QUALITY
AWARENESS
TOPIC:- CASTING AND CURING CONCRETE TEST
SPECIMEN( CUBE CASTING).
PREPARED BY : CONSTRUCTIONQUALITYWORK.COM
MAKING AND CURING CONCRETE TEST
SPECIMEN.( CUBE CASTING)
• Nominal Size of aggregate not more than 38 mm.
• Workability shall be checked prior concrete placing (i.e
Flow/Slump Checks).
• Cube mould size -150mm X150mmX150mm.
• Minimum size of sampling 0.02 cum.
• In assembling cube mould, Oil shall be applied.
MAKING AND CURING CONCRETE
TEST SPECIMEN.( CUBE CASTING)
• In no case shall the concrete to be subjected less then
35 strokes per layer for 15 cm cube. Where voids are
left by the tamping rod, sides of the mould shall be
tapped to close the voids. ( As per IS 516)
• Procedure:
• A concrete cube must be filled in 3 layers. Each Un
compacted layer of concrete must be filled about 25
mm more than the 1/3rd level, since concrete will settle
after compacting.
MAKING AND CURING CONCRETE TEST
SPECIMEN.( CUBE CASTING)
• Each layer must be compacted with the 600 mm long
long rounded end of 16 mm Dia. Tamping bar, by
roding 4times along each of the 4 side edge of the
cube mould and 4 times from centre towards edge.
This will ensure at least 32 times of minimum 35
strokes specified.
• Each layer has to be compacted sufficiently to ensure
that cement slurry called laitance is seen along all 4
edges of mould as well as on the top surface of the
concrete. i.e. no CA particles or void must be visible.
• After top layer has been compacted the extra concrete
must be compacted and level of with wooden plank.
• Filled mould shall be then cleaned externally and
shifted in overnight shelter storage place.
• Final leveling and finishing of concrete top surface
must be done with masons float. After 10 to 20 min
depending on ambient temperature.
MAKING AND CURING CONCRETE TEST
SPECIMEN.( CUBE CASTING)
• After 1 to2 hrs. when the concrete surface has
hardened sufficiently each concrete have their own
identification Marking by engraving on top surface
with nail.
• Proper Curing and Maintenance to be done.
MAKING AND CURING CONCRETE
TEST SPECIMEN. ( CUBE CASTING)
• Training given to Pll staff,
contractor Labour, Supervisor
& engineer.( Mr. Prashant)
• Give details to how tamping
cube and sequence for filling
of concrete in cube.
• Tamping rod, Tray etc.
material as mention above to
be available during casting of
cubes at site.
MAKING AND CURING CONCRETE
TEST SPECIMEN. ( CUBE CASTING)
• Shown how to sampling and fill
cubes.
• Maintenance & Sampling process.
• Proper Identifications Markings
Process.
• Proper Monitoring, Curing &
Periodic Testing Scheduled to be
followed & Maintained at site.
MAKING AND CURING CONCRETE
TEST SPECIMEN. ( CUBE CASTING)
SITE CONDITIONS:
• Proper Curing Tank with Water level in
such a way that cubes must be properly
submerged in water.
• Partition to be done for particular days (
i.e. 3days, 7days, 14th days & 28days).
• Curing Tank Water must be Replenished
within a week and proper next week date
with board to be mention near curing tank
area.
THANK YOU

More Related Content

PPTX
Curing of concrete
PPTX
Detailed ppt on Curing of concrete
PPTX
Strength of concrete (for civil engineering)
PDF
Acceptance criteria of cube
PDF
Hardened concrete
PPTX
Test on fresh concrete and harden concrete
PPT
Concrete testing
DOCX
Quality control of concrete
Curing of concrete
Detailed ppt on Curing of concrete
Strength of concrete (for civil engineering)
Acceptance criteria of cube
Hardened concrete
Test on fresh concrete and harden concrete
Concrete testing
Quality control of concrete

What's hot (20)

