SlideShare a Scribd company logo
Railway track:An Introduction
:
Railway track:An Introduction
Load Transfer
Important Functions of Ballast
 To transfer and distribute the load form sleepers to a
larger area of formation.

 To provide elasticity and resilience to track for getting
proper riding comfort .
 To provide necessary resistance to track for
longitudinal lateral stability .
 To provide effective drainage to track.
 To provide effective means of maintaining evenness
and alignment of track
Standard Ballast Profile
Advantage of Traditional Ballasted Track
Advantage
•
•
•
•

Relatively low construction costs.
High elasticity.
High maintainability at relatively low costs.
High noise absorption.
Disadvantage of Traditional Ballasted
Track
Disadvantage
• Over time, track tends to ‘float’, in both longitudinal and
lateral direction, as a result of non linear, irreversible
behaviour of the materials.
• Limited non-compensated lateral acceleration in curves, due
to limited lateral resistance offered by the ballast.
• Ballast can be churned up at high speeds, causing serious
damage to the rails and wheels.
• Reduced permeability due to contamination, grinding down of
ballast and transfer of fine particles from sub grade.
• Ballast is relatively heavy, leading to an increase in costs of
building bridges and viaducts, if they are to carry continuous
ballasted track.
• ballasted track is relatively high, this direct consequences on
tunnel diameter and access points.
Advantage of Ballastless Track
• Reduced Height
• Lower maintenance requirement and hence,
higher availability for train operation
• Increased service life
• Lack of suitable ballasted material
• A requirement for track to cause(even) less
noise and vibration nuisance
• Ballastless tracks are the good options for high speed
heavy haul trains; but on the other hands they are
costly also.
PRINCIPAL FEATURES OF
PERMANENT-WAY

12
rails
Sleepers

Ballast
Embankment
Function
•Support & guide vehicles running on it
13
•Conventional Track
•Consists of two “Rails” located at a fixed distance apart
•Called “Gauge”
•The Gauge of a track is the distance between inner edges of the
heads of rails in track, measured at 16mm below the top surface
of the rail.
14
Rails
Rails are members of the track laid in two parallel lines to provide
on our continuous and land surface for the movement of
Trains.

Function of rails
(a)
(b)
(c)
(d)
(e)

Provide a continuous and level surface
Provide a pathway which is smooth and less friction
Lateral guide for the wheels
Bear changes due to vertical loads etc.
Transfers to formation through sleepers on wider area.

15
16
Coning of wheels – The distance between the inside edges of
wheel flanges is generally kept less than the gauge. Gap is
about 38 mm on Either side. Normally the tyre is absolutely
ahead centre on the head of the rail, as the wheel is coned to
keep it in this central position automatically. These wheel are
coned at a slope

Theory of coning:- On a level track, as soon as the axle moves
towards one rail, the diameter of the wheel tread over the rail
increases, while It decreases over the other rail. This prevents
to further movement And axle retreats back to its original
position ( with equal dia or both rails and equal pressure on
both rails).

17
• Advantages of coning of the wheels are :1. To reduce the wheel and tear of wheel flange
and rails which due
• To rubbing action of flanges with inside to
cess of the rail head.
2. To provide a possibility of lateral movement.
Sleepers
Sleepers are transverse ties that are laid to support the rails. They
Have an important role in the track as they transmit the wheel load
From the rails to the ballast.
Functions and requirement of sleepers
(a) Holding the rails to their correct gauge alignment
(b) Giving a firm and ever support to the rails
(c) Transfering the load evenly from rails to a wider area of the ballast.
(d) Providing longitudinal and lateral stability the permanent way.
Sleeper density and spacing of sleepers
Sleeper density is the number of sleeper per rail length. It is M +X
Specified on where
M– length of the rail

19
Sleeper Density
• M+4 low density traffic < 10 GMT & D & E
routes
• M+7
– M is the rail length for 13 m rail length M+7 =20

• For Long Welded Track 1540 sleepers per Km
or 1660 sleepers per Km

20
Concrete Sleeper
Pre-Stressed Concrete Sleeper (PSC)

21
REQUIREMENT OF SLEEPER
• IT SHOULD PROVIDE EASY MEANS OF MAINTAINABILITY
•

HANDLING OF RAILS, SLEEPER & FASTENING SHOULD BE EASY

• QUICK RESTORATION AFTER ACCIDENT IS POSSIBLE

•

MATERIAL AND DESIGN IS AVAILABLE

•

IT SHOULD HAVE ANTI THEFT AND ANTI-SABOTAGE QUALITY

•

IT SHOULD BE OVERALL CHEAP
LOAD DISTRIBUTION FROM AXLE TO SLEEPERS
DESIGN CONSIDERATIONS
• THE REACTION AT THE RAIL SEAT DEPENDS
UPON------– SLEEPERS SPACING
– AXLE LOADS
– SPEED OF TRAINS
– THE STANDARD OF MAINTENANCE OF TRACK
DESIGN CONSIDERATIONS
• TO CALCULATE THE FORCES TO WHICH THE
CONCRETE SLEEPERS ARE SUBJECTED
IS
COMPLICATED AND IS GENERALLY BASED ON
OBSERVATIONS,
EXPERIENCE
AND
MEASUREMENTS.
DESIGN CONSIDERATIONS
• FOR BG (22T AXLE LOAD), A WHEEL LOAD OF 11 T
AT THE RAIL TOP WILL CAUSE A VERTICAL SLEEPER
REACTION OF 6 T.
• FOR MG (14T AXLE LOAD), THIS VALUE IS 5 T.
THESE LOADS ARE AUGMENTED BY 150% TO CATER
FOR DYNAMIC AUGMENT FOR DESIGN PURPOSE.
CONDITION NO. 1

NO CENTRE BINDING

15 TONNE

15 TONNE

1750 MM

p
670MM
1040 MM

1040 MM
CONDITION NO. 2

WITH CENTRE BINDING

15 TONNE

15 TONNE

1750 MM

p’

p’

670MM
1040 MM

1040 MM
CONDITION NO. 3 : Lateral load

13 TONNE
7 TONNE
1750 MM

p
DESIGN CONSIDERATIONS

1.237

CONDITION 2

B.M.

