HAMILTON INTERNATIONAL
PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS)
Pre-Construction Phase (HI.BO.PC.01)
Contract Setting Up Planning Phase Engineering and Procurement
COMMERCIAL
BUSINESS
DEVELOPMENT
FINANCEOPERATIONSCLIENT
Price agreed.
Award of contract /
LOI / LOA
“Advice of New
Contract”
(HI.QF.05.01)
Conduct and minute
Tender Handover
Meeting (HI.QF.05.02).
Handover the “Contract
Conditions Summary”
(HI.QF.04.19) to Q.S and
Contract Manager.
Prepare the “Construction Preliminary Budget”
(HI.QF.04.10)
Obtain Client
document and
NOC for authority
approvals.
Commercial
Engineering
Submittals:
1. RFI (HI.QF.05.07)
2. Shop drawings
3. Material Submittal
4. Method Statement
5. HSE
6. Quality Plan
Procurement
Operations
Place order, as per the
“Purchasing Procedure”
(HI.QAP.06).
Link to
BO.EP.01
Prepare:
1. Tender Event Schedule (HI.QF.04.05)
2. Subcontractor /Material Procurement Log”
(HI.QF.04.06) (Identify long lead items and bulk
items.).
3. “Material Submission Tracking Log”
(HI.QF.04.08)
PROJECT EXECUTION PLANPrepare the “Project
Invoicing / Valuation
Protocol” (HI.QF.04.21)
and attach it to the
minutes of the Client KO
meeting.
Conduct and minute Client
Kick Off Meeting, based on
standard agenda,
HI.QF.05.05.
Conduct and minute the
Internal Kick Off Meeting,
based on the standard
agenda, (HI.QF.05.03).
Prepare the “Cash Flow
and Valuation Schedule”
(HI.QF.04.11) and input
the “Valuation Tracking
Log” (HI.QF.04.13) with
the forecast valuations.
Populate Project Specific
Cost Report template.
Prepare Preliminary Cash
Flow based on the tender
program, for bank bond
application.
Application for municipality
approval.
Receipt of municipality approval.
Raise “Invoice
Request Form”
(HI.QF.04.12) for
advance payment as
per “Invoicing /
Collections Procedure”
(HI.QAP.04.01)
Raise Invoice for
advance payment as
per “Invoicing /
Collections Procedure”
(HI.QAP.04.01)
Obtain the APG,
Performance Bond and
Insurance.
Apply for APG,
Performance bond and
Insurance (where
applicable). Agree
bond wording with
client and bank.
Arrange for the “Notice of
Assignment” (If required)
Release of advance
payment. Client approval
Review cost report
and agree on monthly
reporting.
Prepare “Project Execution Plan”:
1. Project Directory
2. Tender Program
3. Contract Program
4. Target Program
5. Critical Milestone Schedule
6. Authority Approval / Fit out Permit
7. Site Survey Report
8. Shop drawing Submittal Schedule
(HI.QF.05.18)
9. RFI Log (HI.QF.05.08)
10. Contract Manager Daily Diary Tracker
11. Construction Managers Daily Diary Tracker.
12. Labour Histogram
13. Quality Plan
14. H&S Plan
15. Contract Documentation
16. Site Office Set-up Document / Pack.
Possiblythe2meetingscanmerge.
Approved
Tender all project specific
material / sub-contractors.
HAMILTON INTERNATIONAL
PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS)
Execution Phase and Defects Liability Period Phase (HI.BO.EP.01)
Project Execution Phase Defects Liability Period
CLIENTFINANCEOPERATIONSCOMMERCIAL
Maintain the “Contract Managers
Daily Diary Tracker” and update
“Critical Milestone Schedule”.
Submit to the Operations Director on
a weekly basis.
Conduct weekly the “Internal
Project Review Meeting”
(HI.QF.05.04).
Submit “Weekly
Progress
Reports”
(HI.QF.05.38) to
client, signed off
by the Operations
Director.
Mobilisation
Raise Material Request from site.
Link
BO.EP.01
Identify all project specific items and place order, as per the “Purchasing Procedure” (HI.QAP.06).
Raise Valuations as per
“Project Invoicing/
Valuation Protocol”
(HI.QF.04.)
Client
certification
Release
payments against
invoice.
Approved
Update “Project
Critical Tasks
Log”
Issue “Taking
Over Certificate”
to client.
1 month prior to the
completion of DLP,
notify the client of
the completion of
DLP.
Issue Final Taking
Over Certificate.
Prepare:
1. O&M Manual
2. As build drawings
3. Close out authority
approvals.
Raise “Invoice Request
Form” (HI.QF.04.12).
Issue an invoice.
Prepare “Monthly Cost
Reports” (HI.QF.04.15).
Update the “Cash Flow
and Valuation
Schedule”
(HI.QF.04.11).
HI final snagging.
Final inspection done
before handover, using
the “Pre handover
Prompt Sheet”
(HI.QF.05.41) as a
checklist.
INTERNAL PROGRESS REPORTING
Identify, prepare and file the project
close out documentation.
Review “Monthly Cost
Reports”
(HI.QF.04.15).
Update the “Project
Critical Tasks Log” and
inform Document Control
to move the Project folder
from the Completed folder
to Archived folder.
Agree Final
Account with
client.
INVOICING / COLLECTIONS PROCEDURE (HI.QAP.04.01) *
“Invoicing /
Collections
Procedure”
(HI.QAP.04.01)
“Invoicing /
Collections
Procedure”
(HI.QAP.04.01)
Snagging process
* Update the “Valuation Tracking Log” (HI.QF.04.13) at each stage of the “Invoicing / Collections Procedure” (HI.QAP.04.01)
12 months period
NOTE: Variations shall be controlled as per the “Contracts Management / Process Control Procedure” (HI.QAP.05).