PPTX
Self compacting concrete
PPT
Compressive strength in concrete test
PPT
Hardened Concrete
PPTX
CONCRETE MIX DESIGN
PPTX
Hydration of cement
PPTX
Pull out test for concrete
PPT
Properties of fresh and Hardened Concrete
PPT
Fresh Concrete
PPTX
Concrete Mix Design 10262-2019.pptx
PPTX
Marsh cone test
PDF
Concrete design mix (ss)
PPTX
High strength concrete
PPTX
Workability of Concrete
PPTX
Test of concrete
PPTX
Hardened concrete
PDF
Compressivestrength concrete
PPTX
Ultrasonic pulse velocity test for concrete
PPTX
Self compacting concrete (scc)
PPTX
How to determine Initial and Final Setting Time of Cement?
PPTX
Non destructive test on concrete (ndt)
Self compacting concrete
Compressive strength in concrete test
Hardened Concrete
CONCRETE MIX DESIGN
Hydration of cement
Pull out test for concrete
Properties of fresh and Hardened Concrete
Fresh Concrete
Concrete Mix Design 10262-2019.pptx
Marsh cone test
Concrete design mix (ss)
High strength concrete
Workability of Concrete
Test of concrete
Hardened concrete
Compressivestrength concrete
Ultrasonic pulse velocity test for concrete
Self compacting concrete (scc)
How to determine Initial and Final Setting Time of Cement?
Non destructive test on concrete (ndt)
Ad

Similar to Concrete cube casting and Testing. (20)

PPT
Shrinkage of concrete sdfdgdfggfdggd.ppt
PPT
Shrinkage and plastic of concrete samples.ppt
PDF
IRJET- Effect of Different Curing on Strength of Concrete
PPTX
Cube test REPORT - DCC2042
PPTX
Making and curing concrete test specimens in the field
PPTX
concrete placement,testing, curing and compaction (1).pptx
PPTX
DOCX
Manual Of Concrete Compression Test
PPTX
CURING AND ITS TESTS.pptx 8eiiejdjdhdhhdhd
PPT
Heals - structural presentation
PDF
34p making concrete test in field
PDF
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
PDF
Comparative study on compressive strength of Self cured SCC and Normally cure...
PPTX
Concreting work
PPT
concrete curing.ppt
PPTX
HARDENED CONCRETE in Civil Engineering.pptx
PPT
curing.ppt
PPT
Cement and admixtures
PPTX
Samples for Courses Developer Concrete Curing Practices_Methods and Materials...
PDF
Experimental study on the behaviour of retempered concrete
Shrinkage of concrete sdfdgdfggfdggd.ppt
Shrinkage and plastic of concrete samples.ppt
IRJET- Effect of Different Curing on Strength of Concrete
Cube test REPORT - DCC2042
Making and curing concrete test specimens in the field
concrete placement,testing, curing and compaction (1).pptx
Manual Of Concrete Compression Test
CURING AND ITS TESTS.pptx 8eiiejdjdhdhhdhd
Heals - structural presentation
34p making concrete test in field
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Comparative study on compressive strength of Self cured SCC and Normally cure...
Concreting work
concrete curing.ppt
HARDENED CONCRETE in Civil Engineering.pptx
curing.ppt
Cement and admixtures
Samples for Courses Developer Concrete Curing Practices_Methods and Materials...
Experimental study on the behaviour of retempered concrete
Ad

Recently uploaded (20)

PPTX
Classifying Objects and Events or Situations.pptx
PDF
Exploring the Spectrum of Design Philosophies
PDF
The Serene at Jabal Ali – Sobha Realty
PPTX
Construction Remodeling Contractors – Montecito Building’s Expertise in Quali...
PDF
Estate Management Services Bangalore .pdf
PPTX
Introduction_to_Property_Management.pptx
PDF
MSN Realty 4 BHK Luxury Apartments in Neopolis Hyderabad | Premium Homes with...
PDF
Chelsea Residences 1 at Dubai Maritime City – DAMAC Properties
PPTX
Tangled Up in Green Luxury Developments
PDF
2, 3, and 4 BHK Superior Apartment in Coimbatore
PDF
BAYZ 102 at Business Bay, Dubai – Danube Properties
PPTX
Smart Lead Generation & Management Strategies for Real Estate Success.pptx
PDF
M3M Infinum - Prime Business Hub in Noida
PDF
Senfoni Etiler Presentation English - Listing Turkey
PDF
Top 5 Gemba Walks Apps with eAuditor Audits & Inspections
PDF
Lesson 9 _ the role of plantrdetrtbtvrcterxwctvyrbutynibvrtcewrxctv and anim...
PDF
DG Listing Photo Book 1915 Cutlass Cove.pdf
PDF
Real Estate Investment in Trichy – Why 2025 is the Best Time to Invest.pdf
PDF
Taormina Village At Wadi Al Safa By Reportage Properties
PDF
The S At Sobha Hartland 2 – Sobha Group
Classifying Objects and Events or Situations.pptx
Exploring the Spectrum of Design Philosophies
The Serene at Jabal Ali – Sobha Realty
Construction Remodeling Contractors – Montecito Building’s Expertise in Quali...
Estate Management Services Bangalore .pdf
Introduction_to_Property_Management.pptx
MSN Realty 4 BHK Luxury Apartments in Neopolis Hyderabad | Premium Homes with...
Chelsea Residences 1 at Dubai Maritime City – DAMAC Properties
Tangled Up in Green Luxury Developments
2, 3, and 4 BHK Superior Apartment in Coimbatore
BAYZ 102 at Business Bay, Dubai – Danube Properties
Smart Lead Generation & Management Strategies for Real Estate Success.pptx
M3M Infinum - Prime Business Hub in Noida
Senfoni Etiler Presentation English - Listing Turkey
Top 5 Gemba Walks Apps with eAuditor Audits & Inspections
Lesson 9 _ the role of plantrdetrtbtvrcterxwctvyrbutynibvrtcewrxctv and anim...
DG Listing Photo Book 1915 Cutlass Cove.pdf
Real Estate Investment in Trichy – Why 2025 is the Best Time to Invest.pdf
Taormina Village At Wadi Al Safa By Reportage Properties
The S At Sobha Hartland 2 – Sobha Group

