Project Management
PRINCE2®
in 30 mins
P R I N C E 2 I N 3 0 M I N U T E S
Introduction
2
Karen Swanston
A very enthusiastic and experienced trainer,
specialising in PRINCE2 and M_o_R
(Management of Risk) training for more than
nine years.
Along with her experience, Karen has a
passion for designing and delivering training
in a fun and easy manner. Because of this,
she consistently receives above average
feedback and exam results from her
students. Her blend of experience and
enthusiasm is what makes her the ideal
speaker for this session
P R I N C E 2 I N 3 0 M I N U T E S
This session will take you through how easy
PRINCE2 can be to learn.
We’ll look at the basics of the framework without
overcomplicating it, and provide you with some
quick and easy-to-use hints and tips.
Easy to learn
P R I N C E 2 I N 3 0 M I N U T E S
Definition of a PRINCE2 Project
A project is a temporary organisation
that is created for the purpose of delivering
one or more business products,
according to an agreed business case.
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Product
ProjectBusinessasusual
Output
Change
Outcome
Users
Benefit Dis-benefit
Stuff
Specialist Product
P R I N C E 2 I N 3 0 M I N U T E S
OutPut
Change
OutCome
Users
Stuff
Specialist Product
ProjectBusinessasusual
Benefit Dis-benefit
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 four integrated elements
7 Principles (guiding obligations and good practices)
Washing your hands
7 Themes (Addressed continually throughout the project)
Ingredients to be used
7 Processes (step-wise progression through a project)
Recipe to follow
Tailoring to the environment (flexibility)
Cottage Pie for one? Including Carrots?
P R I N C E 2 I N 3 0 M I N U T E S
Principles
• Continued business justification
• Learn from experience
• Defined roles & responsibilities
• Manage by stages
• Manage by exception
• Focus on products
• Tailor to suit the project environment
P R I N C E 2 I N 3 0 M I N U T E S
Themes
• Business case
• Organization
• Quality
• Plans
• Risk
• Change
• Progress
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 processes
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
INITIATING
A PROJECT
DIRECTING A PROJECT
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 processes
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
INITIATING
A PROJECT
DIRECTING A PROJECT
P R I N C E 2 I N 3 0 M I N U T E S
Starting up a project
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Organization
PROJECTMANAGEMENTTEAM
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
Corporate or programme management
Directing – Project Board
Managing – Project Manager
Delivering – Team Manager
ProjectManagementTeam
P R I N C E 2 I N 3 0 M I N U T E S
Business case
Confirm
benefit
Verify
updated
Business Case
Verify
outline
Business Case
Verify
detailed
Business Case
Develop
Business Case
Maintain
Business Case
Pre-
project
Initiation
stage
Subsequent delivery
stage(s)
Final delivery
stage
Post-
project
Confirm
benefit
Confirm
benefit
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
Initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
PRINCE2 processes
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
Authorize
Initiation
PRINCE2 processes
INITIATING
A PROJECT
P R I N C E 2 I N 3 0 M I N U T E S
Initiating a project
© Copyright 2013.
Reproduced under
Licence from
AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Risk definition
A risk is: an uncertain event or set of
events that, should it occur, will have an
effect on the achievement of objectives
MAY
MIGHT
COULD
P R I N C E 2 I N 3 0 M I N U T E S
Issue definition
A issue is: something that has happened
or it will happen that was not planned.
WILL
HAS
NO UNCERTAINTY
P R I N C E 2 I N 3 0 M I N U T E S
Quality
PRODUCT
DESCRIPTION
Engine: petrol,
3.5L
PROJECT PRODUCT DESCRIPTION
PRODUCT
DESCRIPTION
Cream leather
seats
PRODUCT
DESCRIPTION
Tyres: Dunlop
245/40 R19
ACCEPTANCE
CRITERIA
1. 0-60 mph in 3 seconds
2. Up to 2 years old
3. ‘What Car’ top 10 most
desirable cars
CUSTOMER
QUALITY
EXPECTATIONS
1.Fast Car
2.New Car
3.Flashy Car
P R I N C E 2 I N 3 0 M I N U T E S
Plans
TIME & COSTPROJECT PLAN
e e e e
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
DIRECTING A PROJECT
PRINCE2 processes
P R I N C E 2 I N 3 0 M I N U T E S
Plans
TIME & COSTSTAGE PLAN
TIME & COSTPROJECT PLAN
e e e e
e e e e
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
PRINCE2 processes
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
PRINCE2 processes
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
PRINCE2 processes
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Plans
TEAM
PLAN
WORKPACKAGE
TIME & COSTSTAGE PLAN
TIME & COSTPROJECT PLAN
e e e e
e e e e
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 processes
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
Checkpoint
report
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Progress – reporting
P R O J E C T B O A R D
S e n i o r u s e r E x e c u t i v e S e n i o r s u p p l i e r
C O R P O R AT E O R P R O G R AM M E M AN A G E M E N T
P R O J E C T M A N A G E R
T E A M M A N A G E R
H I G H L I G H T R E P O R T
C H E C K P O I N T R E P O R T
H I G H L I G H T R E P O R T
P R I N C E 2 I N 3 0 M I N U T E S
Progress – tolerances
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
Confirm all
products are
completed
Evaluate the
project
Communication
Archive project
documentation
PRINCE2 processes
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
Confirm all
products are
completed
Evaluate the
project
Communication
Archive project
documentation
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
PRINCE2 processes
M A N D A T E
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
During this session we
have stepped through some of the
basic concepts of PRINCE2
without overcomplicating it,
and provided you with some quick,
easy-to-use hints and tips.
Easy to learn
P R I N C E 2 I N 3 0 M I N U T E S
Questions?
P R I N C E 2 I N 3 0 M I N U T E S
Why ILX?
For more information about our courses,
visit our website ilxgroup.com,
give us a call on +44 (0) 1270 611 600 or send an email to:
Individuals enquiries suzanne.bailey@ilxgroup.com
Corporate enquiries paula.gower@ilxgroup.com
P R I N C E 2 I N 3 0 M I N U T E S
Recommended courses
PRINCE2
Programme
& Project
Sponsorship
APM Project
Management
Qualification
Change
Management
P R I N C E 2 I N 3 0 M I N U T E S
I L X G R O U P, U n i t e d K i n g d o m
7 t h F l o o r
9 5 A l d w y c h
L o n d o n W C 2 B 4 J F - U K
T: + 4 4 ( 0 ) 2 0 7 3 7 1 4 4 4 4
Thank you for listening
I L X G R O U P, Au s t r a l i a
7 3 0 S p r i n g v a l e R d
M u l g r a v e , V I C 3 1 7 0
A u s t r a l i a
T: + 6 1 1 3 0 0 4 5 9 4 5 9
www.ilxgroup.com

