SlideShare a Scribd company logo
© 2006 Prentice Hall, Inc.
6/18/20201
Welcome To Heartiest
Students
Dereje Jima
Construction Planning and Management
Department of Civil Engineering
ADDIS COLLEGE
Semester I
2017
6/18/20202
Stochastic Project Scheduling
Lecture
On
Stochastic Project Scheduling – Project Evaluation
and Review Technique
[PERT]
6/18/20203
Stochastic Project Scheduling [PERT]
Introduction
In some situations, estimating activity duration becomes
a difficult task due to ambiguity inherited in and the
risks associated with some work.
Thus, the duration of an activity is estimated as a
range of time values rather than being a single
value.
This section deals with the scheduling of the project
6/18/20204
Stochastic Project Scheduling
[PERT]
Scheduling with Uncertain Durations
Using the probabilistic distribution of activity
durations.
Duration of a particular activity is assumed to be a
random variable that is distributed in a particular fashion.
An activity duration might be assumed to be distributed
as a normal or a beta distributed random variable as
shown in figure below.
Stochastic Project Scheduling [PERT]
6/18/20205
Stochastic Project Scheduling
[PERT]
Figure shows the probability or chance of experiencing
a particular activity duration based on a probabilistic
distribution.
Stochastic Project Scheduling [PERT]
6/18/20206
Stochastic Project Scheduling
[PERT]
The beta distribution is often used to characterize
activity durations, since it can have an absolute
minimum and an absolute maximum of possible
duration times.
The normal distribution is a good approximation to the
beta distribution in the center of the distribution and
is easy to work with, so it is often used as an
approximation.
Stochastic Project Scheduling [PERT]
6/18/20207
Stochastic Project Scheduling
[PERT]
The most common formal approach to incorporate
uncertainty in the scheduling process is to apply the
critical path scheduling process and then analyze the
results from a probabilistic perspective.
This process is usually referred to as the Program
Evaluation and Review Technique [PERT] method.
The critical path [determined] is then used to analyze
the duration of the project incorporating the uncertainty
of the activity durations along the critical path.
Stochastic Project Scheduling [PERT]
6/18/20208
Stochastic Project Scheduling
[PERT]
The expected project duration is equal to the sum of
the expected durations of the activities along
the critical path.
Assuming that activity durations are independent
random variables, the variance or variation in the
duration of this critical path is calculated as the
sum of the variances along the critical path.
Stochastic Project Scheduling [PERT]
6/18/20209
Stochastic Project Scheduling
[PERT]
With the mean and variance of the identified critical
path known, the distribution of activity durations can also
be computed.
Stochastic Project Scheduling [PERT]
6/18/202010
Stochastic Project Scheduling
[PERT]
Program Evaluation and Review Technique
PERT introduces uncertainty into the estimates for
activity and project durations.
PERT is well suited for those situations where there is
either insufficient background information to specify
accurately time and cost or where project activities
require research and development.
Stochastic Project Scheduling [PERT]
6/18/202011
Stochastic Project Scheduling
[PERT]
AON diagramming can be easily used alternatively
AOA [original development approach].
The method is based on the well-known “central
limit theorem”.
Stochastic Project Scheduling [PERT]
6/18/202012
Stochastic Project Scheduling
[PERT]
The theorem states that:
… “Where a series of sequential independent activities
lie on the critical path of a network, the sum of the
individual activity durations will be distributed in
approximately normal fashion, regardless of the
distribution of the individual activities themselves….
… The mean of the distribution of the sum of the activity
durations will be the sum of the means of the individual
activities and its variance will be the sum of the
Stochastic Project Scheduling [PERT]
6/18/202013
Stochastic Project Scheduling
[PERT]
Primary assumptions of PERT can be summarized as
follows:
Any PERT path must have enough activities to make
central limit theorem valid.
The mean of the distribution of the path with the
greatest duration, from the initial node to a given
node, is given by the maximum mean of the duration
distribution of the paths entering the node.
