SlideShare a Scribd company logo
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-1
Project Evaluation and Control
Chapter 13
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-2
The Project Control Cycle
1. Setting a Goal
4. Taking Action
and Recycling
the Process
2. Measuring
Progress
3. Comparing Actual
with Planned
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-3
The Project S-Curve
Elapsed Time (in weeks)
10
5 45
40
35
30
25
20
15 50
20
60
40
Cumulative
Cost
($
in
thousands)
Cumulative
Budgeted Cost
Cumulative
Actual Cost
$10,000 Negative Var
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-4
Milestone Analysis
Milestones are events or stages of the project
that represent a significant accomplishment.
Milestones
…show completion of important steps
…signal the team and suppliers
…can motivate the team
…offer reevaluation points
…help coordinate schedules
…identify key review gates
…delineate work packages
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-5
Tracking Gantt Chart
Project status is updated by
linking task completion to the
schedule baseline
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-6
Earned Value Management
Schedule
Cost
Performance
Tracking Control Charts
Cost
Performance Schedule
Earned
Value
Project
S-Curves
Cost
Performance Schedule
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-7
Earned Value Terms
Planned value (PV)
Earned value (EV)
Actual cost of work performed (AC)
Schedule performance index (SPI)
Cost performance index (CPI)
Budgeted cost at completion (BAC)
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-8
Steps in Earned Value Management
1. Clearly define each activity including its
resource needs and budget
2. Create usage schedules for activities and
resources
3. Develop a time-phased budget (PV)
4. Total the actual costs of doing each task (AC)
5. Calculate both the budget variance (CV) and
schedule variance (SV)
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-9
Earned Value Milestones
PV EV
AC
Slip
Overspend
Schedule Performed
Actual
Budget
Schedule
Cost
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-10
Earned Value Example
Activity Jan Feb Mar April Plan %C Value
Staffing 8 7 15 100 15
Blueprint 4 6 10 80 8
Prototype 2 8 10 60 6
Design 3 3 33 1
Mon Plan 8 7 6 17 38 āˆ‘ 30
Cmltv 8 15 21 38
Mon Act 8 11 8 13
Cmltv Act 8 19 27 40
Planned Value
38=15+10+10+3
Earned Value
30=15+8+6+1
Value
8=80%(10)
Cumulative
40=8+11+8+13
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-11
Earned Value Example
Schedule Variances
Planned Value (PV) = 38 = 15+10+10+3
Earned Value (EV) = 30 = 15+8+6+1
Schedule Performance Index = .79 = 30/38 = EV/PV
Estimated Time to Completion = (1/.79)x4=5
Cost Variances
Actual Cost of Work Performed (AC) = 40 = 8+11+8+13
Cost Performance Index = .75 = 30/40 = EV/AC
Estimated Cost to Completion = 50.7 = (1/.75)x38
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-12
Completion Values in EVM
Accurate and up-to-date information is critical
in the use of EVM
 0/100 Rule
 50/50 Rule
 Percentage Complete Rule
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-13
Human Factors in
Project Evaluation & Control
Optimistic progress reports
Level of detail
Process evaluation
Non-technical performance measurement
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-14
Critical Success Factors in the
Project Implementation Profile
1. Project mission
2. Top management support
3. Project plans & schedules
4. Client consultation
5. Personnel
6. Technical tasks
7. Client acceptance
8. Monitoring & feedback
9. Communication channels
10. Troubleshooting
Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-15

More Related Content

PPT
Project Planning and Excution chapter 4.ppt
PDF
Tracking a Typical Apartment Construction using Earned Value Management
PDF
Earned value management
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PPTX
Project Cost Management
PPTX
Earned Value Management - Project Controls - Schedule Only.pptx
PPSX
Culture Check on using Earned Value in Organization
Project Planning and Excution chapter 4.ppt
Tracking a Typical Apartment Construction using Earned Value Management
Earned value management
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Project Cost Management
Earned Value Management - Project Controls - Schedule Only.pptx
Culture Check on using Earned Value in Organization

Similar to Project evaluation in project management (20)

PPTX
101 - A Beginner's Guide To Earned Value Management
PDF
Project monitoring and controlling with earned value management
PPTX
Earned value management for Beginners
PDF
Topic 10 - Project Performance Management.pdf
PDF
Application of Earned Value Method and Delay Analysis on Construction Project...
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PPT
Earned value
PPT
Lecture 5- Monitoring and Controlling Projects.ppt
PPT
Earned value Project Management (evpm)
PPS
Earned Value Management
PPTX
PMP COST FORMULAE
PDF
Odoo experience 2015 earned value management
PPTX
Jason douglas earned value 1 0
PPTX
Earned value analysis (1)
PPT
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
PPTX
Earned Value Analysis in construction projects
PPT
Project Earned Value Management and principles
PDF
Earned Value Management
101 - A Beginner's Guide To Earned Value Management
Project monitoring and controlling with earned value management
Earned value management for Beginners
Topic 10 - Project Performance Management.pdf
Application of Earned Value Method and Delay Analysis on Construction Project...
Earned Value AnalysisTracking Project ProgressWh.docx
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
Earned value
Lecture 5- Monitoring and Controlling Projects.ppt
Earned value Project Management (evpm)
Earned Value Management
PMP COST FORMULAE
Odoo experience 2015 earned value management
Jason douglas earned value 1 0
Earned value analysis (1)
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
Earned Value Analysis in construction projects
Project Earned Value Management and principles
Earned Value Management
Ad