More Related Content

PPT
PRINCE2 - Presentation
PDF
PRINCE2 Foundation Training Manual by Frank Turley
PDF
Learn the PRINCE2 Principles ebook
PDF
Data Lake Architecture – Modern Strategies & Approaches
PDF
PRINCE2 Foundation Slides - Sample
PDF
The funkiest PRINCE2 Processes revision guide on the internet
PDF
Agile Fundamentals
PRINCE2 - Presentation
PRINCE2 Foundation Training Manual by Frank Turley
Learn the PRINCE2 Principles ebook
Data Lake Architecture – Modern Strategies & Approaches
PRINCE2 Foundation Slides - Sample
The funkiest PRINCE2 Processes revision guide on the internet
Agile Fundamentals

What's hot (20)

PDF
PRINCE2 Process Model
PDF
7 Themes of Prince2
PDF
Pmbok6 to 7 transformation
PPTX
Project management
PDF
PRINCE2 Practitioner Classroom slides - Sample
PDF
Prince2 resources e book 2
PPTX
Project Management
PPTX
Instructor Slides - PMP/CAPM PMBOK 6th Edition
PDF
Pmo
PDF
7 Principles of PRINCE 2
PDF
Establishing an Effective PMO
PPTX
Project Management - PMI Approach
PPTX
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PDF
PDF
Project Management Steps And Process PowerPoint Presentation Slides
PPT
Pmi - Project Management Professional (Pmp) Certification Study Guide
PDF
Project governance
PDF
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
PRINCE2 Process Model
7 Themes of Prince2
Pmbok6 to 7 transformation
Project management
PRINCE2 Practitioner Classroom slides - Sample
Prince2 resources e book 2
Project Management
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Pmo
7 Principles of PRINCE 2
Establishing an Effective PMO
Project Management - PMI Approach
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
Project Management Steps And Process PowerPoint Presentation Slides
Pmi - Project Management Professional (Pmp) Certification Study Guide
Project governance
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Ad

