Project Management:
A Managerial Approach 4/e
By Jack R. Meredith and Samuel J. Mantel, Jr.
Published by John Wiley & Sons, Inc.
Presentation prepared by RTBM WebGroup
Project Management
A Managerial Approach
Chapter 5
Project Planning
Project Planning
There are several reasons to use
considerable care when planning projects:
The primary purpose of planning is to
establish a set of directions in enough detail
to tell the project team exactly what must be
done
The purpose of planning is to facilitate later
accomplishment
Chapter 5-1
Initial Project Coordination
It is crucial that the project’s objectives be
clearly tied to the overall mission of the firm
A project launch meeting is an initial
coordinating meeting that serves as a visible
symbol of top management’s commitment to the
project
The project launch meeting’s success is
absolutely dependent on the existence of a well-
defined set of objectives
Chapter 5-2
Project Launch Meeting
Should not allow plans, schedules, and budgets
to go beyond the most aggregated level at the
launch meeting
The outcomes should be:
1. Technical Scope is established
2. Basic areas of performance responsibility
are accepted by the participants
3. Some tentative overall schedules and
budgets are spelled out
Chapter 5-3
Composite Plan
Each individual/unit accepting responsibility for a portion
of the project should agree to deliver a preliminary plan
about how that responsibility will be accomplished
These plans should contain descriptions of the required
tasks, and estimates of the budgets and schedules
These plans are then scrutinized by the group and
combined into a composite project plan
Chapter 5-4
Composite Plan
The composite plan, still not completely firm, is approved
by each participating group, by the project manager, and
then by senior organizational management
Each subsequent approval hardens the plan, and when
senior management has endorsed it, any further changes
in the project’s scope must be made by processing a
formal change order
Chapter 5-5
Project Plan
The final approved result of this procedure is the project
plan, also known as a Master or Baseline plan
Once planning phase is complete, it is beneficial to hold a
post-planning review
The major purpose of the review is to ensure that all
necessary elements of a project plan have been properly
developed and communicated
Chapter 5-6
Project Plan Elements
The process of developing the project plan varies
among organizations, but any project plan must
contain the following elements:
Overview - a short summary of the objectives and
scope of the project
Objectives - A more detailed statement of the general
goals noted in the overview section
General Approach - describes both the managerial
and technical approaches to the work
Chapter 5-7
Project Plan Elements
Contractual Aspects - includes a complete list and
description of all reporting requirements, customer supplied
resources, liaison arrangements, advisory committees,
project review and cancellation procedures, etc.
Schedules - this section outlines the various schedules
and lists all the milestone events
Resources - this includes the budget (both capital and
expense requirements) as well as cost monitoring and
control procedures
Chapter 5-8
Project Plan Elements
Personnel - this section lists the expected personnel
requirements of the project including special skills, training
needs, and security clearances
Evaluation Methods - every project should be evaluated
against standards and by methods established at the project’s
inception
Potential Problems - this section should include any
potential difficulties such as subcontractor default, technical
failure, tight deadlines, resource limitations and the like.
Preplanning may avert some crises
Chapter 5-9
Project Planning in Action
Project plans are usually constructed by
listing the sequence of activities required to
carry the project from start to completion,
and developing an action plan to complete
the activities
This helps the planner decide the necessary
sequence of things
Sequencing is a necessary consideration for
determining the project schedule and
duration
Chapter 5-10
Project Planning in Action
Software and hardware developers
commonly use a planning process
oriented around the life cycle events:
Concept evaluation
Requirements identification
Design
Implementation
Test
Chapter 5-11
Project Planning in Action
Software and hardware development
planning process (cont.)
Integration
Validation
Customer test and evaluation
Operations and maintenance
Chapter 5-12
Systems Integration
Systems Integration is one part of integration
management and plays a crucial role in the
performance aspect of the project
This includes any technical specialist in the
science or art of the project who is capable of
integrating the technical disciplines to achieve
the customer’s objectives
Chapter 5-13
Systems Integration
Systems Integration is concerned with three
major objectives:
Performance - what a system does
Effectiveness - achieve desired performance in an
optimal manner
Requires no component specifications unless necessary to
meet one or more systems requirements
Every component requirement should be traceable to one or
more systems requirements
Design components to optimize system performance, not
the performance of subsystems
Cost Systems - cost is a design parameter
Chapter 5-14
Hierarchical Planning
System
All activities required to complete a project must
be precisely delineated, and coordinated
Some activities must be done sequentially, and
some simultaneously
Using a hierarchical planning system will allow
these activities to be identified and sorted
appropriately
Also know as the “even planning process”
Chapter 5-15
Sorting Out the Project
The importance of careful planning can scarcely
be overemphasized
Pinto and Slevin developed a list of ten factors
that should be associated with success in
implementation projects
The factors were split into strategic and tactical
clusters Chapter 5-16
Sorting Out the Project
Strategic Success Factors:
Project Mission - spell out clearly defined and agreed-
upon objectives in the project plan