PERT critical path is longer enough than any other path in
Stochastic Project Scheduling [PERT]
6/18/202014
Stochastic Project Scheduling [PERT]
Six Steps PERT & CPM
1. Define the project and prepare the work breakdown
structure
2. Develop relationships among the activities - decide
which activities must precede and which must follow
others
3. Draw the network connecting all of the activities
Stochastic Project Scheduling [PERT]
6/18/202015
Stochastic Project Scheduling [PERT]
Step Cont’d
4. Assign time and/or cost estimates to each activity
5. Compute the longest time path through the network –
this is called the critical path
6. Use the network to help plan, schedule, monitor, and
control the project
Stochastic Project Scheduling [PERT]
Questions PERT & CPM Can Answer
1. When will the entire project be completed?
2. What are the critical activities or tasks in the project?
3. Which are the noncritical activities?
4. What is the probability the project will be completed by
a specific date?
6/18/202016
Stochastic Project Scheduling
[PERT]
Stochastic Project Scheduling [PERT]
5. Is the project on schedule, behind schedule, or ahead
of schedule?
6. Is the money spent equal to, less than, or greater than
the budget?
7. Are there enough resources available to finish the
project on time?
8. If the project must be finished in a shorter time, what is
the way to accomplish this at least cost?6/18/202017
Stochastic Project Scheduling
[PERT]
Stochastic Project Scheduling [PERT]
6/18/202018
Stochastic Project Scheduling
[PERT]
Variability in Activity Times
CPM assumes we know a fixed time estimate for
each activity and there is no variability in activity
times
PERT uses a probability distribution for activity
times to allow for variability
Stochastic Project Scheduling [PERT]
6/18/202019
Stochastic Project Scheduling
[PERT]
Variability in Activity Times: Three time
estimates are required
Optimistic time (a): Estimate of the minimum time
required for an activity if exceptionally good luck is
experienced. If everything goes according to
plan.
Most–likely or modal time (m) [Most
realistic/probable estimate]: Time required if the
activity is repeated a number of times under
Stochastic Project Scheduling [PERT]
6/18/202020
Stochastic Project Scheduling
[PERT]
Pessimistic time (b) [Assuming very
unfavorable conditions]: Estimate of the maximum
time required if unusually bad luck is experienced.
Stochastic Project Scheduling [PERT]
6/18/202021
Stochastic Project Scheduling
[PERT]
These three time estimates become the framework on
which the probability distribution curve for the
activity is erected.
Many authors argue that beta distribution is mostly
fit construction activities.
The three times are thought to be easier for
managers to estimate subjectively.
Stochastic Project Scheduling [PERT]
6/18/202022
Stochastic Project Scheduling
[PERT]
Using the three times estimates, the expected mean
time (te) is derived using equation below.
Then, te is used as the best available time
approximation for the activity in question.
The standard deviation (σ) is given by equation below,
The variance (ν) can be determined as ν = σ2.
Stochastic Project Scheduling [PERT]
6/18/202023
Stochastic Project Scheduling
[PERT]
Estimate follows beta distribution
Standard Deviation
Expected time:
Variance of times:
t = (a + 4m +
b)/6
v = [(b – a)/6]2
Stochastic Project Scheduling [PERT]
6/18/202024
Stochastic Project Scheduling
[PERT]
By adopting activity expected mean time, the critical
path calculations proceed as CPM.
Associated with each duration in PERT, however,
is its standard deviation or its variance.
The project duration is determined by summing up the
activity expected mean time along the critical path
and thus will be an expected mean duration.
Stochastic Project Scheduling [PERT]
6/18/202025
Stochastic Project Scheduling
[PERT]
Since the activities on the critical path are
independent of each other, central limit theory gives
the variance of the project duration as the sum of
the individual variances of these critical path
activities.
Stochastic Project Scheduling [PERT]
6/18/202026
Stochastic Project Scheduling
[PERT]
Once the expected mean time for project duration
(TX) and its standard deviation (σX) are determined,
it is possible to calculate the chance of meeting
specific project duration (TS).
Then normal probability tables are used to
determine such chance using Equation below.