Similar to Prince2 explained in 30mins (20)

PDF
prince2in30mins-170503124814.pdf
DOCX
A guide for project managers prince2
PDF
4Cite Capability Statement (pdf)
PPTX
PRINCE2 Basic Concepts
PDF
PRINCE2 quick guide
PPT
Project Management Methodology
PPT
Project management in easy steps
PPTX
Aula de Gerenciamento aplicado a Projetos
PDF
ePMO & Enterprise Implementations
PDF
Project management intro from prince2 foundation
PPTX
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
PPT
Pmi Pmbok Vs Prince2
PPT
PMBOK® Vs PRINCE2®
PPTX
PRINCE2 Executive Briefing
ODP
Guidelines for Managing Projects
PDF
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
PPTX
Project Management Slides Powerpoint Template.pptx
PPTX
Project Management Slides Powerpoint Template.pptx
PPTX
PRINCE 2 foundation & practitioner certification training
PPTX
Project management - Basics for all
prince2in30mins-170503124814.pdf
A guide for project managers prince2
4Cite Capability Statement (pdf)
PRINCE2 Basic Concepts
PRINCE2 quick guide
Project Management Methodology
Project management in easy steps
Aula de Gerenciamento aplicado a Projetos
ePMO & Enterprise Implementations
Project management intro from prince2 foundation
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
Pmi Pmbok Vs Prince2
PMBOK® Vs PRINCE2®
PRINCE2 Executive Briefing
Guidelines for Managing Projects
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
Project Management Slides Powerpoint Template.pptx
Project Management Slides Powerpoint Template.pptx
PRINCE 2 foundation & practitioner certification training
Project management - Basics for all
Ad

More from ILX Group (16)

PPTX
Agile: a fresh perspective
PPTX
How to identify and manage resistance to change
PPTX
What's changing with ITIL® 4?
PDF
PRINCE2®: The 7 principles of football management
PDF
An introduction to the Praxis Framework™ webinar
PPTX
Identifying and managing resistance to change
PPTX
Prince2 2017
PPTX
Change Management - Implementing Swift & Sudden Change (Brexit)
PPTX
Lean six sigma demystified webinar
PPTX
Actionable outputs from capability assessments - project challenge
PPTX
Project management - Stakeholders and project success - Overcoming project f...
PPTX
How combining the methodology of PRINCE2 and the framework of ITIL can enable...
PDF
AN INSIGHT INTO PRINCE2®
PDF
Introduction to ITIL® Practitioner
PPTX
Mind the Gap - Learning Technologies Conference 2016 by Russell Kenrick
PDF
Maximising and monitoring project management competence
Agile: a fresh perspective
How to identify and manage resistance to change
What's changing with ITIL® 4?
PRINCE2®: The 7 principles of football management
An introduction to the Praxis Framework™ webinar
Identifying and managing resistance to change
Prince2 2017
Change Management - Implementing Swift & Sudden Change (Brexit)
Lean six sigma demystified webinar
Actionable outputs from capability assessments - project challenge
Project management - Stakeholders and project success - Overcoming project f...
How combining the methodology of PRINCE2 and the framework of ITIL can enable...
AN INSIGHT INTO PRINCE2®
Introduction to ITIL® Practitioner
Mind the Gap - Learning Technologies Conference 2016 by Russell Kenrick
Maximising and monitoring project management competence

Recently uploaded (20)

