The document describes a job sequencing problem to minimize idle time across two machines. It provides processing times for 7 jobs on each of the two machines. The optimal job sequence is determined to be A, D, E, C, B, G, F, with a minimum total time of 134 hours and idle times of 2 hours for machine 1 and 34 hours for machine 2.