SAP B1 IMPLEMENTATION
Risk Management Plan Page 1 of 12
Risk Management Plan
SAP B1 IMPLIMENTATION
INSTRUCTOR: SIR. Salman Bilal
Date: 3-28-2015
Version: 1.1
STUDENT: FAHAD SALEEM
[SAP B1 IMPLEMENTATION]
Risk Management Plan Page 1 of 12
DocumentControl
Methodology
Methodology
PM BOK 5
Document location
Location
BAHRIA UNIVERSITY LAHORE
Author
Position Name Contact no
Stakeholders and other contributors
Position Name
RISK MANAGER FAHAD SALEEM
PROJECT MANAGER
Revision history
Version Issue date Author/editor Description/Summary of changes
1.0 3-28-2015 FAHAD REVIEW
1.1 4-4-2015 FAHAD CHANGE IN CONTENTS
Reviewed by
Version Issue date Name Position Review date
1.0 3-21-2015 Sir Salman Bilal Instructor 3-28-2015
1.1 3-28-2015 Sir Salman Bilal Instructor
Approvals
.
Version Issue date Name Position Approval date
1.1 3-21-2015 Sir Salman Bilal Instructor 3-28-2015
Related documents
Document Location
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438
Table of Contents
1 PROJECT SUMMARY......................................................................................................................3
1.1. Opportunity Statement ..............................................................................................................3
1.2. Objectives and Critical Success Factors .....................................................................................3
1.3. Scope ......................................................................................................................................3
1.3.1. In scope 4
1.3.2. Out of scope 4
1.3.3. Assumptions 4
1.3.4. Constraints 4
1.3.5. Business Constraints 5
1.3.6. Technical Constraints 5
1.4. Recommended Solution ............................................................................................................5
2. PROJECT RISK ASSESSMENT .......................................................................................................5
2.1. Risk Rating Methodology...........................................................................................................5
2.2. Consequence Legend ...............................................................................................................6
2.3. Risk Identification .....................................................................................................................7
2.3.1. Operational Risks 7
2.3.2. Legal Risks 8
2.3.3. Market Risks 9
2.3.4. Financial Risks 9
2.3.5. Miscellaneous Risks 9
3. RISK MANAGEMENT PROCESSES ...............................................................................................10
3.1. Organisation...........................................................................................................................10
3.2. Risk Reporting........................................................................................................................11
3.3. Tracking.................................................................................................................................11
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438
1 ProjectSummary
This document is the Project Risk management plan for the SAP Business One (ERP) implementation
project, at XYZ Ltd.. The Project Plan follows Hussain Chaudhury Consulting proposal to implement SAP
Business One, which was accepted by XYZ Ltd .
The proposal defined the high-level project scope and approach. The plan also incorporates various
activities that will be required so that XYZ Ltd. can use the SAP Business One ERP properly.
1.1. Opportunity Statement
The purpose of this phase is to prepare the SAP Business One system and the client organization for
production go-live. During this phase Cut-over activities are completed Along with final system testing and
necessary adjustments are made to resolve all remaining critical open issues.
1.2. Objectives and Critical Success Factors
.
 Senior management commitment and support at all levels
 Participation of team leads in the project team
 Empowered project team to make decisions as well as existence of forums to support a rapid
decision making process
 High-calibre project team members
 Project team availability and full-time dedication to the project
 Communication with key stakeholders, project team and all users
 Alignment of expectations to project scope
 Appropriate human resources, budget and/or time to complete the project
 Organizational readiness and ability to change
 Full incorporation of redesigned processes for increased efficiency, effectiveness and alignment with
strategic priorities
 Strong focus on organizational change management
 Sufficient training on new application
 Minimization of unique or local requirements within the organization
 Strong team environment within the Project Office.
 Availability of all the data on timely manner.
.
1.3. Scope
Implementation Services (here in after referred to as “Services”) shall mean to include some or all of the
following:
 Installation and setup of SAP Business One at Customer’s premises, whether on stand-alone system
or network provided by the Customer
 Understanding of Customer’s existing systems / processes and development of Business Blueprint of
the new system (ASAP Methodology)
 Proposing the coding schema for chart of accounts & coding structures in different modules of SAP
Business One
 System Initialization and set up of the system and uploads of master data
 HCC Technical team will be responsible for Software (SAP Business One) installation on interim
server, production server and on the Customer site.
 Training of designated Customer personnel in the proper use of SAP Business One. (Project plan will
