PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
1
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
Sl.No Description of Content Page No.
1 Start of Project 2
2 Creating EPS and OBS 2
3 Define a New Activity 2
4 Calendar 2
5 Scheduling of a project 3
6 Budgeting and Costing 4
7 How to Change a Currency 5
8 Material Unit Definition 5
9 Units and Abbreviations 5
10 Assigning of labor 6
11 Presentation of Cost Details 6
12 Printing 6
13 Filters 7
14 Milestone 7
15 Entry of Non-Uniform Resource 7
16 Baseline 7
17 Import and Export 7
18 Layout 8
19 Gantt Chart Area 9
20 To Add a new Field 9
21 Reflections during Changes 10
22 Note Book 10
23 Project Risk 11
24 Other Basic Details 11
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
2
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
1. Start of a Project
First of all, before start of any project,
File
Close All
How to add a new project
Look at Right side “add” option/click that option, you will have a new project window
2. Creating EPS and OBS
EPS-Departments
Next
Enter the Project ID and Project Name
Project Start and End Dates (Don’t enter the finish date during first entry)
Select Projectright clickopen project
Project
WBS
If you want to see the details of an activity at the bottom side,then
ViewShow on BottomActivity Details
Whenever you open the Activities Screen, WBS Will be there. We have to open the “WBS”
WBS
Then Project Activities
3. Define new Activity
Don’t put any Activity ID (It will automatically assign ID)
If your activities are not shown, then Click LayoutOpen Click “NO”Click 2 weeks
Look Ahead Open
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
3
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
Duration:
Original duration is plan duration. When activities are changing
Click “Activity ID”Then you will come to Know
To change the duration of the activity “double click” the duration and change.
Relationships:
Select the activity
Predecessor (Bottom Side)
AssignDouble Click
Then don’t close the window.
Just Click the activity and double click on the right side of “predecessors”
4. Calendar:
EnterpriseCalendarSelect the Days and Click Non work, Leave etc.,
Work Week-Hours can be mentioned. If you enter “0”, it will be a non-work.
Enterprise Enterprise Structure  Create a new enterprise structure (EPS)  Create Sub title.
EnterpriseOBSAdd the Organizational Breakdown Structure.
If you want to change the start date of project then enterpriseProjectsDates you can change
the Date
If you want to change the calendar under “defaults” you can change the calendar.
If you want to insert a Calendar
5. Scheduling of a project
To schedule a project
Tools
Schedule
Schedule (In Screen)
.
Whenever you change in ‘activity’, duration, predecessor, you have to click again and again
“Schedule” in each change of above
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
4
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
Whenever you feel nothing is showing in screen
View
Filters
Select All Activities
Note:
Bar chart optionsShow relationships
TimescaleYou can change the 2 levels also
6. Budgeting and Costing
EnterpriseResources Units & prices
Assigning of Resource in the following categories to be followed in Primavera
Manpower - Labor
Machines - Non Labor
Materials - Materials
 Management Personnel is not to be entered in Resource
Lead and Lag to be adjusted
Negative Number is “Lead”
Positive Number is “Lag”
There is only In “Lag” Column. So we can use lead and lag
Activities:
Four types of predecessor are as below
Finish to Start, Finish to Finish, Start to Start, Start to Finish
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
5
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
7. How to change the Currency
Admin
Currency
Add Currency
Edit
User preferences
Select Currency
EditUser PreferencesSelect CurrencyCheck Decimal Units
8. Material Unit Definition
Admin
Admin Categories
Units of measure
Add new units
9. Unit Abbreviations
Short name Full name
Cu.M Cubic Meter
GL Gallons
M Meter
Ton 1000 Kg
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
6
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
10. Assigning of labor
If you want to assign multiple labor, then you can do it in two ways as follows
Addition Method Labor-Labor-Labor-Labor-Labor
Change of unit- 8 Hrs /Day x Multiple of 5 Times 40 Hrs/Day
Suppose if rate is changing for some resource like labor rate is changing from Jan-2018 then
Select Resource Add (Bottom side) Change the price from the effective date
Suppose you assigned some rate like: Electrician 12 SAR/Hr. Later you found that rate is 18 SAR/Hr.
You change the rate in Resource then
Tools
Recalculate Assignment Costs
Recalculate
11. Presentation of Cost Details
You have to create a column as below
Budgeted Labor Cost
Budgeted Material Cost
Budgeted Non-Labor Cost
Budgeted Total Cost
So we have activities wise cost, WBS Wise and Total Project also.