CONDITION 3

CONDITION 1

1.277
DESIGN CONSIDERATIONS
• MAX. B.M. AT RAIL SEAT IS GOVERNED BY
CONDITION NO.1
• MAX. B.M. AT CENTRE IS GOVERNED BY
CONDITION NO.2
• CONDITION NO.3 DOES NOT GOVERN THE
MAX. B.M. AT ANY LOCATION AND HENCE
IS NOT CONSIDERED
SHAPE OF SLEEPER IN PLAN –
– SHOULD NOT ALLOW CONCENTRATION
OF THE BALLAST REACTION IN MIDDLE
HENCE TRAPEZOIDAL SHAPE

ADDITIONAL LATERAL RESISTANCE DUE
TO WEDGING ACTION
SHAPE OF SLEEPER IN PLAN
•SLEEPER PROFILE IS TRAPEZOIDAL BECAUSE
IT IS HAVING MORE SECTION MODULUS COMPARED
TO RECTANGULAR SECTIONS WITH SAME CROSS
SECTIONAL AREA.
IT ALSO FECILITATE EASY DEMOULDING AND
MORE ROOM FOR HTS WIRES AT THE BOTTOM.
ADVANTAGES OF PSC SLEEPERS
• HEAVY WEIGHT--PROVIDES LONGITUDINAL & LATERAL
STABILITY REQUIRED FOR LWR
• WITH ELASTIC FASTENING, IT CAN MAINTAIN GAUGE
AND ALIGNMENT PROPERLY, HENCE MORE SAFE
• FLAT BOTTOM –SUITES MECH. TAMPING
• COST EFFECTIVE
• DURABLE--IMMUNE TO TERMITE, FIRE, RUSTS, ETC.
• ANTI THEFT & ANTI-SABOTAGE
• SUITED FOR TRACK CIRCUITING
DISADVANTAGES OF PSC SLEEPERS
LAYING & HANDLING IS DIFFICULT AS IT IS HEAVY
DIFFICULT TO RESTORE TRAFFIC AFTER ACCIDENT
NOT AMENABLE TO MANUAL LAYING OR MAINT.
REQUIRES MORE BALLAST AND WIDER FORMATION
NO SCRAP VALUE- DIFFICULT TO DISPOSE
MAINTENANCE OF JOINT IS DIFFICULT
NOT UNIVERSAL --USE OF DIFF. TYPE OF SLEEPERS
FUNCTIONS OF SLEEPER ASSEMBALY
• TRANSMIT AXLE LOAD OF VEHICLES TO
BALLAST PROPERLY
• HOLD
– GAUGE
– LEVEL
– ALIGNMENT

• PROVIDING LONGITUDINAL & LATERAL
STABILITY TO TRACK
Fishplate
– To provide continuity across rail joint for the
movement of railway vehicles
– Rail ends are connected by “fishplates” & “fish
bolt”

37
FASTENINGS
• Fixing
arrangement for
Rails and
sleepers
• Various types
• Depending on
type of Rails &
Sleepers,
38
FASTENING
• UIC ORE DEFINITION
– FASTENINGS OR FASTENING DEVICES ARE DESIGNED AS
THAT ASSEMBLY OF PARTS , ENSURING THE CONNECTION
BETWEEN RAILS AND SLEEPERS OR RAIL BEARERS IN THE
CASE OF TRADITIONAL TRACK LAYING SYSTEM OR WITH
SUBSTRUCTURE IN CASE THE TRACK IS LAID DIRECTLY ON
THE STRUCTURES OR ON THE TUNNEL BASE.
FASTENING TYPES

• VARIOUS TYPES
–RAIL FREE
–RIGID
–ELASTIC
FASTENING (FORCES)
• FORCES IN TRACK
– DOWNWARD FORCES: SLEEPER UNDER
LOAD,THERE WILL BE A TENDENCY OF GAP
BETWEEN RAIL AND FASTENING - FASTENING
PREVENTS THIS
– UPWARD FORCES: LOAD AWAY FROM
SLEEPER, TRACK TENDS TO LIFT UPWARD,GAP
BETWEEN RAIL AND SLEEPER – FASTENING
PREVENT THIS
FASTENING (FORCES)
– ROTATION OF SLEEPERS: ROTATION OF SLEEPERS
ABOUT ITS OWN AXIS - FASTENING TO PREVENT THIS
– LATERAL FORCES: DUE TO PARASITIC MOTIONS AND
DUE TO LONGITUDINAL COMPRESSION(DURING
BUCKLING)– RAIL HAS TENDENCY TO MOVE LATERALLY
ON SLEEPER AND SOMETIME COMPLETE TRACK MOVE
LATERALLY-FASTENING SHOULD PROVIDE BUCKLING
STRENGTH AND TORSIONAL STRENGTH
FASTENING (FORCES)
• LONGITUDINAL FORCES: CAUSED BY THERMAL
STRESSES,WAVE ACTION AND ADHESION
BETWEEN RAIL AND WHEEL.THESE FORCES MAY
CAUSE MOVEMENT OF RAIL OVER SLEEPER OR
MOVEMENT
OF
ENTIRE
RAIL/SLEEPER
ASSEMBLY--FASTENING SHOULD PREVENT THIS.
DOWNWARD LOAD ON TOE OF RAIL CAUSED BY
ELASTIC FASTENING IS CALLED TOE LOAD.
FASTENING (FORCES)

– VIBRATIONS- LOW FREQUENCY DUE TO
PARASITIC MOTION and VERY HIGH
FREQUENCY VIBRATIONS IN VERTICAL PLANE
DUE TO RAIL WHEEL INTERACTION 700 TO
1200 CPS AND AMPLITUDE OF 0.1 MM TO 0.3
MM WITH ACCELRATION OF 70 TO 100 g
EFFECTS OF VERY HIGH FREQUENCY
VIBRATIONS
– CAUSE OF FATIGUE FAILURE
– LOOSENING OF FASTENING
– LOOSENING OF BALLAST
– LOSS OF TOE LOAD
– EFFECT ON ROLLING STOCK
– RAIL CORRUGATION