be delivered at the preceding week of start of the project)
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438
1.4. In scope
 Financials
 Sales Opportunities
 Sales A/R
 Purchasing A/P
 Banking
 Inventory
 Human Resource
1.5. Out of scope
 Point of Sale
 Payroll
 Asset Maintenance
 Gate Security
1.6. Assumptions
Assumptions need to be analysed
 You will get all resources required by you.
 During the implementation, Technical Staff will be available.
 All important stakeholders will come to the next meeting.
1.7. Constraints
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438
1.8. Business Constraints
Business constraints depend on the state of your organization time, budget, and
resource.
1.9. Technical Constraints
Technical constraints limit your design choice
1.10. Recommended Solution
…………
2. ProjectRisk Assessment
2.1. Risk Rating Methodology
Consequence
Rating Insignificant Minor Moderate Major Catastrophic
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438
Consequence
Rating Insignificant Minor Moderate Major Catastrophic
Almost certain - controls
unsatisfactory to mitigate
the risk
High High Extreme Extreme Extreme
Likely - Controls
inadequate to mitigate the
risk and require
improvement
Medium High High Extreme Extreme
Possible - Controls
reasonable / adequate to
mitigate the risk but may
still require improvement
Low Medium High Extreme Extreme
Unlikely - Controls robust
and adequate to mitigate
the risk
Low Medium Medium High Extreme
Rare - Controls strong to
mitigate the risk Low Low Medium High High
2.2. Consequence Legend
Rating Description
Insignificant Impact can be easily absorbed without requiring management effort
Minor Impact can be readily absorbed but some management effort is
required
Moderate Impact cannot be managed under normal operating conditions;
requiring moderate level of resource and management input
Major Impact requires a high level of management attention / effort and
resources to rectify
Catastrophic Disaster with potential to lead to business collapse and requiring
almost total management attention / effort to rectify
HIGH BROWN
MEDIUM YELLOW
LOW GREEN
EXTREME ORANGE
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 7 of 12
2.3. Risk Identification
2.4. Operational Risks
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Lack of Top Management commitment and
support
Minor Medium
Unclear goals and objectives Major high
Limitation in resources Moderate low
Failure to redesign business process Major high
Poor of changes and risks management catastrophic extreme
Poor project management Major high
Ineffective communications Moderate low
Poor conflict management catastrophic extreme
Lack of proper project planning and
controlling
Major high
Insufficient testing phase Moderate low
2.4.1.1. Technical Risks
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Insufficient training of end-users Moderate low
Lack of business and technical knowledge Major high
Underestimation of organizational structure
and business processes
Catastrophic extreme
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 8 of 12
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Poor integration of the infrastructure systems Catastrophic extreme
The design and implementation of system
disrupts the business operations
Catastrophic extreme
Insufficient automation Moderate medium
Underestimation of system technical
architecture
Moderate medium
Poor software troubleshooting Moderate Medium
Data losses Major high
Too many customizations without knowing
exactly which processes should be
customized and which need to follow Best
Practices.
Catastrophic extreme
2.5. Legal Risks
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Access Governance Catastrophic extreme
audit management Catastrophic extreme
controls and compliance management Catastrophic extreme
enterprise risk management (ERM) Catastrophic extreme
fraud management Catastrophic extreme
international trade management Catastrophic extreme
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 9 of 12
2.6. Market Risks
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Lack of vendor support and partnership Major High
2.7. Financial Risks
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Ineffective project cost and time management Catastrophic extreme
Unfunded for the ERP Catastrophic extreme
2.8. Miscellaneous Risks
Risk Summary Description Preliminary
Risk Rating
Risk Mitigation Description Residual
Risk Rating
Lack of competence of ERP’s consultants Major high
Poor conflict management Catastrophic extreme
Poor motivation and project team work Moderate low
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 10 of 12
3. Risk ManagementProcesses
.
3.1. Organisation
Organizational risk management is risk management at the strategic level. Risk management
concepts are discussed in the "Technical Risk Management" practice area, which describes the
activities that are necessary for project-level risk management. An organizational risk management
process relies on the existence of such project-level risk management and provides mechanisms for
surfacing and managing risks that transcend, or are shared across, projects.
The seven principles of risk management are shown in the following figure. These principles are
divided into one core principle, three sustaining principles, and three defining principles. An effective
risk management program exhibits characteristics of all seven principles.
75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 11 of 12
3.2. Risk Reporting
Risk ID Description Risk Owner Risk
Responsible
Recommended
Action
3.3. Tracking
Monthly ranking
Risk item Weekly Monthly Quarterly Risk resolution progress