12. Printing
FilePrint PreviewFit to (Options What data you need)
If you want to print for selected period then select
Custom dateselect the datePrint
To print in Pdf
FilePrintPdfSave as Pdf
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
7
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
13. FiltersView Filters
(Critical Path—Longest Duration of the Activity)
To create a new filter
Enter filter name
Where Condition is “equals or more than 10”
Click “Ok”,
Click “Apply”
Then you can see the activities which are more than 10 days.
14. Milestone
Define Milestone Activities
General TabSelect Milestone Start or Finish
Add Predecessors also
Then go for “Schedule”
If you do any change in Relationship, new activity addition, you have to reschedule it. Then only it
will be shown in the effected project.
22. If you want to change the activity in between two activities enter the next activity ID after the
Activity ID. Then it will create next activity.
15. Entry of Non-Uniform Resource
If you want to enter non-uniform resources
EnterpriseResource Curvesallows you to control non-uniform resources.
(ViewShow on BottomResource Allocation Sheet)
ViewExpand All
Collapse All
Collapse to—WBS1
16. Baseline
Baseline schedule is the approved schedule by the management after the discussion with all the
interrelated and intra departments. This Baseline Schedule is done after round of Discussion
PM-Always go with Max.Duration/Max Resources
But Management always try to squeeze the project schedule.
We can do “Re- baseline” if required.
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
8
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
ProjectMaintain Baseline AddOk
ProjectAssign Baseline
In Project Baseline Select the Project-B1
Then
In USER Baseline
Click “ok”
You can see yellow line in Bar Chart.
17. Import and Export:
“Export” and “Checkout” are almost same.
Fileexport
Primavera pm/mm-(xer)-Both primavera software installed.
Xml - global understandable
Primavera pm/mm project  projects to export
While saving the name delete the “*”and then save it.
Import:
Importing the data from a project
Checked in & Checked Out
If you checked out a project means you can’t modify it until you checked in.
You can modify after checked in only
When you export a project means you are sending to somebody for review and modify
But for Checked out means only for view and no modification.
18. Layout (Screen wise settings for WBS, Activities)
View
Layout  Save as  Layout Name
Then
Layout  open  user-admin
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
9
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
To show some quickly layout according to our project requirements.
If you want to hide/show some additional information, then layout can be used.
PrintOptionsYou can change the Date.
19. Gantt chart area
Right Click
Attachments
Text
You type you want and change the Text for your requirements.
Right Click
Attachments
Curtain
You can do some bar chart changes to highlight some areas for presentation.
20. To Add a new field:
Enterprise  User defined fields
Resources (For Iqama Numbers) - Type Iqama Number and Close It.
Then go to Enterprise Resources Right Click
Column and Add Iqama number. Now you can enter your Iqama Number.
If you want to add some performance Indicator then you go to
Enterprise  User Defined Fields
Resource
Performance (Select type of Indicator)
Then Insert Column
PerformanceSelect 4 types of Performance
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
10
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
Activities also we can do user defined fields.
Select ActivitiesThen go to Enterpriseuser defined field
21. Reflections during Changes:
If you want to change something in the project by another person, then reflection can be used.
EnterpriseProjectSelect Your ProjectRight ClickCreate ReflectionOk.
Review Changes done-Accept or Reject, then Make it in original BL Schedule.
Then you will find a project with question mark.
EnterpriseSelect the ProjectMerge Changes-Select or Deselect Bottom Side (Merge Changes)
Then Merge Changes Completed.
Activity Steps:
If you want to check Main activity, Sub-Activity for understanding purpose.
Bottom SideRight Click Click All
Select Steps Add Sub Activities as you want
% Completion:
Select “Physical % Complete” and Insert this new Column to show the Completion %, We can show
the physical %.
EnterpriseProjects Click Calculations
Check % based on Activity Steps
Step Weight:
Bottom sideRight ClickCustomize Steps ColumnsStep Weight
To incorporate step weight according to your requirements
Customize Step ColumnsGeneralStep % Complete
You can select based on %
Expenses:
Indirect Cost like Travel Allowances, Party Expenses
You can add these cost in Budgeted Expense Cost like Party Expenses.
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
11
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
Then you add the Column “Budgeted expenses Cost”
ProjectExpenses
22. Note Book:
Remarks, can be added based on meetings, advice in each meeting.
NotesAddSelect some syllable in like Status Report etc.
Then add the notes as per requirements.