Top Management Support - it is necessary for top
management to get behind the project at the outset, and
make clear to all personnel involved that they support
successful completion
Project’s Action Plan - detailed plan of the required
steps in the implementation process needs to be
developed including all resource requirements
Chapter 5-17
The Work Breakdown Structure
The Work Breakdown Structure (WBS) can take
a variety of forms that serve a variety of
purposes
The WBS often appears as an outline with Level
I tasks on the left and successive levels
appropriately indented
The WBS may also picture a project subdivided
into hierarchical units of tasks, subtasks, work
packages, etc.
Chapter 5-18
The Work Breakdown Structure
The WBS is an important document and can be
tailored for use in a number of different ways
It may illustrate how each piece of the project contributes to
the whole in terms of performance, responsibility, schedule,
and budget
It may list the vendors or subcontractors associated with
specific tasks
It may serve as the basis for making cost estimates or
estimates of task duration
It may be used to document that all parties have signed off
on their various commitments to the project
Chapter 5-19
The Work Breakdown Structure
General steps for designing and using the WBS:
1. Using information from the action plan, list the task
breakdown in successively finer levels of detail. Continue
until all meaningful tasks or work packages have been
identified
2. For each such work package, identify the data relevant to
the WBS. List the personnel and organizations
responsible for each task.
3. All work package information should be reviewed with
the individuals or organizations who have responsibility
for doing or supporting the work in order to verify the
accuracy of the WBS Chapter 5-20
The Work Breakdown Structure
General steps for designing and using the WBS (cont.):
4. The total project budget should consist of four elements: direct
budgets from each task; an indirect cost budget for the project; a
“contingency” reserve for unexpected emergencies; and any residual,
which includes the profit derived from the project
5. The project master schedule integrates the many different schedules
relevant to the various parts of the project
Items 1-5 focus on the WBS as a planning tool but it may also
be used to monitor and control the project
Chapter 5-21
The Work Breakdown Structure
Items 6 and 7 focus on the WBS as an aid to monitor
and control a project:
6. The project manager can examine actual resource use,
by work element, work package, task, up to the full
project level. The project manager can identify
problems, harden the estimates of final cost, and make
sure that relevant corrections have been designed and
are ready to implement
7. The project schedule may be subjected to the same
comparisons as the project budget. Actual progress is
compared to scheduled and corrective action can be
taken Chapter 5-22
Interface Coordination through
Integration Management
The most difficult aspect of implementing a
project is the coordination and integration of the
various elements of the project
The intricate process of coordinating the work
and timing of all inputs is called integration
management
Interface coordination is used to denote the
process of managing this work across multiple
groups
Chapter 5-23
Approaches to Interface
Management
Recent work on managing the interface
focuses on the use of multifunctional
teams (MT)
There is general agreement that MT has a
favorable impact on product/service design
and delivery
Successfully involving cross-functional teams
in project planning requires that some
structure be imposed on the planning process
Chapter 5-24
Approaches to Interface
Management
A different attack on the problem is defining and
mapping all interdependencies between the various
members of the project team
Rather than mapping interfaces on the firm’s organizational
chart, instead it maps the interdependencies directly
Does not ignore the value of the WBS, action plan, or
PERT/CPM networks, but simply uses interface maps as a
source of the coordination requirement to manage the
interdependencies
Chapter 5-25
Summary
The preliminary work plans are important
because they serve as the basis for personnel
selection, budgeting, scheduling and control
Top management should be represented in the
initial coordinating meeting where technical
objectives are established, participant
responsibility is accepted, and preliminary
budgets and schedules are defined
Chapter 5-26
Summary
Common elements of the project plan are the
overview, statement of objectives, general
approach, contractual requirements, schedules,
budget, cost control procedures, evaluation
procedures, and potential problems
System integration concerns the smooth
coordination of project systems in terms of cost,
performance, and effectiveness
Chapter 5-27
Summary
The work breakdown structure (WBS) relates the details
of each subtask to its task and provides the final basis fir
the project budget, schedule, personnel, and control
When multifunctional teams are used to plan complex
projects their work must be integrated and coordinated.
Interface maps are a useful way of identifying the
interdependencies that must be managed
Chapter 5-28
Project Planning
Questions?
Chapter 5-29
Project Planning
Picture Files
Project Planning
Figure 5-1
Project Planning
Figure 5-2
Project Planning
Figure 5-4
Project Planning
Figure 5-6
Project Planning
Figure 5-11
Project Planning
Figure 5-12
Project Planning
Table Files
Project Planning
Project Planning
Copyright © 2000 John Wiley & Sons, Inc. All rights
reserved. Reproduction or translation of this work
beyond that permitted in Section 117 of the 1976 United
States Copyright Act without the express written
permission of the copyright owner is unlawful. Request
for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. The
purchaser may make back-up copies for his/her own use
only and not for distribution or resale. The Publisher
assumes no responsibility for errors, omissions, or
damages, caused by the use of these programs or from
the use of the information contained herein.