THE FASTENING SHOULD ABSORB
AND DAMP THE HIGH ENERGY VIBRATIONS.
ELASTIC FASTENING
• RAIL IS CONNECTED WITH SLEEPER THROUGH AN
ELASTIC MEDIUM, SUCH THAT IT ABSORBS ENERGY
OF VIBRATIONS AND DOES NOT ALLOW TO CAUSE
GAP BETWEEN RAIL AND SLEEPERS.
• THERE SHOULD BE DAMPED ELASTIC SUSPENSION
WITHOUT PLAY. THE FASTENING PERMITS THE
MOVEMENT OF RAIL WITHOUT CAUSING ANY GAP.
TYPE OF ELASTIC FASTENING
• TYPE I – IN WHICH TOE LOAD IS DERIVED FROM
A FRICTIONAL GRIP OR NAILING EFFECT
• ERS, DS 18 AND MACBETH

• TYPE II – IN WHICH LOAD APPLICATION IS
OBTAINED THROUGH A SCREW THREAD
• HM, NABLA, VASSLOH

• TYPE III – IN WHICH THE LOAD IS
PREDETERMINED AT THE DESIGN STAGE
• PENDROL
OBJECTIVES OF ELASTIC FASTENING
• ELASTIC RUBBER PAD
• ABSORBS SHOCKS AND DAMP OUT VIBRATIONS
• INCREASE FRICTIONAL RESISTANCE TO LONG. OR
LATERAL MOVEMENT OF RAIL.
• DISTRIBUTE LOAD UNIFORMLY OVER SLEEPER
• PROVIDE ELECTRIC INSULATION BETWEEN RAIL
AND SLEEPER
• REDUCE NOISE LEVEL
MECHANISM
Weight of rail
Source of
Vibration
Vibration blocked by fastening
spring

Rail
Fastening

GRP
Sleeper

Ballast

Wt of
sleeper

Vibration absorbed by rubber pad

Vibration absorbed
By stone friction &
Spring action
MECHANISM
LOAD

ENERGY
ABSORBED

ERC & GRP 60 %

BALLAST 25%

FORMATION

15%
VOSSLOH FASTENING
Sleeper screw
in dowel

Tension clamps

Guide plate

Rail Pad
COMPARISION BETWEEN ELASTIC
FASTENING
TYPE II (BOLTED FASTENER)

TYPE III ( CAST IN ANCHORAGE
FASTENER)
THREADED ELEMENT APPLYING ANCHORAGE FIXED AT THE TIME
FORCE TO A SPRING STEEL
OF CASTING
ELEMENT
THREADED ELEMENT IS
-------REMOVABLE
RUBBER PAD BETWEEN RAIL
RUBBER PAD BETWEEN RAIL AND
AND SLEEPER
SLEEPER
TOE LOAD GENERATED BY
NO SUCH PROVISION
TIGHTENING NUT
ADJUSTABLE TOE LOAD
FIXED TOE LOAD
ALLOWS REPLACEMENT OF
CASTING ANCHORAGES CANNOT
ALL THE COMPONENTS IN THE BE RENEWED
EVENT OF DAMAGE
OILING OF THREADS ONCE IN 3 NO NEED.FIT AND FORGET TYPE
YEARS
REQUIREMENT OF TOE LOAD

• ERC MARK III HAS AV. TOE LOAD OF 1000 KG
UNDER 12 MM. DEFLECTION.
– THE AV. STATIC TOE LOAD =1000x4 =4000 KG.
ASSUMING 0.5 AS COEFF. OF FRICTION BETWEEN
RUBBER PAD AND RAIL, THE RAIL TO SLEEPER
RESISTANCE IS APPROX. 2000 KG.
– THIS IS > AV. SLEEPER TO BALLAST RESISTANCE ( 1000
KG.). SO THE CHANCES OF RELATIVE RAIL TO SLEEPER
MOVEMENT ARE LESS.
WHY GREASING?
LOADED
CONDITION
AXLELOAD
22 Tons

FREE
CONDITION

FREE
CONDITION

TOE LOAD
850-1100Kg

TOE LOAD
850-1100Kg

Minimum
Compressive
stress

Maximum
Compressive
stress

Minimum
Compressive
stress
WHY GREASING?
Figure shows the torsional
force exerted due to
corrosion.

Torsional Force

ERC
ERC

CORROSION

Torsional Force

LINER

INSERT

PSC
WHY GREASING?

CORROSION

End of function life

Rate of
corrosion

Jamming of ERC

Reduction of strength
Loss of Toe Load

End of function Life

Life cycle Time
RUBBER PAD
• FUNCTIONS
–
–
–

DAMPING OF HIGH FREQUENCY VIBRATIONS
VIBRATIONALLY ISOLATE RAIL
PREVENT GAP

THE MECHANISM FOR ACHIEVING THIS IS – MOLECULES
BROUGHT CLOSER UNDER FORCE, ENERGY DISSIPATION
WHEN FORCE IS REMOVED.
DAMPING IS BEST WHEN RESTRAINING FORCE IS
PREPORTIONAL TO AMPLITUDE OF VIBRATION.
RUBBER PAD
• COMMON TYPE OF PADS
– PIMPLE TYPE PADS
– GROOVED TYPE PADS

• THICKNESS

6 MM
LOAD DEFLECTION CHARACTERSTICS
25
SOLID PAD

PRESSURE ON RAIL(T)