If you want to show, multiple resources go to Insert Column, Select Lists and Select
Resources, then you can see the resources.
If you want to “add” some Note category you go to
AdminAdmin CategoriesSelect Notebook Topics Add
You can add the new syllable as you want.
23. Project Risk:
RiskMay Happen in future
IssuesAlready Available
Project Issues you can add notes according to the review meeting and in General tab you can assign.
The responsible person using OBS (Organization Breakdown Structure)- Set the Priority- as per the
risks quantum may be like top, normal etc.
You can assign the risk in WBS wise also.
Thresholds:
Setting the limits
Like if nay project is delayed start or delayed completion beyond the planned date, then create an
issue.
ProjectThresholdsThreshold parameterUpper threshold/lower threshold etc.
Then Select “Run”Button Right Side
Then go to “Issues” to see the generated issues according to threshold value you have given.
24. Other Basic Details:
Reports:
ToolsReports Reports
Select the type of reportRun ReportOk. (Risk=Probability x Impact)
You have to enter the impact according to the Risks.
Monthly Cash Flow, CT-01, R, AD-04
PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR
BASIC DETAILS-FOR INITIAL STAGE LEARNERS
12
Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com
Select the required reports as per your requirements and Run Report and you can find the required
report.
You can save it in “pdf” format also. Click print and save the file in pdf format
Ctrl + Select the ActivitiesFill down
Some activities will be repeated.
ProjectWork ProductsDocuments
We can add the activities according to the requirements.
ToolsPublishProject Website
Don’t give any important folder name in publish Directory. As it will delete the details. So give always
temporary file.
Resource Histogram:
ViewShow on Bottom Resource usage profile
Resource in Numbers Spread sheet:
ViewShow on BottomResource usage spread sheet
ToolsLevel Resources
S-CURVE:
When you enter the progress data date to be changed.
Then schedule it.
If the value in brackets in “()” it means negative value.
S-Curve Generation View:
ViewShow on bottomActivity wise usage profile
Right ClickActivity usage
Select all the Checkbox

More Related Content

PDF
Primavera P6 manual
PDF
Primavera - Tutorial
PPTX
PRIMAVERA P6 manual.pptx
PDF
Pdf primavera tutorial
PPT
Primavera Training P6
PDF
PM using P6
PPTX
Spillways components and types
PPTX
Primavera presentation
Primavera P6 manual
Primavera - Tutorial
PRIMAVERA P6 manual.pptx
Pdf primavera tutorial
Primavera Training P6
PM using P6
Spillways components and types
Primavera presentation

What's hot (20)

PPTX
ppt for primevera
PPTX
Introduction To Primavera (P6)
PDF
Primavera p6 18.8 planning and scheduling guide r3
PPTX
tcc primavera
PDF
Loading cost in primavera schedule using resources and expenses r01
PPTX
03 Construction Project Planning and Scheduling
PPTX
Primavara
PDF
Primavera P6 Tips and Tricks
PDF
Primavera p6 advanced project planning
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PDF
Primavera P6
PDF
Scheduling by using microsoft project 2013
PPTX
Ms project 2016 overview
PPTX
Eot claims hr__may2012
PPTX
Construction planning & management
PDF
Introduction to Primavera Reflections
PDF
Schedule Updates
PPSX
Chapter 2 construction project planning and scheduling
PDF
Project planning and scheduling
PDF
Microsoft Projects; a step by-step guide for beginner's
ppt for primevera
Introduction To Primavera (P6)
Primavera p6 18.8 planning and scheduling guide r3
tcc primavera
Loading cost in primavera schedule using resources and expenses r01
03 Construction Project Planning and Scheduling
Primavara
Primavera P6 Tips and Tricks
Primavera p6 advanced project planning
Extension of time (E.O.T) By Ahmed Ibarhim
Primavera P6
Scheduling by using microsoft project 2013
Ms project 2016 overview
Eot claims hr__may2012
Construction planning & management
Introduction to Primavera Reflections
Schedule Updates
Chapter 2 construction project planning and scheduling
Project planning and scheduling
Microsoft Projects; a step by-step guide for beginner's
Ad

Similar to Primavera P6 Notes for Beginners (20)

PPTX
Mastering Project Planning with Microsoft Project 2016.pptx
PPSX
P6 Version 7 Tricks and Traps
PPS
100632 p6 v7 tricks and traps
DOCX
© SAP SE CASE STUDY .docx
PPTX
Deltek Vision User Group | October 2016
PDF
Pras s curve final
PDF
S Curves Made Easy With Primavera P6
PDF
Pras s curve final
PPTX
Maximo 7.6.0.8
PDF
MS Project Integration: Tips, Tricks and What's New for You
DOCX
Work Breakdown Structure (WBS) ActivityYour organisati.docx