More Related Content

PPT
4. the project in the organizational structure
PDF
Project Management Playbook
PPTX
An Introduction to Project Management
PPTX
PROJECT LIFE CYCLE
PPT
Project audit
PPTX
project life cycle
PPTX
Project Management Principles and Process
PPSX
Project organization
4. the project in the organizational structure
Project Management Playbook
An Introduction to Project Management
PROJECT LIFE CYCLE
Project audit
project life cycle
Project Management Principles and Process
Project organization

What's hot (20)

PDF
project Scope management
PPT
Introduction to Project Management
PPTX
Portfolio management
PPT
Project Management Tools and Techniques
PDF
PMP PMBOK 6th
PPT
Introduction-to-project-management
PPTX
5 phases of project management
PPTX
Prince2 explained in 30mins
PPSX
Project Management Fundamentals
PDF
Lecture 1. general introduction to project management
PPT
Project Management
PPT
Project cycle
PPTX
Project Implementation
PPT
07. Project Integration Management
PPTX
Project management
PPT
Project manager
PPT
Project Management
PPTX
Project management cycle
PPTX
PMP Training - 01 introduction to framework
PDF
Logical framework
project Scope management
Introduction to Project Management
Portfolio management
Project Management Tools and Techniques
PMP PMBOK 6th
Introduction-to-project-management
5 phases of project management
Prince2 explained in 30mins
Project Management Fundamentals
Lecture 1. general introduction to project management
Project Management
Project cycle
Project Implementation
07. Project Integration Management
Project management
Project manager
Project Management
Project management cycle
PMP Training - 01 introduction to framework
Logical framework
Ad

Viewers also liked (20)

PDF
Project management
PPT
introduction to project management
PPTX
PM 01 - Introduction to Project Management
PPT
PPT
Chap001
PPSX
Project management
PPT
PPT
PPT
PPT
Chapter 1 An Overview Of Project Management
PPT
Introduction to project management
DOC
Pinto pm2 ism_ch04
PPTX
Project Management
PDF
Chapter 3
PPT
Chap014
PPT
Chap001 (1)
PPT
Chap001
PPT
PPT
Chap002
PPT
Chap007
Project management
introduction to project management
PM 01 - Introduction to Project Management
Chap001
Project management
Chapter 1 An Overview Of Project Management
Introduction to project management
Pinto pm2 ism_ch04
Project Management
Chapter 3
Chap014
Chap001 (1)
Chap001
Chap002
Chap007
Ad