PDF
ANIn Mumbai 2025 | Measuring Business Value during Agile Transformation by Pr...
PDF
Joshua Moll on Leadership & Mindset..pdf
PPTX
Principles & Theories of Mgt-Master in PM.pptx
PDF
"Strategic Communication in the Digital Era: Navigating Success in a Connecte...
PDF
Case study -Uber strategic plan and management
PDF
Certified Information Systems Security Professional (CISSP) Specialization Ce...
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PDF
TED Talk on how to make TED Talk slides.pdf
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PDF
Phillips model training for evaluation pdf
PPTX
Mangeroal Finance for Strategic Management
PDF
Organizational Effectiveness in companies
PDF
How Do You Track Project Milestones in Risk Management?
PPTX
4 5 6 7 Intro to Ramayan MANAGEMENT LESSONS and Qualities.pptx
PPTX
Chapter-3.pptx project life cycle presentation
PDF
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PPTX
TCoE_IT_Concrete industry.why is it required
PPTX
Chapter One an overview of political economy
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPT
Introduction to Operations And Supply Management
ANIn Mumbai 2025 | Measuring Business Value during Agile Transformation by Pr...
Joshua Moll on Leadership & Mindset..pdf
Principles & Theories of Mgt-Master in PM.pptx
"Strategic Communication in the Digital Era: Navigating Success in a Connecte...
Case study -Uber strategic plan and management
Certified Information Systems Security Professional (CISSP) Specialization Ce...
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
TED Talk on how to make TED Talk slides.pdf
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Phillips model training for evaluation pdf
Mangeroal Finance for Strategic Management
Organizational Effectiveness in companies
How Do You Track Project Milestones in Risk Management?
4 5 6 7 Intro to Ramayan MANAGEMENT LESSONS and Qualities.pptx
Chapter-3.pptx project life cycle presentation
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
TCoE_IT_Concrete industry.why is it required
Chapter One an overview of political economy
Human Resource Management | Introduction,Meaning and Definition
Introduction to Operations And Supply Management