More Related Content

PDF
Software project management
PPTX
Software Project Management
PDF
Portfolio mostafa saad_jan_2020
PPT
Corporate Governance to Project Governance
PDF
Software Project Management (SPM)
PDF
2. project scope management
PPTX
Pmp basics you need to know
PPT
Episode 20 :PROJECT MANAGEMENT CONTEXT
Software project management
Software Project Management
Portfolio mostafa saad_jan_2020
Corporate Governance to Project Governance
Software Project Management (SPM)
2. project scope management
Pmp basics you need to know
Episode 20 :PROJECT MANAGEMENT CONTEXT

What's hot (20)

PPT
PMI Project Management Framework
PDF
James dimas it infrastructure approach
PPT
Article18
PDF
PMP PMBok 5th Project management processes
PDF
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
PDF
Pmbok 6th edition summary
PPTX
Project Management Framework
PPTX
2015 - RT & AWAY Intro Pack
PDF
Project Controls Expo, 13th Nov 2013 - "CREATING CONFIDENCE THROUGH PROJECT C...
PPTX
Deliverables Mapping
DOCX
World Class Maintenance_DurgaPrasadMishra
PPTX
software project management
PPTX
Staff training and certification
PDF
Project Success: The Basis of the Five Immutable Principles
PDF
Heliotropic Abundance
PPTX
Project Management
PDF
PMBOK_5th_Project Management Framework
PDF
Policy and Procedure Rollout
PPT
Process auditing as per VDA 6.3
PDF
The Critical Success Factors For Erp Implementation An Organisational Fit Per...
PMI Project Management Framework
James dimas it infrastructure approach
Article18
PMP PMBok 5th Project management processes
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Pmbok 6th edition summary
Project Management Framework
2015 - RT & AWAY Intro Pack
Project Controls Expo, 13th Nov 2013 - "CREATING CONFIDENCE THROUGH PROJECT C...
Deliverables Mapping
World Class Maintenance_DurgaPrasadMishra
software project management
Staff training and certification
Project Success: The Basis of the Five Immutable Principles
Heliotropic Abundance
Project Management
PMBOK_5th_Project Management Framework
Policy and Procedure Rollout
Process auditing as per VDA 6.3
The Critical Success Factors For Erp Implementation An Organisational Fit Per...
Ad

Viewers also liked (20)

PPTX
Tejidos basicos
RTF
Albeiro grado 6 1
PDF
Asajn
DOC
Reglamento automotriz vergara
PDF
Tech Transformation Brochure
PPTX
A Walk Through Germany
PDF
Practica n° 04
PPT
Encontro com André Sardet
DOCX
DIA DEL AGUA
PPTX
Regencia de farmacia (1)
PDF
Practica numero 4
PDF
BEYA Certificate
PDF
Album 1
PPS
Ppt explicativo
PDF
Trabajo de excel n° 04
DOCX
PDF
20160517160917
Tejidos basicos
Albeiro grado 6 1
Asajn
Reglamento automotriz vergara
Tech Transformation Brochure
A Walk Through Germany
Practica n° 04
Encontro com André Sardet
DIA DEL AGUA
Regencia de farmacia (1)
Practica numero 4
BEYA Certificate
Album 1
Ppt explicativo
Trabajo de excel n° 04
20160517160917
Ad

Similar to RiskManagementPlanFinal1.3 (20)