PDF
367261758-Primavera-P6-Hands-on-Training-Course-Content.pdf
PDF
MS Project Guide.pdf
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
DOCX
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mastering Project Planning with Microsoft Project 2016.pptx
P6 Version 7 Tricks and Traps
100632 p6 v7 tricks and traps
© SAP SE CASE STUDY .docx
Deltek Vision User Group | October 2016
Pras s curve final
S Curves Made Easy With Primavera P6
Pras s curve final
Maximo 7.6.0.8
MS Project Integration: Tips, Tricks and What's New for You
Work Breakdown Structure (WBS) ActivityYour organisati.docx
367261758-Primavera-P6-Hands-on-Training-Course-Content.pdf
MS Project Guide.pdf
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
Ad

Recently uploaded (20)

PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PDF
Phillips model training for evaluation pdf
PPTX
TCoE_IT_Concrete industry.why is it required
PDF
40.-Rizal-And-Philippine-Identity-Formation.pdf
PDF
Contemporary management and it's content
PPTX
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
PDF
Organisational Behaviour And it's concepts
PPTX
Press Release Importance & Structure.pptx
PDF
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PPTX
Human Resources management _HR structure
PDF
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
PDF
The-Power-of-Communication (1).pdf......
PDF
Case study -Uber strategic plan and management
PDF
CISSP - Domain 7: Security Operations - InfoSec Institute
PPTX
Course Overview of the Course Titled.pptx
PPTX
Improved_Leadership_in_Total_Quality_Lesson.pptx
PDF
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
PPTX
Strategic Plan 2023-2024 Presentation.pptx
PDF
The Plan: Save the Palestinian Nation Now
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
Phillips model training for evaluation pdf
TCoE_IT_Concrete industry.why is it required
40.-Rizal-And-Philippine-Identity-Formation.pdf
Contemporary management and it's content
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
Organisational Behaviour And it's concepts
Press Release Importance & Structure.pptx
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Human Resources management _HR structure
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
The-Power-of-Communication (1).pdf......
Case study -Uber strategic plan and management
CISSP - Domain 7: Security Operations - InfoSec Institute
Course Overview of the Course Titled.pptx
Improved_Leadership_in_Total_Quality_Lesson.pptx
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
Strategic Plan 2023-2024 Presentation.pptx
The Plan: Save the Palestinian Nation Now

Primavera P6 Notes for Beginners

  • 1. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 1 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com Sl.No Description of Content Page No. 1 Start of Project 2 2 Creating EPS and OBS 2 3 Define a New Activity 2 4 Calendar 2 5 Scheduling of a project 3 6 Budgeting and Costing 4 7 How to Change a Currency 5 8 Material Unit Definition 5 9 Units and Abbreviations 5 10 Assigning of labor 6 11 Presentation of Cost Details 6 12 Printing 6 13 Filters 7 14 Milestone 7 15 Entry of Non-Uniform Resource 7 16 Baseline 7 17 Import and Export 7 18 Layout 8 19 Gantt Chart Area 9 20 To Add a new Field 9 21 Reflections during Changes 10 22 Note Book 10 23 Project Risk 11 24 Other Basic Details 11
  • 2. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 2 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com 1. Start of a Project First of all, before start of any project, File Close All How to add a new project Look at Right side “add” option/click that option, you will have a new project window 2. Creating EPS and OBS EPS-Departments Next Enter the Project ID and Project Name Project Start and End Dates (Don’t enter the finish date during first entry) Select Projectright clickopen project Project WBS If you want to see the details of an activity at the bottom side,then ViewShow on BottomActivity Details Whenever you open the Activities Screen, WBS Will be there. We have to open the “WBS” WBS Then Project Activities 3. Define new Activity Don’t put any Activity ID (It will automatically assign ID) If your activities are not shown, then Click LayoutOpen Click “NO”Click 2 weeks Look Ahead Open
