SlideShare a Scribd company logo
1/5
Civilverse Admin 17 April 2021
Project Time Estimation-6 Powerful Tips&Tricks
civilverse.org/project-time-estimation
Table of Contents for Project Time Estimation-Tips & Tricks–
1. Introduction
2. How to Estimate Activity Duration?
3. Bottom to Top Estimation
4. Top to Bottom Estimation
5. Expert Judgement
6. Analogous Estimation
7. Parametric Estimation
8. Three-Point Estimation
9. Conclusion
Introduction
The duration estimation of an activity is an important step in making a project schedule.
The success of the project schedule lies in the completion of scope work within the time.
Thus, the correct time estimation of activity is a critical task to ensure the timely
completion of the job.
The correct estimation of duration is also critical in terms of resource planning. The
incorrect duration estimate may lead to either scarcity of resource or the wastage of the
same. In the said case, either the time is lost or money or both.
The project time estimation tips & tricks include the top six approaches commonly
applied in construction, IT, defence, healthcare etc.
2/5
How to Estimate Project Activity Duration?
The precision in duration estimation of an activity depends on the quantum of work
involved in it. The higher the duration of an activity, the lesser is the precision in duration
estimation. DCMA recommends the activity to have a lower duration than 44 days. If
unavoidable, such activities should not be more than 5% of the total activities.
To accurately determine the time duration for an activity, the following data is required-
1. Complete Scope and inter-dependencies of the activities.
2. Available resources.
3. Priority of the job and criticality of the activity.
4. Working space availability.
5. Risks involved in the activity.
6. Time estimates from previous projects of similar nature.
The choice of the technique varies with the project, industry and organisation. It is the key
responsibility of the project manager to determine the correct duration estimation
technique.
The top six project time estimate tips & tricks are listed below.
Project Time Estimation Techniques
1. Bottom to Top Estimation
The bottom to top estimation method comprises of duration estimate of smaller activities
and summarising them to get the complete project duration. The method is backed up by
the data available from previous projects of similar nature.
3/5
The method is highly accurate as each activity is drilled down to the lowest level and is
discrete in nature. Bottom to top approach works well with projects that have clearly
defined activities and clear scope such as construction projects. It is a quick method to
assess the resources required for the project.
2. Top to Bottom Estimation
The project is divided into work packages. The packages are assigned with the duration
estimate. These packages are further divided into smaller activities when sufficient
information gets available.
Top to bottom method is suitable for initial planning and schedule. The planner can
suitably divide the work package and determines the duration using historical data.
3. Expert Judgement
The expert judgement technique can be used in conjugation with the top to bottom and
bottom to top technique. An expert’s opinion on duration estimation is bound by his/her
experience in similar nature projects, understanding of the project’s complexity and
analytical ability.
A planner should also consult the team members while deciding the duration of an
activity. The team is often comprised of people having experience of similar projects.
Thus, their input in duration estimation is valuable.
The method is useful in complex projects and estimation is to be done beyond the
numerical data.
The drawback of this method lies in the fact that it is opinion-based. The opinion for
duration estimate may change from person to person and hence not too reliable.
4. Analogous Estimation
The analogous estimation technique uses the data from previous projects of similar
nature. This method helps in estimating when and when not. The positive and negative
feedback both help in determining the duration of an activity.
It is the fastest method to estimate the time required for a job to complete. However,
similar projects may have different constraints that affect the project completion. Thus,
the analogous estimation may yield wrong data if the constraints of new and old projects
are not well understood.
5. Parametric Estimation
Parametric estimation is done by dividing the project scope into work packages of similar
nature and identifying the time taken by a single work package.
4/5
The duration estimate of any work package is determined either by historical data or
expert’s opinion. Thus, the accuracy of this method depends on the quality of data and its’
interpretation.
The method is useful for projects that have repetitive activities such as pipeline
construction, power transmission line construction etc.
6. Three-Point Estimation
The three-point estimation is widely used in research projects and product development.
The technique is highly suitable for projects that have high uncertainty and the duration
estimate is difficult.
The three-point technique uses three-time estimates to determine the likely time required
to complete the activity. The three estimates are-
1. Optimistic Time (t )- The time duration in which the activity can be completed if
all the ideal conditions are met.
2. Most Probable Time (t )- The time required for an activity to be completed in
normal working conditions.
3. Pessimistic Time (t )- The pessimistic time is the minimum duration of activity if
all the adverse conditions prevail.
The likely time to complete the activity is calculated as follows-
Three Point Time Estimate
Conclusion
The technique selection depends on the scope, details available, historical data
availability, complexity of the project, bottlenecks and constraints.
For the detailed scope project, bottom to top technique is best suited. If the detailed scope
of work is not defined, top to bottom technique provides a reasonable time estimate.
The research projects and new projects that have no historical data available, expert
judgement is crucial. If the experts’ opinion widely differs, a common ground should be
established and a three-point estimate technique should be used.
For projects of the same nature and similar scope, the analogous technique works well. It
saves a lot of effort. The projects having repeated work packages should use the
parametric technique.
o
m
p
5/5
Learn to create a construction project schedule with an example here.
Read my experiences of waterfall project management here.
Read about the schedule and project management here.