Recently uploaded (20)

PDF
composite construction of structures.pdf
PPTX
Artificial Intelligence
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
Construction Project Organization Group 2.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Geodesy 1.pptx...............................................
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
web development for engineering and engineering
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Ā 
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
additive manufacturing of ss316l using mig welding
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
composite construction of structures.pdf
Artificial Intelligence
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
bas. eng. economics group 4 presentation 1.pptx
Construction Project Organization Group 2.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Geodesy 1.pptx...............................................
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
CH1 Production IntroductoryConcepts.pptx
UNIT 4 Total Quality Management .pptx
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Operating System & Kernel Study Guide-1 - converted.pdf
web development for engineering and engineering
Fundamentals of safety and accident prevention -final (1).pptx
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Ā 
CYBER-CRIMES AND SECURITY A guide to understanding
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
additive manufacturing of ss316l using mig welding
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Ad

Project evaluation in project management

  • 1. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-1 Project Evaluation and Control Chapter 13
  • 2. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-2 The Project Control Cycle 1. Setting a Goal 4. Taking Action and Recycling the Process 2. Measuring Progress 3. Comparing Actual with Planned
  • 3. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-3 The Project S-Curve Elapsed Time (in weeks) 10 5 45 40 35 30 25 20 15 50 20 60 40 Cumulative Cost ($ in thousands) Cumulative Budgeted Cost Cumulative Actual Cost $10,000 Negative Var
  • 4. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-4 Milestone Analysis Milestones are events or stages of the project that represent a significant accomplishment. Milestones …show completion of important steps …signal the team and suppliers …can motivate the team …offer reevaluation points …help coordinate schedules …identify key review gates …delineate work packages
  • 5. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-5 Tracking Gantt Chart Project status is updated by linking task completion to the schedule baseline
  • 6. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-6 Earned Value Management Schedule Cost Performance Tracking Control Charts Cost Performance Schedule Earned Value Project S-Curves Cost Performance Schedule
  • 7. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-7 Earned Value Terms Planned value (PV) Earned value (EV) Actual cost of work performed (AC) Schedule performance index (SPI) Cost performance index (CPI) Budgeted cost at completion (BAC)
  • 8. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-8 Steps in Earned Value Management 1. Clearly define each activity including its resource needs and budget 2. Create usage schedules for activities and resources 3. Develop a time-phased budget (PV) 4. Total the actual costs of doing each task (AC) 5. Calculate both the budget variance (CV) and schedule variance (SV)
  • 9. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-9 Earned Value Milestones PV EV AC Slip Overspend Schedule Performed Actual Budget Schedule Cost
  • 10. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-10 Earned Value Example Activity Jan Feb Mar April Plan %C Value Staffing 8 7 15 100 15 Blueprint 4 6 10 80 8 Prototype 2 8 10 60 6 Design 3 3 33 1 Mon Plan 8 7 6 17 38 āˆ‘ 30 Cmltv 8 15 21 38 Mon Act 8 11 8 13 Cmltv Act 8 19 27 40 Planned Value 38=15+10+10+3 Earned Value 30=15+8+6+1 Value 8=80%(10) Cumulative 40=8+11+8+13
  • 11. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-11 Earned Value Example Schedule Variances Planned Value (PV) = 38 = 15+10+10+3 Earned Value (EV) = 30 = 15+8+6+1 Schedule Performance Index = .79 = 30/38 = EV/PV Estimated Time to Completion = (1/.79)x4=5 Cost Variances Actual Cost of Work Performed (AC) = 40 = 8+11+8+13 Cost Performance Index = .75 = 30/40 = EV/AC Estimated Cost to Completion = 50.7 = (1/.75)x38
  • 12. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-12 Completion Values in EVM Accurate and up-to-date information is critical in the use of EVM  0/100 Rule  50/50 Rule  Percentage Complete Rule
  • 13. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-13 Human Factors in Project Evaluation & Control Optimistic progress reports Level of detail Process evaluation Non-technical performance measurement
  • 14. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-14 Critical Success Factors in the Project Implementation Profile 1. Project mission 2. Top management support 3. Project plans & schedules 4. Client consultation 5. Personnel 6. Technical tasks 7. Client acceptance 8. Monitoring & feedback 9. Communication channels 10. Troubleshooting
  • 15. Copyright Ā© 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-15