20
15

GROOVED PAD

10
5
0
0

10

20
30
40
50
DEFLECTION 1/100 MM

60
RUBBER PAD
• MATERIAL
– NATURAL RUBBER
– RIBBED SMOKED SHEET
– BLEND OF STYRENE RUBBER/ POLY
BUTADIENE RUBBER
RUBBER PAD
• THE TOP SURFACE OF RUBBER PAD, WHICH
COMES DIRECTLY IN CONTACT WITH RAIL,
EXECUTE VERY HIGH FREQUENCY 1000 Hz (LOW
AMPLITUDE 0.05- 0.1 mm) VIBRATIONS.
• WHILE THE BOTTOM SURFACE, WHICH COMES IN
CONTACT WITH SLEEPER, EXECUTE LOW
FREQUENCY 20 Hz VIBRATIONS.
RUBBER PAD
• FOR IMPROVING THE PERFORMANCE OF RUBBER
PAD , MATERIAL SHOULD BE WITH VARYING
ELASTIC PROPERTIES.
• SO THE TOP OF RUBBER PAD SHOULD HAVE HIGHER
MODULUS OF ELASTICITY( HARDER) WHILE
BOTTOM SHOULD BE OF SOFTER MATERIAL.
LINERS
– DISTRIBUTION OF TOE LOAD OVER LARGER AREA
ON RAIL FOOT
– ALLOW FLEXIBILITY FOR USE OF DIFFERENT RAIL
SECTION ON THE SAME/ COMMON SLEEPER
– PERMITS GAUGE ADJUSTMENT IN CURVED
TRACK AND CORRECTION IN ALIGNMENT
– PROVIDE INSULATION BETWEEN RAIL AND
INSERT
LINERS
• THE REQUIREMENTS OF LINER
– THE LINER SHOULD HAVE PROPER SLOPE TO
MATCH WITH RAIL FOOT SLOPE
– THE VERTICAL LEG OF LINER SHOULD FIT
PROPERLY BETWEEN RAIL AND MCI INSERT TO
MAINTAIN GAUGE
– IT SHOULD BE EASY TO FIX & MANUFACTURE
INSERTS

• IT IS EMBEDDED IN CONCRETE AT THE TIME
OF CASTING
• THIS IS ANCHORAGE FOR ERC
• GRIPS THE CLIP EFFECTIVELY
• PROVIDES LATERAL SUPPORT TO RAIL
• SHOULD HAVE ADEQUATE PULL STRENGTH
(MORE THAN 10T)
INSERTS
• TOE LOAD IS FUNCTION OF DIA. OF HOLE
AND DIFFERENCE BETWEEN APEX OF HOLE
AND TOP OF SHOULDER
• CORRECT POSITIONING IS IMPORTANT
– VERTICAL POSITIONING FOR TOE LOAD
– LATERAL POSITIONING FOR GAUGE

• THE GAP BETWEEN TOE AND RAIL SEAT
SURFACE SHOULD BE 8 MM.
MAINTENANCE OF RAIL JOINTS ON CONCRETE
SLEEPERS
• RAIL JOINTS TO HAVE 1 M. LONG FISHPLATE
• RUBBER PAD OF THE JOINT & SHOULDER
SLEEPERS TO BE RENEWED EVERY YEAR
• CRIB & SHOULDER BALLAST AROUND THE JOINT
TO BE SCREENED EVERY YEAR
• THE FISH PLATE SHOULD BE GROUND TO
ACCOMMODATE ELASTIC RAIL CLIP / PROVIDE JCLIP
Thank You

More Related Content

PDF
Track work presentation
PDF
Lecture 4: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
PPTX
Railway Planning - Unit 1
PDF
Cross Section of Permanent Way.pdf
PPTX
Plastering and pointing
PDF
Transportation engineering 2
PPTX
Cladding
PPTX
Wall finishes
Track work presentation
Lecture 4: Railway Engineering ( هندسة السكك الحديدية ) Dr. Alaa Gabr
Railway Planning - Unit 1
Cross Section of Permanent Way.pdf
Plastering and pointing
Transportation engineering 2
Cladding
Wall finishes

What's hot (20)

PPTX
Points and crossings
PPTX
Points and crossings
PPTX
Railway Engineering - Geometric design of track
PPTX
Points and Crossings
PPTX
Introduction to railway engineering (T.E 2)
PDF
Alignment of railway tracks
PPTX
Railway Track Maintenance
PPTX
railway failure and its type
PPTX
Point and crossing of railway
PPTX
Railway engineering
PDF
Construction of a New Railway Track
PPTX
Signals on Railway
PPTX
Unit 1. introduction to Railway Engineering
PPTX
Railway track
PPTX
PERMANANT WAY
PPTX
Corrugated (roaring), Hogging, Buckling, Kinks in rails
PDF
Creep of Rails.pdf
PPTX
Sleepers and Ballast
PPTX
1.railway intro and rails
PPTX
Bearings in bridges
Points and crossings
Points and crossings
Railway Engineering - Geometric design of track
Points and Crossings
Introduction to railway engineering (T.E 2)
Alignment of railway tracks
Railway Track Maintenance
railway failure and its type
Point and crossing of railway
Railway engineering
Construction of a New Railway Track
Signals on Railway
Unit 1. introduction to Railway Engineering
Railway track
PERMANANT WAY
Corrugated (roaring), Hogging, Buckling, Kinks in rails
Creep of Rails.pdf
Sleepers and Ballast
1.railway intro and rails
Bearings in bridges
Ad

Viewers also liked (20)

DOC
2 handouts-lecture-7
PPTX
Stream flow measurement
PDF
Railway engineering
PDF
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
PDF
Geometric desing of railway track
PDF
Precipitation and its estimation
PPTX
Stations and Yards of Railway
PPTX
Geometric design of the track
PDF
PPTX
Station yards
PPTX
Railway engineering
PPT
Points and crossings ( special assigments )
PDF
Surface runoff
PDF
Introduction to ground water hydrology
PPTX
Points and crossings
PDF
Water cycle and water budget
PPT
Railway transportation 2.1
PDF
Topic%20 compression
PDF
Chapter 6 concrete dam engineering with examples
PPTX
Bolted connections
2 handouts-lecture-7
Stream flow measurement
Railway engineering
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Geometric desing of railway track
Precipitation and its estimation
Stations and Yards of Railway
Geometric design of the track
Station yards
Railway engineering
Points and crossings ( special assigments )
Surface runoff
Introduction to ground water hydrology
Points and crossings
Water cycle and water budget
Railway transportation 2.1
Topic%20 compression
Chapter 6 concrete dam engineering with examples
Bolted connections
Ad