Stochastic Project Scheduling [PERT]
6/18/202027
Stochastic Project Scheduling
[PERT]
The procedure for hand probability computations using
PERT can be summarized in the following steps:
1. Make the usual forward and backward pass
computations based on a single estimate (mean) for
each activity.
2. Obtain estimates for a, m, and b for only critical
activities. If necessary, adjust the length of the critical
path as dictated by the new te values based on a, m,
and b.
Stochastic Project Scheduling [PERT]
6/18/202028
Stochastic Project Scheduling
[PERT]
3. Compute the variance for event x (νX) by
summing the variances for the critical activities
leading to event x.
4. Compute Z and find the corresponding normal
probability.
Stochastic Project Scheduling [PERT]
6/18/202029
Stochastic Project Scheduling
[PERT]
Estimate follows beta distribution
Expected time:
Variance of times:
t = (a + 4m + b)/6
v = [(b − a)/6]2
Probability
of 1 in 100
of > b
occurring
Probability
of 1 in 100
of
< a
occurring
Probability
Optimistic
Time (a)
Most Likely
Time (m)
Pessimistic
Time (b)
Activity
Time
Stochastic Project Scheduling [PERT]
6/18/202030
Stochastic Project Scheduling
[PERT]
Most Expected
Optimistic Likely Pessimistic Time Variance
Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2
A 1 2 3 2 .11
B 2 3 4 3 .11
C 1 2 3 2 .11
D 2 4 6 4 .44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 .11
Computing Variance
Stochastic Project Scheduling [PERT]
6/18/202031
Stochastic Project Scheduling
[PERT]
Project variance is computed by summing the
variances of critical activities
s2 = Project variance
= (variances of activities
on critical path)
p
Probability of Project Completion
Stochastic Project Scheduling [PERT]
6/18/202032
Stochastic Project Scheduling
[PERT]
Project variance
s2 = .11 + .11 + 1.00 + 1.78 + .11 = 3.11
Project standard deviation
sp = Project variance
= 3.11 = 1.76 weeks
p
Stochastic Project Scheduling [PERT]
6/18/202033
Stochastic Project Scheduling
[PERT]
Standard deviation = 1.76 weeks
15 Weeks
(Expected Completion Time)
Stochastic Project Scheduling [PERT]
6/18/202034
Stochastic Project Scheduling
[PERT]
What is the probability this project can be completed
on or before the 16 week deadline?
Z = – /sp
= (16 wks – 15 wks)/1.76
= 0.57
due expected date
date of completion
Where Z is the number of
standard deviations the due
date lies from the mean
Stochastic Project Scheduling [PERT]
6/18/202035
Stochastic Project Scheduling
[PERT]
Z= − /sp
= (16 wks − 15 wks)/1.76
= 0.57
due expected date
date of completion
Where Z is the number of
standard deviations the due
date lies from the mean
.00 .01 .07 .08
.1 .50000 .50399 .52790 .53188
.2 .53983 .54380 .56749 .57142
.5 .69146 .69497 .71566 .71904
.6 .72575 .72907 .74857 .75175
From Appendix I
Stochastic Project Scheduling [PERT]
6/18/202036
Stochastic Project Scheduling
[PERT]
Time
Probability
(T ≤ 16 weeks)
is 71.57%
0.57 Standard deviations
15 16
Weeks Weeks
Stochastic Project Scheduling [PERT]
6/18/202037
Stochastic Project Scheduling
[PERT]
Probability
of 0.01
Z
From Appendix I
Probability
of 0.99
2.33
Standard
deviations0 2.33
Determining Project Completion Time
Stochastic Project Scheduling [PERT]
6/18/202038
6/18/202039
Stochastic Project Scheduling
[PERT]
Stochastic Project Scheduling
[PERT]

More Related Content

PDF
Case study 4 project cost management -- ppt slides
PDF
07 project cost management
PDF
construction project planing
PPTX
Group Sim Project Power Point 2015 Ver5
PPTX
Building a-project-schedule
PPT
Construction scheduling & Cost control
PDF
10 Project Management Knowledge Areas
PDF
PERT AND CPM PROJECT MANAGEMENT
Case study 4 project cost management -- ppt slides
07 project cost management
construction project planing
