • 2. SWAT EMERALD MINES BY Arif khan 7th semester Department of Mining Engineering UET Peshawar 2
  • 3. Introduction Location Geology Previous working Proposed working plan Mine supporting facilities Production chart Summary of expenditure Contents3
  • 4. Introduction  Mingora Emerald deposit known as Swat Emerald mines  cover an area of about 182 Acres  Mining start in 1958 under the Wali of swat Miangul Abdul HaqJahanzeb  After 1969 PIDC run the Mine up to 1972  Provincial government , PMDC & GC run the Mine up to 1995  In Sep1996 the Mine was hands over to EMERALD MINING COMPANY  In 2009 the Mine was taken by local Taliban  Now Mine is handed over to M/S FAZAl KHALIQ & Company 4 PIDC (Pakistan industrial Development Corporation) GC (Gemstone corporation)
  • 5. Location  Alternate names Mingora mine , Fizagat mine  Situated in the close proximity of Mingora town in district swat  At a distance of about 130 miles to the northeast of Peshawar  200 miles northwest of Islamabad  The Mines are closed to the main Swat highway  Nearest to Railway station Durgai about 50 miles to the southwest 5
  • 6. Geology  Emerald is a gemstone and its formula is 𝐵𝑒3 𝐴𝑙2(𝑠𝑖𝑂3)6  Swat Emerald Mines area comprised of  Low-grade Chlorite-Mica schist’s: youngest units , grayish green color  Amphibolites: underlie the chlorite-mica schist , black to green in color  Carbonate-tale schist: underlie the amphibolites, Emerald rich  Dykes: two types older dykes , younger dykes  Serpentinites: two types older serpentinites , younger  Quartz Vein: two types Quartz-calcite-talc-mica veins, Quartz-talc vein 6
  • 7. Previous working  world good class emeralds are being explored since 1958 from Swat mine  most of the emerald recovered from Mine No.1 and Mine No.2 areas  The Swat Emerald mine is divided as  Mine No.1: divided into two faces , Islamia , Farooq , 80 feet, not finished  Mine No.2 : two working faces , North and South face, fault line is present  Sarkan Area: It is on top of Mine No 1,2 ,main fault line is passing through it  Caral Trench: It is close to Mine No.1, hard rock composes of quartz 7
  • 8. Proposed working plan  In 2012 M/s karim and company proposed a working plan to Government  Following short term plan will be carried out at Mine1, Mine2 ,Mine3 area  Mine 1: Debries produced during illegal mining/rainfall which have buried the mineralized body should be cleared in 3 months  Mine2:- The debries removal work would be started from the South and North faces of M2 to clear in 5 months  Sarkan area: It is the extreme north of the Swat Emerald Mine and the present adit should need proper timbering  Sarkan:- This area is badly affected by the fault line and the cracks developed will have to be removed through Mine machinery 8
  • 9. Mine supporting facilities  following supporting facilities are available  Work shop: contain hand electric drill machine or a column mounted drill machine, electric grinding machines, a small welding unit  Store: contain maintenance tools and equipment's electric fittings, buildings and maintenance store clothing/uniform etc  Lamp Room: Room will be used as a storage and maintenance of lamps  First Aid Room: contain safety and mine rescue kits along with first ointment and equipment is kept ready for emergency  Canteen 9
  • 11. Summary of expenditure  For 10 years from DEC 2010 to DEC 2020  A Capital Expenditure ……………………………………………… 2,20,30000  B Revenue Expenditure……………………………………………. 5,47,20000  C Operating Expenses……………………………………………….. 1,34,76,100  Total = A+B+C  Total =9,02,26100 11