Prince2 explained in 30mins

  • 1. www.ilxgroup.com by Karen Swanston Project Management PRINCE2® in 30 mins
  • 2. P R I N C E 2 I N 3 0 M I N U T E S Introduction 2 Karen Swanston A very enthusiastic and experienced trainer, specialising in PRINCE2 and M_o_R (Management of Risk) training for more than nine years. Along with her experience, Karen has a passion for designing and delivering training in a fun and easy manner. Because of this, she consistently receives above average feedback and exam results from her students. Her blend of experience and enthusiasm is what makes her the ideal speaker for this session
  • 3. P R I N C E 2 I N 3 0 M I N U T E S This session will take you through how easy PRINCE2 can be to learn. We’ll look at the basics of the framework without overcomplicating it, and provide you with some quick and easy-to-use hints and tips. Easy to learn
  • 4. P R I N C E 2 I N 3 0 M I N U T E S Definition of a PRINCE2 Project A project is a temporary organisation that is created for the purpose of delivering one or more business products, according to an agreed business case. © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 5. P R I N C E 2 I N 3 0 M I N U T E S Product ProjectBusinessasusual Output Change Outcome Users Benefit Dis-benefit Stuff Specialist Product
  • 6. P R I N C E 2 I N 3 0 M I N U T E S OutPut Change OutCome Users Stuff Specialist Product ProjectBusinessasusual Benefit Dis-benefit
  • 7. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 four integrated elements 7 Principles (guiding obligations and good practices) Washing your hands 7 Themes (Addressed continually throughout the project) Ingredients to be used 7 Processes (step-wise progression through a project) Recipe to follow Tailoring to the environment (flexibility) Cottage Pie for one? Including Carrots?
  • 8. P R I N C E 2 I N 3 0 M I N U T E S Principles • Continued business justification • Learn from experience • Defined roles & responsibilities • Manage by stages • Manage by exception • Focus on products • Tailor to suit the project environment
  • 9. P R I N C E 2 I N 3 0 M I N U T E S Themes • Business case • Organization • Quality • Plans • Risk • Change • Progress
  • 10. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 processes Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT INITIATING A PROJECT DIRECTING A PROJECT
  • 11. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 processes Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT INITIATING A PROJECT DIRECTING A PROJECT
  • 12. P R I N C E 2 I N 3 0 M I N U T E S Starting up a project © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 13. P R I N C E 2 I N 3 0 M I N U T E S Organization PROJECTMANAGEMENTTEAM © Copyright 2013. Reproduced under Licence from AXELOS Limited. Corporate or programme management Directing – Project Board Managing – Project Manager Delivering – Team Manager ProjectManagementTeam
  • 14. P R I N C E 2 I N 3 0 M I N U T E S Business case Confirm benefit Verify updated Business Case Verify outline Business Case Verify detailed Business Case Develop Business Case Maintain Business Case Pre- project Initiation stage Subsequent delivery stage(s) Final delivery stage Post- project Confirm benefit Confirm benefit © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 15. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize Initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT PRINCE2 processes
  • 16. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT Authorize Initiation PRINCE2 processes INITIATING A PROJECT
  • 17. P R I N C E 2 I N 3 0 M I N U T E S Initiating a project © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 18. P R I N C E 2 I N 3 0 M I N U T E S Risk definition A risk is: an uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives MAY MIGHT COULD
  • 19. P R I N C E 2 I N 3 0 M I N U T E S Issue definition A issue is: something that has happened or it will happen that was not planned. WILL HAS NO UNCERTAINTY
  • 20. P R I N C E 2 I N 3 0 M I N U T E S Quality PRODUCT DESCRIPTION Engine: petrol, 3.5L PROJECT PRODUCT DESCRIPTION PRODUCT DESCRIPTION Cream leather seats PRODUCT DESCRIPTION Tyres: Dunlop 245/40 R19 ACCEPTANCE CRITERIA 1. 0-60 mph in 3 seconds 2. Up to 2 years old 3. ‘What Car’ top 10 most desirable cars CUSTOMER QUALITY EXPECTATIONS 1.Fast Car 2.New Car 3.Flashy Car
  • 21. P R I N C E 2 I N 3 0 M I N U T E S Plans TIME & COSTPROJECT PLAN e e e e
  • 22. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID) DIRECTING A PROJECT PRINCE2 processes
  • 23. P R I N C E 2 I N 3 0 M I N U T E S Plans TIME & COSTSTAGE PLAN TIME & COSTPROJECT PLAN e e e e e e e e
  • 24. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report PRINCE2 processes MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 25. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM PRINCE2 processes MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 26. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM PRINCE2 processes MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 27. P R I N C E 2 I N 3 0 M I N U T E S Plans TEAM PLAN WORKPACKAGE TIME & COSTSTAGE PLAN TIME & COSTPROJECT PLAN e e e e e e e e
  • 28. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 processes Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT Checkpoint report INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 29. P R I N C E 2 I N 3 0 M I N U T E S Progress – reporting P R O J E C T B O A R D S e n i o r u s e r E x e c u t i v e S e n i o r s u p p l i e r C O R P O R AT E O R P R O G R AM M E M AN A G E M E N T P R O J E C T M A N A G E R T E A M M A N A G E R H I G H L I G H T R E P O R T C H E C K P O I N T R E P O R T H I G H L I G H T R E P O R T
  • 30. P R I N C E 2 I N 3 0 M I N U T E S Progress – tolerances
  • 31. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 32. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 33. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 34. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 35. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan Confirm all products are completed Evaluate the project Communication Archive project documentation PRINCE2 processes DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 36. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT Confirm all products are completed Evaluate the project Communication Archive project documentation CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan PRINCE2 processes M A N D A T E DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 37. P R I N C E 2 I N 3 0 M I N U T E S During this session we have stepped through some of the basic concepts of PRINCE2 without overcomplicating it, and provided you with some quick, easy-to-use hints and tips. Easy to learn
  • 38. P R I N C E 2 I N 3 0 M I N U T E S Questions?
  • 39. P R I N C E 2 I N 3 0 M I N U T E S Why ILX? For more information about our courses, visit our website ilxgroup.com, give us a call on +44 (0) 1270 611 600 or send an email to: Individuals enquiries suzanne.bailey@ilxgroup.com Corporate enquiries paula.gower@ilxgroup.com
  • 40. P R I N C E 2 I N 3 0 M I N U T E S Recommended courses PRINCE2 Programme & Project Sponsorship APM Project Management Qualification Change Management
  • 41. P R I N C E 2 I N 3 0 M I N U T E S I L X G R O U P, U n i t e d K i n g d o m 7 t h F l o o r 9 5 A l d w y c h L o n d o n W C 2 B 4 J F - U K T: + 4 4 ( 0 ) 2 0 7 3 7 1 4 4 4 4 Thank you for listening I L X G R O U P, Au s t r a l i a 7 3 0 S p r i n g v a l e R d M u l g r a v e , V I C 3 1 7 0 A u s t r a l i a T: + 6 1 1 3 0 0 4 5 9 4 5 9 www.ilxgroup.com