Similar to Project mgmt. (20)

PPT
Ch5ProjectPlanning.ppt
PPT
Strengths (Internal, Positive Factors).ppt
PPTX
5 phases of project management
PDF
4. Proper planning of a software project unless the project is trivia.pdf
PPTX
Smart project management - Best Practices to Manage Project effectively
PPT
5 project management project planning
PPTX
Project Life Cycle.pptx
PPTX
PMP Training - 04 project integration management
PPTX
Presentation4 5.1.pptx
PPT
unit-vpart-2.ppt
PPTX
Chapter 3 Lecture Slides
PPT
L03 integration management
PPT
project Development Management (Scope Management )
DOCX
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
PDF
PDF
All chapter download Project Management A Managerial Approach 8th Edition Mer...
PPT
Ch04
DOCX
Modern Project ManagementPowerPoint Presentation by Charlie .docx
PPT
Chapter 5(1) system development life .ppt
PPT
Chapter 5(1)system development life .ppt
Ch5ProjectPlanning.ppt
Strengths (Internal, Positive Factors).ppt
5 phases of project management
4. Proper planning of a software project unless the project is trivia.pdf
Smart project management - Best Practices to Manage Project effectively
5 project management project planning
Project Life Cycle.pptx
PMP Training - 04 project integration management
Presentation4 5.1.pptx
unit-vpart-2.ppt
Chapter 3 Lecture Slides
L03 integration management
project Development Management (Scope Management )
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
All chapter download Project Management A Managerial Approach 8th Edition Mer...
Ch04
Modern Project ManagementPowerPoint Presentation by Charlie .docx
Chapter 5(1) system development life .ppt
Chapter 5(1)system development life .ppt

Recently uploaded (20)

PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PDF
A Brief Introduction About Julia Allison
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
DOCX
Business Management - unit 1 and 2
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
Types of control:Qualitative vs Quantitative
PDF
MSPs in 10 Words - Created by US MSP Network
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PDF
Deliverable file - Regulatory guideline analysis.pdf
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Laughter Yoga Basic Learning Workshop Manual
PDF
Unit 1 Cost Accounting - Cost sheet
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
IFRS Notes in your pocket for study all the time
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
A Brief Introduction About Julia Allison
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Business Management - unit 1 and 2
Belch_12e_PPT_Ch18_Accessible_university.pptx
Types of control:Qualitative vs Quantitative
MSPs in 10 Words - Created by US MSP Network
Ôn tập tiếng anh trong kinh doanh nâng cao
WRN_Investor_Presentation_August 2025.pdf
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
COST SHEET- Tender and Quotation unit 2.pdf
Deliverable file - Regulatory guideline analysis.pdf
ICG2025_ICG 6th steering committee 30-8-24.pptx
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Laughter Yoga Basic Learning Workshop Manual
Unit 1 Cost Accounting - Cost sheet
unit 1 COST ACCOUNTING AND COST SHEET
IFRS Notes in your pocket for study all the time
DOC-20250806-WA0002._20250806_112011_0000.pdf
Power and position in leadershipDOC-20250808-WA0011..pdf

Project mgmt.