More Related Content

PDF
Most Popular 20 Evergreen Project Management Terms
PDF
How Does MS Project Works 6- Task Controlling Factors
PDF
My 5 Learnings of Waterfall Project Management
PDF
Managing the Construction Claims Effectively
PDF
5 Popular Types of Construction Contracts
PDF
MS Project Terminology -Top 20 terms everyone must know
PDF
Construction Project Schedule Example- Residential Building
PDF
DCMA 14-Point Schedule Quality Check
Most Popular 20 Evergreen Project Management Terms
How Does MS Project Works 6- Task Controlling Factors
My 5 Learnings of Waterfall Project Management
Managing the Construction Claims Effectively
5 Popular Types of Construction Contracts
MS Project Terminology -Top 20 terms everyone must know
Construction Project Schedule Example- Residential Building
DCMA 14-Point Schedule Quality Check

What's hot (20)

PDF
How to change working days and time in MS Project?
PDF
Construction Project Schedule Template- Residential Building
PDF
Critical Path Explained With 7 Q&As and a Free Excel Template
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PPTX
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
PDF
Statistical Methods for Construction Delay Analysis
PDF
Delay analysis ... wise after the event.
PPTX
Extension of time Analysis
PPTX
Eot claims hr__may2012
PDF
Planning can we do with out it?
PPT
06 pert cpm
PDF
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
PPTX
Construction Delay Analysis, Simplified
PPT
Estimating Time & Costs
PDF
Construction Management - New Trends
PPTX
VERTEX Construction Delays and Forensic Schedule Analyses
PPTX
Delay analysis of raw water reservoir and pumping Station
PPTX
Pert, cpm & gert
PDF
Baseline Compliance Analysis
DOCX
Construction Planning and Scheduling of Residential Building by MS Project by...
How to change working days and time in MS Project?
Construction Project Schedule Template- Residential Building
Critical Path Explained With 7 Q&As and a Free Excel Template
Extension of time (E.O.T) By Ahmed Ibarhim
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
Statistical Methods for Construction Delay Analysis
Delay analysis ... wise after the event.
Extension of time Analysis
Eot claims hr__may2012
Planning can we do with out it?
06 pert cpm
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Construction Delay Analysis, Simplified
Estimating Time & Costs
Construction Management - New Trends
VERTEX Construction Delays and Forensic Schedule Analyses
Delay analysis of raw water reservoir and pumping Station
Pert, cpm & gert
Baseline Compliance Analysis
Construction Planning and Scheduling of Residential Building by MS Project by...
Ad

Similar to Project Time Estimation 6 Powerful Tips & Tricks (20)

PPTX
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
PPTX
Project Estimation
PDF
Project Duration Estimation
PPTX
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
PPT
PM Estimation techniques
PDF
Time Estimation: Expert Tips & Proven Project Techniques
PDF
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
PPTX
BWU_BTA_22_508_RANJAN DAS(software_project_management).pptx
DOCX
Project selection and estimating technique spencer o’briencpmgt303
PPTX
Estimating
PPTX
Estimating
PPTX
Estimating in Project Scheduling
PDF
Project Cost.pdf
PPTX
Software Test Estimation
PDF
Pert techniques
PPTX
Estimation
PPTX
4 Project Estimation Techniques That Can Make You Super Successful
PPTX
Session 7 4th edition PMP
PPTX
Project Proposal for Development Training
PPSX
3 pm3 t_2%20-%20activity%20duration%20estimating
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Estimation
Project Duration Estimation
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
PM Estimation techniques
Time Estimation: Expert Tips & Proven Project Techniques
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
BWU_BTA_22_508_RANJAN DAS(software_project_management).pptx
Project selection and estimating technique spencer o’briencpmgt303
Estimating
Estimating
Estimating in Project Scheduling
Project Cost.pdf
Software Test Estimation
Pert techniques
Estimation
4 Project Estimation Techniques That Can Make You Super Successful
Session 7 4th edition PMP
Project Proposal for Development Training
3 pm3 t_2%20-%20activity%20duration%20estimating
Ad