PDF
Bpo risk management
PPTX
Financial Crime Projects
PPT
Risk Management
PPTX
Risk Management -- Business Continuity Planning and Management.pptx
PDF
Riskpro Information Risk Management
PDF
Riskpro information risk management
PDF
Riskpro Information Risk Management
PDF
Riskpro Information Risk Management
PPTX
Software risk analysis and management
PDF
Governance, Risk, and Compliance Services
PDF
Riskpro Iso 31000 Services
PDF
Riskpro Iso 31000 Services
PDF
Riskpro Iso 31000 Services
PDF
Riskpro Iso 31000 Services
PDF
Riskpro Iso 31000 Services
PPT
Risk managementforsponsors barnes
PPT
bpm-risk-analysis
PPT
project_risk_mgmt_final 1.ppt
PPTX
Maulia chapter 9 IT BSC jessica keyes
PDF
Sap Risk Advisory Presentation
Bpo risk management
Financial Crime Projects
Risk Management
Risk Management -- Business Continuity Planning and Management.pptx
Riskpro Information Risk Management
Riskpro information risk management
Riskpro Information Risk Management
Riskpro Information Risk Management
Software risk analysis and management
Governance, Risk, and Compliance Services
Riskpro Iso 31000 Services
Riskpro Iso 31000 Services
Riskpro Iso 31000 Services
Riskpro Iso 31000 Services
Riskpro Iso 31000 Services
Risk managementforsponsors barnes
bpm-risk-analysis
project_risk_mgmt_final 1.ppt
Maulia chapter 9 IT BSC jessica keyes
Sap Risk Advisory Presentation

More from Fahad Saleem (20)

PPTX
Tally Enterprise Resource Planning System
PPTX
STRIVEN Accounting ERP System
PPTX
Survey Monkey SAAS ERP
PPTX
Sap Lumira Presentation
PPTX
Fedena School Management System
PPTX
SIEBEL Customer Relationship Management
PPTX
Ellucian Banner Enterprise Resource Planning
PPTX
Priority Enterprise Resource Planning Software
PPTX
Oracle NetSuite Cloud Enterprise Resource Planning System
PPTX
Munis Enterprise Resource Planning System
PPTX
Daecom Enterprise Resource Planning System
PPTX
Aptean Enterprise Resource Planning System
PPTX
Applane Enterprise Resource Planning System
PPTX
Win team Enterprise Resource Planning System
PPTX
Scoro Cloud Based ERP System
PPTX
Sap business by design Cloud ERP System
PPTX
Acumatica Cloud ERP System
PPTX
Orion Enterprise Resource Planning System
PPTX
Odoo Enterprise Resource Planning System
PPTX
MARG Enterprise Resource Planning System
Tally Enterprise Resource Planning System
STRIVEN Accounting ERP System
Survey Monkey SAAS ERP
Sap Lumira Presentation
Fedena School Management System
SIEBEL Customer Relationship Management
Ellucian Banner Enterprise Resource Planning
Priority Enterprise Resource Planning Software
Oracle NetSuite Cloud Enterprise Resource Planning System
Munis Enterprise Resource Planning System
Daecom Enterprise Resource Planning System
Aptean Enterprise Resource Planning System
Applane Enterprise Resource Planning System
Win team Enterprise Resource Planning System
Scoro Cloud Based ERP System
Sap business by design Cloud ERP System
Acumatica Cloud ERP System
Orion Enterprise Resource Planning System
Odoo Enterprise Resource Planning System
MARG Enterprise Resource Planning System