  • 1. Project Management: A Managerial Approach 4/e By Jack R. Meredith and Samuel J. Mantel, Jr. Published by John Wiley & Sons, Inc. Presentation prepared by RTBM WebGroup
  • 2. Project Management A Managerial Approach Chapter 5 Project Planning
  • 3. Project Planning There are several reasons to use considerable care when planning projects: The primary purpose of planning is to establish a set of directions in enough detail to tell the project team exactly what must be done The purpose of planning is to facilitate later accomplishment Chapter 5-1
  • 4. Initial Project Coordination It is crucial that the project’s objectives be clearly tied to the overall mission of the firm A project launch meeting is an initial coordinating meeting that serves as a visible symbol of top management’s commitment to the project The project launch meeting’s success is absolutely dependent on the existence of a well- defined set of objectives Chapter 5-2
  • 5. Project Launch Meeting Should not allow plans, schedules, and budgets to go beyond the most aggregated level at the launch meeting The outcomes should be: 1. Technical Scope is established 2. Basic areas of performance responsibility are accepted by the participants 3. Some tentative overall schedules and budgets are spelled out Chapter 5-3
  • 6. Composite Plan Each individual/unit accepting responsibility for a portion of the project should agree to deliver a preliminary plan about how that responsibility will be accomplished These plans should contain descriptions of the required tasks, and estimates of the budgets and schedules These plans are then scrutinized by the group and combined into a composite project plan Chapter 5-4
  • 7. Composite Plan The composite plan, still not completely firm, is approved by each participating group, by the project manager, and then by senior organizational management Each subsequent approval hardens the plan, and when senior management has endorsed it, any further changes in the project’s scope must be made by processing a formal change order Chapter 5-5
  • 8. Project Plan The final approved result of this procedure is the project plan, also known as a Master or Baseline plan Once planning phase is complete, it is beneficial to hold a post-planning review The major purpose of the review is to ensure that all necessary elements of a project plan have been properly developed and communicated Chapter 5-6
  • 9. Project Plan Elements The process of developing the project plan varies among organizations, but any project plan must contain the following elements: Overview - a short summary of the objectives and scope of the project Objectives - A more detailed statement of the general goals noted in the overview section General Approach - describes both the managerial and technical approaches to the work Chapter 5-7
  • 10. Project Plan Elements Contractual Aspects - includes a complete list and description of all reporting requirements, customer supplied resources, liaison arrangements, advisory committees, project review and cancellation procedures, etc. Schedules - this section outlines the various schedules and lists all the milestone events Resources - this includes the budget (both capital and expense requirements) as well as cost monitoring and control procedures Chapter 5-8
  • 11. Project Plan Elements Personnel - this section lists the expected personnel requirements of the project including special skills, training needs, and security clearances Evaluation Methods - every project should be evaluated against standards and by methods established at the project’s inception Potential Problems - this section should include any potential difficulties such as subcontractor default, technical failure, tight deadlines, resource limitations and the like. Preplanning may avert some crises Chapter 5-9
  • 12. Project Planning in Action Project plans are usually constructed by listing the sequence of activities required to carry the project from start to completion, and developing an action plan to complete the activities This helps the planner decide the necessary sequence of things Sequencing is a necessary consideration for determining the project schedule and duration Chapter 5-10
  • 13. Project Planning in Action Software and hardware developers commonly use a planning process oriented around the life cycle events: Concept evaluation Requirements identification Design Implementation Test Chapter 5-11
  • 14. Project Planning in Action Software and hardware development planning process (cont.) Integration Validation Customer test and evaluation Operations and maintenance Chapter 5-12
  • 15. Systems Integration Systems Integration is one part of integration management and plays a crucial role in the performance aspect of the project This includes any technical specialist in the science or art of the project who is capable of integrating the technical disciplines to achieve the customer’s objectives Chapter 5-13
  • 16. Systems Integration Systems Integration is concerned with three major objectives: Performance - what a system does Effectiveness - achieve desired performance in an optimal manner Requires no component specifications unless necessary to meet one or more systems requirements Every component requirement should be traceable to one or more systems requirements Design components to optimize system performance, not the performance of subsystems Cost Systems - cost is a design parameter Chapter 5-14
  • 17. Hierarchical Planning System All activities required to complete a project must be precisely delineated, and coordinated Some activities must be done sequentially, and some simultaneously Using a hierarchical planning system will allow these activities to be identified and sorted appropriately Also know as the “even planning process” Chapter 5-15