Similar to Railway track:An Introduction (20)

PPTX
Unit 1.pptx
PPTX
5.track or permanent way and track stresses
PDF
5-180501044424.pdf
PPT
Unit 1 gauge creep
PPTX
Elastic fastenings in Modern Track structure railway .pptx
PPTX
Chapter 5 Introduction to railway
PDF
Introduction railway engineering
PPTX
Railway Engineering , Operation Of Railways
PPT
Chapter - 2.ppt railway engineering chapter 2
PPTX
P.way
PPTX
1. Introduction to Railway engg..pptx
PPTX
Curves and elevation
PPTX
Railway engineering
PPTX
Railway simple curve design and maintenance
PPTX
chapter-3 Track Stracture.pptx
PPTX
3.Railways infrastructure engineering.pptx
PDF
lecturenote_1888016911chapter-3 track.pdf
PPTX
Railway and Airport Engineering
PPTX
Railway engg geometric design
PPTX
Railway planning RHTA - VTU Module 1
Unit 1.pptx
5.track or permanent way and track stresses
5-180501044424.pdf
Unit 1 gauge creep
Elastic fastenings in Modern Track structure railway .pptx
Chapter 5 Introduction to railway
Introduction railway engineering
Railway Engineering , Operation Of Railways
Chapter - 2.ppt railway engineering chapter 2
P.way
1. Introduction to Railway engg..pptx
Curves and elevation
Railway engineering
Railway simple curve design and maintenance
chapter-3 Track Stracture.pptx
3.Railways infrastructure engineering.pptx
lecturenote_1888016911chapter-3 track.pdf
Railway and Airport Engineering
Railway engg geometric design
Railway planning RHTA - VTU Module 1

More from Prem Prakash Kumar (8)

PDF
Report on insertion of br. approach sleeper to standardised the approach slee...
PPTX
Correct method of handling and stacking of rails
PPTX
Noble thoughts
PPTX
Monsoon precaution [aden pku]
PPTX
Translamatic robotic reconditioning by aden(pku)
PPTX
Rail Grinding Machine:A Basic approach
PDF
Development dynamics
PDF
Administrative tribunals
Report on insertion of br. approach sleeper to standardised the approach slee...
Correct method of handling and stacking of rails
Noble thoughts
Monsoon precaution [aden pku]
Translamatic robotic reconditioning by aden(pku)
Rail Grinding Machine:A Basic approach
Development dynamics
Administrative tribunals

Recently uploaded (20)

DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PDF
Indian roads congress 037 - 2012 Flexible pavement
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
Introduction to Building Materials
PDF
advance database management system book.pdf
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PDF
What if we spent less time fighting change, and more time building what’s rig...
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
Computing-Curriculum for Schools in Ghana
PPTX
20th Century Theater, Methods, History.pptx
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PPTX
Virtual and Augmented Reality in Current Scenario
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
IGGE1 Understanding the Self1234567891011
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
Indian roads congress 037 - 2012 Flexible pavement
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
LDMMIA Reiki Yoga Finals Review Spring Summer
Introduction to Building Materials
advance database management system book.pdf
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
What if we spent less time fighting change, and more time building what’s rig...
Introduction to pro and eukaryotes and differences.pptx
Computing-Curriculum for Schools in Ghana
20th Century Theater, Methods, History.pptx
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
FORM 1 BIOLOGY MIND MAPS and their schemes
Virtual and Augmented Reality in Current Scenario
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
IGGE1 Understanding the Self1234567891011

