The document shows a schedule diagram comparing the original 514 day contract duration to the actual 698 day completion duration for a project, which resulted in a total delay of 184 days. 61 days of the delay were considered excusable, while 123 days were considered non-excusable according to the analysis, which is illustrated schematically.