  • 18. Sorting Out the Project The importance of careful planning can scarcely be overemphasized Pinto and Slevin developed a list of ten factors that should be associated with success in implementation projects The factors were split into strategic and tactical clusters Chapter 5-16
  • 19. Sorting Out the Project Strategic Success Factors: Project Mission - spell out clearly defined and agreed- upon objectives in the project plan Top Management Support - it is necessary for top management to get behind the project at the outset, and make clear to all personnel involved that they support successful completion Project’s Action Plan - detailed plan of the required steps in the implementation process needs to be developed including all resource requirements Chapter 5-17
  • 20. The Work Breakdown Structure The Work Breakdown Structure (WBS) can take a variety of forms that serve a variety of purposes The WBS often appears as an outline with Level I tasks on the left and successive levels appropriately indented The WBS may also picture a project subdivided into hierarchical units of tasks, subtasks, work packages, etc. Chapter 5-18
  • 21. The Work Breakdown Structure The WBS is an important document and can be tailored for use in a number of different ways It may illustrate how each piece of the project contributes to the whole in terms of performance, responsibility, schedule, and budget It may list the vendors or subcontractors associated with specific tasks It may serve as the basis for making cost estimates or estimates of task duration It may be used to document that all parties have signed off on their various commitments to the project Chapter 5-19
  • 22. The Work Breakdown Structure General steps for designing and using the WBS: 1. Using information from the action plan, list the task breakdown in successively finer levels of detail. Continue until all meaningful tasks or work packages have been identified 2. For each such work package, identify the data relevant to the WBS. List the personnel and organizations responsible for each task. 3. All work package information should be reviewed with the individuals or organizations who have responsibility for doing or supporting the work in order to verify the accuracy of the WBS Chapter 5-20
  • 23. The Work Breakdown Structure General steps for designing and using the WBS (cont.): 4. The total project budget should consist of four elements: direct budgets from each task; an indirect cost budget for the project; a “contingency” reserve for unexpected emergencies; and any residual, which includes the profit derived from the project 5. The project master schedule integrates the many different schedules relevant to the various parts of the project Items 1-5 focus on the WBS as a planning tool but it may also be used to monitor and control the project Chapter 5-21
  • 24. The Work Breakdown Structure Items 6 and 7 focus on the WBS as an aid to monitor and control a project: 6. The project manager can examine actual resource use, by work element, work package, task, up to the full project level. The project manager can identify problems, harden the estimates of final cost, and make sure that relevant corrections have been designed and are ready to implement 7. The project schedule may be subjected to the same comparisons as the project budget. Actual progress is compared to scheduled and corrective action can be taken Chapter 5-22
  • 25. Interface Coordination through Integration Management The most difficult aspect of implementing a project is the coordination and integration of the various elements of the project The intricate process of coordinating the work and timing of all inputs is called integration management Interface coordination is used to denote the process of managing this work across multiple groups Chapter 5-23
  • 26. Approaches to Interface Management Recent work on managing the interface focuses on the use of multifunctional teams (MT) There is general agreement that MT has a favorable impact on product/service design and delivery Successfully involving cross-functional teams in project planning requires that some structure be imposed on the planning process Chapter 5-24
  • 27. Approaches to Interface Management A different attack on the problem is defining and mapping all interdependencies between the various members of the project team Rather than mapping interfaces on the firm’s organizational chart, instead it maps the interdependencies directly Does not ignore the value of the WBS, action plan, or PERT/CPM networks, but simply uses interface maps as a source of the coordination requirement to manage the interdependencies Chapter 5-25
  • 28. Summary The preliminary work plans are important because they serve as the basis for personnel selection, budgeting, scheduling and control Top management should be represented in the initial coordinating meeting where technical objectives are established, participant responsibility is accepted, and preliminary budgets and schedules are defined Chapter 5-26
  • 29. Summary Common elements of the project plan are the overview, statement of objectives, general approach, contractual requirements, schedules, budget, cost control procedures, evaluation procedures, and potential problems System integration concerns the smooth coordination of project systems in terms of cost, performance, and effectiveness Chapter 5-27
  • 30. Summary The work breakdown structure (WBS) relates the details of each subtask to its task and provides the final basis fir the project budget, schedule, personnel, and control When multifunctional teams are used to plan complex projects their work must be integrated and coordinated. Interface maps are a useful way of identifying the interdependencies that must be managed Chapter 5-28
  • 42. Copyright © 2000 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without the express written permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.