Group Sim Project Power Point 2015 Ver5
Building a-project-schedule
Construction scheduling & Cost control
10 Project Management Knowledge Areas
PERT AND CPM PROJECT MANAGEMENT

What's hot (20)

PPTX
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
PPTX
Project Control
PDF
1440 pmp exam question bank
PPTX
Project Resource Management - PMBOK6
PDF
Topic 11 - Project Schedule Management.pdf
PPTX
Project management tools
PPTX
PROJECT LIFE CYCLE
PPT
Cost plan
PDF
Construction Project management
PDF
Project Closure Powerpoint Presentation Slides
PPTX
Project management
PPTX
Parametric Estimation in a nutshell
PPT
Project planning and Scheduling
PPTX
Construction disputes
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PPTX
Project cost & control
PPT
Depreciation & obsolescence
PDF
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
PDF
PPT on Construction Costing
PPT
Project Cost Management
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
Project Control
1440 pmp exam question bank
Project Resource Management - PMBOK6
Topic 11 - Project Schedule Management.pdf
Project management tools
PROJECT LIFE CYCLE
Cost plan
Construction Project management
Project Closure Powerpoint Presentation Slides
Project management
Parametric Estimation in a nutshell
Project planning and Scheduling
Construction disputes
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Project cost & control
Depreciation & obsolescence
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
PPT on Construction Costing
Project Cost Management
Ad

Similar to PERT (20)

PDF
Cpm module iii reference
PPTX
PERT.pptx
PPTX
PERT DIAGRAMS IN MANAGEMENT AND CONSTRUCTION.pptx
PPTX
Project Scheduling techniques in Project PERT.pptx
PPTX
Quantitative analysis for business decision- Program Evaluation and Review Te...
PPTX
Lecture 5 Project Scheduling-PERT.pptx
PPT
Pert Cpm Nis
PDF
Pert techniques
PPT
chapter 6.ppt
DOC
Pearson1e ch14 appendix_14_1
PPTX
Ch 06 - CPM PERT (1).pptx
PPTX
Applying the PERT Technique_UNIT III.pptx
PPTX
Pert cpm
PDF
PDF
Pmp time chapter 6
PPTX
PERT
PPT
P E R T
PPT
CPM-PERT.ppt
PPT
Management Science : Project SchedulingPert_cpm.ppt
PDF
CPM AND PERT
Cpm module iii reference
PERT.pptx
PERT DIAGRAMS IN MANAGEMENT AND CONSTRUCTION.pptx
Project Scheduling techniques in Project PERT.pptx
Quantitative analysis for business decision- Program Evaluation and Review Te...
Lecture 5 Project Scheduling-PERT.pptx
Pert Cpm Nis
Pert techniques
chapter 6.ppt
Pearson1e ch14 appendix_14_1
Ch 06 - CPM PERT (1).pptx
Applying the PERT Technique_UNIT III.pptx
Pert cpm
Pmp time chapter 6
PERT
P E R T
CPM-PERT.ppt
Management Science : Project SchedulingPert_cpm.ppt
CPM AND PERT
Ad

More from Dereje Jima (8)

PDF
Manage Quality Customer Service1.pdf
PDF
Arrange building applications and approvals.pdf
DOCX
Administer Legal Obligations of Construction Contract.docx
PDF
Covariance and correlation(Dereje JIMA)
PDF
system analysis and management techniques (Dereje jima)
PPT
Project planning
PPTX
Special concrete and advanced construction materials
PDF
CONSTRUCTION STATISTICS pr by Dereje jima
Manage Quality Customer Service1.pdf
Arrange building applications and approvals.pdf
Administer Legal Obligations of Construction Contract.docx
Covariance and correlation(Dereje JIMA)
system analysis and management techniques (Dereje jima)
Project planning
Special concrete and advanced construction materials
CONSTRUCTION STATISTICS pr by Dereje jima

Recently uploaded (20)

PPTX
Internet of Things (IOT) - A guide to understanding
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
web development for engineering and engineering
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
DOCX
573137875-Attendance-Management-System-original
PDF
Well-logging-methods_new................