Concrete cube casting and Testing.

  • 1. QUALITY AWARENESS TOPIC:- CASTING AND CURING CONCRETE TEST SPECIMEN( CUBE CASTING). PREPARED BY : CONSTRUCTIONQUALITYWORK.COM
  • 2. MAKING AND CURING CONCRETE TEST SPECIMEN.( CUBE CASTING) • Nominal Size of aggregate not more than 38 mm. • Workability shall be checked prior concrete placing (i.e Flow/Slump Checks). • Cube mould size -150mm X150mmX150mm. • Minimum size of sampling 0.02 cum. • In assembling cube mould, Oil shall be applied.
  • 3. MAKING AND CURING CONCRETE TEST SPECIMEN.( CUBE CASTING) • In no case shall the concrete to be subjected less then 35 strokes per layer for 15 cm cube. Where voids are left by the tamping rod, sides of the mould shall be tapped to close the voids. ( As per IS 516) • Procedure: • A concrete cube must be filled in 3 layers. Each Un compacted layer of concrete must be filled about 25 mm more than the 1/3rd level, since concrete will settle after compacting.
  • 4. MAKING AND CURING CONCRETE TEST SPECIMEN.( CUBE CASTING) • Each layer must be compacted with the 600 mm long long rounded end of 16 mm Dia. Tamping bar, by roding 4times along each of the 4 side edge of the cube mould and 4 times from centre towards edge. This will ensure at least 32 times of minimum 35 strokes specified. • Each layer has to be compacted sufficiently to ensure that cement slurry called laitance is seen along all 4 edges of mould as well as on the top surface of the concrete. i.e. no CA particles or void must be visible.
  • 5. • After top layer has been compacted the extra concrete must be compacted and level of with wooden plank. • Filled mould shall be then cleaned externally and shifted in overnight shelter storage place. • Final leveling and finishing of concrete top surface must be done with masons float. After 10 to 20 min depending on ambient temperature. MAKING AND CURING CONCRETE TEST SPECIMEN.( CUBE CASTING)
  • 6. • After 1 to2 hrs. when the concrete surface has hardened sufficiently each concrete have their own identification Marking by engraving on top surface with nail. • Proper Curing and Maintenance to be done. MAKING AND CURING CONCRETE TEST SPECIMEN. ( CUBE CASTING)
  • 7. • Training given to Pll staff, contractor Labour, Supervisor & engineer.( Mr. Prashant) • Give details to how tamping cube and sequence for filling of concrete in cube. • Tamping rod, Tray etc. material as mention above to be available during casting of cubes at site. MAKING AND CURING CONCRETE TEST SPECIMEN. ( CUBE CASTING)
  • 8. • Shown how to sampling and fill cubes. • Maintenance & Sampling process. • Proper Identifications Markings Process. • Proper Monitoring, Curing & Periodic Testing Scheduled to be followed & Maintained at site. MAKING AND CURING CONCRETE TEST SPECIMEN. ( CUBE CASTING)
  • 9. SITE CONDITIONS: • Proper Curing Tank with Water level in such a way that cubes must be properly submerged in water. • Partition to be done for particular days ( i.e. 3days, 7days, 14th days & 28days). • Curing Tank Water must be Replenished within a week and proper next week date with board to be mention near curing tank area.