More from SHAZEBALIKHAN1 (19)

PDF
5 Project Risk Identification Tools I Use & How You Can Use Them Too
PDF
Top 20 Standard Contract Clauses Every Manager Should Know
PDF
Residential Building Preliminary Cost Estimate- Excel Template
PDF
3 Most Important In-situ Soil Tests for Construction Works
PDF
5 Must Know Types of Concrete Testing for Civil Engineers
PDF
All About Construction Labour Planning- Excel Template
PDF
10 Powerful Construction Cost Estimation Steps
PDF
Construction Material Estimate with MS Excel file
PDF
Top 5 Concrete Quality Control Methods at Site
PDF
Types of Building Foundations- Shallow and Deep
PDF
Basics of Contract Management
PDF
Bamboo Reinforced Concrete - Criteria & Performance
PDF
Bricks- Size, Classification, Composition & Quality Control
PDF
Design of Beam- RCC Singly Reinforced Beam
PDF
Pile foundation -Types, Advantages & Load Carrying Capacity
PDF
Steel Reinforcement Facts Every Civil Engineer Must Know
PDF
Project schedule- What, How, Tools & Techniques
PDF
Civil Design of Structures -WSM & LSM
PDF
Cement -Types, Composition & QC
5 Project Risk Identification Tools I Use & How You Can Use Them Too
Top 20 Standard Contract Clauses Every Manager Should Know
Residential Building Preliminary Cost Estimate- Excel Template
3 Most Important In-situ Soil Tests for Construction Works
5 Must Know Types of Concrete Testing for Civil Engineers
All About Construction Labour Planning- Excel Template
10 Powerful Construction Cost Estimation Steps
Construction Material Estimate with MS Excel file
Top 5 Concrete Quality Control Methods at Site
Types of Building Foundations- Shallow and Deep
Basics of Contract Management
Bamboo Reinforced Concrete - Criteria & Performance
Bricks- Size, Classification, Composition & Quality Control
Design of Beam- RCC Singly Reinforced Beam
Pile foundation -Types, Advantages & Load Carrying Capacity
Steel Reinforcement Facts Every Civil Engineer Must Know
Project schedule- What, How, Tools & Techniques
Civil Design of Structures -WSM & LSM
Cement -Types, Composition & QC

Recently uploaded (20)

PPT
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
web development for engineering and engineering
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
UNIT 4 Total Quality Management .pptx
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
Construction Project Organization Group 2.pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PDF
PPT on Performance Review to get promotions
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
Geodesy 1.pptx...............................................
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
Lecture Notes Electrical Wiring System Components
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
web development for engineering and engineering
Operating System & Kernel Study Guide-1 - converted.pdf
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
UNIT 4 Total Quality Management .pptx
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
bas. eng. economics group 4 presentation 1.pptx
Automation-in-Manufacturing-Chapter-Introduction.pdf
Construction Project Organization Group 2.pptx
Model Code of Practice - Construction Work - 21102022 .pdf
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPT on Performance Review to get promotions
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Geodesy 1.pptx...............................................