  • 3. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 3 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com Duration: Original duration is plan duration. When activities are changing Click “Activity ID”Then you will come to Know To change the duration of the activity “double click” the duration and change. Relationships: Select the activity Predecessor (Bottom Side) AssignDouble Click Then don’t close the window. Just Click the activity and double click on the right side of “predecessors” 4. Calendar: EnterpriseCalendarSelect the Days and Click Non work, Leave etc., Work Week-Hours can be mentioned. If you enter “0”, it will be a non-work. Enterprise Enterprise Structure  Create a new enterprise structure (EPS)  Create Sub title. EnterpriseOBSAdd the Organizational Breakdown Structure. If you want to change the start date of project then enterpriseProjectsDates you can change the Date If you want to change the calendar under “defaults” you can change the calendar. If you want to insert a Calendar 5. Scheduling of a project To schedule a project Tools Schedule Schedule (In Screen) . Whenever you change in ‘activity’, duration, predecessor, you have to click again and again “Schedule” in each change of above
  • 4. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 4 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com Whenever you feel nothing is showing in screen View Filters Select All Activities Note: Bar chart optionsShow relationships TimescaleYou can change the 2 levels also 6. Budgeting and Costing EnterpriseResources Units & prices Assigning of Resource in the following categories to be followed in Primavera Manpower - Labor Machines - Non Labor Materials - Materials  Management Personnel is not to be entered in Resource Lead and Lag to be adjusted Negative Number is “Lead” Positive Number is “Lag” There is only In “Lag” Column. So we can use lead and lag Activities: Four types of predecessor are as below Finish to Start, Finish to Finish, Start to Start, Start to Finish
  • 5. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 5 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com 7. How to change the Currency Admin Currency Add Currency Edit User preferences Select Currency EditUser PreferencesSelect CurrencyCheck Decimal Units 8. Material Unit Definition Admin Admin Categories Units of measure Add new units 9. Unit Abbreviations Short name Full name Cu.M Cubic Meter GL Gallons M Meter Ton 1000 Kg
  • 6. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 6 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com 10. Assigning of labor If you want to assign multiple labor, then you can do it in two ways as follows Addition Method Labor-Labor-Labor-Labor-Labor Change of unit- 8 Hrs /Day x Multiple of 5 Times 40 Hrs/Day Suppose if rate is changing for some resource like labor rate is changing from Jan-2018 then Select Resource Add (Bottom side) Change the price from the effective date Suppose you assigned some rate like: Electrician 12 SAR/Hr. Later you found that rate is 18 SAR/Hr. You change the rate in Resource then Tools Recalculate Assignment Costs Recalculate 11. Presentation of Cost Details You have to create a column as below Budgeted Labor Cost Budgeted Material Cost Budgeted Non-Labor Cost Budgeted Total Cost So we have activities wise cost, WBS Wise and Total Project also. 12. Printing FilePrint PreviewFit to (Options What data you need) If you want to print for selected period then select Custom dateselect the datePrint To print in Pdf FilePrintPdfSave as Pdf
  • 7. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 7 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com 13. FiltersView Filters (Critical Path—Longest Duration of the Activity) To create a new filter Enter filter name Where Condition is “equals or more than 10” Click “Ok”, Click “Apply” Then you can see the activities which are more than 10 days. 14. Milestone Define Milestone Activities General TabSelect Milestone Start or Finish Add Predecessors also Then go for “Schedule” If you do any change in Relationship, new activity addition, you have to reschedule it. Then only it will be shown in the effected project. 22. If you want to change the activity in between two activities enter the next activity ID after the Activity ID. Then it will create next activity. 15. Entry of Non-Uniform Resource If you want to enter non-uniform resources EnterpriseResource Curvesallows you to control non-uniform resources. (ViewShow on BottomResource Allocation Sheet) ViewExpand All Collapse All Collapse to—WBS1 16. Baseline Baseline schedule is the approved schedule by the management after the discussion with all the interrelated and intra departments. This Baseline Schedule is done after round of Discussion PM-Always go with Max.Duration/Max Resources But Management always try to squeeze the project schedule. We can do “Re- baseline” if required.
