The document outlines the steps for well drilling and site preparation. It describes leveling the site, digging a cellar and mud pits, hammering a conductor pipe, drilling a rathole, and transporting equipment to the site. It then details rig setup including raising the mast and substructure, connecting the conductor pipe, rig acceptance checks, and making up drill pipes. Preparing the spud mud by mixing and pumping it is covered. The process of spudding in the hole and cleaning mud returns is also outlined. Subsequent steps reviewed are picking up drill pipes, running and cementing the surface casing, waiting for the cement to cure, and completing the cement job.