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
Welding lecture in detail for understanding
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
additive manufacturing of ss316l using mig welding
PDF
PPT on Performance Review to get promotions
PDF
composite construction of structures.pdf
Internet of Things (IOT) - A guide to understanding
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
web development for engineering and engineering
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
573137875-Attendance-Management-System-original
Well-logging-methods_new................
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
CH1 Production IntroductoryConcepts.pptx
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Welding lecture in detail for understanding
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Lecture Notes Electrical Wiring System Components
additive manufacturing of ss316l using mig welding
PPT on Performance Review to get promotions
composite construction of structures.pdf

PERT

  • 1. © 2006 Prentice Hall, Inc. 6/18/20201 Welcome To Heartiest Students Dereje Jima Construction Planning and Management Department of Civil Engineering ADDIS COLLEGE Semester I 2017
  • 2. 6/18/20202 Stochastic Project Scheduling Lecture On Stochastic Project Scheduling – Project Evaluation and Review Technique [PERT]
  • 3. 6/18/20203 Stochastic Project Scheduling [PERT] Introduction In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. Thus, the duration of an activity is estimated as a range of time values rather than being a single value. This section deals with the scheduling of the project
  • 4. 6/18/20204 Stochastic Project Scheduling [PERT] Scheduling with Uncertain Durations Using the probabilistic distribution of activity durations. Duration of a particular activity is assumed to be a random variable that is distributed in a particular fashion. An activity duration might be assumed to be distributed as a normal or a beta distributed random variable as shown in figure below. Stochastic Project Scheduling [PERT]
  • 5. 6/18/20205 Stochastic Project Scheduling [PERT] Figure shows the probability or chance of experiencing a particular activity duration based on a probabilistic distribution. Stochastic Project Scheduling [PERT]
  • 6. 6/18/20206 Stochastic Project Scheduling [PERT] The beta distribution is often used to characterize activity durations, since it can have an absolute minimum and an absolute maximum of possible duration times. The normal distribution is a good approximation to the beta distribution in the center of the distribution and is easy to work with, so it is often used as an approximation. Stochastic Project Scheduling [PERT]
  • 7. 6/18/20207 Stochastic Project Scheduling [PERT] The most common formal approach to incorporate uncertainty in the scheduling process is to apply the critical path scheduling process and then analyze the results from a probabilistic perspective. This process is usually referred to as the Program Evaluation and Review Technique [PERT] method. The critical path [determined] is then used to analyze the duration of the project incorporating the uncertainty of the activity durations along the critical path. Stochastic Project Scheduling [PERT]
  • 8. 6/18/20208 Stochastic Project Scheduling [PERT] The expected project duration is equal to the sum of the expected durations of the activities along the critical path. Assuming that activity durations are independent random variables, the variance or variation in the duration of this critical path is calculated as the sum of the variances along the critical path. Stochastic Project Scheduling [PERT]
  • 9. 6/18/20209 Stochastic Project Scheduling [PERT] With the mean and variance of the identified critical path known, the distribution of activity durations can also be computed. Stochastic Project Scheduling [PERT]
  • 10. 6/18/202010 Stochastic Project Scheduling [PERT] Program Evaluation and Review Technique PERT introduces uncertainty into the estimates for activity and project durations. PERT is well suited for those situations where there is either insufficient background information to specify accurately time and cost or where project activities require research and development. Stochastic Project Scheduling [PERT]