More Related Content

DOCX
kiran Planning sche engineer CV
PDF
Professional Practice I Assignment
PDF
Recommendation_Siemens
PDF
ARAMCO Email and Letter for Sulzer Pumps Workshop approval
PDF
أدعية يوم عرفة 💛..pdf
DOCX
Construction lawprint-final-update-21112017
PDF
Curriculum vitae of civil engineer for construction manager or Sr. project en...
PDF
Assignment - Final Account
kiran Planning sche engineer CV
Professional Practice I Assignment
Recommendation_Siemens
ARAMCO Email and Letter for Sulzer Pumps Workshop approval
أدعية يوم عرفة 💛..pdf
Construction lawprint-final-update-21112017
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Assignment - Final Account

What's hot (20)

DOCX
PP2 - Assignment
DOCX
Pp1 group assignment
DOCX
SITE MECHANICAL SUPERVISOR - Copy
PDF
Sajid CV BE Civil 2007
PPTX
Time management in fidic red book 2017(prmg080 project)
PDF
Planning Engineer Resume-mech
PDF
Construction Law Assignment BQS Taylor's University
PDF
PP2 final report
PPTX
Payments in the construction industry
DOCX
CL Final Report
DOCX
ARUNKUMAR CV
PDF
Professional Practice 1 Group Assignment
PDF
Ranjith_Kumar R - CV
DOC
Sohail Afzaal CV for Site Engineer
DOCX
CV Site Engineer Civil
PDF
AutoCAD 2014 Certified Professional
DOC
Resume sales engineer
DOCX
Pp group assignment
PDF
architecture engineer/my cv
DOCX
Karthikeyan CIVIL Engg Resume (1)
PP2 - Assignment
Pp1 group assignment
SITE MECHANICAL SUPERVISOR - Copy
Sajid CV BE Civil 2007
Time management in fidic red book 2017(prmg080 project)
Planning Engineer Resume-mech
Construction Law Assignment BQS Taylor's University
PP2 final report
Payments in the construction industry
CL Final Report
ARUNKUMAR CV
Professional Practice 1 Group Assignment
Ranjith_Kumar R - CV
Sohail Afzaal CV for Site Engineer
CV Site Engineer Civil
AutoCAD 2014 Certified Professional
Resume sales engineer
Pp group assignment
architecture engineer/my cv
Karthikeyan CIVIL Engg Resume (1)
Ad

Similar to Project Flow Chart-BO Major Projects FINAL (with Hyperlinks) (20)

PDF
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
PDF
Job Profile as a Planning Engineer
DOCX
Maaden Exp.
DOC
Pc iv-new
PDF
IFAD Procurement Guidelines revised 2008
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PPT
LECTURE - Planning.ppt
PDF
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
PDF
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
PPTX
projectclosure-rutik.pptx project management
PPT
Construction process
PPT
08-Project-Control-ppt.ppt
PDF
PROJECT 2Construction of a Medical ClinicMany people were severe.pdf
DOCX
MBA 572Project Management WorksheetsReprinted from The Project.docx
DOCX
CV_Saifullah Khalid-
PDF
API 610 pumps .pdf
PDF
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
PDF
RIBA Revit.pdf
PPTX
Procurement Expediting _ Materi Training SCM
PDF
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Job Profile as a Planning Engineer
Maaden Exp.
Pc iv-new
IFAD Procurement Guidelines revised 2008
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
LECTURE - Planning.ppt
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
projectclosure-rutik.pptx project management
Construction process
08-Project-Control-ppt.ppt
PROJECT 2Construction of a Medical ClinicMany people were severe.pdf
MBA 572Project Management WorksheetsReprinted from The Project.docx
CV_Saifullah Khalid-
API 610 pumps .pdf
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
RIBA Revit.pdf
Procurement Expediting _ Materi Training SCM
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Ad

Project Flow Chart-BO Major Projects FINAL (with Hyperlinks)