RiskManagementPlanFinal1.3

  • 1. SAP B1 IMPLEMENTATION Risk Management Plan Page 1 of 12 Risk Management Plan SAP B1 IMPLIMENTATION INSTRUCTOR: SIR. Salman Bilal Date: 3-28-2015 Version: 1.1 STUDENT: FAHAD SALEEM
  • 2. [SAP B1 IMPLEMENTATION] Risk Management Plan Page 1 of 12 DocumentControl Methodology Methodology PM BOK 5 Document location Location BAHRIA UNIVERSITY LAHORE Author Position Name Contact no Stakeholders and other contributors Position Name RISK MANAGER FAHAD SALEEM PROJECT MANAGER Revision history Version Issue date Author/editor Description/Summary of changes 1.0 3-28-2015 FAHAD REVIEW 1.1 4-4-2015 FAHAD CHANGE IN CONTENTS Reviewed by Version Issue date Name Position Review date 1.0 3-21-2015 Sir Salman Bilal Instructor 3-28-2015 1.1 3-28-2015 Sir Salman Bilal Instructor Approvals . Version Issue date Name Position Approval date 1.1 3-21-2015 Sir Salman Bilal Instructor 3-28-2015 Related documents Document Location
  • 3. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Table of Contents 1 PROJECT SUMMARY......................................................................................................................3 1.1. Opportunity Statement ..............................................................................................................3 1.2. Objectives and Critical Success Factors .....................................................................................3 1.3. Scope ......................................................................................................................................3 1.3.1. In scope 4 1.3.2. Out of scope 4 1.3.3. Assumptions 4 1.3.4. Constraints 4 1.3.5. Business Constraints 5 1.3.6. Technical Constraints 5 1.4. Recommended Solution ............................................................................................................5 2. PROJECT RISK ASSESSMENT .......................................................................................................5 2.1. Risk Rating Methodology...........................................................................................................5 2.2. Consequence Legend ...............................................................................................................6 2.3. Risk Identification .....................................................................................................................7 2.3.1. Operational Risks 7 2.3.2. Legal Risks 8 2.3.3. Market Risks 9 2.3.4. Financial Risks 9 2.3.5. Miscellaneous Risks 9 3. RISK MANAGEMENT PROCESSES ...............................................................................................10 3.1. Organisation...........................................................................................................................10 3.2. Risk Reporting........................................................................................................................11 3.3. Tracking.................................................................................................................................11
  • 4. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 1 ProjectSummary This document is the Project Risk management plan for the SAP Business One (ERP) implementation project, at XYZ Ltd.. The Project Plan follows Hussain Chaudhury Consulting proposal to implement SAP Business One, which was accepted by XYZ Ltd . The proposal defined the high-level project scope and approach. The plan also incorporates various activities that will be required so that XYZ Ltd. can use the SAP Business One ERP properly. 1.1. Opportunity Statement The purpose of this phase is to prepare the SAP Business One system and the client organization for production go-live. During this phase Cut-over activities are completed Along with final system testing and necessary adjustments are made to resolve all remaining critical open issues. 1.2. Objectives and Critical Success Factors .  Senior management commitment and support at all levels  Participation of team leads in the project team  Empowered project team to make decisions as well as existence of forums to support a rapid decision making process  High-calibre project team members  Project team availability and full-time dedication to the project  Communication with key stakeholders, project team and all users  Alignment of expectations to project scope  Appropriate human resources, budget and/or time to complete the project  Organizational readiness and ability to change  Full incorporation of redesigned processes for increased efficiency, effectiveness and alignment with strategic priorities  Strong focus on organizational change management  Sufficient training on new application  Minimization of unique or local requirements within the organization  Strong team environment within the Project Office.  Availability of all the data on timely manner. . 1.3. Scope Implementation Services (here in after referred to as “Services”) shall mean to include some or all of the following:  Installation and setup of SAP Business One at Customer’s premises, whether on stand-alone system or network provided by the Customer  Understanding of Customer’s existing systems / processes and development of Business Blueprint of the new system (ASAP Methodology)  Proposing the coding schema for chart of accounts & coding structures in different modules of SAP Business One  System Initialization and set up of the system and uploads of master data  HCC Technical team will be responsible for Software (SAP Business One) installation on interim server, production server and on the Customer site.  Training of designated Customer personnel in the proper use of SAP Business One. (Project plan will be delivered at the preceding week of start of the project)