Railway track:An Introduction

  • 2. :
  • 5. Important Functions of Ballast  To transfer and distribute the load form sleepers to a larger area of formation.  To provide elasticity and resilience to track for getting proper riding comfort .  To provide necessary resistance to track for longitudinal lateral stability .  To provide effective drainage to track.  To provide effective means of maintaining evenness and alignment of track
  • 7. Advantage of Traditional Ballasted Track Advantage • • • • Relatively low construction costs. High elasticity. High maintainability at relatively low costs. High noise absorption.
  • 8. Disadvantage of Traditional Ballasted Track Disadvantage • Over time, track tends to ‘float’, in both longitudinal and lateral direction, as a result of non linear, irreversible behaviour of the materials. • Limited non-compensated lateral acceleration in curves, due to limited lateral resistance offered by the ballast. • Ballast can be churned up at high speeds, causing serious damage to the rails and wheels. • Reduced permeability due to contamination, grinding down of ballast and transfer of fine particles from sub grade.
  • 9. • Ballast is relatively heavy, leading to an increase in costs of building bridges and viaducts, if they are to carry continuous ballasted track. • ballasted track is relatively high, this direct consequences on tunnel diameter and access points.
  • 10. Advantage of Ballastless Track • Reduced Height • Lower maintenance requirement and hence, higher availability for train operation • Increased service life • Lack of suitable ballasted material • A requirement for track to cause(even) less noise and vibration nuisance
  • 11. • Ballastless tracks are the good options for high speed heavy haul trains; but on the other hands they are costly also.
  • 14. •Conventional Track •Consists of two “Rails” located at a fixed distance apart •Called “Gauge” •The Gauge of a track is the distance between inner edges of the heads of rails in track, measured at 16mm below the top surface of the rail. 14
  • 15. Rails Rails are members of the track laid in two parallel lines to provide on our continuous and land surface for the movement of Trains. Function of rails (a) (b) (c) (d) (e) Provide a continuous and level surface Provide a pathway which is smooth and less friction Lateral guide for the wheels Bear changes due to vertical loads etc. Transfers to formation through sleepers on wider area. 15
  • 16. 16
  • 17. Coning of wheels – The distance between the inside edges of wheel flanges is generally kept less than the gauge. Gap is about 38 mm on Either side. Normally the tyre is absolutely ahead centre on the head of the rail, as the wheel is coned to keep it in this central position automatically. These wheel are coned at a slope Theory of coning:- On a level track, as soon as the axle moves towards one rail, the diameter of the wheel tread over the rail increases, while It decreases over the other rail. This prevents to further movement And axle retreats back to its original position ( with equal dia or both rails and equal pressure on both rails). 17
  • 18. • Advantages of coning of the wheels are :1. To reduce the wheel and tear of wheel flange and rails which due • To rubbing action of flanges with inside to cess of the rail head. 2. To provide a possibility of lateral movement.
  • 19. Sleepers Sleepers are transverse ties that are laid to support the rails. They Have an important role in the track as they transmit the wheel load From the rails to the ballast. Functions and requirement of sleepers (a) Holding the rails to their correct gauge alignment (b) Giving a firm and ever support to the rails (c) Transfering the load evenly from rails to a wider area of the ballast. (d) Providing longitudinal and lateral stability the permanent way. Sleeper density and spacing of sleepers Sleeper density is the number of sleeper per rail length. It is M +X Specified on where M– length of the rail 19
  • 20. Sleeper Density • M+4 low density traffic < 10 GMT & D & E routes • M+7 – M is the rail length for 13 m rail length M+7 =20 • For Long Welded Track 1540 sleepers per Km or 1660 sleepers per Km 20
  • 22. REQUIREMENT OF SLEEPER • IT SHOULD PROVIDE EASY MEANS OF MAINTAINABILITY • HANDLING OF RAILS, SLEEPER & FASTENING SHOULD BE EASY • QUICK RESTORATION AFTER ACCIDENT IS POSSIBLE • MATERIAL AND DESIGN IS AVAILABLE • IT SHOULD HAVE ANTI THEFT AND ANTI-SABOTAGE QUALITY • IT SHOULD BE OVERALL CHEAP
  • 23. LOAD DISTRIBUTION FROM AXLE TO SLEEPERS
  • 24. DESIGN CONSIDERATIONS • THE REACTION AT THE RAIL SEAT DEPENDS UPON------– SLEEPERS SPACING – AXLE LOADS – SPEED OF TRAINS – THE STANDARD OF MAINTENANCE OF TRACK