  • 11. 6/18/202011 Stochastic Project Scheduling [PERT] AON diagramming can be easily used alternatively AOA [original development approach]. The method is based on the well-known “central limit theorem”. Stochastic Project Scheduling [PERT]
  • 12. 6/18/202012 Stochastic Project Scheduling [PERT] The theorem states that: … “Where a series of sequential independent activities lie on the critical path of a network, the sum of the individual activity durations will be distributed in approximately normal fashion, regardless of the distribution of the individual activities themselves…. … The mean of the distribution of the sum of the activity durations will be the sum of the means of the individual activities and its variance will be the sum of the Stochastic Project Scheduling [PERT]
  • 13. 6/18/202013 Stochastic Project Scheduling [PERT] Primary assumptions of PERT can be summarized as follows: Any PERT path must have enough activities to make central limit theorem valid. The mean of the distribution of the path with the greatest duration, from the initial node to a given node, is given by the maximum mean of the duration distribution of the paths entering the node. PERT critical path is longer enough than any other path in Stochastic Project Scheduling [PERT]
  • 14. 6/18/202014 Stochastic Project Scheduling [PERT] Six Steps PERT & CPM 1. Define the project and prepare the work breakdown structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities Stochastic Project Scheduling [PERT]
  • 15. 6/18/202015 Stochastic Project Scheduling [PERT] Step Cont’d 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network – this is called the critical path 6. Use the network to help plan, schedule, monitor, and control the project Stochastic Project Scheduling [PERT]
  • 16. Questions PERT & CPM Can Answer 1. When will the entire project be completed? 2. What are the critical activities or tasks in the project? 3. Which are the noncritical activities? 4. What is the probability the project will be completed by a specific date? 6/18/202016 Stochastic Project Scheduling [PERT] Stochastic Project Scheduling [PERT]
  • 17. 5. Is the project on schedule, behind schedule, or ahead of schedule? 6. Is the money spent equal to, less than, or greater than the budget? 7. Are there enough resources available to finish the project on time? 8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost?6/18/202017 Stochastic Project Scheduling [PERT] Stochastic Project Scheduling [PERT]
  • 18. 6/18/202018 Stochastic Project Scheduling [PERT] Variability in Activity Times CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a probability distribution for activity times to allow for variability Stochastic Project Scheduling [PERT]
  • 19. 6/18/202019 Stochastic Project Scheduling [PERT] Variability in Activity Times: Three time estimates are required Optimistic time (a): Estimate of the minimum time required for an activity if exceptionally good luck is experienced. If everything goes according to plan. Most–likely or modal time (m) [Most realistic/probable estimate]: Time required if the activity is repeated a number of times under Stochastic Project Scheduling [PERT]
  • 20. 6/18/202020 Stochastic Project Scheduling [PERT] Pessimistic time (b) [Assuming very unfavorable conditions]: Estimate of the maximum time required if unusually bad luck is experienced. Stochastic Project Scheduling [PERT]
  • 21. 6/18/202021 Stochastic Project Scheduling [PERT] These three time estimates become the framework on which the probability distribution curve for the activity is erected. Many authors argue that beta distribution is mostly fit construction activities. The three times are thought to be easier for managers to estimate subjectively. Stochastic Project Scheduling [PERT]
  • 22. 6/18/202022 Stochastic Project Scheduling [PERT] Using the three times estimates, the expected mean time (te) is derived using equation below. Then, te is used as the best available time approximation for the activity in question. The standard deviation (σ) is given by equation below, The variance (ν) can be determined as ν = σ2. Stochastic Project Scheduling [PERT]
  • 23. 6/18/202023 Stochastic Project Scheduling [PERT] Estimate follows beta distribution Standard Deviation Expected time: Variance of times: t = (a + 4m + b)/6 v = [(b – a)/6]2 Stochastic Project Scheduling [PERT]