  • 5. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 1.4. In scope  Financials  Sales Opportunities  Sales A/R  Purchasing A/P  Banking  Inventory  Human Resource 1.5. Out of scope  Point of Sale  Payroll  Asset Maintenance  Gate Security 1.6. Assumptions Assumptions need to be analysed  You will get all resources required by you.  During the implementation, Technical Staff will be available.  All important stakeholders will come to the next meeting. 1.7. Constraints
  • 6. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 1.8. Business Constraints Business constraints depend on the state of your organization time, budget, and resource. 1.9. Technical Constraints Technical constraints limit your design choice 1.10. Recommended Solution ………… 2. ProjectRisk Assessment 2.1. Risk Rating Methodology Consequence Rating Insignificant Minor Moderate Major Catastrophic
  • 7. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Consequence Rating Insignificant Minor Moderate Major Catastrophic Almost certain - controls unsatisfactory to mitigate the risk High High Extreme Extreme Extreme Likely - Controls inadequate to mitigate the risk and require improvement Medium High High Extreme Extreme Possible - Controls reasonable / adequate to mitigate the risk but may still require improvement Low Medium High Extreme Extreme Unlikely - Controls robust and adequate to mitigate the risk Low Medium Medium High Extreme Rare - Controls strong to mitigate the risk Low Low Medium High High 2.2. Consequence Legend Rating Description Insignificant Impact can be easily absorbed without requiring management effort Minor Impact can be readily absorbed but some management effort is required Moderate Impact cannot be managed under normal operating conditions; requiring moderate level of resource and management input Major Impact requires a high level of management attention / effort and resources to rectify Catastrophic Disaster with potential to lead to business collapse and requiring almost total management attention / effort to rectify HIGH BROWN MEDIUM YELLOW LOW GREEN EXTREME ORANGE
  • 8. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 7 of 12 2.3. Risk Identification 2.4. Operational Risks Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Lack of Top Management commitment and support Minor Medium Unclear goals and objectives Major high Limitation in resources Moderate low Failure to redesign business process Major high Poor of changes and risks management catastrophic extreme Poor project management Major high Ineffective communications Moderate low Poor conflict management catastrophic extreme Lack of proper project planning and controlling Major high Insufficient testing phase Moderate low 2.4.1.1. Technical Risks Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Insufficient training of end-users Moderate low Lack of business and technical knowledge Major high Underestimation of organizational structure and business processes Catastrophic extreme
  • 9. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 8 of 12 Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Poor integration of the infrastructure systems Catastrophic extreme The design and implementation of system disrupts the business operations Catastrophic extreme Insufficient automation Moderate medium Underestimation of system technical architecture Moderate medium Poor software troubleshooting Moderate Medium Data losses Major high Too many customizations without knowing exactly which processes should be customized and which need to follow Best Practices. Catastrophic extreme 2.5. Legal Risks Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Access Governance Catastrophic extreme audit management Catastrophic extreme controls and compliance management Catastrophic extreme enterprise risk management (ERM) Catastrophic extreme fraud management Catastrophic extreme international trade management Catastrophic extreme
  • 10. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 9 of 12 2.6. Market Risks Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Lack of vendor support and partnership Major High 2.7. Financial Risks Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Ineffective project cost and time management Catastrophic extreme Unfunded for the ERP Catastrophic extreme 2.8. Miscellaneous Risks Risk Summary Description Preliminary Risk Rating Risk Mitigation Description Residual Risk Rating Lack of competence of ERP’s consultants Major high Poor conflict management Catastrophic extreme Poor motivation and project team work Moderate low
  • 11. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 10 of 12 3. Risk ManagementProcesses . 3.1. Organisation Organizational risk management is risk management at the strategic level. Risk management concepts are discussed in the "Technical Risk Management" practice area, which describes the activities that are necessary for project-level risk management. An organizational risk management process relies on the existence of such project-level risk management and provides mechanisms for surfacing and managing risks that transcend, or are shared across, projects. The seven principles of risk management are shown in the following figure. These principles are divided into one core principle, three sustaining principles, and three defining principles. An effective risk management program exhibits characteristics of all seven principles.
  • 12. 75ec6beb-5612-41ed-9e17-41d4d5a4ffd8-161028082438 Page 11 of 12 3.2. Risk Reporting Risk ID Description Risk Owner Risk Responsible Recommended Action 3.3. Tracking Monthly ranking Risk item Weekly Monthly Quarterly Risk resolution progress