Project Time Estimation 6 Powerful Tips & Tricks

  • 1. 1/5 Civilverse Admin 17 April 2021 Project Time Estimation-6 Powerful Tips&Tricks civilverse.org/project-time-estimation Table of Contents for Project Time Estimation-Tips & Tricks– 1. Introduction 2. How to Estimate Activity Duration? 3. Bottom to Top Estimation 4. Top to Bottom Estimation 5. Expert Judgement 6. Analogous Estimation 7. Parametric Estimation 8. Three-Point Estimation 9. Conclusion Introduction The duration estimation of an activity is an important step in making a project schedule. The success of the project schedule lies in the completion of scope work within the time. Thus, the correct time estimation of activity is a critical task to ensure the timely completion of the job. The correct estimation of duration is also critical in terms of resource planning. The incorrect duration estimate may lead to either scarcity of resource or the wastage of the same. In the said case, either the time is lost or money or both. The project time estimation tips & tricks include the top six approaches commonly applied in construction, IT, defence, healthcare etc.
  • 2. 2/5 How to Estimate Project Activity Duration? The precision in duration estimation of an activity depends on the quantum of work involved in it. The higher the duration of an activity, the lesser is the precision in duration estimation. DCMA recommends the activity to have a lower duration than 44 days. If unavoidable, such activities should not be more than 5% of the total activities. To accurately determine the time duration for an activity, the following data is required- 1. Complete Scope and inter-dependencies of the activities. 2. Available resources. 3. Priority of the job and criticality of the activity. 4. Working space availability. 5. Risks involved in the activity. 6. Time estimates from previous projects of similar nature. The choice of the technique varies with the project, industry and organisation. It is the key responsibility of the project manager to determine the correct duration estimation technique. The top six project time estimate tips & tricks are listed below. Project Time Estimation Techniques 1. Bottom to Top Estimation The bottom to top estimation method comprises of duration estimate of smaller activities and summarising them to get the complete project duration. The method is backed up by the data available from previous projects of similar nature.
  • 3. 3/5 The method is highly accurate as each activity is drilled down to the lowest level and is discrete in nature. Bottom to top approach works well with projects that have clearly defined activities and clear scope such as construction projects. It is a quick method to assess the resources required for the project. 2. Top to Bottom Estimation The project is divided into work packages. The packages are assigned with the duration estimate. These packages are further divided into smaller activities when sufficient information gets available. Top to bottom method is suitable for initial planning and schedule. The planner can suitably divide the work package and determines the duration using historical data. 3. Expert Judgement The expert judgement technique can be used in conjugation with the top to bottom and bottom to top technique. An expert’s opinion on duration estimation is bound by his/her experience in similar nature projects, understanding of the project’s complexity and analytical ability. A planner should also consult the team members while deciding the duration of an activity. The team is often comprised of people having experience of similar projects. Thus, their input in duration estimation is valuable. The method is useful in complex projects and estimation is to be done beyond the numerical data. The drawback of this method lies in the fact that it is opinion-based. The opinion for duration estimate may change from person to person and hence not too reliable. 4. Analogous Estimation The analogous estimation technique uses the data from previous projects of similar nature. This method helps in estimating when and when not. The positive and negative feedback both help in determining the duration of an activity. It is the fastest method to estimate the time required for a job to complete. However, similar projects may have different constraints that affect the project completion. Thus, the analogous estimation may yield wrong data if the constraints of new and old projects are not well understood. 5. Parametric Estimation Parametric estimation is done by dividing the project scope into work packages of similar nature and identifying the time taken by a single work package.
  • 4. 4/5 The duration estimate of any work package is determined either by historical data or expert’s opinion. Thus, the accuracy of this method depends on the quality of data and its’ interpretation. The method is useful for projects that have repetitive activities such as pipeline construction, power transmission line construction etc. 6. Three-Point Estimation The three-point estimation is widely used in research projects and product development. The technique is highly suitable for projects that have high uncertainty and the duration estimate is difficult. The three-point technique uses three-time estimates to determine the likely time required to complete the activity. The three estimates are- 1. Optimistic Time (t )- The time duration in which the activity can be completed if all the ideal conditions are met. 2. Most Probable Time (t )- The time required for an activity to be completed in normal working conditions. 3. Pessimistic Time (t )- The pessimistic time is the minimum duration of activity if all the adverse conditions prevail. The likely time to complete the activity is calculated as follows- Three Point Time Estimate Conclusion The technique selection depends on the scope, details available, historical data availability, complexity of the project, bottlenecks and constraints. For the detailed scope project, bottom to top technique is best suited. If the detailed scope of work is not defined, top to bottom technique provides a reasonable time estimate. The research projects and new projects that have no historical data available, expert judgement is crucial. If the experts’ opinion widely differs, a common ground should be established and a three-point estimate technique should be used. For projects of the same nature and similar scope, the analogous technique works well. It saves a lot of effort. The projects having repeated work packages should use the parametric technique. o m p
  • 5. 5/5 Learn to create a construction project schedule with an example here. Read my experiences of waterfall project management here. Read about the schedule and project management here.