  • 8. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 8 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com ProjectMaintain Baseline AddOk ProjectAssign Baseline In Project Baseline Select the Project-B1 Then In USER Baseline Click “ok” You can see yellow line in Bar Chart. 17. Import and Export: “Export” and “Checkout” are almost same. Fileexport Primavera pm/mm-(xer)-Both primavera software installed. Xml - global understandable Primavera pm/mm project  projects to export While saving the name delete the “*”and then save it. Import: Importing the data from a project Checked in & Checked Out If you checked out a project means you can’t modify it until you checked in. You can modify after checked in only When you export a project means you are sending to somebody for review and modify But for Checked out means only for view and no modification. 18. Layout (Screen wise settings for WBS, Activities) View Layout  Save as  Layout Name Then Layout  open  user-admin
  • 9. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 9 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com To show some quickly layout according to our project requirements. If you want to hide/show some additional information, then layout can be used. PrintOptionsYou can change the Date. 19. Gantt chart area Right Click Attachments Text You type you want and change the Text for your requirements. Right Click Attachments Curtain You can do some bar chart changes to highlight some areas for presentation. 20. To Add a new field: Enterprise  User defined fields Resources (For Iqama Numbers) - Type Iqama Number and Close It. Then go to Enterprise Resources Right Click Column and Add Iqama number. Now you can enter your Iqama Number. If you want to add some performance Indicator then you go to Enterprise  User Defined Fields Resource Performance (Select type of Indicator) Then Insert Column PerformanceSelect 4 types of Performance
  • 10. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 10 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com Activities also we can do user defined fields. Select ActivitiesThen go to Enterpriseuser defined field 21. Reflections during Changes: If you want to change something in the project by another person, then reflection can be used. EnterpriseProjectSelect Your ProjectRight ClickCreate ReflectionOk. Review Changes done-Accept or Reject, then Make it in original BL Schedule. Then you will find a project with question mark. EnterpriseSelect the ProjectMerge Changes-Select or Deselect Bottom Side (Merge Changes) Then Merge Changes Completed. Activity Steps: If you want to check Main activity, Sub-Activity for understanding purpose. Bottom SideRight Click Click All Select Steps Add Sub Activities as you want % Completion: Select “Physical % Complete” and Insert this new Column to show the Completion %, We can show the physical %. EnterpriseProjects Click Calculations Check % based on Activity Steps Step Weight: Bottom sideRight ClickCustomize Steps ColumnsStep Weight To incorporate step weight according to your requirements Customize Step ColumnsGeneralStep % Complete You can select based on % Expenses: Indirect Cost like Travel Allowances, Party Expenses You can add these cost in Budgeted Expense Cost like Party Expenses.
  • 11. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 11 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com Then you add the Column “Budgeted expenses Cost” ProjectExpenses 22. Note Book: Remarks, can be added based on meetings, advice in each meeting. NotesAddSelect some syllable in like Status Report etc. Then add the notes as per requirements. If you want to show, multiple resources go to Insert Column, Select Lists and Select Resources, then you can see the resources. If you want to “add” some Note category you go to AdminAdmin CategoriesSelect Notebook Topics Add You can add the new syllable as you want. 23. Project Risk: RiskMay Happen in future IssuesAlready Available Project Issues you can add notes according to the review meeting and in General tab you can assign. The responsible person using OBS (Organization Breakdown Structure)- Set the Priority- as per the risks quantum may be like top, normal etc. You can assign the risk in WBS wise also. Thresholds: Setting the limits Like if nay project is delayed start or delayed completion beyond the planned date, then create an issue. ProjectThresholdsThreshold parameterUpper threshold/lower threshold etc. Then Select “Run”Button Right Side Then go to “Issues” to see the generated issues according to threshold value you have given. 24. Other Basic Details: Reports: ToolsReports Reports Select the type of reportRun ReportOk. (Risk=Probability x Impact) You have to enter the impact according to the Risks. Monthly Cash Flow, CT-01, R, AD-04
  • 12. PRIMEAVERA-P6 NOTES-, Mr. Abu Babar-Training Session, 26-AUG-2017- KHOBAR BASIC DETAILS-FOR INITIAL STAGE LEARNERS 12 Prepared By: Siva Subramanian Sakthivel., Project Engineer, engrsiva25@gmail.com Select the required reports as per your requirements and Run Report and you can find the required report. You can save it in “pdf” format also. Click print and save the file in pdf format Ctrl + Select the ActivitiesFill down Some activities will be repeated. ProjectWork ProductsDocuments We can add the activities according to the requirements. ToolsPublishProject Website Don’t give any important folder name in publish Directory. As it will delete the details. So give always temporary file. Resource Histogram: ViewShow on Bottom Resource usage profile Resource in Numbers Spread sheet: ViewShow on BottomResource usage spread sheet ToolsLevel Resources S-CURVE: When you enter the progress data date to be changed. Then schedule it. If the value in brackets in “()” it means negative value. S-Curve Generation View: ViewShow on bottomActivity wise usage profile Right ClickActivity usage Select all the Checkbox