  • 25. DESIGN CONSIDERATIONS • TO CALCULATE THE FORCES TO WHICH THE CONCRETE SLEEPERS ARE SUBJECTED IS COMPLICATED AND IS GENERALLY BASED ON OBSERVATIONS, EXPERIENCE AND MEASUREMENTS.
  • 26. DESIGN CONSIDERATIONS • FOR BG (22T AXLE LOAD), A WHEEL LOAD OF 11 T AT THE RAIL TOP WILL CAUSE A VERTICAL SLEEPER REACTION OF 6 T. • FOR MG (14T AXLE LOAD), THIS VALUE IS 5 T. THESE LOADS ARE AUGMENTED BY 150% TO CATER FOR DYNAMIC AUGMENT FOR DESIGN PURPOSE.
  • 27. CONDITION NO. 1 NO CENTRE BINDING 15 TONNE 15 TONNE 1750 MM p 670MM 1040 MM 1040 MM
  • 28. CONDITION NO. 2 WITH CENTRE BINDING 15 TONNE 15 TONNE 1750 MM p’ p’ 670MM 1040 MM 1040 MM
  • 29. CONDITION NO. 3 : Lateral load 13 TONNE 7 TONNE 1750 MM p
  • 31. DESIGN CONSIDERATIONS • MAX. B.M. AT RAIL SEAT IS GOVERNED BY CONDITION NO.1 • MAX. B.M. AT CENTRE IS GOVERNED BY CONDITION NO.2 • CONDITION NO.3 DOES NOT GOVERN THE MAX. B.M. AT ANY LOCATION AND HENCE IS NOT CONSIDERED
  • 32. SHAPE OF SLEEPER IN PLAN – – SHOULD NOT ALLOW CONCENTRATION OF THE BALLAST REACTION IN MIDDLE HENCE TRAPEZOIDAL SHAPE ADDITIONAL LATERAL RESISTANCE DUE TO WEDGING ACTION
  • 33. SHAPE OF SLEEPER IN PLAN •SLEEPER PROFILE IS TRAPEZOIDAL BECAUSE IT IS HAVING MORE SECTION MODULUS COMPARED TO RECTANGULAR SECTIONS WITH SAME CROSS SECTIONAL AREA. IT ALSO FECILITATE EASY DEMOULDING AND MORE ROOM FOR HTS WIRES AT THE BOTTOM.
  • 34. ADVANTAGES OF PSC SLEEPERS • HEAVY WEIGHT--PROVIDES LONGITUDINAL & LATERAL STABILITY REQUIRED FOR LWR • WITH ELASTIC FASTENING, IT CAN MAINTAIN GAUGE AND ALIGNMENT PROPERLY, HENCE MORE SAFE • FLAT BOTTOM –SUITES MECH. TAMPING • COST EFFECTIVE • DURABLE--IMMUNE TO TERMITE, FIRE, RUSTS, ETC. • ANTI THEFT & ANTI-SABOTAGE • SUITED FOR TRACK CIRCUITING
  • 35. DISADVANTAGES OF PSC SLEEPERS LAYING & HANDLING IS DIFFICULT AS IT IS HEAVY DIFFICULT TO RESTORE TRAFFIC AFTER ACCIDENT NOT AMENABLE TO MANUAL LAYING OR MAINT. REQUIRES MORE BALLAST AND WIDER FORMATION NO SCRAP VALUE- DIFFICULT TO DISPOSE MAINTENANCE OF JOINT IS DIFFICULT NOT UNIVERSAL --USE OF DIFF. TYPE OF SLEEPERS
  • 36. FUNCTIONS OF SLEEPER ASSEMBALY • TRANSMIT AXLE LOAD OF VEHICLES TO BALLAST PROPERLY • HOLD – GAUGE – LEVEL – ALIGNMENT • PROVIDING LONGITUDINAL & LATERAL STABILITY TO TRACK
  • 37. Fishplate – To provide continuity across rail joint for the movement of railway vehicles – Rail ends are connected by “fishplates” & “fish bolt” 37
  • 38. FASTENINGS • Fixing arrangement for Rails and sleepers • Various types • Depending on type of Rails & Sleepers, 38
  • 39. FASTENING • UIC ORE DEFINITION – FASTENINGS OR FASTENING DEVICES ARE DESIGNED AS THAT ASSEMBLY OF PARTS , ENSURING THE CONNECTION BETWEEN RAILS AND SLEEPERS OR RAIL BEARERS IN THE CASE OF TRADITIONAL TRACK LAYING SYSTEM OR WITH SUBSTRUCTURE IN CASE THE TRACK IS LAID DIRECTLY ON THE STRUCTURES OR ON THE TUNNEL BASE.
  • 40. FASTENING TYPES • VARIOUS TYPES –RAIL FREE –RIGID –ELASTIC
  • 41. FASTENING (FORCES) • FORCES IN TRACK – DOWNWARD FORCES: SLEEPER UNDER LOAD,THERE WILL BE A TENDENCY OF GAP BETWEEN RAIL AND FASTENING - FASTENING PREVENTS THIS – UPWARD FORCES: LOAD AWAY FROM SLEEPER, TRACK TENDS TO LIFT UPWARD,GAP BETWEEN RAIL AND SLEEPER – FASTENING PREVENT THIS
  • 42. FASTENING (FORCES) – ROTATION OF SLEEPERS: ROTATION OF SLEEPERS ABOUT ITS OWN AXIS - FASTENING TO PREVENT THIS – LATERAL FORCES: DUE TO PARASITIC MOTIONS AND DUE TO LONGITUDINAL COMPRESSION(DURING BUCKLING)– RAIL HAS TENDENCY TO MOVE LATERALLY ON SLEEPER AND SOMETIME COMPLETE TRACK MOVE LATERALLY-FASTENING SHOULD PROVIDE BUCKLING STRENGTH AND TORSIONAL STRENGTH
  • 43. FASTENING (FORCES) • LONGITUDINAL FORCES: CAUSED BY THERMAL STRESSES,WAVE ACTION AND ADHESION BETWEEN RAIL AND WHEEL.THESE FORCES MAY CAUSE MOVEMENT OF RAIL OVER SLEEPER OR MOVEMENT OF ENTIRE RAIL/SLEEPER ASSEMBLY--FASTENING SHOULD PREVENT THIS. DOWNWARD LOAD ON TOE OF RAIL CAUSED BY ELASTIC FASTENING IS CALLED TOE LOAD.
  • 44. FASTENING (FORCES) – VIBRATIONS- LOW FREQUENCY DUE TO PARASITIC MOTION and VERY HIGH FREQUENCY VIBRATIONS IN VERTICAL PLANE DUE TO RAIL WHEEL INTERACTION 700 TO 1200 CPS AND AMPLITUDE OF 0.1 MM TO 0.3 MM WITH ACCELRATION OF 70 TO 100 g
  • 45. EFFECTS OF VERY HIGH FREQUENCY VIBRATIONS – CAUSE OF FATIGUE FAILURE – LOOSENING OF FASTENING – LOOSENING OF BALLAST – LOSS OF TOE LOAD – EFFECT ON ROLLING STOCK – RAIL CORRUGATION THE FASTENING SHOULD ABSORB AND DAMP THE HIGH ENERGY VIBRATIONS.
  • 46. ELASTIC FASTENING • RAIL IS CONNECTED WITH SLEEPER THROUGH AN ELASTIC MEDIUM, SUCH THAT IT ABSORBS ENERGY OF VIBRATIONS AND DOES NOT ALLOW TO CAUSE GAP BETWEEN RAIL AND SLEEPERS. • THERE SHOULD BE DAMPED ELASTIC SUSPENSION WITHOUT PLAY. THE FASTENING PERMITS THE MOVEMENT OF RAIL WITHOUT CAUSING ANY GAP.
  • 47. TYPE OF ELASTIC FASTENING • TYPE I – IN WHICH TOE LOAD IS DERIVED FROM A FRICTIONAL GRIP OR NAILING EFFECT • ERS, DS 18 AND MACBETH • TYPE II – IN WHICH LOAD APPLICATION IS OBTAINED THROUGH A SCREW THREAD • HM, NABLA, VASSLOH • TYPE III – IN WHICH THE LOAD IS PREDETERMINED AT THE DESIGN STAGE • PENDROL