  • 24. 6/18/202024 Stochastic Project Scheduling [PERT] By adopting activity expected mean time, the critical path calculations proceed as CPM. Associated with each duration in PERT, however, is its standard deviation or its variance. The project duration is determined by summing up the activity expected mean time along the critical path and thus will be an expected mean duration. Stochastic Project Scheduling [PERT]
  • 25. 6/18/202025 Stochastic Project Scheduling [PERT] Since the activities on the critical path are independent of each other, central limit theory gives the variance of the project duration as the sum of the individual variances of these critical path activities. Stochastic Project Scheduling [PERT]
  • 26. 6/18/202026 Stochastic Project Scheduling [PERT] Once the expected mean time for project duration (TX) and its standard deviation (σX) are determined, it is possible to calculate the chance of meeting specific project duration (TS). Then normal probability tables are used to determine such chance using Equation below. Stochastic Project Scheduling [PERT]
  • 27. 6/18/202027 Stochastic Project Scheduling [PERT] The procedure for hand probability computations using PERT can be summarized in the following steps: 1. Make the usual forward and backward pass computations based on a single estimate (mean) for each activity. 2. Obtain estimates for a, m, and b for only critical activities. If necessary, adjust the length of the critical path as dictated by the new te values based on a, m, and b. Stochastic Project Scheduling [PERT]
  • 28. 6/18/202028 Stochastic Project Scheduling [PERT] 3. Compute the variance for event x (νX) by summing the variances for the critical activities leading to event x. 4. Compute Z and find the corresponding normal probability. Stochastic Project Scheduling [PERT]
  • 29. 6/18/202029 Stochastic Project Scheduling [PERT] Estimate follows beta distribution Expected time: Variance of times: t = (a + 4m + b)/6 v = [(b − a)/6]2 Probability of 1 in 100 of > b occurring Probability of 1 in 100 of < a occurring Probability Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) Activity Time Stochastic Project Scheduling [PERT]
  • 30. 6/18/202030 Stochastic Project Scheduling [PERT] Most Expected Optimistic Likely Pessimistic Time Variance Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2 A 1 2 3 2 .11 B 2 3 4 3 .11 C 1 2 3 2 .11 D 2 4 6 4 .44 E 1 4 7 4 1.00 F 1 2 9 3 1.78 G 3 4 11 5 1.78 H 1 2 3 2 .11 Computing Variance Stochastic Project Scheduling [PERT]
  • 31. 6/18/202031 Stochastic Project Scheduling [PERT] Project variance is computed by summing the variances of critical activities s2 = Project variance = (variances of activities on critical path) p Probability of Project Completion Stochastic Project Scheduling [PERT]
  • 32. 6/18/202032 Stochastic Project Scheduling [PERT] Project variance s2 = .11 + .11 + 1.00 + 1.78 + .11 = 3.11 Project standard deviation sp = Project variance = 3.11 = 1.76 weeks p Stochastic Project Scheduling [PERT]
  • 33. 6/18/202033 Stochastic Project Scheduling [PERT] Standard deviation = 1.76 weeks 15 Weeks (Expected Completion Time) Stochastic Project Scheduling [PERT]
  • 34. 6/18/202034 Stochastic Project Scheduling [PERT] What is the probability this project can be completed on or before the 16 week deadline? Z = – /sp = (16 wks – 15 wks)/1.76 = 0.57 due expected date date of completion Where Z is the number of standard deviations the due date lies from the mean Stochastic Project Scheduling [PERT]
  • 35. 6/18/202035 Stochastic Project Scheduling [PERT] Z= − /sp = (16 wks − 15 wks)/1.76 = 0.57 due expected date date of completion Where Z is the number of standard deviations the due date lies from the mean .00 .01 .07 .08 .1 .50000 .50399 .52790 .53188 .2 .53983 .54380 .56749 .57142 .5 .69146 .69497 .71566 .71904 .6 .72575 .72907 .74857 .75175 From Appendix I Stochastic Project Scheduling [PERT]
  • 36. 6/18/202036 Stochastic Project Scheduling [PERT] Time Probability (T ≤ 16 weeks) is 71.57% 0.57 Standard deviations 15 16 Weeks Weeks Stochastic Project Scheduling [PERT]
  • 37. 6/18/202037 Stochastic Project Scheduling [PERT] Probability of 0.01 Z From Appendix I Probability of 0.99 2.33 Standard deviations0 2.33 Determining Project Completion Time Stochastic Project Scheduling [PERT]