  • 1. HAMILTON INTERNATIONAL PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS) Pre-Construction Phase (HI.BO.PC.01) Contract Setting Up Planning Phase Engineering and Procurement COMMERCIAL BUSINESS DEVELOPMENT FINANCEOPERATIONSCLIENT Price agreed. Award of contract / LOI / LOA “Advice of New Contract” (HI.QF.05.01) Conduct and minute Tender Handover Meeting (HI.QF.05.02). Handover the “Contract Conditions Summary” (HI.QF.04.19) to Q.S and Contract Manager. Prepare the “Construction Preliminary Budget” (HI.QF.04.10) Obtain Client document and NOC for authority approvals. Commercial Engineering Submittals: 1. RFI (HI.QF.05.07) 2. Shop drawings 3. Material Submittal 4. Method Statement 5. HSE 6. Quality Plan Procurement Operations Place order, as per the “Purchasing Procedure” (HI.QAP.06). Link to BO.EP.01 Prepare: 1. Tender Event Schedule (HI.QF.04.05) 2. Subcontractor /Material Procurement Log” (HI.QF.04.06) (Identify long lead items and bulk items.). 3. “Material Submission Tracking Log” (HI.QF.04.08) PROJECT EXECUTION PLANPrepare the “Project Invoicing / Valuation Protocol” (HI.QF.04.21) and attach it to the minutes of the Client KO meeting. Conduct and minute Client Kick Off Meeting, based on standard agenda, HI.QF.05.05. Conduct and minute the Internal Kick Off Meeting, based on the standard agenda, (HI.QF.05.03). Prepare the “Cash Flow and Valuation Schedule” (HI.QF.04.11) and input the “Valuation Tracking Log” (HI.QF.04.13) with the forecast valuations. Populate Project Specific Cost Report template. Prepare Preliminary Cash Flow based on the tender program, for bank bond application. Application for municipality approval. Receipt of municipality approval. Raise “Invoice Request Form” (HI.QF.04.12) for advance payment as per “Invoicing / Collections Procedure” (HI.QAP.04.01) Raise Invoice for advance payment as per “Invoicing / Collections Procedure” (HI.QAP.04.01) Obtain the APG, Performance Bond and Insurance. Apply for APG, Performance bond and Insurance (where applicable). Agree bond wording with client and bank. Arrange for the “Notice of Assignment” (If required) Release of advance payment. Client approval Review cost report and agree on monthly reporting. Prepare “Project Execution Plan”: 1. Project Directory 2. Tender Program 3. Contract Program 4. Target Program 5. Critical Milestone Schedule 6. Authority Approval / Fit out Permit 7. Site Survey Report 8. Shop drawing Submittal Schedule (HI.QF.05.18) 9. RFI Log (HI.QF.05.08) 10. Contract Manager Daily Diary Tracker 11. Construction Managers Daily Diary Tracker. 12. Labour Histogram 13. Quality Plan 14. H&S Plan 15. Contract Documentation 16. Site Office Set-up Document / Pack. Possiblythe2meetingscanmerge. Approved Tender all project specific material / sub-contractors.
  • 2. HAMILTON INTERNATIONAL PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS) Execution Phase and Defects Liability Period Phase (HI.BO.EP.01) Project Execution Phase Defects Liability Period CLIENTFINANCEOPERATIONSCOMMERCIAL Maintain the “Contract Managers Daily Diary Tracker” and update “Critical Milestone Schedule”. Submit to the Operations Director on a weekly basis. Conduct weekly the “Internal Project Review Meeting” (HI.QF.05.04). Submit “Weekly Progress Reports” (HI.QF.05.38) to client, signed off by the Operations Director. Mobilisation Raise Material Request from site. Link BO.EP.01 Identify all project specific items and place order, as per the “Purchasing Procedure” (HI.QAP.06). Raise Valuations as per “Project Invoicing/ Valuation Protocol” (HI.QF.04.) Client certification Release payments against invoice. Approved Update “Project Critical Tasks Log” Issue “Taking Over Certificate” to client. 1 month prior to the completion of DLP, notify the client of the completion of DLP. Issue Final Taking Over Certificate. Prepare: 1. O&M Manual 2. As build drawings 3. Close out authority approvals. Raise “Invoice Request Form” (HI.QF.04.12). Issue an invoice. Prepare “Monthly Cost Reports” (HI.QF.04.15). Update the “Cash Flow and Valuation Schedule” (HI.QF.04.11). HI final snagging. Final inspection done before handover, using the “Pre handover Prompt Sheet” (HI.QF.05.41) as a checklist. INTERNAL PROGRESS REPORTING Identify, prepare and file the project close out documentation. Review “Monthly Cost Reports” (HI.QF.04.15). Update the “Project Critical Tasks Log” and inform Document Control to move the Project folder from the Completed folder to Archived folder. Agree Final Account with client. INVOICING / COLLECTIONS PROCEDURE (HI.QAP.04.01) * “Invoicing / Collections Procedure” (HI.QAP.04.01) “Invoicing / Collections Procedure” (HI.QAP.04.01) Snagging process * Update the “Valuation Tracking Log” (HI.QF.04.13) at each stage of the “Invoicing / Collections Procedure” (HI.QAP.04.01) 12 months period NOTE: Variations shall be controlled as per the “Contracts Management / Process Control Procedure” (HI.QAP.05).