  • 48. OBJECTIVES OF ELASTIC FASTENING • ELASTIC RUBBER PAD • ABSORBS SHOCKS AND DAMP OUT VIBRATIONS • INCREASE FRICTIONAL RESISTANCE TO LONG. OR LATERAL MOVEMENT OF RAIL. • DISTRIBUTE LOAD UNIFORMLY OVER SLEEPER • PROVIDE ELECTRIC INSULATION BETWEEN RAIL AND SLEEPER • REDUCE NOISE LEVEL
  • 49. MECHANISM Weight of rail Source of Vibration Vibration blocked by fastening spring Rail Fastening GRP Sleeper Ballast Wt of sleeper Vibration absorbed by rubber pad Vibration absorbed By stone friction & Spring action
  • 50. MECHANISM LOAD ENERGY ABSORBED ERC & GRP 60 % BALLAST 25% FORMATION 15%
  • 51. VOSSLOH FASTENING Sleeper screw in dowel Tension clamps Guide plate Rail Pad
  • 52. COMPARISION BETWEEN ELASTIC FASTENING TYPE II (BOLTED FASTENER) TYPE III ( CAST IN ANCHORAGE FASTENER) THREADED ELEMENT APPLYING ANCHORAGE FIXED AT THE TIME FORCE TO A SPRING STEEL OF CASTING ELEMENT THREADED ELEMENT IS -------REMOVABLE RUBBER PAD BETWEEN RAIL RUBBER PAD BETWEEN RAIL AND AND SLEEPER SLEEPER TOE LOAD GENERATED BY NO SUCH PROVISION TIGHTENING NUT ADJUSTABLE TOE LOAD FIXED TOE LOAD ALLOWS REPLACEMENT OF CASTING ANCHORAGES CANNOT ALL THE COMPONENTS IN THE BE RENEWED EVENT OF DAMAGE OILING OF THREADS ONCE IN 3 NO NEED.FIT AND FORGET TYPE YEARS
  • 53. REQUIREMENT OF TOE LOAD • ERC MARK III HAS AV. TOE LOAD OF 1000 KG UNDER 12 MM. DEFLECTION. – THE AV. STATIC TOE LOAD =1000x4 =4000 KG. ASSUMING 0.5 AS COEFF. OF FRICTION BETWEEN RUBBER PAD AND RAIL, THE RAIL TO SLEEPER RESISTANCE IS APPROX. 2000 KG. – THIS IS > AV. SLEEPER TO BALLAST RESISTANCE ( 1000 KG.). SO THE CHANCES OF RELATIVE RAIL TO SLEEPER MOVEMENT ARE LESS.
  • 54. WHY GREASING? LOADED CONDITION AXLELOAD 22 Tons FREE CONDITION FREE CONDITION TOE LOAD 850-1100Kg TOE LOAD 850-1100Kg Minimum Compressive stress Maximum Compressive stress Minimum Compressive stress
  • 55. WHY GREASING? Figure shows the torsional force exerted due to corrosion. Torsional Force ERC ERC CORROSION Torsional Force LINER INSERT PSC
  • 56. WHY GREASING? CORROSION End of function life Rate of corrosion Jamming of ERC Reduction of strength Loss of Toe Load End of function Life Life cycle Time
  • 57. RUBBER PAD • FUNCTIONS – – – DAMPING OF HIGH FREQUENCY VIBRATIONS VIBRATIONALLY ISOLATE RAIL PREVENT GAP THE MECHANISM FOR ACHIEVING THIS IS – MOLECULES BROUGHT CLOSER UNDER FORCE, ENERGY DISSIPATION WHEN FORCE IS REMOVED. DAMPING IS BEST WHEN RESTRAINING FORCE IS PREPORTIONAL TO AMPLITUDE OF VIBRATION.
  • 58. RUBBER PAD • COMMON TYPE OF PADS – PIMPLE TYPE PADS – GROOVED TYPE PADS • THICKNESS 6 MM
  • 59. LOAD DEFLECTION CHARACTERSTICS 25 SOLID PAD PRESSURE ON RAIL(T) 20 15 GROOVED PAD 10 5 0 0 10 20 30 40 50 DEFLECTION 1/100 MM 60
  • 60. RUBBER PAD • MATERIAL – NATURAL RUBBER – RIBBED SMOKED SHEET – BLEND OF STYRENE RUBBER/ POLY BUTADIENE RUBBER
  • 61. RUBBER PAD • THE TOP SURFACE OF RUBBER PAD, WHICH COMES DIRECTLY IN CONTACT WITH RAIL, EXECUTE VERY HIGH FREQUENCY 1000 Hz (LOW AMPLITUDE 0.05- 0.1 mm) VIBRATIONS. • WHILE THE BOTTOM SURFACE, WHICH COMES IN CONTACT WITH SLEEPER, EXECUTE LOW FREQUENCY 20 Hz VIBRATIONS.
  • 62. RUBBER PAD • FOR IMPROVING THE PERFORMANCE OF RUBBER PAD , MATERIAL SHOULD BE WITH VARYING ELASTIC PROPERTIES. • SO THE TOP OF RUBBER PAD SHOULD HAVE HIGHER MODULUS OF ELASTICITY( HARDER) WHILE BOTTOM SHOULD BE OF SOFTER MATERIAL.
  • 63. LINERS – DISTRIBUTION OF TOE LOAD OVER LARGER AREA ON RAIL FOOT – ALLOW FLEXIBILITY FOR USE OF DIFFERENT RAIL SECTION ON THE SAME/ COMMON SLEEPER – PERMITS GAUGE ADJUSTMENT IN CURVED TRACK AND CORRECTION IN ALIGNMENT – PROVIDE INSULATION BETWEEN RAIL AND INSERT
  • 64. LINERS • THE REQUIREMENTS OF LINER – THE LINER SHOULD HAVE PROPER SLOPE TO MATCH WITH RAIL FOOT SLOPE – THE VERTICAL LEG OF LINER SHOULD FIT PROPERLY BETWEEN RAIL AND MCI INSERT TO MAINTAIN GAUGE – IT SHOULD BE EASY TO FIX & MANUFACTURE
  • 65. INSERTS • IT IS EMBEDDED IN CONCRETE AT THE TIME OF CASTING • THIS IS ANCHORAGE FOR ERC • GRIPS THE CLIP EFFECTIVELY • PROVIDES LATERAL SUPPORT TO RAIL • SHOULD HAVE ADEQUATE PULL STRENGTH (MORE THAN 10T)
  • 66. INSERTS • TOE LOAD IS FUNCTION OF DIA. OF HOLE AND DIFFERENCE BETWEEN APEX OF HOLE AND TOP OF SHOULDER • CORRECT POSITIONING IS IMPORTANT – VERTICAL POSITIONING FOR TOE LOAD – LATERAL POSITIONING FOR GAUGE • THE GAP BETWEEN TOE AND RAIL SEAT SURFACE SHOULD BE 8 MM.
  • 67. MAINTENANCE OF RAIL JOINTS ON CONCRETE SLEEPERS • RAIL JOINTS TO HAVE 1 M. LONG FISHPLATE • RUBBER PAD OF THE JOINT & SHOULDER SLEEPERS TO BE RENEWED EVERY YEAR • CRIB & SHOULDER BALLAST AROUND THE JOINT TO BE SCREENED EVERY YEAR • THE FISH PLATE SHOULD BE GROUND TO ACCOMMODATE ELASTIC RAIL CLIP / PROVIDE JCLIP